Transportudvalget 2021-22
TRU Alm.del Bilag 97
Offentligt
2501644_0001.png
25 OCTOBER 2021
DANISH ROAD DIRECTORATE
STORSTRØM BRIDGE
INVESTIGATION REPORT
WORK PLAN AND TIME SCHEDULE FOR DESIGN & CONSTRUCTION
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0003.png
ADDRESS
COWI North America Ltd.
138 13th Street East,
Suite 400
North Vancouver, BC
V7L 0E5
Canada
TEL
FAX
WWW
+1 604 986 1222
+1 604 986 1302
cowi-na.com
25 OCTOBER 2021
DANISH ROAD DIRECTORATE
STORSTRØM BRIDGE
INVESTIGATION REPORT
WORK PLAN AND TIME SCHEDULE FOR DESIGN & CONSTRUCTION
PROJECT NO.
DOCUMENT NO.
PREPARED
REVIEWED
A047030
VERSION
A047030-COWI-RPT-001-0
DATE OF ISSUE
DESCRIPTION
Nedim Alca
James Campbell
APPROVED
0
25 October 2021
Final Report
Peter Reinholdt
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0005.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
EXECUTIVE SUMMARY
A 4 km long combined road and rail bridge, Storstrøm Bridge, is being constructed between
the islands of Sjælland and Falster. It is being built under a Design and Build Contract by
Storstrøm Bridge Joint Venture (SBJV) for the Danish Road Directorate (DRD). The Contract
was signed in early 2018, but the Project has suffered significant delays.
COWI North America Ltd. (COWI) was requested by the DRD to provide an unbiased
assessment of the time schedule, on which the DRD has based their estimated timing for
opening of the new bridge to road traffic and have it ready for installing catenary system
for railway by second half of year 2024, and to advise on possible actions which could be
taken to improve speed of construction and reliability of predictions.
In this study, the overall construction programme was reviewed with a fresh set of eyes, a
site visit was conducted, DRD and COWI site staff were interviewed, the construction
schedule was assessed by considering three scenarios, and suggestions on how to improve
the schedule are provided.
This report covers:
A brief description of the bridge (Section 2);
Current state of design & construction and remaining work (Section 3);
SBJV's design & construction schedule (proposed, updated, and actual) (Section 4);
Site visit & observations (Section 5);
Analysis of schedule for three potential scenarios (Section 6);
Assessment of construction schedule going forward and recommended measure to
improve the construction schedule (Section 7); and
Summary & recommendations (Section 8).
In this study, three different construction scenarios are considered. Using the progress to
date to predict the future is not meaningful as only a few precast segments have been
produced and extrapolating their production duration would lead to an unrealistically long
construction period. However, there is no doubt that it is feasible to increase the
construction speed. It will take some time to ramp-up production and the production rate
might vary depending on steps taken related to workforce and equipment. Considering all
of these, the three scenarios considered in this study are:
Scenario 1: Pessimistic case – slow ramp-up and slow progress.
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0006.png
6
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
Scenario 2: Realistic case – ramp-up and progress between Scenarios 1 and 3.
Scenario 3: Optimistic case – ramp-up and progress expected for a well-organized and
experienced design & build team working collaboratively.
This study finds that if radical changes to construction are not implemented by January
2022, it will be unlikely that the new bridge can be opened to road traffic and that it will be
ready for installing the catenary system for railway by second half of year 2024.
The radical changes might include one or more of the following (each would take some time
to implement, hence, a decision needs to be made regarding which one(s) to adopt
quickly):
Adding a major international contractor with a large workforce (including workers,
foremen, engineers, and management staff experienced in similar major bridge
construction projects) and equipment to the SBJV team.
SBJV increasing its own capacity with a large injection of workforce (including workers,
foremen, engineers, and management staff experienced in similar major bridge
construction projects) and equipment well beyond currently on site.
Working on multiple fronts by switching to traditional in-situ construction for parts of
the bridge.
Adding one more precast girder production facility.
A significant investment by SBJV has been made in the prefabrication yard and the
equipment. The segment fabrication facilities and segment installation equipment are
appropriate for the project; however, they need to be utilized much more effectively than
they have been to date. Even if the facilities and equipment are used effectively, it will still
be very challenging to complete construction by mid 2024.
Completion of design, including design approvals, is not expected to be critical. It is
recommended that SBJV be open to DRD's design improvement suggestions for increasing
construction speed.
