Uddannelses- og Forskningsudvalget 2022-23 (2. samling)
L 77 Bilag 1
Offentligt
2683147_0001.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
E
UROPEAN
R
OCKETRY
C
HALLENGE
D
ESIGN
, T
EST
& E
VALUATION
G
UIDE
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0002.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
European Rocketry Challenge
Design, Test & Evaluation Guide
INTERNAL APPROVAL
PREPARED BY:
Álvaro Lopes, Portuguese Space Agency
Inês d’Ávila, Portuguese Space Agency
Manuel Wilhelm, Portuguese Space Agency
Paulo Quental, Portuguese Space Agency
Jacob Larsen, Copenhagen Suborbitals
Signature:
Date:
07/02/2022
VERIFIED BY:
Marta Gonçalves, Portuguese Space Agency
Signature:
Date: 07/02/2022
APPROVED BY:
Ricardo Conde, Portuguese Space Agency
Signature:
Date: 07/02/2022
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 2 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0003.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
TABLE OF CONTENTS
LIST OF REVISIONS ....................................................................................................................... 7
1. INTRODUCTION........................................................................................................................ 8
1.1. B
ACKGROUND
.......................................................................................................................... 8
1.2. P
URPOSE
................................................................................................................................. 8
1.3. D
OCUMENTATION
................................................................................................................... 10
2. PROPULSION SYSTEMS ........................................................................................................... 10
2.1. N
ON
-
TOXIC
P
ROPELLANTS
......................................................................................................... 10
2.2. S
OLID
M
OTORS
....................................................................................................................... 11
2.3. I
GNITION
S
YSTEMS FOR
S
OLID
M
OTORS
........................................................................................ 11
2.4. P
ROPULSION
S
YSTEM
S
AFING AND
A
RMING
................................................................................... 11
2.4.1. G
ROUND
-
START
I
GNITION
C
IRCUIT
A
RMING
......................................................................................... 11
2.4.2. A
IR
-
START
I
GNITION
C
IRCUIT
A
RMING
................................................................................................. 12
2.4.3. C
LUSTERED
P
ROPULSION
................................................................................................................... 12
2.5. A
IR
-
START
I
GNITION
C
IRCUIT
E
LECTRONICS
.................................................................................... 13
2.6. SRAD P
ROPULSION
S
YSTEMS
..................................................................................................... 13
2.6.1. C
OMBUSTION
C
HAMBER
P
RESSURE
T
ESTING
........................................................................................ 13
2.6.2. H
YBRID AND
L
IQUID
P
ROPULSION
F
ILLING
S
YSTEMS
............................................................................... 13
2.6.3. H
YBRID AND
L
IQUID
P
ROPULSION
S
YSTEM
T
ANKING
T
ESTING
.................................................................. 14
2.6.4. H
YBRID
/L
IQUID
V
ENTING
.................................................................................................................. 14
2.6.5. P
ROPELLANT
O
FFLOADING
A
FTER
L
AUNCH
A
BORT
................................................................................. 15
2.6.6. S
TATIC
H
OT
-
FIRE
T
ESTING
................................................................................................................. 15
3. RECOVERY SYSTEMS AND AVIONICS ....................................................................................... 15
3.1. D
UAL
-
EVENT
P
ARACHUTE AND
P
ARAFOIL
R
ECOVERY
........................................................................ 15
3.1.1. I
NITIAL
D
EPLOYMENT
E
VENT
.............................................................................................................. 16
3.1.2. M
AIN
D
EPLOYMENT
E
VENT
............................................................................................................... 16
3.1.3. E
JECTION
G
AS
P
ROTECTION
............................................................................................................... 16
3.1.4. P
ARACHUTE
S
WIVEL
L
INKS
................................................................................................................. 16
3.1.5. P
ARACHUTE
C
OLORATION AND
M
ARKINGS
........................................................................................... 16
3.2. N
ON
-
PARACHUTE
/P
ARAFOIL
R
ECOVERY
S
YSTEMS
........................................................................... 17
3.3. R
EDUNDANT
E
LECTRONICS
......................................................................................................... 17
3.4. O
N
-
BOARD POWER SYSTEMS AND RAIL STANDBY TIME
...................................................................... 17
3.4.1. R
EDUNDANT
COTS R
ECOVERY
E
LECTRONICS
........................................................................................ 18
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 3 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0004.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
3.4.2. D
ISSIMILAR
R
EDUNDANT
R
ECOVERY
E
LECTRONICS
................................................................................. 19
3.4.3. R
ECOVERY
E
LECTRONICS
A
CCESS
........................................................................................................ 19
3.5. O
FFICIAL
A
LTITUDE
L
OGGING AND
T
RACKING
S
YSTEM
...................................................................... 19
3.5.1. TRS F
LIGHT
C
OMPUTER AS
COTS F
LIGHT COMPUTER FOR
R
ECOVERY
....................................................... 20
3.5.2. TRS F
LIGHT
C
OMPUTER
F
REQUENCIES
................................................................................................. 20
3.5.3. TRS F
LIGHT
C
OMPUTER OPERATING FREQUENCY ALLOCATION
................................................................. 21
3.5.4. TRS F
LIGHT
C
OMPUTER FIRMWARE UPDATE
......................................................................................... 21
3.5.5. TRS
COMPATIBLE RECEIVER
(
S
)............................................................................................................ 21
3.5.6. TRS E
LECTRONICS
A
CCESS
................................................................................................................. 21
3.6. S
AFETY
C
RITICAL
W
IRING
.......................................................................................................... 22
3.6.1. C
ABLE
M
ANAGEMENT
....................................................................................................................... 22
3.6.2. S
ECURE
C
ONNECTIONS
...................................................................................................................... 22
3.6.3. C
RYO
-
COMPATIBLE
W
IRE
I
NSULATION
................................................................................................. 22
3.7. R
ECOVERY
S
YSTEM
E
NERGETIC
D
EVICES
........................................................................................ 22
3.8. R
ECOVERY
S
YSTEM
T
ESTING
....................................................................................................... 22
3.8.1. G
ROUND
T
EST
D
EMONSTRATION
........................................................................................................ 23
3.8.2. O
PTIONAL
F
LIGHT
T
EST
D
EMONSTRATION
............................................................................................ 23
3.8.3. O
PTIONAL
F
LIGHT
E
LECTRONICS
D
EMONSTRATION
................................................................................ 24
4. STORED-ENERGY DEVICES ...................................................................................................... 24
4.1. E
NERGETIC
D
EVICE
S
AFING AND
A
RMING
...................................................................................... 24
4.1.1. A
RMING
D
EVICE
A
CCESS
................................................................................................................... 25
4.1.2. A
RMING
D
EVICE
L
OCATION
................................................................................................................ 25
4.2. SRAD P
RESSURE
V
ESSELS
.......................................................................................................... 25
4.2.1. R
ELIEF
D
EVICE
................................................................................................................................. 26
4.2.2. D
ESIGNED
B
URST
P
RESSURE FOR
M
ETALLIC
P
RESSURE
V
ESSELS
............................................................... 26
4.2.3. D
ESIGNED
B
URST
P
RESSURE FOR
C
OMPOSITE
P
RESSURE
V
ESSELS
............................................................ 26
4.2.4. SRAD P
RESSURE
V
ESSEL
T
ESTING
....................................................................................................... 26
5. ACTIVE FLIGHT CONTROL SYSTEMS ......................................................................................... 27
5.1. R
ESTRICTED
C
ONTROL
F
UNCTIONALITY
......................................................................................... 27
5.2. U
NNECESSARY FOR
S
TABLE
F
LIGHT
............................................................................................... 27
5.3. D
ESIGNED TO
F
AIL
S
AFE
............................................................................................................ 28
5.4. B
OOST
P
HASE
D
ORMANCY
........................................................................................................ 28
5.5. A
CTIVE
F
LIGHT
C
ONTROL
S
YSTEM
E
LECTRONICS
.............................................................................. 28
5.6. A
CTIVE
F
LIGHT
C
ONTROL
S
YSTEM
E
NERGETICS
................................................................................ 29
6. AIRFRAME STRUCTURES ......................................................................................................... 29
6.1. A
DEQUATE
V
ENTING
................................................................................................................ 29
6.2. O
VERALL
S
TRUCTURAL
I
NTEGRITY
................................................................................................ 29
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 4 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0005.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
6.2.1. M
ATERIAL
S
ELECTION
....................................................................................................................... 29
6.2.2. L
OAD
B
EARING
E
YEBOLTS AND
U-
BOLTS
.............................................................................................. 30
6.2.3. I
MPLEMENTING
C
OUPLING
T
UBES
....................................................................................................... 30
6.2.4. L
AUNCH
L
UG
M
ECHANICAL
A
TTACHMENT
............................................................................................ 30
6.3. RF T
RANSPARENCY
.................................................................................................................. 31
6.4. I
DENTIFYING
M
ARKINGS
............................................................................................................ 31
6.5. O
THER
M
ARKINGS
................................................................................................................... 32
7. PAYLOAD ............................................................................................................................... 32
7.1. P
AYLOAD
R
ECOVERY
................................................................................................................ 32
7.1.1. P
AYLOAD
R
ECOVERY
S
YSTEM
E
LECTRONICS AND
S
AFETY
C
RITICAL
W
IRING
................................................ 32
7.1.2. P
AYLOAD
R
ECOVERY
S
YSTEM
T
ESTING
................................................................................................. 32
7.1.3. D
EPLOYABLE PAYLOAD
GPS T
RACKING
R
EQUIRED
................................................................................. 33
7.2. P
AYLOAD
E
NERGETIC
D
EVICES
.................................................................................................... 33
8. LAUNCH AND ASCENT TRAJECTORY REQUIREMENTS ............................................................... 33
8.1. L
AUNCH
A
ZIMUTH AND
E
LEVATION
.............................................................................................. 33
8.2. L
AUNCH
S
TABILITY
................................................................................................................... 33
8.3. A
SCENT
S
TABILITY
................................................................................................................... 34
8.4. O
VER
-
STABILITY
...................................................................................................................... 34
9. EUROC LAUNCH SUPPORT EQUIPMENT .................................................................................. 34
9.1. L
AUNCH
R
AILS
........................................................................................................................ 34
9.1.1. L
AUNCH
R
AIL
F
IT
C
HECK
.................................................................................................................... 35
9.2. E
U
R
O
C-
PROVIDED
L
AUNCH
C
ONTROL
S
YSTEM
............................................................................... 36
10. TEAM-PROVIDED LAUNCH SUPPORT EQUIPMENT ................................................................. 36
10.1. E
QUIPMENT
P
ORTABILITY
........................................................................................................ 36
10.2. L
AUNCH
R
AIL
E
LEVATION
......................................................................................................... 36
10.3. O
PERATIONAL
R
ANGE
............................................................................................................. 36
10.4. F
AULT
T
OLERANCE AND
A
RMING
............................................................................................... 36
10.5. S
AFETY
C
RITICAL
S
WITCHES
...................................................................................................... 37
APPENDIX A: ACRONYMS, ABBREVIATIONS & TERMS ................................................................. 38
APPENDIX B: FIRE CONTROL SYSTEM DESIGN GUIDELINES .......................................................... 39
APPENDIX C: OFFICIAL ALTITUDE LOGGING AND TRACKING SYSTEM ........................................... 44
APPENDIX D: FLIGHT READINESS REVIEW CHECKLIST .................................................................. 68
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 5 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0006.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 6 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0007.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
LIST OF REVISIONS
R
EVISION
Version 01
Version 02
Version 03
D
ATE
20/07/2020
03/03/2021
04/02/2022
D
ESCRIPTION
Original edition.
Second version, major revisions for EuRoC 2021.
Third version, major revision for EuRoC 2022.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 7 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0008.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
1. INTRODUCTION
1.1. B
ACKGROUND
The Portuguese Space Agency
Portugal Space promotes the EuRoC
European Rocketry Challenge,
hosted in the Municipality of Ponte de Sor, a competition that seeks to stimulate university level
students to fly sounding rockets, by designing and building the rockets themselves. It is widely
recognized that such competitions foster innovation and motivate students to extend themselves
beyond the classroom, while learning to work as a team, solving real world problems under the same
pressures they will experience in their future careers.
EuRoC is fully aligned with the strategic goals of Portugal Space, namely the development and
evolution of the cultural/educational internationalization frameworks capable of boosting the
development of the Space sector in Portugal.
Since EuRoC’s first edition, in 2020, where 100 students
were present to 2021, with 400 students
participating, the growth of the competition within Europe is visible, and especially within Portugal,
with an increasing number of interested teams applying to the competition. For the future, it is
Portugal Space’s
goal to continue to foster the exchange of knowledge and international interaction
inherent to the event, allowing more students to gain from the Challenge and, at the same time,
contribute to it.
This document defines the rules and requirements governing participation in EuRoC. Major revisions
of this document will be accomplished by complete document reissue. Smaller revisions will be
reflected in updates to the document’s effective date and marked by the revision number. The
authority to approve and issue revised versions of this document rests with Portugal Space.
1.2. P
URPOSE
This document defines the minimum design, test and evaluation criteria that teams must meet before
launching at the competition. These criteria main goal is to promote flight safety. Departures from
the guidance this document provides may negatively impact a team’s score and flight status,
depending on the degree of severity. The foundational, qualifying criteria for EuRoC are contained in
the EuRoC Rules & Requirements document.
The following definitions differentiate between requirements and other statements. The degree to
which a team satisfies the spirit and intent of these statements will guide the competition officials’
decisions on a project’s overall score in EuRoC and flight status at the competition.
Shall
Denotes mandatory requirements.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 8 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0009.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Failure to satisfy the spirit and intent of a mandatory requirement will always affect a project’s score
and flight status negatively.
Should
Denotes non-mandatory goals.
Failure to satisfy the spirit and intent of a non-mandatory
goal may affect a project’s score and flight
status, depending on design implementation and the team’s ability to provide thorough documentary
evidence of their due diligence on-demand.
Compliance to recommended goals and requirements may impact a team’s score and flight status in
a positive way, as demonstrating additional commitment and diligence to implement (often safety
and reliability related guidelines) is commendable.
Will
States facts and declarations of purpose.
These statements are used to clarify the spirit and intent of requirements and goals.
Flight status
Refers to the granting of permission to attempt a launch and the provisions under which that
permission remains valid.
A project’s flight status may be either nominal, provisional, or denied. The default flight status of any
team is from the project onset
“denied”, until project deliverables, and ultimately a successful Flight
Readiness Review and Flight Safety Review, convinces the technical jury to upgrade the flight status
of teams.
1) Nominal:
o
A project assigned nominal flight status meets or exceeds the minimum expectations of this
document and reveals no obvious flight safety concerns during flight safety review at the
competition.
2) Provisional:
o
A project assigned provisional flight status generally meets the minimum expectations of
this document but reveals flight safety concerns during flight safety review at the
competition which may be mitigated by field modification or by adjusting launch
environment constraints. Launch may occur only when the prescribed provisions are met.
3) Denied:
Competition officials reserve the right to deny flight status to any project which fails to
meet the minimum expectations of this document or reveals un-mitigatable flight safety
concerns during flight safety review at the competition.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 9 of 88
o
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0010.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
An effort is made throughout this document to differentiate between launch vehicle and payload
associated systems. Unless otherwise stated, requirements referring only to the launch vehicle do not
apply to payloads and vice versa.
1.3. D
OCUMENTATION
The following documents include standards, guidelines, schedules, or required standard forms. The
documents listed in this section (Table 1) are either applicable to the extent specified herein or contain
reference information useful in the application of this document.
Table 1: Documents file location.
D
OCUMENT
EuRoC Rules & Requirements
EuRoC Design, Test & Evaluation Guide
EuRoC Launch Operations
EuRoC Entry Form
EuRoC Academic Institution Letter Template
EuRoC Motors List
EuRoC Technical Questionnaire
EuRoC Temporary Admission Guide
EuRoC Waiver and Release of Liability Form
EuRoC Flight Card and Postflight Record
EuRoC Master Schedule
F
ILE LOCATION
http://www.euroc.pt
http://www.euroc.pt
http://www.euroc.pt
http://www.euroc.pt
http://www.euroc.pt
http://www.euroc.pt (Teams’ Reserved Area)
http://www.euroc.pt (Teams’ Reserved Area)
http://www.euroc.pt (Teams’ Reserved Area)
http://www.euroc.pt (Teams’ Reserved Area)
http://www.euroc.pt (Teams’ Reserved Area)
http://www.euroc.pt (Teams’ Reserved Area)
2. PROPULSION SYSTEMS
2.1. N
ON
-
TOXIC
P
ROPELLANTS
Launch vehicles entering EuRoC shall use non-toxic propellants. Ammonium perchlorate composite
propellant (APCP), potassium nitrate and sugar (also known as "rocket candy"), nitrous oxide, liquid
oxygen (LOX), hydrogen peroxide, kerosene, propane, alcohol, and similar substances, are all
considered non-toxic. Toxic propellants are defined as those requiring breathing apparatus, unique
storage and transport infrastructure, extensive personal protective equipment (PPE), etc. Homemade
propellant mixtures containing any fraction of toxic propellants are also prohibited.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 10 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0011.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
2.2. S
OLID
M
OTORS
Only COTS solid motors from the official EuRoC motor list (issued separately) are permitted at EuRoC.
The motors must be ordered via the official EuRoC pyrotechnics. Teams should refrain from contacting
any other pyrotechnics suppliers on their own.
2.3. I
GNITION
S
YSTEMS FOR
S
OLID
M
OTORS
For all solid motors (COTS and SRAD), the use of the electronic ignition system provided by the EuRoC
organisers is mandatory.
2.4. P
ROPULSION
S
YSTEM
S
AFING AND
A
RMING
A propulsion system is considered armed if only one action (e.g., an ignition signal) must occur for the
propellant(s) to ignite. The "arming action" is usually something (i.e., a switch in series) that enables
an ignition signal to ignite the propellant(s). For example, a software-based control circuit that
automatically cycles through an "arm function" and an "ignition function" does not, in fact, implement
arming. In this case, the software's arm function does not prevent a single action (e.g., starting the
launch software) from causing unauthorized ignition. This problem may be avoided by including a
manual interrupt in the software program.
These requirements generally concern more complex propulsion systems (i.e., hybrid, liquid, and
multistage systems) and all team provided launch control systems. Additional requirements for team
provided launch control systems are defined in Section 10. of this document.
2.4.1. G
ROUND
-
START
I
GNITION
C
IRCUIT
A
RMING
All ground-started propulsion system ignition circuits/sequences shall not be "armed" until all
personnel are at least 15 m away from the launch vehicle. The provided launch control system satisfies
this requirement by implementing a removable "safety jumper" in series with the pad relay box's
power supply. The removal of this single jumper prevents firing current from being sent to any of the
launch rails associated with that pad relay box. Furthermore, access to the socket allowing insertion
of the jumper is controlled via multiple physical locks to ensure that all parties have positive control
of their own safety.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 11 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0012.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
2.4.2. A
IR
-
START
I
GNITION
C
IRCUIT
A
RMING
All upper stage (i.e., air-start) propulsion systems shall be armed by launch detection (e.g.,
accelerometers, zero separation force [ZSF] electrical shunt connections, break-wires, or other similar
methods). Regardless of implementation, this arming function will prevent the upper stage from
arming in the event of a misfire.
2.4.3. C
LUSTERED
P
ROPULSION
Partial ignition may occur in clustered propulsion systems, leading to an increased probability of
incident occurrence, mainly by three potential consequences:
1. The thrust force is lower than expected, thus acceleration on the launch rail and resulting
launch rail take-off velocity too low, leading to an unstable flight.
2. The thrust force asymmetric, leading to a sideways momentum on the rocket off the launch
rail, thus to an unstable flight, and potentially a structural failure.
3. Incompletely ignited propulsions systems separate from the vehicle, ignite in the air, or ignite
from the top, and burning parts impact the ground.
To ensure stable flight, all clustered vehicles shall have a launch release system ensuring lift-off only
occurs if a minimum threshold force is met. This can be done for example by implementing a
breakaway coupling, a structural fuse, or a rope with defined breaking force.
An electromechanical alternative to a structural fuse is to measure the thrust of the restrained flight
vehicle and then open a quick release mechanism if certain conditions are fulfilled. For example, as
the vehicle throttles up, a squib/pyro actuated quick release latch can be electrically fired (i.e., Sweeny
quick release latch) when the thrust has continuously exceeded a minimum threshold for perhaps 200
milliseconds (jerk and noise suppression).
Figure 1: Example of a Sweeny quick release latch.
(Source: Matt Sweeney SPFX Inc.)
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 12 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0013.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
To measure the thrust, a strain gauge could be used, or alternatively piezo-electric pressure sensors
can be applied to measure the combustion pressure inside a thrust chamber, verifying that nominal
thrust has been achieved before the quick release squib is fired. If the latter method with pressure
sensors is used, the sensor/transducer shall be of stainless-steel and mounted in a way so that it
remains protected from hot combustion gases by means of an oil trap.
Furthermore, all clustered vehicles shall provide an engineering proof (e.g., analysis and/or simulation)
that stable flight is ensured for a lift-off force above the threshold force, even if the propulsion system
fires asymmetrically (if applicable).
For
vehicles with a “main” and several “secondary” propulsion systems, the arming function of the
secondary propulsion systems shall be armed by launch detection (i.e., air-start), preventing ground
arming of the clustered propulsion in event of misfire.
2.5. A
IR
-
START
I
GNITION
C
IRCUIT
E
LECTRONICS
All upper stage ignition systems shall comply with same requirements and goals for "redundant
electronics" and "safety critical wiring" as recovery systems
understanding that in this case
"initiation" refers to upper stage ignition rather than a recovery event. These requirements and goals
are defined in Sections 3.3. and 3.4. respectively.
2.6. SRAD P
ROPULSION
S
YSTEMS
Teams shall comply with all rules, regulations, and best practices imposed by the authorities at their
chosen test location(s). The following requirements concern verification testing of student researched
and developed (SRAD) and modified commercial-off-the-shelf (COTS) propulsion systems.
2.6.1. C
OMBUSTION
C
HAMBER
P
RESSURE
T
ESTING
SRAD and modified COTS propulsion system combustion chambers shall be designed and tested
according to the SRAD pressure vessel requirements defined in Section 4.2.. Note that combustion
chambers are exempted from the requirement for a relief device.
2.6.2. H
YBRID AND
L
IQUID
P
ROPULSION
F
ILLING
S
YSTEMS
Team shall demonstrate that the filling/loading/unloading of the liquid fuels can be done to be ready
for the launch window (maximum 90 minutes for liquid propellant loading, including pressurization).
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 13 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0014.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Teams utilising liquid propellants with low boiling point are also strongly encouraged to consider
abandoning the use of “passive” or “self-pressurization” of propellants and adopt active external or
internal pressurization (nitrogen or helium). Besides removing the significant propellant density
uncertainties of two-phase flows (a volatile and somewhat arbitrary mixture of gas bubbles and liquid)
in injectors, the flight vehicle can be pressurized in typically less than 15 seconds, at any point in time
after having been loaded on the launch rail.
If teams utilise any kind of remote-controlled loading mechanism for gases or liquid propellants, the
loading mechanism shall feature a clearly marked and labelled, single action, hand actuated,
“Emergency Release Mechanism”, just in case a remote-controlled
release mechanism jams and
requires manual LCO assistance.
It is strongly recommended that the flight vehicle is designed such that any filling/loading/unloading
connections for fluid propellants are readily accessible from the ground. No propellant loading
procedure should necessitate ladders or other elevation devices. Furthermore, teams should account
for a “failed” launch and subsequent unloading in launch preparation, thus teams should ensure the
availability of additional propellants, igniters, and any other parts that might need replacement or
adjustment in case a second launch attempt would be possible.
2.6.3. H
YBRID AND
L
IQUID
P
ROPULSION
S
YSTEM
T
ANKING
T
ESTING
SRAD and modified COTS propulsion systems using liquid propellant(s) shall successfully (without
significant anomalies) have completed a propellant loading and off-loading test in
"launchconfiguration", prior to the rocket being brought to the competition. This test may be
conducted using either actual propellant(s) or suitable proxy fluids, with the test results to be
considered a mandatory deliverable and an annex to the Technical Report, in the form of a loading
and off-loading checklist, complete with dates, signatures (at least three) and a statement of a
successful test. Referring to Section 2.4.3., it is highly recommended to perform this test multiple times
as a part of the “all-up static engine test” configuration, described in that section.
The described annex may be amended to the Technical Report, as results become available, up to the
day final deadline for delivery of the Technical Report. Failure to deliver this annex will automatically
result in a “denied” flight status.
Loading and unloading of liquid propellants must be a well-drilled, safe and efficient operation at the
competition launch rails.
2.6.4. H
YBRID
/L
IQUID
V
ENTING
For hybrid and liquid motors, it is imperative that teams can facilitate oxidizer tank venting to prevent
over-pressure situations. Teams will only be able to launch in specific time slots, so pressure relief
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 14 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0015.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
measures must be implemented to account for rockets potentially sitting a long time in waiting on the
launch rail. At no time oxidizer tanks must become safety liabilities.
2.6.5. P
ROPELLANT
O
FFLOADING
A
FTER
L
AUNCH
A
BORT
Hybrid and liquid propulsion systems shall implement a means for remotely controlled venting or
offloading of all liquid and gaseous propellants in the event of a launch abort.
2.6.6. S
TATIC
H
OT
-
FIRE
T
ESTING
SRAD propulsion systems shall successfully (without significant anomalies) complete an instrumented
(chamber pressure and/or thrust), full scale (including system working time) static hot-fire test prior
to EuRoC. In the case of solid rocket motors, this test needs not to be performed with the same motor
casing and/or nozzle components intended for use at the EuRoC (i.e., teams must verify their casing
design, but are not forced to design reloadable/reusable motor cases).
The test shall, to the extent possible, be conducted as an “all-up static engine test”, which means that
the completed flight vehicle, rigidly fastened to a suitable test stand in an upright position, should be
tested for a full duration burn under the most realistic settings possible. Test results from horizontal
tests, using flight components is less optimum, whereas test results from test benches (not using flight
components) do not qualify.
The test results and a statement of a successful test, complete with dates and signatures (at least
three) are considered a mandatory deliverable and an annex to the Technical Report.
The described annex may be amended to the Technical Report, as results become available, up to the
day final deadline for delivery of the Technical Report. Failure to deliver this annex will automatically
result in a “denied” flight status.
“Test as you fly – Fly as you test”. This test-mentality
significantly increases the chances of a lift-off
and a nominal flight.
3. RECOVERY SYSTEMS AND AVIONICS
3.1. D
UAL
-
EVENT
P
ARACHUTE AND
P
ARAFOIL
R
ECOVERY
Each independently recovered launch vehicle body, anticipated to reach an apogee above 450 m
above ground level (AGL), shall follow a "dual-event" recovery operations concept, including an initial
deployment event (e.g., a drogue parachute deployment; reefed main parachute deployment or
similar) and a main deployment event (e.g., a main parachute deployment; main parachute un-reefing
or similar). Independently recovered bodies, whose apogee is not anticipated to exceed 450 m AGL,
are exempt and may feature only a single/main deployment event.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 15 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0016.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
3.1.1. I
NITIAL
D
EPLOYMENT
E
VENT
The initial deployment event shall occur at or near apogee, stabilize the vehicle's attitude (i.e., prevent
or eliminate tumbling), and reduce its descent rate sufficiently to permit the main deployment event,
yet not so much as to exacerbate wind drift. Any part, assembly or device, featuring an initial
deployment event, shall result in a descent velocity of said item of 23-46 m/s.
3.1.2. M
AIN
D
EPLOYMENT
E
VENT
The main deployment event shall occur at an altitude no higher than 450 m AGL and reduce the
vehicle's descent rate sufficiently to prevent excessive damage upon impact with ground. Any part,
assembly or device, featuring a main deployment event, shall result in a descent velocity of said item
of less than 9 m/s.
3.1.3. E
JECTION
G
AS
P
ROTECTION
The recovery system shall implement adequate protection (e.g., fire-resistant material, pistons, baffles
etc.) to prevent hot ejection gases (if implemented) from causing burn damage to retaining chords,
parachutes, and other vital components as the specific design demands.
3.1.4. P
ARACHUTE
S
WIVEL
L
INKS
The recovery system rigging (e.g., parachute lines, risers, shock chords, etc.) shall implement swivel
links at connections to relieve torsion, as the specific design demands. This will mitigate the risk of
torque loads unthreading bolted connections during recovery as well as parachute lines twisting up.
3.1.5. P
ARACHUTE
C
OLORATION AND
M
ARKINGS
When separate parachutes are used for the initial and main deployment events, these parachutes
should be visually highly dissimilar from one another. This is typically achieved by using parachutes
whose primary colours contrast those of the other chute. This will enable ground-based observers to
characterize deployment events more easily with high-power optics.
Utilised parachutes should use colours providing a clear contrast to a blue sky and a grey/white cloud
cover.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 16 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0017.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
3.2. N
ON
-
PARACHUTE
/P
ARAFOIL
R
ECOVERY
S
YSTEMS
Teams exploring other recovery methods (i.e., non-parachute or parafoil based) shall mention them
in the dedicated field of the Technical Questionnaire (see Section 9.1. of the EuRoC Rules &
Requirements document). The organisers may make additional requests for information and draft
unique requirements depending on the team's specific design implementation.
3.3. R
EDUNDANT
E
LECTRONICS
Launch vehicles shall implement redundant recovery system electronics, including sensors/flight
computers and "electric initiators"
assuring initiation by a backup system, with a separate power
supply (i.e., battery), if the primary system fails. In this context, electric initiators are the devices
energized by the sensor electronics, which then initiates some other mechanical or chemical energy
release, to deploy its portion of the recovery system (i.e., electric matches, nichrome wire, flash bulbs,
etc.).
3.4. O
N
-
BOARD POWER SYSTEMS AND RAIL STANDBY TIME
Loss of launch slots have been experienced on multiple occasions as onboard batteries are typically
located in inaccessible positions. Despite the requirement of at least six hours of battery life on the
launch rail, an unsuccessful launch attempt typically results in the teams deciding to:
Disarm any energetic pyrotechnics;
Take the flight vehicle off the launch rail;
Haul the rocket back to the team’s preparation area;
Use tools to perform medium to extensive disassembly of the flight vehicle to extract
batteries;
Spend one to several hours recharging the batteries, if charged spares are not readily
available;
Perform the whole operation in reverse and return to the launch rail many hours later, to
perform an additional launch attempt, if the possibility is given.
This is a critically inefficient use of valuable and limited launch campaign time.
Teams should adopt one of the following two strategies:
Implement an on-board charging and charge level maintenance system using an umbilical
connection and cable;
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 17 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0018.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Place all rechargeable or replaceable batteries conveniently under service panels accessible
from ground level, without resorting to ladders or lowering the launch rail, having several
spare sets of charged batteries ready at any time.
The implementation of an on-board charging and charge level maintenance system, based on a
vehicle-wide charging bus and an umbilical cable (featuring friction-based pull-release), connected to
a ground-based power supply, should be designed/implemented as follows:
A “charging bus” should run along the
entire length of the flight vehicle, interfacing to all
batteries to facilitate charging and continuous charging and subsequent maintenance
tricklecharging;
o
Use mating connectors at every structural joint;
o
Largely all benefits of the system are lost if even a single battery is left out of the
umbilical charging bus system.
Each tap-off from the on-board charging bus to individual battery subsystems shall be reverse
current flow protected by a suitably rated diode;
All on-board batteries should feature the same nominal voltage, as far as possible;
o
If bus
voltage step-down is required for batteries with lower nominal voltage, adequately heat-
dissipated linear regulators are strongly recommended and placed upstream of the
mandatory cell balancing circuits;
o
o
Switch-mode regulation or onboard battery chargers are strongly discouraged due to
generated EMI and electrical noise;
LiPo battery cell balancing circuits shall protect each individual battery pack;
o
LiPo
battery cell balancing circuits of up to 12S cell count are widely available as
preassembled PCBs for a low price, complete with built-in undervoltage-cut-off,
overcurrent-protection and overcharging cut-off;
Flight vehicle batteries could all be considered “permanently” installed, not requiring
removal past initial installation during on-site preparation. The ground-based power
supply should simply be outputting the battery trickle charge voltage, plus a diode
drop, for easiest implementation.
o
The advantages of implementing such a system are in most cases worth the efforts. Most significantly,
the launch vehicle rail standby time changes to “infinite” and the launch vehicle is always launched
with 100% peak charged batteries.
3.4.1. R
EDUNDANT
COTS R
ECOVERY
E
LECTRONICS
At least one redundant recovery system electronics subsystem shall implement a COTS flight computer
(e.g., StratoLogger, G-Wiz, Raven, Parrot, Eggtimer, AIM, EasyMini, TeleMetrum, RRC3, etc.).
To be considered COTS, the flight computer (including flight software) must have been developed and
validated by a commercial third party. While commercially designed flight computer “kits” (e.g., the
Eggtimer) are permitted and considered COTS, any student developed flight computer assembled from
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 18 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0019.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
separate COTS components will not be considered a COTS system. Similarly, any COTS microcontroller
running student developed flight software will not be considered a COTS system.
The interconnection redundancy of the nominal and redundant recovery electronics and recovery
systems should be implemented as illustrated in Figure 2.
Figure 2: Interconnection redundancy implementation. (Source: Jacob Larsen)
3.4.2. D
ISSIMILAR
R
EDUNDANT
R
ECOVERY
E
LECTRONICS
There is no requirement that the redundant/backup system be dissimilar to the primary; however,
there are advantages to using dissimilar primary and backup systems. Such configurations are less
vulnerable to any inherent environmental sensitivities, design, or production flaws affecting a
particular component.
3.4.3. R
ECOVERY
E
LECTRONICS
A
CCESS
As for all electronics, it is highly recommended to ensure easy and quick access to switches/connectors
via an access panel on the airframe. Access panels should be positioned so they are reachable from
ground level, ideally without ladders. Access panels shall be secured for flight.
3.5. O
FFICIAL
A
LTITUDE
L
OGGING AND
T
RACKING
S
YSTEM
Single-stage flight vehicles and upper-most stages of flight vehicles shall feature a mandatory
operational Eggtimer TRS Flight Computer for official altitude logging and GPS tracking. For more
details see http://eggtimerrocketry.com/.
The competition achieved apogee will be determined from this device.
Note:
Deployable payloads and lower stages also require a mandatory Eggfinder GPS tracking device,
but this need not be the TRS Flight Computer.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 19 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0020.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
More technical details on the Eggtimer TRS Flight Computer along with recommendations and lessons
learned can be found in Appendix C.
The Eggtimer TRS Flight Computer system serves two purposes:
Providing the EuRoC evaluation board with the means to easily determine and record the
apogee altitude in a fast, efficient, and consistent way. Since the flight vehicle apogee is a
fundamental part of the competition, the method of determining it must be equally fair (hence
identical) for all teams;
Provide the student/recovery teams an efficient means of quickly tracking down the location
of all landed flight vehicles (and any other tracked payload/components), to quickly clear the
launch range.
The Eggtimer TRS Flight Computer System was chosen to impose the least amount of inconvenience
to the teams:
Low weight and volume transmitter, to not impede flight vehicle design or performance;
Being cheap and imposing the smallest financial burden possible.
3.5.1. TRS F
LIGHT
C
OMPUTER AS
COTS F
LIGHT COMPUTER FOR
R
ECOVERY
The Eggtimer TRS Flight Computer may be used as the COTS flight computers to comply with the
requirements for redundant COTS Recovery Electronics according to section 3.3., or it may be used as
an additional, independent standalone system.
The Eggtimer system was NOT chosen because it provides the best overall performance or versatility.
It is however the cheapest system which fulfil the EuRoC organisation minimum functional
requirements with regards to apogee logging and GPS tracking. It is therefore recommended that
teams evaluate the specifications and functionality of the system before they decide between
implementing it as their main flight computer or leaving it as a stand-alone
“payload”.
3.5.2. TRS F
LIGHT
C
OMPUTER
F
REQUENCIES
EuRoC will make specific frequencies available for tracking system use, without the need for specific
radio amateur licenses. Eggtimer Ham-frequency equipment can thus legally be used during EuRoC
without a license. This means that all mandatory TRS Flight Computers must be purchased in the US
“Ham” frequency range.
While the “EU” license free version of the TRS sounds like a compelling option,
there is a major
drawback in the fact, that the EU license free band contains only three separate channels/frequencies,
and TRS systems cannot share the same frequency.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 20 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0021.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
This is a major problem since multiple flight vehicles might be on the launch rails at the opening of a
launch window. These vehicles will (when propulsive technology permits) be launched successively,
as soon as the previous flight vehicle is believed landed, with no time for additional pre-flight
preparations in between launches.
Therefore,
purchasing the “EU” version of the TRS Flight Computer is highly discouraged, despite being
legal to use.
3.5.3. TRS F
LIGHT
C
OMPUTER OPERATING FREQUENCY ALLOCATION
The EuRoC organisation intends to allocate unique TRS Flight Computer operating frequencies to
teams, at the latest shortly after the FRR. This includes the frequency for the upper-most stage of the
flight vehicle, as well as any other frequencies for lower stages and/or deployable payloads.
Teams shall however be capable of (and prepared to) re-program their operating frequencies of
Eggtimer/finder equipment at short notice in case launch schedule reshuffling requires it so.
3.5.4. TRS F
LIGHT
C
OMPUTER FIRMWARE UPDATE
Teams must ensure that the TRS Flight Computer is running a custom version of the firmware for the
70 cm Ham frequency band, having a channel selection resolution of 25 kHz. This is necessary in order
to be able to select the frequencies allotted to EuRoC.
Please note that firmware updates can be done at any time by participating teams, as long as the
hardware has been procured.
3.5.5. TRS
COMPATIBLE RECEIVER
(
S
)
While teams are not required to procure one or more receivers
for the Eggfinder “Ham-version” TRS
Flight Computer, according to the EuRoC Rules and Requirements, teams shall procure the “full kit
package”, as it includes the LCD GPS receiver.
3.5.6. TRS E
LECTRONICS
A
CCESS
As for all electronics, it is highly recommended to ensure easy and quick access to switches/connectors
via an access panel on the airframe. Access panels should be positioned so they are reachable from
ground level, ideally without ladders. Access panels shall be secured for flight.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 21 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0022.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
3.6. S
AFETY
C
RITICAL
W
IRING
For the purposes of this document, safety critical wiring is defined as electrical wiring associated with
recovery system deployment events and any "air started" rocket motors.
3.6.1. C
ABLE
M
ANAGEMENT
All safety critical wiring shall implement a cable management solution (e.g., wire ties, wiring,
harnesses, cable raceways) which will prevent tangling and excessive free movement of significant
wiring/cable lengths due to expected launch loads. This requirement is not intended to negate the
small amount of slack necessary at all connections/terminals to prevent unintentional de-mating due
to expected launch loads transferred into wiring/cables at physical interfaces.
3.6.2. S
ECURE
C
ONNECTIONS
All safety critical wiring/cable connections shall be sufficiently secure as to prevent de-mating due to
expected launch loads. This will be evaluated by a "tug test", in which the connection is gently but
firmly "tugged" by hand to verify it is unlikely to break free in flight.
3.6.3. C
RYO
-
COMPATIBLE
W
IRE
I
NSULATION
In case of propellants with a boiling point of less than -50°C any wiring or harness passing within close
proximity of a cryogenic device (e.g., valve, piping, etc.) or a cryogenic tank (e.g., a cable tunnel next
to a LOX tank) shall utilize safety critical wiring with cryo-compatible insulation (i.e., Teflon, PTFE, etc.).
3.7. R
ECOVERY
S
YSTEM
E
NERGETIC
D
EVICES
All stored-energy devices (i.e., energetics) used in recovery systems shall comply with the energetic
device requirements defined in Section 4. of this document.
3.8. R
ECOVERY
S
YSTEM
T
ESTING
Recovery system testing has proven to be one of the most critical and at the same time
underestimated tasks. Teams are strongly encouraged to test the system back-to-back as good as they
can and implement standard procedures that they can fall back onto even during the most stressful of
launch days.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 22 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0023.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Teams shall comply with all rules, regulations, and best practices imposed by the authorities at their
chosen test location(s). The following requirements concern verification testing of all recovery
systems.
3.8.1. G
ROUND
T
EST
D
EMONSTRATION
All recovery system mechanisms shall be successfully (without significant anomalies) tested prior to
EuRoC, either by flight testing, or through one or more ground tests of key subsystems. In the case of
such ground tests, sensor electronics will be functionally included in the demonstration by simulating
the environmental conditions under which their deployment function is triggered.
The test results and a statement of a successful test, complete with dates and signatures (at least
three) are considered a mandatory deliverable and annex to the Technical Report.
The described annex may be amended to the Technical Report, as results become available, up to the
day final deadline for delivery of the Technical Report. Failure to deliver this annex will automatically
result in a “denied” flight status.
Correct, reliable and repeatable recovery system performance is absolute top priority from a safety
point of view. Statistical data also concludes that namely recovery system failures are the major cause
of abnormal “landings”.
3.8.2. O
PTIONAL
F
LIGHT
T
EST
D
EMONSTRATION
All recovery system mechanisms shall be successfully (without significant anomalies) tested prior to
EuRoC, either by flight testing, or through one or more ground tests of key subsystems. While not
required, a flight test demonstration may be used in place of ground testing. In the case of such a flight
test, the recovery system flown will verify the intended design by implementing the same major
subsystem components (e.g., flight computers and parachutes) as will be integrated into the launch
vehicle intended for EuRoC (i.e., a surrogate booster may be used).
The test results and a statement of a successful test, complete with dates and signatures (at least
three) are considered a mandatory deliverable and annex to the Technical Report.
The described annex may be amended to the Technical Report, as results become available, up to the
day final deadline for delivery of the Technical Report. Failure to deliver this annex will automatically
result in a “denied” flight status.
Correct, reliable and repeatable recovery system performance is absolute top priority from a safety
point of view. Statistical data also concludes that namely recovery system failures are the major cause
of abnormal “landings”.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 23 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0024.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
3.8.3. O
PTIONAL
F
LIGHT
E
LECTRONICS
D
EMONSTRATION
Teams are encouraged to have a setup to demonstrate the electronics and recovery system working
routine in the FRR, either by a software routine that actuates the outputs of the flight computer and
using LED indicators or buzzers or by a self-developed setup. This step is not mandatory, it is instead
a recommendation for teams to detect some possible bugs and defects in their system.
4. STORED-ENERGY DEVICES
4.1. E
NERGETIC
D
EVICE
S
AFING AND
A
RMING
All energetics shall be “safed” until the rocket is in the launch position, at which point they may be
"armed". An energetic device is considered safed when two separate events are necessary to release
the energy of the system. An energetic device is considered armed when only one event is necessary
to release the energy. For the purpose of this document, energetics are defined as all stored-energy
devices
other than propulsion systems
that have reasonable potential to cause bodily injury upon
energy release. The following table lists some common types of stored-energy devices and overviews
and in which configurations they are considered non-energetic, safed, or armed.
Table 2: Overviews and configurations of stored-energy devices.
D
EVICE
C
LASS
N
ON
-
ENERGETIC
Small igniters/squibs,
nichrome, wire or
similar
Very small quantities
contained in non-
shrapnel producing
devices (e.g., pyrocutters
or pyro-valves)
De-energized/relaxed
state, small devices, or
captured devices (i.e.,
no jettisoned parts)
Non-charged pressure
vessels
S
AFED
Large igniters with leads
shunted
Large quantities with no
igniter, shunted igniter
leads, or igniter(s)
connected to unpowered
avionics
Mechanically locked and
not releasable by a single
event
Charged vessels with two
events required to open
main valve
A
RMED
Large igniters with
no- shunted leads
Large quantities with
non-shunted igniter
or igniter(s)
connected to
powered avionics
Unlocked and
releasable by a single
event
Charged vessels with
one event required
to open main valve
Igniters/Squibs
Pyrogens (e.g.,
black powder)
Mechanical Devices
(e.g., powerful
springs)
Pressure Vessels
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 24 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0025.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Although these definitions are consistent with the propulsion system arming definition provided in
Section 2. of this document, this requirement is directed mainly at the energetics used by recovery
systems and extends to all other energetics used in experiments, control systems, etc. Note that while
Section 2.4.1. requires propulsion systems to be armed only after the launch rail area is evacuated to
a specified distance, this requirement permits personnel to arm other stored-energy devices at the
launch rail.
4.1.1. A
RMING
D
EVICE
A
CCESS
All energetic device arming features shall be externally accessible/controllable. This does not preclude
the limited use of access panels which may be secured for flight while the vehicle is in the launch
position.
4.1.2. A
RMING
D
EVICE
L
OCATION
All energetic device arming features shall be located on the airframe such that any inadvertent energy
release by these devices will not impact personnel arming them. For example, the arming key switch
for an energetic device used to deploy a hatch panel shall not be located at the same airframe clocking
position as the hatch panel deployed by that charge.
Furthermore, it is highly recommended that the arming mechanism is accessible from ground level,
without the use of ladders or other elevation devices, when the rocket is at a vertical orientation on
the launch rail. If this requirement is considered early in the design process, implementing the arming
devices in the lower section of the rocket is easy, while also mitigating the need for risky or hazardous
arming procedures at a height.
4.2. SRAD P
RESSURE
V
ESSELS
The following requirements concern design and verification testing of SRAD and modified COTS
pressure vessels. Unmodified COTS pressure vessels utilized for other than their advertised
specifications will be considered modified, and subject to these requirements. SRAD (including
modified COTS) rocket motor propulsion system combustion chambers are included as well but are
exempted from the relief device requirement.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 25 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0026.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
4.2.1. R
ELIEF
D
EVICE
SRAD pressure vessels shall implement a relief device, set to open at no greater than the proof
pressure specified in the following requirements. SRAD (including modified COTS) rocket motor
propulsion system combustion chambers are exempted from this requirement.
4.2.2. D
ESIGNED
B
URST
P
RESSURE FOR
M
ETALLIC
P
RESSURE
V
ESSELS
SRAD and modified COTS pressure vessels constructed entirely from isotropic materials (e.g., metals)
shall be designed to a burst pressure no less than 2 times the maximum expected operating pressure,
where the maximum operating pressure is the maximum pressure expected during pre-launch, flight,
and recovery operations.
4.2.3. D
ESIGNED
B
URST
P
RESSURE FOR
C
OMPOSITE
P
RESSURE
V
ESSELS
All SRAD and modified COTS pressure vessels either constructed entirely from non-isotropic materials
(e.g., fibre reinforced plastics; FRP; composites) or implementing composite overwrap of a metallic
vessel (i.e., composite overwrapped pressure vessels; COPV), shall be designed to a burst pressure no
less than 3 times the maximum expected operating pressure, where the maximum operating pressure
is the maximum pressure expected during pre-launch, flight, and recovery operations.
4.2.4. SRAD P
RESSURE
V
ESSEL
T
ESTING
Teams shall comply with all rules, regulations, and best practices imposed by the authorities at their
chosen test location(s). The following requirements concern design and verification testing of SRAD
and modified COTS pressure vessels. Unmodified COTS pressure vessels utilized for other than their
advertised specifications will be considered modified, and subject to these requirements. SRAD
(including modified COTS) rocket motor propulsion system combustion chambers are included as well.
4.2.4.1. P
ROOF
P
RESSURE
T
ESTING
SRAD and modified COTS pressure vessels shall be proof pressure tested successfully (without
significant anomalies) to 1.5 times the maximum expected operating pressure for no less than twice
the maximum expected system working time, using the intended flight article(s) (e.g., the pressure
vessel(s) used in proof testing must be the same one(s) flown at EuRoC). The maximum system working
time is defined as the maximum uninterrupted time duration the vessel will remain pressurized during
pre-launch, flight, and recovery operations.
The test results and a statement of a successful test, complete with dates and signatures (at least
three) are considered mandatory deliverable and annexed to the Technical Report.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 26 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0027.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
The described annex may be amended to the Technical Report, as results become available, up to the
day final deadline for delivery of the Technical Report. Failure to deliver this annex will automatically
result in a “denied” flight status.
The pressure testing is an important factor in instilling confidence in the structural strength and
integrity of the flown pressure vessels. Since liquid propellant loading onto hybrid or bi-liquid
propelled flight vehicles will in the majority of cases involve manual loading, there will be times where
ground personnel will be in close proximity with pressurized systems. It is crucial that ground
personnel safety is heightened by the use of proof pressure tested pressure vessels.
4.2.4.2. O
PTIONAL
B
URST
P
RESSURE TESTING
Although there is no requirement for burst pressure testing, a rigorous verification & validation test
plan typically includes a series of both non-destructive (i.e., proof pressure) and destructive (i.e., burst
pressure) tests. A series of burst pressure tests performed on the intended design will be viewed
favourably; however, this will not be considered an alternative to proof pressure testing of the
intended flight article.
5. ACTIVE FLIGHT CONTROL SYSTEMS
5.1. R
ESTRICTED
C
ONTROL
F
UNCTIONALITY
Launch vehicle active flight control systems shall be optionally implemented strictly for pitch and/or
roll stability augmentation, or for aerodynamic "braking". Under no circumstances will a launch vehicle
entered in EuRoC be actively guided towards a designated spatial target. The organisers may make
additional requests for information and draft unique requirements depending on the team's specific
design implementation.
5.2. U
NNECESSARY FOR
S
TABLE
F
LIGHT
Launch vehicles implementing active flight controls shall be naturally stable without these controls
being implemented (e.g., the launch vehicle may be flown with the control actuator system [CAS]
including any control surfaces
either removed or rendered inert and mechanically locked, without
becoming unstable during ascent).
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 27 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0028.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Attitude Control Systems (ACS) will serve only to mitigate the small perturbations which affect the
trajectory of a stable rocket that implements only fixed aerodynamic surfaces for stability. Stability is
defined in Section 8.3. of this document. The organisers may make additional requests for information
and draft unique requirements depending on the team's specific design implementation.
5.3. D
ESIGNED TO
F
AIL
S
AFE
Control Actuator Systems (CAS) shall mechanically lock in a neutral state whenever either an abort
signal is received for any reason, primary system power is lost, or the launch vehicle's attitude exceeds
30° from its launch elevation. Any one of these conditions being met will trigger the fail-safe, neutral
system state. A neutral state is defined as one which does not apply any moments to the launch vehicle
(e.g., aerodynamic surfaces trimmed or retracted, gas jets off, etc.).
5.4. B
OOST
P
HASE
D
ORMANCY
CAS shall mechanically lock in a neutral state until either the mission’s boost phase has ended (i.e., all
propulsive stages have ceased producing thrust), the launch vehicle has crossed the point of maximum
aerodynamic pressure (i.e., max Q) in its trajectory, or the launch vehicle has reached an altitude of
6000 m AGL. Any one of these conditions being met will permit the active system state. A neutral state
is defined as one which does not apply any moments to the launch vehicle (e.g., aerodynamic surfaces
trimmed or retracted, gas jets off, etc.).
Since all flight vehicles with Control Actuator Systems (guidance systems) are to be designed inherently
passively stable at lift-off, CAS are not needed until somewhat into the flight, performing minor course
corrections thereafter. In enforcing a boost dormancy phase, any unexpected, erratic, or faulty CAS
system behaviour will take place far from the launch rail, minimizing the chances of putting EuRoC
participants at risk near the launch rail.
5.5. A
CTIVE
F
LIGHT
C
ONTROL
S
YSTEM
E
LECTRONICS
Wherever possible, all active control systems should comply with requirements and goals for
"redundant electronics" and "safety critical wiring" as recovery systems
understanding that in this
case "initiation" refers CAS commanding rather than a recovery event. These requirements and goals
are defined in Sections 3.3. and Section 3.4. respectively of this document. Flight control systems are
exempt from the requirement for COTS redundancy, given that such components are generally
unavailable as COTS to the amateur high-power rocketry community.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 28 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0029.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
As for all electronics, it is highly recommended to ensure easy and quick access to switches/connectors
via an access panel on the airframe. Access panels should be positioned so they are reachable from
ground level, ideally without ladders. Access panels shall be secured for flight.
5.6. A
CTIVE
F
LIGHT
C
ONTROL
S
YSTEM
E
NERGETICS
All stored-energy devices used in an active flight control system (i.e., energetics) shall comply with the
energetic device requirements defined in Section 4. of this document.
6. AIRFRAME STRUCTURES
6.1. A
DEQUATE
V
ENTING
Launch vehicles shall be adequately vented to prevent unintended internal pressures developed
during flight from causing either damage to the airframe or any other unplanned configuration
changes. Typically, a 3 mm to 5 mm hole is drilled in the booster section just behind the nosecone or
payload shoulder area, and through the hull or bulkhead of any similarly isolated compartment/bay.
6.2. O
VERALL
S
TRUCTURAL
I
NTEGRITY
Launch vehicles will be constructed to withstand the operating stress and retain structural integrity
under the conditions encountered during handling as well as rocket flight. The following requirements
address some key points applicable to almost all amateur high-power rockets but are not exhaustive
of the conditions affecting each unique design. Student teams are ultimately responsible for
thoroughly understanding, analysing and mitigating their design’s unique load set.
6.2.1. M
ATERIAL
S
ELECTION
PVC (and similar low-temperature polymers), Public Missiles Ltd. (PML) Quantum Tube components
shall not be used in any structural (i.e., load bearing) capacity, most notably as load bearing eyebolts,
launch vehicle airframes, or propulsion system combustion chambers.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 29 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0030.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
6.2.2. L
OAD
B
EARING
E
YEBOLTS AND
U-
BOLTS
All load bearing eyebolts shall be of the closed-eye, forged type
NOT of the open eye, bent wire
type. Furthermore, all load bearing eyebolts and U-Bolts shall be steel or stainless steel. This
requirement extends to any bolt and eye-nut assembly used in place of an eyebolt.
6.2.3. I
MPLEMENTING
C
OUPLING
T
UBES
Airframe joints which implement "coupling tubes" should be designed such that the coupling tube
extends no less than one body calibre (1D) on either side of the joint
measured from the separation
plane. This rule applies both for “half” couplings (e.g., nosecone –
body tube/coupling tube) as well as
for “full” couplings (e.g., body tube –
coupling tube
body tube). See example in Figure 3 for clarity.
Regardless of implementation (e.g., RADAX or other join types) airframe joints need to be "stiff" (i.e.,
prevent bending).
Figure 3: Examples for coupling tubes.
6.2.4. L
AUNCH
L
UG
M
ECHANICAL
A
TTACHMENT
Launch lugs (i.e., rail guides) should implement "hard points" for mechanical attachment to the launch
vehicle airframe. These hardened/reinforced areas on the vehicle airframe, such as a block of wood
installed on the airframe interior surface where each launch lug attaches, will assist in mitigating lug
"tear outs" during operations.
The aft most launch lug shall support the launch vehicle's fully loaded launch weight while vertical.
At EuRoC, competition officials will require teams to lift their launch vehicles by the rail guides and/or
demonstrate that the bottom guide can hold the vehicle's weight when vertical. This test needs to be
completed successfully before the admittance of the team to Launch Readiness Review.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 30 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0031.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
6.3. RF T
RANSPARENCY
Any internally mounted RF transmitter, receiver or transceiver, not having the applicable antenna or
antennas mounted externally on the airframe, shall employ “RF windows" in the airframe shell plating
(typically glass fibre panels), enabling RF devices with antennas mounted inside the airframe, to
transmit the signal though the airframe shell.
RF windows in the flight vehicle shell shall be a 360° circumference and be at least two body diameters
in length. The internally mounted RF antenna(s) shall be placed at the midpoint of the RF window
section, facilitating maximizing the azimuth radiation pattern.
RF transmitter, receivers or transceivers are not allowed to be mounted externally.
Please note, that even though a single downward facing antenna mounted on a stabilization fin near
the engine seems like a good way to provide nearly a 360° radiation pattern from a single antenna
without significant dead-zones. This is true at any point in time, except when the rocket engine is
active. The ionized exhaust gas from the engine is highly disruptive to RF signals, so degradation or
loss of link is to be expected.
As popular as carbon fibre is for the construction of strong and lightweight airframes, it is also
conductive and will significantly shield and/or degrade RF signals, which is unacceptable. Externally
mounted antennas often provide a more powerful and uniform radiation pattern but finds the flight
vehicle body providing RF dead zones, meaning that at least two antennas on opposite sides of the
airframe are advisable.
RF antennas shall be kept as far away as possible from wiring and metallic structural elements.
Numerous examples of poor installation practice have at a great extent ruined telemetry and link
performances. Teams are highly advised to follow best RF-practices.
6.4. I
DENTIFYING
M
ARKINGS
The team's Team ID (a number assigned by EuRoC prior to the competition event), project name, and
academic affiliation(s) shall be clearly identified on the launch vehicle airframe. The Team ID
especially, will be prominently displayed (preferably visible on all four quadrants of the vehicle, as well
as fore and aft), assisting competition officials to positively identify the project hardware with its
respective team throughout EuRoC.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 31 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0032.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
6.5. O
THER
M
ARKINGS
There are no requirements for airframe coloration or markings beyond those specified in Section 6.4.
of this document. However, EuRoC offers the following recommendations to student teams: mostly
white or lighter tinted colour (e.g., yellow, red, orange, etc.) airframes are especially conducive to
mitigating some of the solar heating experienced in the EuRoC launch environment. Furthermore,
high-visibility schemes (e.g., high-contrast black, orange, red, etc.) and roll patterns (e.g., contrasting
stripes, “V” or “Z” marks, etc.) may allow ground-based
observers to track and record the launch
vehicle’s trajectory with high-power
optics more easily.
7. PAYLOAD
7.1. P
AYLOAD
R
ECOVERY
Payloads may be deployable or remain attached to the launch vehicle throughout the flight.
Deployable payloads shall incorporate an independent recovery system, reducing the payload's
descent velocity to less than 9 m/s before it descends through an altitude of 450 m AGL.
All types of deployable payloads must be authorized by the EuRoC Technical Evaluation Board prior to
the EuRoC. Deployable payloads without two-stage recovery systems (drogue and main chute, like the
rockets) will be subjective to considerable drift during descent.
Note that deployable payloads implementing a parachute or parafoil based recovery system are not
required to comply with the dual-event requirements described in Section 3.1. of this document, being
allowed to utilize a single-stage 8-9m/s descent rate from apogee recovery system, subject to case-
by-case EuRoC approval (the intent being to accommodate certain science/engineering packages
requiring extended airborne mission time).
7.1.1. P
AYLOAD
R
ECOVERY
S
YSTEM
E
LECTRONICS AND
S
AFETY
C
RITICAL
W
IRING
Payloads implementing independent recovery systems shall comply with the same requirements and
goals as the launch vehicle for "redundant electronics" and "safety critical wiring". These requirements
and goals are defined in Sections 3.3. and 3.4. respectively.
7.1.2. P
AYLOAD
R
ECOVERY
S
YSTEM
T
ESTING
Payloads implementing independent recovery systems shall comply with the same requirements and
goals as the launch vehicle for "recovery system testing". These requirements and goals are defined
in Section 3.8..
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 32 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0033.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
7.1.3. D
EPLOYABLE PAYLOAD
GPS T
RACKING
R
EQUIRED
It must be noted that deployable payloads are equivalent to flight vehicle bodies and sections, in that
they can be difficult to locate after landing. All deployable payloads shall feature the same mandatory
GPS tracking system as all rockets and rocket stages as specified in Section 3.5. of this document.
The GPS locator ID must differ from the ID of the launch vehicle.
7.2. P
AYLOAD
E
NERGETIC
D
EVICES
All stored-energy devices (i.e., energetics) used in payload systems shall comply with the energetic
device requirements defined in Section 4. of this document.
8. LAUNCH AND ASCENT TRAJECTORY REQUIREMENTS
8.1. L
AUNCH
A
ZIMUTH AND
E
LEVATION
Launch vehicles shall nominally launch at an elevation angle of 84° ±1° and a launch azimuth defined
by competition officials at EuRoC. Competition officials reserve the right to require certain vehicles'
launch elevation be as low as 70° if flight safety issues are identified during pre-launch activities.
The tolerance expressed within the nominal launch azimuth is intended as nothing more than an
expression of acceptable human error by the operator setting the launch rail elevation prior to launch.
8.2. L
AUNCH
S
TABILITY
Launch vehicles shall have sufficient velocity upon "departing the launch rail" to ensure they will follow
predictable flight paths. In lieu of detailed analysis, a rail departure velocity of at least 30 m/s is
generally acceptable. Alternatively, the team may use detailed analysis to prove stability is achieved
at a lower rail departure velocity 20 m/s either theoretically (e.g., computer simulation) or empirically
(e.g., flight testing).
Teams shall comply with all rules, regulations, and best practices imposed by the authorities at their
chosen test location(s). Departing the launch rail is defined as the first instant in which the launch
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 33 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0034.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
vehicle becomes free to move about the pitch, yaw, or roll axis. This generally occurs at the instant
the last rail guide forward of the vehicle's centre of gravity (CG) separates from the launch rail.
The requirements for team provided launch rails are defined in Section 10. of this document.
8.3. A
SCENT
S
TABILITY
Launch vehicles shall remain "stable" for the entire ascent. Stable is defined as maintaining a static
stability margin of at least 1.5 calibres throughout the whole flight phase (upon leaving the launch
rail), regardless of CG movement due to depleting consumables and shifting centre of pressure (CP)
location due to wave drag effects (which may become significant as low as 0.5 Mach).
8.4. O
VER
-
STABILITY
All launch vehicles should avoid becoming "over-stable" during their ascent. A launch vehicle may be
considered over-stable with a static margin significantly greater than 2 body calibres (e.g., greater than
6 body calibres).
9. EUROC LAUNCH SUPPORT EQUIPMENT
9.1. L
AUNCH
R
AILS
EuRoC will provide standardised launch rails for the teams that do not intend to bring their own launch
rail. One of the EuRoC Launch rails which will generally be near the paddock during Flight Readiness
Reviews for the Launch Rail Fit Check, while three will be at the Launch Site. The vehicle is guided by
a 50 mm x 50 mm cross-section aluminium rail by Kanya (see Figure 4 for details) The launch rail length
is 12 m and the launch rail inclination usually 84±1° to vertical, which may be lowered on a case-by-
case basis if the EuRoC officials deem it necessary. For details on the launch lugs, please see Section
6.2.4..
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 34 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0035.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Figure 4: EuRoC launch rail profile.
9.1.1. L
AUNCH
R
AIL
F
IT
C
HECK
All teams shall perform a “launch rail fit check” as a part of the flight preparations (the
Flight Readiness
Review), before going to the launch range. This requirement is particularly important if a team is not
bringing their own launch rail, but instead relying on EuRoC provided launch rails. Teams shall provide
their own bottom “spacer” to define their vehicles’ vertical position on the rail.
Arriving at the launch rails, only then discovering that a team's launch lugs does not fit the launch rail,
will be considered gross negligence by Mission Control and the EuRoC evaluation board. The launch
rail fit check will ensure that such surprises are not encountered on the launch rails, causing delays
and loss of launch opportunities.
Note:
The launch rail fit check can only be done in the presence of EuRoC officials. Teams cannot use
the EuRoC launch rails without permission, any launch rail related activity shall be duly authorised by
EuRoC officials.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 35 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0036.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
9.2. E
U
R
O
C-
PROVIDED
L
AUNCH
C
ONTROL
S
YSTEM
EuRoC will provide a Launch Control System. The system will be a Wilson F/X Wireless Launch Control
System or equivalent.
The Wilson F/X wireless Launch Control System with one LCU-64x launch control unit and two PBU-8w
encrypted pad relay boxes (more details on Wilson F/X Digital Launch Control Systems may be found
on the Wilson F/X website: www.wilsonfx.com).
10. TEAM-PROVIDED LAUNCH SUPPORT EQUIPMENT
10.1. E
QUIPMENT
P
ORTABILITY
If possible/practicable, teams should make their launch support equipment man-portable over a short
distance (a few hundred metres). Environmental considerations at the launch site permit only limited
vehicle use beyond designated roadways, campgrounds, and basecamp areas.
10.2. L
AUNCH
R
AIL
E
LEVATION
Team provided launch rails shall implement the nominal launch elevation specified in Section 8.1. of
this document and, if adjustable, not permit launch at angles either greater than the nominal elevation
or lower than 70°.
10.3. O
PERATIONAL
R
ANGE
All team provided launch control systems shall be electronically operated and have a maximum
operational range of no less than 650 metres from the launch rail. The maximum operational range is
defined as the range at which launch may be commanded reliably.
10.4. F
AULT
T
OLERANCE AND
A
RMING
All team provided launch control systems shall be at least single fault tolerant by implementing a
removable safety interlock (i.e., a jumper or key to be kept in possession of the arming crew during
arming) in series with the launch switch. Appendix B: Fire Control System Design Guidelines of this
document provides general guidance on assuring fault tolerance in amateur high-power rocketry
launch control systems.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 36 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0037.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
10.5. S
AFETY
C
RITICAL
S
WITCHES
All team provided launch control systems shall implement ignition switches of the momentary,
normally open (also known as "dead man") type so that they will remove the signal when released.
Mercury or "pressure roller" switches are not permitted anywhere in team provided launch control
systems.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 37 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0038.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
APPENDIX A: ACRONYMS, ABBREVIATIONS & TERMS
AA
AGL
APCP
APRS
ANAC
CONOPS
COTS
DTEG
EuRoC
ESRA
FRR
GNSS
GPS
H
HPR
IREC
L
LRR
LOX
P
RF
S
SAC
SRAD
TA
TBD
TBR
TBC
TEB
Actual Apogee
Above Ground Level
Ammonium Perchlorate Composite Propellant
Automatic Packet Reporting System
Portugal’s
National Civil Aviation Authority
Concept of Operations
Commercial of-the-shelf
Design, Test and Evaluation Guide
European Rocketry Challenge
Experimental Sounding Rocket Association
Flight Readiness Review
Global Navigation Satellite System
Global Positioning System
Hybrid
High Power Rocket
Intercollegiate Rocket Engineering Competition
Liquid
Launch Readiness Review
Liquid Oxygen
Points
Radio Frequency
Solid
Spaceport America Cup
Student Researched & Developed
Target Apogee
To be determined or defined
To be resolved
To be confirmed
Technical Evaluation Board
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 38 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0039.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
U
ACS
AGL
APCP
APRS
ANAC
CAS
CONOPS
COPV
COTS
DTEG
EuRoC
ESRA
FRP
GPS
HPR
IREC
LOX
PPE
SRAD
TBD
TBR
Unit, as in Cube-Sat unit
Attitude Control Systems
Above Ground Level
Ammonium Perchlorate Composite Propellant
Automatic Packet Reporting System
Portugal´s National Civil Aviation Authority
Control Actuator System
Concept of Operations
Composite Overwrapped Pressure Vessels
Commercial of-the-shelf
Design, Test and Evaluation Guide
European Rocketry Challenge
Experimental Sounding Rocket Association
Fibre Reinforced Plastics
Global Positioning System
High Power Rocket
Intercollegiate Rocket Engineering Competition
Liquid Oxygen
Personal Protective Equipment
Student Researched & Developed
To be determined or defined
To be resolved
APPENDIX B: FIRE CONTROL SYSTEM DESIGN GUIDELINES
B.1. I
NTRODUCTION
The following white paper is written to illustrate safe fire control system design best practices and
philosophy to student teams participating in the IREC. When it comes to firing (launch) systems for
large amateur rockets, safety is paramount. This is a concept that everyone agrees with, but it is
apparent that few truly appreciate what constitutes a “safe” firing system. Whether they have ever
seen it codified or not, most rocketeers understand the basics:
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 39 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0040.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
The control console should be designed such that two deliberate actions are required to fire
the system;
The system should include a power interrupt such that firing current cannot be sent to the
firing leads while personnel are at the pad and this interrupt should be under the control of
personnel at the pad.
These are good design concepts and if everything is working as it should they result in a perfectly safe
firing system. But “everything is working as it should” is a dangerous assumption to make. Control
consoles bounce around in the backs of trucks during transport. Cables get stepped on, tripped over,
and run over. Switches get sand and grit in them. In other words, components fail. As such there is
one more concept that should be incorporated into the design of a firing system:
The failure of any single component should not compromise the safety of the firing system.
B.2. P
ROPER
F
IRE
C
ONTROL
S
YSTEM
D
ESIGN
P
HILOSOPHY
Let us examine a firing system that may at first glance appear to be simple, well designed, and safe
(Figure 1). If
everything is functioning as designed, this is a perfectly safe firing system, but let’s
examine the system for compliance with proper safe design practices.
The control console should be designed such that two deliberate actions are required to launch the
rocket. Check! There are actually three deliberate actions required at the control console: (1) insert
the key, (2) turn the key to arm the system, (3) press the fire button.
The system should include a power interrupt such that ignition current cannot be sent to the firing
leads while personnel are at the pad and this interrupt should be under control of personnel at the
pad. Check and check! The Firing relay effectively isolates the electric match from the firing power
supply (battery) and as the operator at the pad should have the key in his pocket, there is no way that
a person at the control console can accidentally fire the rocket.
But all of this assumes that everything in the firing system is working as it should. Are there any single
component failures that can cause a compromise in the safety of this system? Yes. In a system that
only has five components beyond the firing lines and e-match, three of those components can fail with
potentially lethal results.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 40 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0041.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Figure 5: A simple high current fire control system.
Firing Relay: If the firing relay was stuck in the ON position: The rocket would fire the moment it was
hooked to the firing lines. This is a serious safety failure with potentially lethal consequences as the
rocket would be igniting with pad personnel in immediate proximity.
Arming Switch: If the arm key switch failed in the ON position simply pushing the fire button would
result in a fired rocket whether intentional or not. This is particularly concerning as the launch key
intended as a safety measure controlled by pad personnel
becomes utterly meaningless. Assuming
all procedures were followed, the launch would go off without a hitch. Regardless, this is a safety
failure as only one action (pressing the fire button) would be required at the control console to launch
the rocket. Such a button press could easily happen by accident. If personnel at the pad were near the
rocket at the time we are again dealing with a potentially lethal outcome
CAT5 Cable: If the CAT5 cable was damaged and had a short in it the firing relay would be closed and
the rocket would fire the moment it was hooked to the firing lines. This too is a potentially lethal safety
failure.
Notice that all three of these failures could result in the rocket being fired while there are still
personnel in immediate proximity to the rocket. A properly designed firing system does not allow
single component failures to have such drastic consequences. Fortunately, the system can be fixed
with relative ease.
Consider the revised system (Figure 6). It has four additional features built into it:
(1) a separate battery to power the relay (as opposed to relying on the primary battery at the pad),
(2) a flip cover over the fire button,
(3) a lamp/buzzer in parallel with the firing leads (to provide a visual/auditory warning in the event
that voltage is present at the firing lines), and
(4) a switch to short-out the firing leads during hook up (pad personnel should turn the shunt switch
ON anytime they approach the rocket).
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 41 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0042.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Figure 6: An improved high current fire control system.
In theory, these simple modifications to the previous firing circuit have addressed all identified single
point failures in the system. The system has 8 components excluding the firing lines and e-match (part
of the rocket itself). Can the failure of any of these components cause an inadvertent firing? That is
the question. Let us examine the consequences of the failure of each of these components.
Fire Button: If the fire button fails in the ON position, there are still two deliberate actions at the
control console required to fire the rocket. (1) The key must be inserted into the arming switch, and
(2) the key must be rotated. The firing will be a bit of a surprise, but it will not result in a safety failure
as all personnel should have been cleared by the time possession of the key is transferred to the Firing
Officer.
Arm Switch: If the arm switch were to fail in the ON position, there are still two deliberate actions at
the control console required to fire the rocket. (1) The cover over the fire button would have to be
removed, and (2) the fire button would have to be pushed. This is not an ideal situation as the system
would appear to function flawlessly even though it is malfunctioning and the key in the possession of
personnel at the launch pad adds nothing to the safety of the overall system. It is for this reason that
the shunting switch should be used. Use of the shunting switch means that any firing current would
be dumped through the shunting switch rather than the e-match until the pad personnel are clear of
the rocket. Thus, personnel at the pad retain a measure of control even in the presence of a
malfunctioning arming switch and grossly negligent use of the control console.
Batteries: If either battery (control console or pad box) fails, firing current cannot get to the e-match
either because the firing relay does not close or because no firing current is available. No fire means
no safety violation.
CAT5 Cable: If the CAT5 cable were to be damaged and shorted, the system would simply not work as
current intended to pull in the firing relay would simply travel through the short. No fire means no
safety violation.
Firing Relay: If the firing relay fails in the ON position the light/buzzer should alert the pad operator of
the failure before he even approaches the pad to hook up the e-match.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 42 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0043.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Shunt switch, Lamp/Buzzer: These are all supplementary safety devices. They are intended as added
layers of safety to protect and/or warn of failures of other system components. Their correct (or
incorrect) function cannot cause an inadvertent firing.
Is this a perfect firing system? No. There is always room for improvement. Lighted switches or similar
features could be added to provide feedback on the health of all components. Support for firings at
multiple launch pads could be included. Support for the fuelling of hybrids and/or liquids could be
required. A wireless data link could provide convenient and easy to set up communications at greater
ranges. The list of desired features is going to be heavily situation dependent and is more likely to be
limited by money than good ideas.
Hopefully the reader is getting the gist: The circuit should be designed such that no single equipment
failure can result in the inadvertent firing of the e-match and thus, the rocket motor. Whether or not
a particular circuit is applicable to any given scenario is beside the larger point that in the event of any
single failure a firing system should always fail safe and never fail in a dangerous manner. No matter
how complicated the system may be, it should be analysed in depth and the failure of any single
component should never result in the firing of a rocket during an unsafe range condition. Note that
this is the bare minimum requirement; ideally, a firing system can handle multiple failures in a safe
manner.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 43 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0044.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
APPENDIX C: OFFICIAL ALTITUDE LOGGING AND TRACKING SYSTEM
C.1. I
NTRODUCTION
This appendix contains mandatory provisions for flight vehicles partaking in the EuRoC competition.
C.1.1. S
COPE
EuRoC calls for a specific system for rocket (flight vehicle) apogee tracking and subsequent
location/recovery of landed vehicles, which this appendix focuses on.
The specific system tested and approved for these tasks is described in further detail in the technical
sections, along with recommendations and lessons learned from the test campaign at the end.
C.1.2. B
ACKGROUND
The fast growth in number of teams attending the EuRoC competition calls for some careful
considerations on how to complete the following two tasks in the most efficient and expedient way:
Providing the EuRoC jury with the means to easily determine and record the apogee altitude
in a fast, efficient, and consistent way. Since the flight vehicle apogee is a fundamental part of
the competition, the method of determining it must be equally fair (hence identical) for all
teams;
Provide the student/recovery teams an efficient means of quickly tracking down the location
of all landed flight vehicles (and any other tracked payload/components), to quickly clear the
launch range.
After careful consideration of what a future-proof solution to the above could look like, EuRoC requires
students to fly a mandatory system for altitude logging and recovery tracking.
C.1.3. R
ATIONALE
While the prime intentions behind instigating a specific mandatory altitude and logging system are
clear, the EuRoC organisation has also put some emphasis on trying to find a solution which will impose
the least amount of inconvenience (in general) on teams.
An example of trying to impose a least amount of inconvenience, for requiring the installation of a
distinct mandatory altitude logging and tracking system is, for example:
Low weight and volume transmitter, to not impede flight vehicle design or performance;
Being cheap and imposing the smallest financial burden possible.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 44 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0045.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
It is the EuRoC organisation main objective to seek out a universally fair and transparent method of
determining apogee, where teams may be separated by only a few meters at apogee.
Furthermore, the EuRoC organisation also focuses on finding a field-rated solution for tracking and
recovering the flight vehicles in the most efficient and expedient manner, minimising at the most the
efforts of, and time spent in the field, trying to locate and recover landed rockets.
C.2. A
LTITUDE
L
OGGING AND TRACKING SYSTEM FUNCTIONAL REQUIREMENTS
C.2.1. A
LTITUDE AND APOGEE REQUIREMENTS
1) The system shall be able to log and store the flight apogee in a non-volatile memory.
Apogee and flight data may still be recoverable after various “unforeseen events”,
such as power-outs or even crashes.
2) The system shall be able to allow the EuRoC Jury to extract the apogee and flight data, using
one fast, efficient, and standardized way, without necessarily requiring student team
assistance.
This means one common system across all flight vehicles, to which the Jury can
extract the needed flight data with one single tool.
3) The system should be able to provide real-time altitude read-outs during flight.
If this data or data stream is captured and logged, it should be possible to reconstruct
the altitude curve and the apogee, in case of a total loss of flight vehicle/data.
4) The system should be able to provide the teams and Jury with a preliminary apogee figure for
quick measure, later to be backed up by detailed recorded flight data.
C.2.2. T
RACKING AND RECOVERY REQUIREMENTS
1)
The system shall consist of a transmitter and a receiver, and the transmitter shall record it’s
position by means of GPS and transmit its location to the receiver.
Both the transmitter and receiver can be transceivers;
More than one transmitter can be employed when the Rules and Regulations call for
it, as required for each stage of multi-stage flight vehicles, as well as for deployable
payloads;
More than one receiver can be employed for various purposes.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 45 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0046.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
2) The system shall as efficiently and directly as possible direct the operator of the receiver to
the landing coordinates of the flight vehicle. This is achieved by the receiver being aware of
the transmitters position (or last
known position), as well as the receiver’s own current
position, through GPS receivers in both devices.
The receiver shall be mobile and transportable (in the operational state) by a single
person, without support.
C.2.3. G
ENERAL REQUIREMENTS
1. The transmitter shall be as small and light as possible, facilitating easy integration into the
flight vehicle and exhibit the least possible mass penalty for flight vehicle mass budgets.
2. The system shall be a commercially available solution, with a history of adequate and reliable
operation, to which EuRoC can acquire and use the organisation’s own receivers.
Teams can fly additional high-end tracking solutions as they please, but EuRoC recovery
crews shall be able to utilize one single type of standardized and fieldprogrammable
system receiver to track and recover all flight vehicles launched.
3. The system shall be field-programmable with regards to RF operating frequency.
Unexpected launch slot re-shuffling may suddenly necessitate a likewise re-shuffling
of GPS tracking system operating frequencies;
“Field-programmable” may include the use of additional equipment, such as a laptop,
to accomplish the task of changing frequencies.
4. The transmitter shall be mounted internally in the flight vehicle, at the location of an
“RFtransparent” section, unless the transmitter features an externally mounted antenna.
No external mounting allowed.
5. The system should be capable of performing its function without the support of other services,
such as mobile cell networks, online web-services, or online apps.
A self-reliant, enclosed, stand-alone system is well suited for field operations, with
intermittent or lacking mobile services (where delicate laptops, wired breakout
boards, and web-based apps are not).
6. The receiver display should be clearly readable in bright sunlight.
Backlit screens and displays can be difficult to read under clear skies and full sun
conditions.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 46 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0047.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
7. The receiver should, to the extent possible, be ruggedized for extended periods of field use.
The receiver and its operator may likely experience a bumpy and dusty cross-country
excursion, while conducting the recovery effort;
The receiver should be able to operate continuously throughout a day.
8. The system should be cheap and affordable to the extent possible, where it does not impact
reliability or function.
Affordable and adequate performance is favoured over fancy and expensive
alternatives.
C.3. M
ANDATORY
A
LTITUDE
L
OGGING AND TRACKING SYSTEM
C.3.1. E
GGTIMER
TRS F
LIGHT
C
OMPUTER
Figure 7: Eggtimer TRS Flight Computer (assembled). (Source: Eggtimer)
Single-stage flight vehicles and upper-most stages of flight vehicles shall feature an operational
Eggtimer TRS Flight Computer for official altitude logging and GPS tracking.
The competition achieved apogee will be determined from this device.
Note:
Deployable payloads and lower stages also require a mandatory Eggfinder GPS tracking device,
but this need not be the TRS Flight Computer. See section C.4.5. for details.
The Eggtimer TRS (Total Recovery System) Flight Computer combines several useful systems in one
device, fulfilling the requirements outlined in section C.2.:
A COTS dual-channel deployment computer;
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 47 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0048.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Barometric pressure sensor for apogee determination and recovery systems deployment;
A non-volatile memory for recording flight data (including altitude) over the full flight
duration.
GPS tracking functionality and a tracking transmitter.
The TRS Flight Computer comes as a kit (PCB, components and some sub-assemblies) and requires
component mounting and testing.
C.3.1.1. TRS F
LIGHT
C
OMPUTER FIRMWARE UPDATE
Teams must ensure that the TRS Flight Computer is running a custom version of the firmware for the
70 cm Ham frequency band, having a channel selection resolution of 25 kHz. This is necessary in order
to be able to select the frequencies allotted to EuRoC.
Please note that firmware updates can be done at any time by participating teams, as long as the
hardware has been procured.
See section C.4. for further details on firmware.
C.3.1.2. T
HE
TRS F
LIGHT
C
OMPUTER IS ELIGIBLE AS THE REDUNDANT
COTS
DEPLOYMENT ELECTRONICS
As per the “Redundant COTS Recovery Electronics” section in the EuRoC Design Guide, the TRS Flight
Computer fulfils this requirement and can be used as the redundant recovery system electronics
subsystem.
C.3.1.3. TRS F
LIGHT
C
OMPUTER OPERATING FREQUENCY ALLOCATION
The EuRoC organisation will allocate TRS Flight Computer operating frequencies to teams no less than
24 hours prior to the Flight Readiness Review. This includes the frequency for the upper-most stage of
the flight vehicle, as well as any other frequencies for lower stages and/or deployable payloads.
Teams must however be capable of (and prepared to) re-program their operating frequencies of
Eggtimer/finder equipment at short notice in case launch schedule reshuffling requires it so.
C.3.1.4. E
U
R
O
C M
ISSION CONTROL
E
GGFINDER
LCD
HANDHELD RECEIVERS
The EuRoC organisation will field a selection of fully upgraded Eggfinder LCD handheld receivers, to be
placed at Mission Control for the duration of the launch campaign:
Four units of Ham-version LCD handheld receivers with LCD-GPS and custom field-use
enclosure upgrade;
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 48 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0049.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
One unit of EU license free version LCD handheld receiver with LCD-GPS and custom field-use
enclosure upgrade.
Up to five of these LCD handheld receivers will be tuned to the individual TRS Flight Computer
transmission frequencies of the flight vehicles scheduled for launch, at each launch slot.
As each rocket launches, each of the EuRoC operated tuned LCD receivers may be connected to a
tripod with high gain directional antennas at mission control. The aim is to receive live telemetry and
altitude data even at 9 km altitude and track the flight vehicle until loss of line-of-sight at very low
altitude. The procedure is predicted to be as follows:
Mission Control will know the flight vehicle assigned operating frequency (or frequencies) and
program the EuRoC operated LCD receivers during launch preparations;
The reception of valid TRS Flight Computer telemetry will be verified prior to (or during) the
Launch Readiness Review, performed at the launch rail;
Mission Control will track the TRS Flight Computer of each flight vehicle during the entire
flight, using high gain antennas at Mission Control, until potential loss of signal, due to loss of
line-of-sight at very low altitude;
Mission control will record the last known GPS coordinates at mission control for reference;
All EuRoC LCD handheld receivers will stay powered while recovery operations are running;
Teams shall each have at least one tracking receiver. Several can be advantageous for more
efficient tracking and recovery;
Recovery teams will change LCD handheld receiver operating frequencies in the field, as
necessary to recover all jettisoned stages and/or deployable payloads;
Teams may leave their TRS Flight Computer powered during recovery and transportation back
to Mission Control, provided that any recovery systems are brought back into a safe state,
where actuation of recovery systems (regardless of status) is prevented;
A representative of the EuRoC organisation will inspect the recovered flight vehicles at Mission
Control and extract flight data and apogee from the TRS Flight Computer, as possible.
C.3.1.5. O
THER ALTITUDE LOGGING AND
GPS
TRACKING SYSTEMS
Teams are welcome to operate and fly one or more of their own altitude logging and/or GPS tracking
solutions, in addition to the mandatory systems, described in this addendum.
Such systems may have superior performance or range compared to the selected mandatory Eggtimer
systems, but this does not exempt teams from implementing the mandatory systems.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 49 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0050.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Again, the EuRoC organisation is firm on testing and validating a system and procedures for the fair,
equal and transparent recording of apogees, and the implementation of efficient tracking and
recovery operations.
C.3.2. E
U
R
O
C
TESTING OF THE
E
GGTIMER
TRS F
LIGHT
C
OMPUTER
The EuRoC organisation conducted both GPS tracking field tests as well as simulated flight tests, using
a vacuum chamber. A short summary of the tests used to evaluate and approve the Eggtimer TRS Flight
Computer (and other Eggfinder products) is outlined as follows.
Note:
The testing was performed using the EU license free frequency version of the Eggtimer product
line (869 MHz range), hence the expected range of the 433 MHz range Ham-version products is
expected to be roughly double of what is described below.
The entire Eggfinder range of GPS tracking solutions, as well as the TRS Flight Computer, utilizes the
same half-duplex RF module for telemetry. As expected, range performance has been found to be
similar for all products.
C.3.2.1. O
N
-
GROUND
GPS
TRACKING TESTS
Two cases of worst-case scenario testing were carried out:
An Eggfinder TX was placed in a wet crop field, 10 cm off the ground (line of sight), with the
aim of having the wet vegetation attenuating the RF link as much as possible;
An Eggfinder TX was placed at a tree stub in a rugged and heavily forested area.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 50 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0051.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Figure 8: Eggfinder TX placed in wet crop field at a distance of 530 meters (heavy digital zoom; red arrow marks TX
location).
(Source: Jacob Larsen)
Figure 9: Another worst-case scenario: A rugged and heavily forested test area. (Source: Jacob Larsen)
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 51 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0052.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
While the crop field test illustrated in Figure 8 did feature line-of-sight between TX transmitter and
LCD handheld receiver, ground effects and wet vegetation should provide a challenging test setup.
Test results indicated that the RF-link range was about 500 meters with a wire antenna on the TX and
an Eggtimer supplied 3 dB stub antenna, as illustrated in Figure 10.
The forest test range limitation was primarily governed by loss of line-of-sight, due to bumpy terrain,
while wet tree trunks were also identified as efficient signal attenuators.
Circling the transmitter in the forest revealed a consistent RF-link range of about 300 meters,
regardless of terrain and foliage.
It can thus be concluded, that at the absolute worst-case scenario of an 869 MHz EU licence free
version in a forest, an LCD handheld receiver will pick up the RF-link signal at a minimum distance of
300 meters, regardless of conditions.
If getting within 300 meters of a GPS transmitter, the LCD handheld receiver will pick up the tracking
signal, no matter what terrain it is in.
433 MHz “Ham” versions are expected to exhibit about twice the range of the above.
Figure 10: LCD handheld receiver detects GPS transmitter at a distance of 530 meters.
(custom enclosure, 3dB stub antenna, SMA board connector options) (Source: Jacob Larsen)
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 52 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0053.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
C.3.2.2. A
IR
-
TO
-
GROUND
GPS
TRACKING TESTS
No air-to-ground GPS tracking tests have been conducted as of time of writing. The manufacturer
indicates about 15 km of line-of-sight aerial range with the Ham-version and a stub antenna. About
half that with the EU license free 869 MHz version.
Based on the above, lack of range of the Eggfinder equipment is not currently a concern.
C.3.2.3. TRS F
LIGHT
C
OMPUTER SIMULATED FLIGHT TEST
In the interest of testing and validating the performance of the TRS Flight Computer, a simulated flight
test case was devised, using a vacuum chamber to simulate the ambient pressure drop experienced
during ascent.
The test objectives were as follows:
To simulate a trajectory the TRS Flight Computer would interpret as a real launch;
To record flight and altitude data onboard the TRS non-volatile memory;
To rehearse and gain experience with the TRS Flight Computer arming sequence;
To rehearse the interpretation of downlink telemetry and flight events displayed at the LCD
handheld receiver;
To rehearse downloading and visualizing the flight data stored in the TRS Flight Computer non-
volatile memory.
The test consisted of quickly drawing a vacuum to simulate ascent and then gradually opening a
manual bleed valve to simulate apogee and descent.
The flight data is easily downloaded from the TRS Flight Computer, using a laptop and the USB/TTL
UART data cable. The data is downloaded and saved into a log file as comma separated ascii values,
using a terminal program.
Figure 11 illustrates the flight data imported into an excel spreadsheet and displayed in a suitable
graph format.
There are two things to note in Figure 11:
All altitudes and velocity data from the TRS Flight Computer are displayed and logged in units
of feet and feet/sec. The TRS Flight Computer is not capable of transmitting and/or recording
flight data in metric units.
o
This is in stark contrast to the GPS and tracking data downrange displayed on the LCD
handheld receiver, which can be switched between feet and meters.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 53 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0054.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
The drogue deployment is delayed, contrary to supposed to happen at “nose-over”, due to an
artifact of the test setup. The apogee is a discontinuous kink in the pressure profile, in contrast
to the continuous inverted parabola expected. The flight computer waits for one second of
vertical velocity below 100 ft/sec, before it arms and fires the drogue pyro channel. This is why
the drogue deployment event does not happen at nose-over in the below test.
o
The TRS Flight Computer deployment channels work as advertised. It is the test setup
which is not capable of generating a smooth simulated apogee.
TRS Flight Computer simulated flight test using vacuum
chamber: Test 4
14400, 11410
12000
10000
8000
21950, 10656
1500
1000
500
6000
4000
2000
0
60950, 1496
0
-500
-1000
-1500
120000
0
20000
40000
60000
80000
100000
Time [ms]
Filtered_Alt
Drogue deploy
Apogee
Main deploy
Nose-over
Filtered:Veloc
Figure 11: TRS downloaded flight data visualization from vacuum chamber test #4, 1500 feet main deployment set
(delayed drogue deployment event is an artifact of having too sharp a kink at apogee). (Source: Jacob Larsen)
C.4. M
ANDATORY SYSTEM
K
EYPOINTS
,
RECOMMENDATIONS AND REQUIREMENTS SUMMARY
C.4.1. M
ANDATORY ALTITUDE LOGGING AND GPS TRACKING SYSTEM
For single-stage flight vehicles (and upper-most stage vehicles), the mandatory Official Altitude
Logging and Tracking device to be installed is the Eggtimer TRS Flight Computer.
The TRS (Total Recovery System) device combines:
o
A COTS dual-channel deployment computer;
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 54 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0055.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
o
o
Barometric pressure sensor for apogee determination and recovery systems
deployment;
A non-volatile memory for recording flight data over the full flight duration;
o
GPS
tracking and recovery transmitter.
C.4.2. TRS F
LIGHT
C
OMPUTER
F
REQUENCY
R
ANGE
EuRoC will make specific frequencies available for tracking system use, without the need for specific
radio amateur licenses. Eggtimer Ham-frequency equipment can thus legally be used during EuRoC
without a license. This means that all mandatory TRS Flight Computers MUST be purchased in the US
“Ham” frequency range.
The recommended package to buy is (approximately $200):
o
o
The “Eggtimer TRS/LCD Starter set, 70cm Ham versions” (includes data cable +
terminal blocks + external antennas) at $168 (2021 price).
The “Eggfinder LCD-GPS module kit” at $40 (2021 price).
C.4.3. “EU”
TRS F
LIGHT
C
OMPUTER VERSIONS
While the “EU” license free version of the TRS sounds like a compelling option, there is a major
drawback in the fact, that the EU license free band contains only three separate channels/frequencies
(and TRS systems cannot share the same frequency).
This is a major problem since multiple flight vehicles will be sitting on the launch rails at the opening
of a launch window. These vehicles will (when engine technology permits) be launched successively,
as soon as the previous flight vehicle is believed landed, with no time for additional pre-flight
preparations in between launches.
Therefore purchasing the “EU” version of the TRS
Flight Computer is highly discouraged,
despite being legal to use;
However, for teams or flight vehicles already having an “EU”-frequency
versions of Eggtimer
products, these “EU” frequency systems can be flown at EuRoC as a replacement for the
“HAM” frequency version. The EuRoC organization only has one “EU” compatible receiver,
limiting its use.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 55 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0056.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
C.4.4. P
ROCUREMENT OF
TRS
COMPATIBLE RECEIVER
(
S
)
While teams are not required to procure one or more receivers for the Eggfinder “Ham-version” TRS
Flight Computer, according to the EuRoC Rules and Requirements, teams are strongly encouraged to
procure the above “full kit package”.
The TRS Flight Computer is best programmed wirelessly from the LCD receiver while firmware
updating, and flight data download happens via the USB-serial adaptor data cable (included
in package).
The LCD receiver has several test functions (including deployment channel testing) which are
very useful.
Having an LCD receiver allows teams to train both programming of the TRS Flight Computer
as well as GPS tracking.
It is difficult to underscore how much easier the GPS tracking and location becomes with the
LCD-GPS
module kit addition to the LCD receiver. Don’t forget to order it.
It is not encouraged to add the Bluetooth option, as the LCD-GPS programming port is much
more useful in the wired configuration. An openlogger module can alternatively be installed
to capture and store all received telemetry. This is very useful for post-flight analysis,
especially of the vehicle is lost.
C.4.5. M
ANDATORY
GPS
TRACKING SYSTEMS FOR DEPLOYABLE PAYLOADS OR STAGES
While the upper-most stage of any multi-stage flight vehicle, as well as any single-stage flight vehicle,
must feature the mandatory Eggfinder TRS Flight Computer for official altitude recording and GPS
tracking, this is not the case for deployable payloads or stages.
It is still mandatory to implement a Eggfinder GPS tracking device for lower stages and deployable
payloads, as the EuRoC operated LCD handheld receivers (or student operated LCD receivers) can be
reprogrammed in the field to track each flight vehicle component.
While the Eggtimer TRS Flight Computer can be utilized in all stages and deployable payloads, there
are some simpler, smaller and cheaper compatible alternatives for lower stages and deployable
payloads:
The Eggfinder TX and TX-mini GPS tracking transmitters are fully eligible for tracking and
location any lower stages or deployable payloads.
The Eggfinder TX and TX-mini transmitters enable EuRoC recovery teams to track and locate
lower stages and deployable payloads, using already available LCD handheld receivers, while
the flight data and apogee of such stages and payloads are not relevant to team scoring.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 56 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0057.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
The Eggfinder LCD receivers are fully compatible with the TX and TX-mini and can be used to
easily program the RF frequency of these transmitters.
C.4.6. U
P
-
TIME REQUIREMENTS OF TRANSMITTERS
The following requirements pertain to the mandatory Eggtimer TRS Flight Computer, TX, TX-mini and
LCD receivers:
The battery capacity of the various Eggtimer/finder transmitters must be sufficient to keep the
GPS tracking systems running continually for at least 12 hours.
C.4.7. U
PDATING FIRMWARE TO THE CUSTOM
25
K
H
Z CHANNEL STEP VERSION
Due to the differences of EU and the US, the frequencies allotted by the Portuguese authorities,
channel
centre frequencies may lie at frequencies “odd” to the US Ham system. Consequently,
students will have to update the firmware of the TRS Flight Computer (and any LCD-GPS receivers)
with a special firmware version capable of 25 kHz channel selection.
The TRS firmware update is described in the “How to update the Eggtimer TRS firmware” document
at the Eggtimer support web page.
Direct link:
http://eggtimerrocketry.com/wp-content/uploads/2018/06/Eggtimer_TRS_Flash_
Update_Instructions1.pdf
Likewise,
there
is
a
document
for
updating
the
LCD-GPS
firmware:
http://eggtimerrocketry.com/wpcontent/uploads/2020/04/Eggfinder-LCD-Flash-Update-
Instructions-1.pdf
Both firmware updates were performed as a part of testing the system, since both devices were
delivered with outdated firmware. The flashing procedure uses the USB data cable and should not
present a challenge to student teams.
C.4.8. TRS F
LIGHT
C
OMPUTER SAMPLE FILE
A sample file captured from a TRS Flight Computer illustrates the recorded data (GPS location and
some NMEA sentences deleted or redacted for clarity). Worthwhile noting, besides the standard
NMEA sentences:
{DM}
is deployment status
o
D for
undeployed drogue chute
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 57 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0058.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
o
d for deployed drogue chute
o
M for undeployed main chute
o
m for deployed main chute
<2>,<-6>
(or other varying number) is the barometric altitude in feet at any time.
<1015>, <1015>
(repeated) is the achieved apogee
This achieved apogee term is however not broadcasted before the TLS Flight Computer has
determined that the rocket has landed. A landing event is determined as an altitude of less
than 30 feet above ground level for 5 seconds, or alternately when the TRS runs out of flight
memory.
@JSL EggTimer@
$GPGGA,211127.000,XXXX.7710,N,0XXXX.4560,E,1,05,3.7,23.1,M,41.8,M,,0000*6C
$GPGSA,A,3,13,15,05,23,18,,,,,,,,4.8,3.7,3.1*33
$GPRMC,211127.000,A,XXXX.7710,N,0XXXX.4560,E,0.42,222.64,140821,,,A*6A
{DM}
<2>
@JSL EggTimer@
$GPGGA,211128.000,XXXX.7709,N,0XXXX.4569,E,1,05,3.7,23.1,M,41.8,M,,0000*62
$GPGSA,A,3,13,15,05,23,18,,,,,,,,4.8,3.7,3.1*33
$GPRMC,211128.000,A,XXXX.7709,N,0XXXX.4569,E,0.30,222.64,140821,,,A*61
{dm}
<-6>
@JSL EggTimer@
$GPGGA,211131.000,XXXX.7709,N,0XXXX.4571,E,1,05,3.7,23.0,M,41.8,M,,0000*62
$GPGSA,A,3,13,15,05,23,18,,,,,,,,4.8,3.7,3.1*33
$GPRMC,211131.000,A,XXXX.7709,N,0XXXX.4571,E,0.00,222.64,140821,,,A*63
{dm}
<1015>
@JSL EggTimer@
$GPGGA,211134.000,XXXX.7709,N,0XXXX.4571,E,1,05,3.7,23.0,M,41.8,M,,0000*67
$GPGSA,A,3,13,15,05,23,18,,,,,,,,4.8,3.7,3.1*33
$GPRMC,211134.000,A,XXXX.7709,N,0XXXX.4571,E,0.00,222.64,140821,,,A*66
{dm}
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 58 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0059.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
<1015>
C.4.9. LCD
HANDHELD RECEIVER
Figure 12: LCD handheld receiver with backlight and custom 3D printed enclosure. (Source: Jacob Larsen)
The LCD handheld receiver is well described in this document, thus this section focuses only on
observations and specific characteristics of the device.
It is necessary to wipe the EEPROM flight memory before use, according to the LCD receiver
user guide.
As illustrated in Figure 12, the backlight option in the LCD handheld receiver is very useful
after dark, if it is not excessively bright. An 86 Ohm series resistor had to be fitted on the leads
going to the backlight, which also brings the back light current consumption down to about 20
mA.
Without this series resistor, the backlight acts like a blinding flood light, gulping up about 200
mA in the process.
The programming port on the rear face of the LCD handheld receiver PCB can be used to log
downlink telemetry data from the TRS Flight Computer, using a USB/TTL UART data cable,
although less elegant than the RX receiver solution outlined in section C.7.. Another
recommended solution is to install an openlog breakout board for telemetry capture.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 59 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0060.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Figure 13: A USB/TTL UART data cable can be used to record TRS Flight Computer downlink data to a laptop.
(Source: Jacob Larsen)
C.5. E
GGTIMER
TRS
ALTITUDE LOGGING AND
GPS
TRACKING SYSTEM
L
ESSONS
L
EARNED
Based on previous editions of EuRoC a number of findings, advantages, disadvantages, and risks for
the mandatory (Eggtimer TRS based) altitude logging and GPS tracking system have been compiled
below (in no particular order):
When properly implemented, the GPS tracing performance is excellent. A rocket which
unintentionally deployed its main chute at an altitude of 9593 meters was continuously
tracked until horizon dependent loss of line-of-sight, at a downrange of 27 kilometers, using a
cheap type 5-element Yagi antenna.
The biggest drawback of the Eggtimer system is that the quality control is left up to the
students assembling and testing the correct performance and tracking range of the system.
This responsibility of inspecting own work and validating performance cannot be overstated.
In some of the worst cases seen, GPS tracking telemetry was lost a little over 100 meters past
the Mission Control tent, which corresponds to the RF-module output not being electrically
connected to the transmitter antenna trace (or very bad installation and RF practices). Such
serious issues will be discovered with rudimentary range testing and performance assessment;
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 60 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0061.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
The Eggtimer TRS documentation quality is lacking. The EuRoC organization will require a
significant improvement of the documentation from the manufacturer, or as a minimum
interact with the manufacturer until all functionality is understood, such that it can be clearly
communicated to teams;
The Eggtimer TRS system requires training and accumulation of experience to realize its full
potential, which is considerable, once full system understanding is achieved. It is a cheap field-
programmable, 2-channel deployment computer, with position and altitude downlink,
deployment test features, e-match continuity checking, stand-alone GPS tracking receiver and
flight data recorder;
Print a rugged case for the LCD tracking receiver and let that one have the experience of
constant exposure to fine flying dust and rattling around in the bottom of an army truck going
off-road in the attempts of recovering a stray rocket, instead of your mint condition Macbook.
Link
to
free
printable
LCD
tracking
receiver
enclosure:
https://www.dropbox.com/sh/i1p1tfhbfjeivvw/AAD5kwoKUdgcNXBqD6kyJ7W4a?dl=0
Appoint a dedicated GPS tracking and recovery responsible team member along with 3-4
recovery team members. Field-train and drill the recovery team in quickly and efficiently
tracking down the rocket, by having team members (not part of the recovery team) place the
rocket in unknown locations and have the recovery team do a series of increasingly
challenging tracking challenges;
Re-acquiring a GPS tracking signal given only an approximate heading and a 3-5 kilometer
downrange is quite challenging. Finding a rocket in thick vegetation without a functional GPS
tracking signal and a handheld tracking receiver is close to impossible. Both scenarios have
proved to be surprisingly common at EuRoC;
It is highly recommended to integrate an openlogger breakout board in the back of the
Eggtimer LCD receiver. This means that the human readable ASCII telemetry downlink data
stream can be captured for post-flight analysis, even in the event of an in-flight failure leading
to a total loss of the vehicle. Besides GPS NMEA sentences, the TRS data downlink barometric
altitude and recovery system deployment events.
A cheap and widely available directional 5-element Yagi antenna with UHF-SMA adaptor cable
does wonders for the tracking range.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 61 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0062.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Figure 14: Yagi 5-element high gain antenna.
C.6. C
USTOM
3D
PRINTED
LCD
RECEIVER ENCLOSURE
A convenient custom enclosure was developed and refined as a part of the Eggtimer/Eggfinder test
campaign, in order to ruggedize the LCD handheld receiver for field use.
The manufacturer’s plastic enclosure and installation of the LCD
receiver in an odd-sized rectangular
box called for something more refined.
The stl-files are for free printing and use, as well as a step-file model of the enclosure design being
available for reference. The latest version files can also be retrieved from the following Dropbox link,
until further notice:
https://www.dropbox.com/sh/i1p1tfhbfjeivvw/AAD5kwoKUdgcNXBqD6kyJ7W4a?dl=0.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 62 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0063.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Figure 15: Updated ruggedized custom enclosure for the LCD handheld receiver. (Source: Jacob Larsen)
Relevant details, in no particular order:
This enclosure design is free for printing and use;
The “CS” is a reference to Copenhagen Suborbitals (www.copsub.com);
The red pushbutton is included in the Eggfinder LCD handheld receiver kit;
A double pole, double throw switch, switches power and backlight on and off simultaneously;
The design consists of three parts:
o
Front section;
o
Rear section;
o
Battery cap (snaps into place).
The rear section contains an opening, providing access to the programming port, which is used
to program TX, Mini or RX operating frequencies;
Put a piece of tape over the opening when not in use. It keeps the dirt out of the unit.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 63 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0064.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Figure 1: Blue recess and dark grey notch mating scheme. (Source: Jacob Larsen)
The front and rear enclosure mates accurately using a notch-and-recess fit. Put a few drops of
glue in there, if you want to assemble the enclosure permanently;
The GPS-LCD module add-on is conveniently soldered to the LCD receiver PCB using a 3-pin
header.
Figure 18: Crude CAD model of LCD receiver PCBs, with LCD-GPS module add-on soldered in place.
(Source: Jacob Larsen and Eggtimer)
Eight PCB mounting points are integrated into the front and rear enclosures. Tap M3 threading
in all eight and fit each of the two LCD receiver PCBs in their respective enclosure segments,
using countersunk M3x6mm countersunk screws with reduced head.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 64 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0065.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Figure 19: Rear section illustrating the programming port opening and where to tap M3 threading. (Source: Jacob Larsen)
The battery compartment fits a 2S 1900 mAh LiPo battery with measures 115 x 34 x 18 mm,
which should provide about 18 hours of operation per charge. The printed battery
compartment cap clicks nicely into position.
Do not print this enclosure using carbon fibre reinforced plastics, since the conductivity of the carbon
fibre may negatively impact the internal GPS receiver sensitivity.
C.7. N
OTES ON ADDITIONAL TESTED
E
GGFINDER DEVICES
This section lists some findings on tested Eggfinder equipments, other than the TRS Flight Computer.
C.7.1. E
GGFINDER
TX T
RANSMITTER
Figure 20: Eggfinder TX transmitter. (Source: Eggtimer)
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 65 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0066.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
The Eggfinder TX transmitter is a simple and useful GPS tracking transmitter. Some observations made
during assembly and testing:
The device is quite simple and just transmits the onboard GPS NMEA sentences at 9600 baud,
to any receiver listening.
It has the added advantage that it features PCB space for an Openlogger device, if one wants
to log whatever is transmitted onboard. (Eggtimer stock Openloggers)
The TX transmitter will accommodate a SMA PCB edge-connector, required for external
antennas, contrary to the Mini transmitter. (Eggtimer stocks SMA PCB edge connectors).
The RF module of the tested device would not transmit anything, until the RF module
frequency was reprogrammed, using the LCD handheld receiver and the included 3-wire
programming cable. It worked flawlessly since then.
The TX transmitter has an included jumper for setting it into programming mode. This is
contrary to the Mini transmitter, which utilizes inconvenient solder jumpers.
C.7.2. E
GGFINDER
TX-
MINI TRANSMITTER
Figure 21: Eggfinder Mini transmitter. (Source: Eggtimer)
The Eggfinder Mini transmitter is a smaller version of the TX transmitter, intended for very small
rockets. Some observations made during assembly and testing:
The Mini transmitter uses solder jumpers for putting the device either in programming or
running mode. This is inconvenient in the event of having to change the RF-link frequency in
the field.
This device cannot accommodate an SMA PCB edge connector. It is stuck with the little stub
antenna.
Some issues were encountered as difficulties with getting good solder joints between the PCB
and the GPS module.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 66 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0067.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
The Mini transmitter, with its short stub antenna, had a very similar RF-link range, compared
to the TX transmitter with a wire antenna.
C.7.3. E
GGFINDER
RX
DONGLE
RECEIVER
Figure 22: Eggfinder RX "dongle" receiver. (Source: Eggtimer)
The RX receiver is potentially a useful device, considering how inexpensive it is. Some observations
made during assembly and testing:
The RX receiver is very inexpensive due to the lack of a GPS receiver.
The RX receiver is available in both a Bluetooth and a USB cable option, of which the latter
seems more useful.
The RX receiver frequency is easily programmed with an LCD handheld receiver and the
included 3-wire programming cable.
The “USB version” of the RX receiver can be powered directly from a laptop, if using a USB/TTL
UART data cable (included). No other accessories required.
The RX receiver (USB cable version) and a laptop makes for an excellent TRS Flight Computer
standalone telemetry backup data logger. While the TRS Flight Computer logs high-speed flight data
to onboard non-volatile EEPROM, said EEPROM may in some unfortunate incidents disintegrate upon
“landing”, taking the recorded flight data with it into oblivion.
If an RX receiver has logged the telemetry, which also includes the altitude reading from the TRS Flight
Computer barometric pressure sensor, the trajectory and apogee may be reconstructed from these
data, enabling the EuRoC Jury to award points for achieved apogee.
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 67 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0068.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
APPENDIX D: FLIGHT READINESS REVIEW CHECKLIST
Table 3: Flight Readiness Review checklist.
S
ECTION
D
ESCRIPTION
PROPULSION SYSTEMS
Upon request, the flier should provide the inspector
with hardcopy checklist procedures for the
propulsion system's safe handling, assembly,
disassembly, and operation (both nominal and
offnominal/contingency
flows)
including
selfinspection/verification steps which make
individual team members accountable to one
another for having completed the preceding
process(es).
A
CTIONS TO BE TAKEN
Checklist
Simple confirmation
Inspection on site
Launch vehicles entering EuRoC shall use non-toxic
propellants. Ammonium perchlorate composite
propellant (APCP), potassium nitrate and sugar (also
known as "rocket candy"), nitrous oxide, liquid
oxygen (LOX), hydrogen peroxide, kerosene,
propane, alcohol, and similar substances, are all
Non-toxic Propellants
considered non-toxic. Toxic propellants are defined
as those requiring breathing apparatus, unique
storage and transport infrastructure, extensive
personal protective equipment (PPE), etc.
Homemade propellant mixtures containing any
fraction of toxic propellants are also prohibited.
The sum of all rocket stages' impulse must either
not exceed 40,960 newton-seconds, or the Flier
must have previously consulted with EuRoC on
provisions for launching a larger rocket.
The design must provide for positive retention of
the propulsion system within the airframe - leaving
no possibility for the propulsion system to shift from
its retaining device(s) and jettison itself.
A "structural chain" that transfers the propulsion
system thrust to various points on the rocket
structure must exist and it must be capable of
withstand these loads.
Simple confirmation
Total Impulse
Simple confirmation
Motor Retention
Inspection on site
Proof by reasoned
argumentation
Inspection on site
Proof by reasoned
argumentation
Thrust Structure
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 68 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0069.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Thrust Curve
Upon request, the flier must provide the inspector
with hardcopy thrust curve data for each individual
rocket motor or engine implemented.
Proof by calculation
P
ROPULSION
S
YSTEM
S
AFING AND
A
RMING
Upon request, the flier should provide the inspector
with hardcopy checklist procedures for any of the
propulsion system's unique final on-pad
preparations, pre-flight, and launch (both nominal
and off-nominal/abort/mishap flows) - including
self-inspection/verification steps which make
individual team members accountable to one
another for having completed the preceding
process(es).
Pre-flight and
Countdown
Procedure
Simple confirmation
Inspection on site
All ground-started propulsion system ignition
circuits/sequences shall not be "armed" until all
personnel are at least 15 m away from the launch
vehicle. The provided launch control system
satisfies this requirement by implementing a
removable "safety jumper" in series with the pad
Ground-start Ignition
relay box's power supply. The removal of this single
Circuit Arming
jumper prevents firing current from being sent to
any of the launch rails associated with that pad relay
box. Furthermore, access to the socket allowing
insertion of the jumper is controlled via multiple
physical locks to ensure that all parties have positive
control of their own safety.
All upper stage (i.e., air-start) propulsion systems
shall be armed by launch detection (e.g.,
accelerometers, zero separation force [ZSF]
Air-start
Ignition
electrical shunt connections, break-wires, or other
Circuit Arming
similar methods). Regardless of implementation,
this arming function will prevent the upper stage
from arming in the event of a misfire.
Hybrid and liquid propulsion systems shall
Propellant Offloading implement a means for remotely controlled venting
or offloading of all liquid and gaseous propellants in
After Launch Abort
the event of a launch abort.
Simple check
Proof by reasoned
argumentation
Inspection on site
Proof by reasoned
argumentation
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 69 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0070.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
All upper stage ignition systems shall comply with
same requirements and goals for "redundant
Air-start
Ignition electronics" and "safety critical wiring" as recovery
systems
understanding that in this case
Circuit Electronics
"initiation" refers to upper stage ignition rather
than a recovery event.
Staging Ignition
Commit Criteria
Positive State
Indication
The electronics controlling the various staging
events must inhibit staging if the rockets' flight
profile deviates from predicted nominal behaviour.
Each independent set of electronics controlling
staging events must provide sensory (i.e., visual or
auditory) indication of its activation.
Simple confirmation
Inspection on site
Proof by reasoned
argumentation
Simple confirmation
Inspection on site
The electronics controlling stage ignition in design's
implementing "drag-separation" must not be
Special Consideration
located in the separating stage - where premature
for "Drag Separation"
separation could prevent ignition of the following
stage.
SRAD P
ROPULSION
S
YSTEM
T
ESTING
SRAD and modified COTS propulsion system
combustion chambers shall be designed and tested
according to the SRAD pressure vessel requirements
defined in Section 4.2. Note that combustion
chambers are exempted from the requirement for a
relief device.
SRAD and modified COTS propulsion systems using
liquid propellant(s) shall successfully (without
significant anomalies) have completed a propellant
loading and off-loading test in "launch-
configuration", prior to the rocket being brought to
the competition. This test may be conducted using
either actual propellant(s) or suitable proxy fluids,
with the test results to be considered a mandatory
deliverable and an annex to the Technical Report, in
the form of a loading and off-loading checklist,
complete with dates, signatures (at least three) and
a statement of a successful test. Failure to deliver
this annex will automatically result in a “denied”
flight status. Loading and unloading of liquid
propellants must be a well-drilled, safe and efficient
operation at the competition launch rails.
European Rocketry Challenge
Design, Test & Evaluation Guide
Simple confirmation
Inspection on site
Combustion
Chamber Pressure
testing
Proof by previous
testing
Hybrid and Liquid
Propulsion System
Tanking Testing
Proof by previous
testing
Page 70 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0071.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
SRAD propulsion systems shall successfully (without
significant anomalies) complete an instrumented
(chamber pressure and/or thrust), full scale
(including system working time) static hot-fire test
prior to EuRoC. In the case of solid rocket motors,
this test needs not to be performed with the same
motor casing and/or nozzle components intended
for use at the EuRoC (i.e., teams must verify their
Static Hot-fire testing casing design, but are not forced to design
reloadable/reusable motor cases). The test results
and a statement of a successful test, complete with
dates and signatures (at least three) are considered
a mandatory deliverable and an annex to the
Technical Report. Failure to deliver this annex will
automatically result in a “denied” flight status. See
Section 2.6.6. for more information.
Proof by previous
testing
RECOVERY SYSTEMS AND AVIONICS
Upon request, the flier must provide the inspector
with hardcopy checklist procedures for the recovery
system's safe handling, assembly, disassembly, and
operation
(both
nominal
and
offnominal/contingency
flows)
-
including
selfinspection/verification steps which make
individual team members accountable to one
another for having completed the preceding
process(es).
Upon request, the flier must provide the inspector
with hardcopy checklist procedures for any of the
recovery system's unique final on-pad preparations,
pre-flight, and launch (both nominal and
offnominal/abort/mishap flows) - including
selfinspection/verification steps which make
individual team members accountable to one
another for having completed the preceding
process(es).
Checklist
Simple confirmation
Inspection on site
Pre-flight and
Countdown
Procedure
Simple confirmation
Inspection on site
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 71 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0072.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Dual-event
Parachute and
Parafoil Recovery
Each independently recovered launch vehicle body,
anticipated to reach an apogee above 450 m above
ground level (AGL), shall follow a "dual-event"
recovery operations concept, including an initial
deployment event (e.g., a drogue parachute
deployment; reefed main parachute deployment or
similar) and a main deployment event (e.g., a main
parachute deployment; main parachute un-reefing
or similar). Independently recovered bodies, whose
apogee is not anticipated to exceed 450 m AGL, are
exempt and may feature only a single/main
deployment event.
If previously flown, any used parachutes, shock
chords, and suspension lines must not exhibit signs
of damage which threatens the safe recovery of the
rocket.
The initial deployment event shall occur at or near
apogee, stabilize the vehicle's attitude (i.e., prevent
or eliminate tumbling), and reduce its descent rate
sufficiently to permit the main deployment event,
yet not so much as to exacerbate wind drift. Any
part, assembly or device, featuring an initial
deployment event, shall result in a descent velocity
of said item of 23-46 m/s.
The main deployment event shall occur at an
altitude no higher than 450 m AGL and reduce the
vehicle's descent rate sufficiently to prevent
excessive damage upon impact with ground. Any
part, assembly or device, featuring a main
deployment event, shall result in a descent velocity
of said item of less than 9 m/s.
Any parachutes or parafoils used must be rated for
the weight of the vehicle and the expected
conditions at deployment.
Parachutes or parafoils intended for the final
descent phase to the ground must not allow a
descent rate that would represent a safety hazard.
Proof by calculation
Proof by reasoned
argumentation
Inspect for Damage
Simple Confirmation
Inspection on site
Proof by reasoned
argument
(Deployment event)
Proof by calculation
(Descent rate)
Proof by previous
testing (Descent
rate)
Proof by reasoned
argumentation
(Deployment event)
Proof by calculation
(Descent rate)
Proof by previous
testing (Descent
rate)
Proof by calculation
Proof by calculation
Proof by reasoned
argumentation
Proof by previous
testing
Initial Deployment
Event
Main Deployment
Event
Parachutes and
Parafoils
Safe Descent rate
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 72 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0073.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Personal Safety
The arming/disarming process must not place the
operator in the predicted path of hot gases, ejecta,
or deployable devices which might result from an
unintentional triggering event
The electronics controlling recovery events must be
activated by externally accessible switches, and do
not require any disassembly of the rocket to either
activate or de-activate.
Each independent set of electronics controlling
recovering events must provide sensory (i.e., visual
or auditory) indication of its activation.
Heavy items - most notably batteries - must be
adequately supported to prevent them becoming
dislodged under anticipated flight loads.
The recovery system shall implement adequate
protection (e.g., fire-resistant material, pistons,
baffles etc.) to prevent hot ejection gases (if
implemented) from causing burn damage to
retaining chords, parachutes, and other vital
components as the specific design demands.
The recovery system rigging (e.g., parachute lines,
risers, shock chords, etc.) shall implement swivel
links at connections to relieve torsion, as the specific
design demands. This will mitigate the risk of torque
loads unthreading bolted connections during
recovery as well as parachute lines twisting up.
Simple check
Activation Devices
Simple confirmation
Positive State
Indication
Acceleration Effects
on Electronics
Simple confirmation
Inspection on site
Simple confirmation
Ejection Gas
Protection
Simple confirmation
Inspection on site
Parachute Swivel
Links
Simple confirmation
Inspection on site
Parachute Coloration
and Markings
When separate parachutes are used for the initial
and main deployment events, these parachutes
should be visually highly dissimilar from one
another. This is typically achieved by using
parachutes whose primary colours contrast those of
the other chute. This will enable ground-based
observers to characterize deployment events more
easily with high-power optics. Utilised parachutes
should use colours providing a clear contrast to a
blue sky and a grey/white cloud cover.
Simple confirmation
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 73 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0074.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Non-
parachute/Parafoil
Recovery Systems
Teams exploring other recovery methods (i.e.,
nonparachute or parafoil based) shall mention them
in the dedicated field of the Technical
Questionnaire. The organisers may make additional
requests for information and draft unique
requirements depending on the team's specific
design implementation.
Simple confirmation
Inspection on site
Proof by reasoned
argumentation
In-depth proofing
needed
R
EDUNDANT
E
LECTRONICS
At least one redundant recovery system electronics
subsystem shall implement a COTS flight computer.
To be considered COTS, the flight computer
(including flight software) must have been
developed and validated by a commercial third
party.
EuRoC will require teams to implement a common
mandatory GPS tracking and locating device in all
rocket systems featuring a dual-event deployment
and recovery system, specified in more detail in
Appendix C.
Redundant COTS
Recovery Electronics
Simple confirmation
Mandatory Official
GPS Tracking and
Tracking Systems
Simple confirmation
Dissimilar Redundant
Recovery Electronics
There is no requirement that the redundant/backup
system be dissimilar to the primary; however, there
are advantages to using dissimilar primary and
backup systems. Such configurations are less
vulnerable to any inherent environmental
sensitivities, design, or production flaws affecting a
particular component.
No action necessary
S
AFETY
C
RITICAL
W
IRING
All safety critical wiring shall implement a cable
management solution (e.g., wire ties, wiring,
harnesses, cable raceways) which will prevent
tangling and excessive free movement of significant
wiring/cable lengths due to expected launch loads.
This requirement is not intended to negate the
small amount of slack necessary at all
connections/terminals to prevent unintentional
demating due to expected launch loads transferred
into wiring/cables at physical interfaces.
Cable Management
Simple confirmation
Inspection on site
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 74 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0075.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Secure Connections
All safety critical wiring/cable connections shall be
sufficiently secure as to prevent de-mating due to
expected launch loads. This will be evaluated by a
"tug test", in which the connection is gently but
firmly "tugged" by hand to verify it is unlikely to
break free in flight.
In case of propellants with a boiling point of less
than -50°C any wiring or harness passing within the
close proximity of a cryogenic device (e.g., valve,
piping, etc.) or a cryogenic tank (e.g., a cable tunnel
next to a LOX tank) shall utilize safety critical wiring
with cryo-compatible insulation (i.e., Teflon, PTFE,
etc.).
All stored-energy devices (aka energetics) used in
recovery systems shall comply with the energetic
device requirements defined in Section 4. of this
document.
Inspection on site
Cryo-compatible
Wire Insulation
Inspection on site
Recovery System
Energetic Devices
Simple confirmation
R
ECOVERY
S
YSTEM
T
ESTING
All recovery system mechanisms shall be
successfully (without significant anomalies) tested
prior to EuRoC, either by flight testing, or through
one or more ground tests of key subsystems. In the
case of such ground tests, sensor electronics will be
functionally included in the demonstration by
simulating the environmental conditions under
which their deployment function is triggered. The
test results and a statement of a successful test,
complete with dates and signatures (at least three)
are considered a mandatory deliverable and annex
to the Technical Report. Failure to deliver this annex
will automatically result in a “denied” flight status.
Ground Test
Demonstration
Proof by previous
testing
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 75 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0076.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Optional Flight Test
Demonstration
All recovery system mechanisms shall be
successfully (without significant anomalies) tested
prior to EuRoC, either by flight testing, or through
one or more ground tests of key subsystems. While
not required, a flight test demonstration may be
used in place of ground testing. In the case of such
a flight test, the recovery system flown will verify
the intended design by implementing the same
major subsystem components (e.g., flight
computers and parachutes) as will be integrated
into the launch vehicle intended for EuRoC (i.e., a
surrogate booster may be used). The test results
and a statement of a successful test, complete with
dates and signatures (at least three) are considered
a mandatory deliverable and annex to the Technical
Report. Failure to deliver this annex will
automatically result in a “denied” flight
status.
STORED-ENERGY DEVICES
No action necessary
All energetics shall be “safed” until the rocket is in
the launch position, at which point they may be
"armed". An energetic device is considered safed
when two separate events are necessary to release
the energy of the system. An energetic device is
Energetic
Device considered armed when only one event is necessary
Safing and Arming
to release the energy. For the purpose of this
document, energetics are defined as all
storedenergy devices
other than propulsion
systems
that have reasonable potential to cause
bodily injury upon energy release. See Section 4.1.
for more information.
All energetic device arming features shall be
externally accessible/controllable. This does not
preclude the limited use of access panels which may
be secured for flight while the vehicle is in the
launch position.
Simple check
Arming Device
Access
Simple confirmation
Inspection on site
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 76 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0077.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Arming Device
Location
All energetic device arming features shall be located
on the airframe such that any inadvertent energy
release by these devices will not impact personnel
arming them. For example, the arming key switch
for an energetic device used to deploy a hatch panel
shall not be located at the same airframe clocking
position as the hatch panel deployed by that charge.
Furthermore, it is highly recommended that the
arming mechanism is accessible from ground level,
without the use of ladders or other elevation
Simple confirmation
devices, when the rocket is at a vertical orientation
on the launch rail.
SRAD P
RESSURE
V
ESSELS
SRAD pressure vessels shall implement a relief
device, set to open at no greater than the proof
pressure specified in the following requirements.
SRAD (including modified COTS) rocket motor
propulsion system combustion chambers are
exempted from this requirement.
SRAD and modified COTS pressure vessels
constructed entirely from isentropic materials (e.g.,
metals) shall be designed to a burst pressure no less
than 2 times the maximum expected operating
pressure, where the maximum operating pressure is
the maximum pressure expected during prelaunch,
flight, and recovery operations.
All SRAD and modified COTS pressure vessels either
constructed entirely from non-isentropic materials
(e.g., fibre reinforced plastics; FRP; composites) or
implementing composite overwrap of a metallic
vessel (i.e., composite overwrapped pressure
vessels; COPV), shall be designed to a burst pressure
no less than 3 times the maximum expected
operating pressure, where the maximum operating
pressure is the maximum pressure expected during
pre-launch, flight, and recovery operations.
Relief Device
Proof by previous
testing
Designed Burst
Pressure for Metallic
Pressure Vessels
Proof by calculation
Proof by reasoned
argumentation
In-depth proofing
needed
Designed Burst
Pressure for
Composite Pressure
Vessels
Proof by calculation
Proof by reasoned
argumentation
In-depth proofing
needed
SRAD P
RESSURE
V
ESSEL
T
ESTING
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 77 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0078.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Proof Pressure
Testing
SRAD and modified COTS pressure vessels shall be
proof pressure tested successfully (without
significant anomalies) to 1.5 times the maximum
expected operating pressure for no less than twice
the maximum expected system working time, using
the intended flight article(s) (e.g., the pressure
vessel(s) used in proof testing must be the same
one(s) flown at EuRoC). The maximum system
working time is defined as the maximum
uninterrupted time duration the vessel will remain
pressurized during pre-launch, flight, and recovery
operations.
The test results and a statement of a successful test,
complete with dates and signatures (at least three)
are considered mandatory deliverable and annexed
to the Technical Report. Failure to deliver
this annex will automatically result in a “denied”
flight status.
Although there is no requirement for burst pressure
testing, a rigorous verification & validation test plan
typically includes a series of both non-destructive
(i.e., proof pressure) and destructive (i.e., burst
pressure) tests. A series of burst pressure tests
performed on the intended design will be viewed
favourably; however, this will not be considered an
alternative to proof pressure testing of the intended
flight article.
ACTIVE FLIGHT CONTROL SYSTEMS
Launch vehicle active flight control systems shall be
optionally implemented strictly for pitch and/or roll
stability augmentation, or for aerodynamic
"braking". Under no circumstances will a launch
vehicle entered in EuRoC be actively guided towards
a designated spatial target. The organisers may
make additional requests for information and draft
unique requirements depending on the team's
specific design implementation.
Proof by previous
testing
Optional Burst
Pressure Testing
No action necessary
Restricted Control
Functionality
Simple confirmation
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 78 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0079.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Unnecessary for
Stable Flight
Launch vehicles implementing active flight controls
shall be naturally stable without these controls
being implemented (e.g., the launch vehicle may be
flown with the control actuator system [CAS]
including any control surfaces
either removed or
rendered inert and mechanically locked, without
becoming unstable during ascent). Attitude Control
Systems (ACS) will serve only to mitigate the small
perturbations which affect the trajectory of a stable
rocket that implements only fixed aerodynamic
surfaces for stability. The organisers may make
additional requests for information and draft
unique requirements depending on the team's
specific design implementation.
Control Actuator Systems (CAS) shall mechanically
lock in a neutral state whenever either an abort
signal is received for any reason, primary system
power is lost, or the launch vehicle's attitude
exceeds 30° from its launch elevation. Any one of
these conditions being met will trigger the fail-safe,
neutral system state. A neutral state is defined as
one which does not apply any moments to the
launch vehicle (e.g., aerodynamic surfaces trimmed
or retracted, gas jets off, etc.).
CAS shall mechanically lock in a neutral state until
either the mission’s boost phase has ended (i.e., all
propulsive stages have ceased producing thrust),
the launch vehicle has crossed the point of
maximum aerodynamic pressure (i.e., max Q) in its
trajectory, or the launch vehicle has reached an
altitude of 6.000 m AGL. Any one of these conditions
being met will permit the active system state. A
neutral state is defined as one which does not apply
any moments to the launch vehicle (e.g.,
aerodynamic surfaces trimmed or retracted, gas jets
off, etc.).
Proof by reasoned
argumentation
Inspection on site
Designed to Fail Safe
Proof by reasoned
argumentation
Inspection on site
Boost Phase
Dormancy
Proof by reasoned
argumentation
Inspection on site
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 79 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0080.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Active Flight Control
System Electronics
Wherever possible, all active control systems should
comply with requirements and goals for "redundant
electronics" and "safety critical wiring" as recovery
systems
understanding that in this case
"initiation" refers CAS commanding rather than a
recovery event. Flight control systems are exempt
from the requirement for COTS redundancy, given
that such components are generally unavailable as
COTS to the amateur highpower rocketry
community.
All stored-energy devices used in an active flight
control system (i.e., energetics) shall comply with
the energetic device requirements defined in
Section 4. of this document.
AIRFRAME STRUCTURES
Launch vehicles shall be adequately vented to
prevent unintended internal pressures developed
during flight from causing either damage to the
airframe or any other unplanned configuration
changes. Typically, a 3 mm to 5 mm hole is drilled in
the booster section just behind the nosecone or
payload shoulder area, and through the hull or
bulkhead
of
any
similarly
isolated
compartment/bay.
Simple confirmation
Active Flight Control
System Energetics
Simple confirmation
Adequate Venting
Simple confirmation
Inspection on site
O
VERALL
S
TRUCTURAL
I
NTEGRITY
Upon request, the flier should provide the inspector
with hardcopy checklist procedures for the rocket's
assembly and integration for flight - including
selfinspection/verification steps which make
individual team members accountable to one
another for having completed the preceding
process(es).
PVC (and similar low-temperature polymers), Public
Missiles Ltd. (PML) Quantum Tube components
shall not be used in any structural (i.e., load bearing)
capacity, most notably as load bearing eyebolts,
launch vehicle airframes, or propulsion system
combustion chambers.
Checklist
Simple confirmation
Inspection on site
Material Selection
No action necessary
(for stainless steel
components)
Simple confirmation
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 80 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0081.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Load Bearing
Eyebolts and U-bolts
All load bearing eyebolts shall be of the closed-eye,
forged type
NOT of the open eye, bent wire type.
Furthermore, all load bearing eyebolts and U-Bolts
shall be steel or stainless steel. This requirement
extends to any bolt and eye-nut assembly used in
place of an eyebolt.
Airframe joints which implement "coupling tubes"
should be designed such that the coupling tube
extends no less than one body calibre on either side
of the joint
measured from the separation plane.
Regardless of implementation (e.g., RADAX or other
join types) airframe joints will be "stiff" (i.e., prevent
bending).
Launch lugs (i.e., rail guides) should implement
"hard points" for mechanical attachment to the
launch vehicle airframe. These hardened/reinforced
areas on the vehicle airframe, such as a block of
wood installed on the airframe interior surface
where each launch lug attaches, will assist in
mitigating lug "tear outs" during operations. The aft
most launch lug shall support the launch vehicle's
fully loaded launch weight while vertical. At EuRoC,
competition officials will require teams to lift their
launch vehicles by the rail guides and/or
demonstrate that the bottom guide can hold the
vehicle's weight when vertical. This test needs to be
completed successfully before the admittance of
the team to Launch Readiness Review.
All teams shall perform a “launch rail fit check” as a
part of the flight preparations (the Launch
Readiness Review), before going to the launch
range. This requirement is particularly important if
a team is not bringing their own launch rail, but
instead relying on EuRoC provided launch rails.
The rail guides must be firmly attached to the rocket
without evidence of cracking in the joints, and the
aft most guide attachment must be sufficient to
bear the rocket's entire mass when erected.
No action necessary
(for stainless steel)
Inspection on site
Implementing
Coupling Tubes
Simple confirmation
Proof by reasoned
argumentation
Launch Lug
Mechanical
Attachment
Inspection on site
Proof by previous
testing
Launch Rail Fit Check
Inspection on site
Rail Guide
Attachment
Inspection on site
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 81 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0082.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Slip-fit Joints
Joints intended to separate in flight cannot become
separated when loaded by their own weight alone,
and the Flier should demonstrate cognizance of
shear pin design (if implemented).
All joints - both separating and non-separating in
flight - must be "stiff", so as to eliminate any visible
airframe bending.
The fins must be firmly attached to the rocket
without evidence of cracking in the joints.
("Hairline" cracks may be acceptable if the fins are
not loose or, if the fins are mounted using the
"through-the-wall" [TTW] construction technique.
The fins must exhibit no shifting and minimal
deflection (i.e., bending) when handled.
The fins must exhibit little-to-no indication of
damage due to moisture penetration or excessive
thermal cycling during storage or transport - leading
to out of tolerance dimensional changes in the part.
Proof by reasoned
argumentation
Joint Stiffness
Inspection on site
Fin Attachment
Inspection on site
Fin Stiffness
Inspection on site
Fin "Warpage"
Inspection on site
RF T
RANSPARENCY
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 82 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0083.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
RF Window Location
Any internally mounted RF transmitter, receiver or
transceiver, not having the applicable antenna or
antennas mounted externally on the airframe, shall
employ “RF windows" in the airframe shell plating
(typically glass fibre panels), enabling RF devices
with antennas mounted inside the airframe, to
transmit the signal though the airframe shell. RF
windows in the flight vehicle shell shall be a 360°
circumference and be at least two body diameters
in length. The internally mounted RF antenna(s)
shall be placed at the midpoint of the RF window
section, facilitating maximizing the azimuth
radiation
pattern.
RF transmitter, receivers or transceivers are not
allowed to be mounted externally. Externally
mounted antennas are allowed, but only if at least
two antennas are mounted on opposite sides of the
airframe, thus retaining circumferential symmetry
and covering sufficient transmission area,
transmitting or receiving identical signals. As
popular as carbon fibre is for the construction of
strong and lightweight airframes, it is also
conductive and will significantly shield and/or
degrade RF signals, which is unacceptable.
The team's Team ID (a number assigned by EuRoC
prior to the competition event), project name, and
academic affiliation(s) shall be clearly identified on
the launch vehicle airframe. The Team ID especially,
will be prominently displayed (preferably visible on
all four quadrants of the vehicle, as well as fore and
aft), assisting competition officials to positively
identify the project hardware with its respective
team throughout EuRoC.
Simple confirmation
Identifying Markings
No action necessary
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 83 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0084.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Other Markings
There are no requirements for airframe coloration
or markings beyond those specified in Section 6.4.
of this document. However, EuRoC offers the
following recommendations to student teams:
mostly white or lighter tinted colour (e.g., yellow,
red, orange, etc.) airframes are especially conducive
to mitigating some of the solar heating experienced
in the EuRoC launch environment. Furthermore,
high-visibility schemes (e.g., highcontrast black,
orange, red, etc.) and roll patterns (e.g., contrasting
stripes, “V” or “Z” marks, etc.) may allow ground-
based observers to more easily track and record the
launch vehicle’s trajectory with high-power
optics.
PAYLOAD
Payloads may be deployable or remain attached to
the launch vehicle throughout the flight. Deployable
payloads shall incorporate an independent recovery
system, reducing the payload's descent velocity to
less than 9 m/s before it descends through an
altitude of 450 m AGL. Deployable payloads without
two-stage recovery systems (drogue and main
chute, like the rockets) will be subjective to
considerable drift during descent.
Payloads implementing independent recovery
systems shall comply with the same requirements
and goals as the launch vehicle for "redundant
electronics" and "safety critical wiring".
Payloads implementing independent recovery
systems shall comply with the same requirements
and goals as the launch vehicle for "recovery system
testing".
No action necessary
Payload recovery
Proof by calculation
Proof by reasoned
argumentation
Proof by previous
testing
Payload Recovery
System
Electronics
and
Safety Critical
Wiring
Payload Recovery
System Testing
Inspection on site
Simple confirmation
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 84 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0085.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Deployable Payload
GPS Tracking
Required
It must be noted that deployable payloads are
equivalent to flight vehicle bodies and sections, in
that they can be difficult to locate after landing. All
deployable payloads shall feature the same
mandatory GPS tracking system as all rockets and
rocket stages as specified in the Appendix C: Official
Altitude Logging and Tracking System. The GPS
locator ID must differ from the ID of the launch
vehicle.
All stored-energy devices (i.e., energetics) used in
payload systems shall comply with the energetic
device requirements defined in Section 4. of this
document.
LAUNCH AND ASCENT TRAJECTORY REQUIREMENTS
Launch vehicles shall nominally launch at an
elevation angle of 84° ±1° and a launch azimuth
defined by competition officials at EuRoC.
Competition officials reserve the right to require
certain vehicles' launch elevation be as low a 70°, if
flight safety issues are identified during pre-launch
activities.
Launch vehicles shall have sufficient velocity upon
"departing the launch rail" to ensure they will follow
predictable flight paths. In lieu of detailed analysis,
a rail departure velocity of at least 30 m/s is
generally acceptable. Alternatively, the team may
use detailed analysis to prove stability is achieved at
a lower rail departure velocity 20 m/s either
theoretically (e.g., computer simulation) or
empirically (e.g., flight testing).
Launch vehicles shall remain "stable" for the entire
ascent. Stable is defined as maintaining a static
margin of at least 1.5 to 2 body calibres, regardless
of CG movement due to depleting consumables and
shifting centre of pressure (CP) location due to wave
drag effects (which may become significant as low
as 0.5 Mach). Not falling below 2 body calibres will
be considered nominal, while falling below 1.5 body
calibres will be considered a loss of stability.
Simple confirmation
Payload Energetic
Devices
Simple confirmation
Launch Azimuth and
Elevation
Simple check
Launch Stability
Proof by calculation
Ascent Stability
Proof by calculation
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 85 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0086.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Over-stability
All launch vehicles should avoid becoming
"overstable" during their ascent. A launch vehicle
may be considered over-stable with a static margin
significantly greater than 2 body calibres (e.g.,
greater than 6 body calibres).
Upon request, the flier should either provide a hard
copy, or demonstrate on a portable computer, a
3degreee-of-freedom (3DoF) simulation (or better)
of the rocket's nominal trajectory.
The fins should be mounted parallel to the roll axis
of the rocket, or (if canted or otherwise roll
inducing) the Flier must demonstrate cognizance of
the predicted roll behaviour and its effects.
Proof by calculation
Flight Simulation
In-depth proofing
needed
Fin Alignment
Inspection on site
Any delays implemented between staging events
must not be so long as to significantly risk the rocket
Staging Event
Sequence and Timing having "arced-over" into an unsafe orientation -
typically by "gravity turn".
TEAM-PROVIDED LAUNCH SUPPORT EQUIPMENT
If possible/practicable, teams should make their
launch support equipment man-portable over a
short distance (a few hundred metres).
Environmental considerations at the launch site
permit only limited vehicle use beyond designated
roadways, campgrounds, and basecamp areas.
Team provided launch rails shall implement the
nominal launch elevation specified in Section 8.1. of
this document and, if adjustable, not permit launch
at angles either greater than the nominal elevation
or lower than 70°.
All team provided launch control systems shall be
electronically operated and have a maximum
operational range of no less than 650 metres from
the launch rail. The maximum operational range is
defined as the range at which launch may be
commanded reliably.
Proof by calculation
Equipment
Portability
Simple confirmation
Launch Rail Elevation
Inspection on site
Operational Range
No action necessary
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 86 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0087.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
Fault Tolerance and
Arming
All team provided launch control systems shall be at
least single fault tolerant by implementing a
removable safety interlock (i.e., a jumper or key to
be kept in possession of the arming crew during
arming) in series with the launch switch.
All team provided launch control systems shall
implement ignition switches of the momentary,
normally open (also known as "dead man") type so
that they will remove the signal when released.
Mercury or "pressure roller" switches are not
permitted anywhere in team provided launch
control systems.
EQUIPMENT
All teams must bring any Personal Protection
Equipment (PPE) required for all preparation- and
launch activities. EuRoC does not have a supply of
spare PPE. PPE includes, but is not limited to, safety
goggles, gloves, safety shoes, hardhats, ear
protection, cryo-protection, etc.
Inspection on site
Safety Critical
Switches
Simple confirmation
Communication
Equipment
No action necessary
Personal Protection
Equipment
All teams must bring any Personal Protection
Equipment (PPE) required for all preparation- and
launch activities. EuRoC does not have a supply of
Simple confirmation
spare PPE. PPE includes, but is not limited to, safety
goggles, gloves, safety shoes, hardhats, ear
protection, cryo-protection, etc.
All teams are encouraged to provide each
participating team member with a suitable
“field/day pack”, which is kept close at hand (or
worn) during launch days. Due to the possibility of
strong sunlight and high temperatures even in
October, some of these provisions are intended to
get students through a hot and dry day in the field,
while other provisions are intended to enable
student teams to continue efficient operation after
loss of daylight after a quick sun-down and a
resulting sudden and significant drop in ambient
temperature.
Table 4: Legend for de-scoping FRR checklist.
Field Equipment
No action necessary
L
EGEND FOR DE
-
SCOPING FEEDBACK
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 87 of 88
L 77 - 2022-23 (2. samling) - Bilag 1: Høringssvar og høringsnotat, fra uddannelses- og forskningsministeren
2683147_0088.png
Portugal Space Reference PTS_EDU_EuRoC_ST_000455
Version 03, Date 04.02.2021
This requirement is very important
This requirement is important
This requirement is of lesser importance
Table 5: Legend for actions to be taken on the FRR checklist.
A
CTIONS TO BE TAKEN
No action necessary
Simple confirmation
Simple check
Inspection on site
Proof by reasoned
argumentation
“I see you used stainless steel here. Okay, fine”
“Are you using non-toxic propellants?” – “Yes, we are”
“Is everybody at least 15 m away when the ground-start
ignition
circuit is arming?” – “Okay now, yes”
“Are all the critical wiring/cable connections sufficiently secured?” –
“I will have a look, ah I see, yes”
“Can you tell me about your process of offloading propellant in case
of a launch abort?” – “Okay, sounds reasonable, this should work.”
“Have you tested the
pressure vessels to 1.5 the maximum expected
operating pressure?” – “Okay, I will have a look at the results and
understand if everything has been tested appropriately.”
“Regarding the launch stability, have you calculated the
lower rail
departure velocity? How did you do it? What is the result?” – “Okay,
I see and understand the calculation, this will work then.”
“How does this design feature work?” – “Okay, so you are not
certain, and I do not understand on site, so let us go to the CAD
model and check.”
Proof by previous testing
Proof by calculation
In-depth proofing needed
European Rocketry Challenge
Design, Test & Evaluation Guide
Page 88 of 88