Additional measures are recommended to improve SBJV's operations and construction
schedule related to the following areas (see Section 7 for more details):
General Approach & Culture
Planning & Scheduling
Segment Fabrication
Storage
Offshore Operations
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0007.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
i
CONTENTS
1
2
2.1
2.2
3
3.1
3.2
3.3
4
4.1
5
6
7
SCOPE OF WORK
PROJECT DESCRIPTION
Storstrøm Project
Storstrøm Bridge
CURRENT STATE OF DESIGN & CONSTRUCTION AND
REMAINING WORK
Key Dates
Design Progress & Remaining Work
Construction Progress & Remaining Work
SBJV's DESIGN & CONSTRUCTION SCHEDULE
SBJV's Proposed & Updated versus Actual Schedule
SITE VISIT & OBSERVATIONS
ANALYSIS OF SCHEDULE FOR THREE SCENARIOS
2
3
3
4
8
8
9
10
12
12
13
18
SCHEDULE ASSESMENT & RECOMMENDED IMPROVEMENT
MEASURES
22
SUMMARY & RECOMMENDATIONS
25
8
Appendix A
Appendix B
Masnedø Yard Layout
High Level Schedules for Three Scenarios
A-1
B-1
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0008.png
2
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
1
SCOPE OF WORK
To evaluate the design and construction progress to date;
To assess whether the bridge can be open to road traffic and installation of railway catenary
system in the second half of 2024;
The overarching purposes of this study are:
To propose actions to be taken to improve progress of work in order to achieve the second
half of 2024 completion goal.
The scope of work of this study includes, but is not limited, to the following:
Analyse the remaining design and construction tasks to be performed.
Prepare a work plan for execution of these design and construction tasks, assuming a speed
of design and construction that can be expected from an experienced international bridge
design & build contractor.
Identify factors that might be obstacles to realisation of this work plan;
Assess their likelihood and extent of delay they could inflict;
Propose actions to minimise the likelihood of these obstacles occurring; and
Identify possible mitigating actions to limit their consequences if they occur.
Describe three scenarios and associated time schedules under these three different
assumptions for speed of construction and evaluate the likelihood of each.
Assess the probability that the bridge will open to road traffic in the second half of 2024.
Describe three different scenarios leading to different opening dates. For each of these
scenarios, assess their likelihood and describe assumptions and a justification.
Perform critical path analysis of the scenarios and identify the most critical activities in
the time schedules.
Propose actions to improve progress of work on site.
Taking past performance into consideration when predicting future progress, the following
activities are performed:
Analyse previous Work Schedules and past performance of SBJV on the project.
Analyse causes for previous delays and slip of the programme, including assessing the effect
of mitigation actions taken and/or not taken.
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0009.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
3
2
2.1
PROJECT DESCRIPTION
Storstrøm Project
The overall Storstrøm Project comprises (see Figure 1):
The new Storstrøm Bridge, an approximately 4 km long combined bridge with a double-track
railway, two-lane carriageway, cycle track and footpath;
Lowering of existing railway on Falster;
Embankments on Masnedø and Falster;
Roads and paths with related drainage;
Minor Underpasses and a roundabouts; and
Demolition of the existing Storstrøm Bridge.
Figure 1 - Storstrøm Project
This report focuses on the design and construction schedule for the new Storstrøm Bridge. The
schedule for the other components of the Storstrøm Project is not on the critical path and hence
are excluded from this study.
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0010.png
4
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
2.2
Storstrøm Bridge
The bridge is a concrete box girder bridge and has a total length of 3,832 m, see Figure 2. The
bridge comprises a central main cable stayed bridge (CSB), connected to land by two approach
viaducts. The cable stayed bridge has two 160 m long spans over the navigation channels. The
south viaduct has 23 spans of 80 m with a total length of 1,840 m. The north viaduct has one
span of 72 m and 20 spans of 80 m with a total length of 1,672 m.
Figure 2 – Bridge Plan & Elevation
For the areas close to Falster and Masnedø the foundations and piers 23S & 22S and 20N & 21N
are constructed in-situ by means of a temporary causeway. The remainder of the pier foundations
are precast concrete elements. There are three defined types of precast foundation ranging in
plan dimensions of 12m x 19m to 20m x 20m, see Figure 3.
Figure 3 – Typical Precast Foundation
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0011.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
5
The first few bridge piers and pier heads are constructed using precast pier segments connected
to each other using 0.8m tall cast in place "stitches". The later piers are constructed using a
jump-form system for the lower pier, precast pier segments connected to each other using 0.8m
tall cast in place "stitches” for the upper pier, and then the pier head H1 is cast in-situ. See
Figure 4 for the later pier construction.
Figure 4 – Precast Pier Segments and Stitches
First two girder spans of the south viaduct (24S to 22S) and first two spans of the north viaduct
(22N to 20N) are constructed over land and/or temporary causeway using cast-in-place concrete
on falsework. The remainder of the spans are constructed using precast superstructure elements,
see Figure 5.
Figure 5 – Bridge Span Lengths
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0012.png
6
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
The cable stayed bridge pylon foundation 1C is precast. After the foundation is placed in the
channel, the pylon is constructed using cast-in-place concrete methods, see Figure 6.
Figure 6 – Precast 1C Foundation and Cast-in-place Pylon
The cable stayed bridge superstructure spans (1C-1S and 1C-1N) comprise precast girders that
are erected on temporary piers, see Figure 7. Once the pylon is complete and the girders have
been positioned, the stay cables are installed and stressed.
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0013.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
7
Figure 7 – Main Cable Stayed Bridge Construction
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0014.png
8
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
3
CURRENT STATE OF DESIGN & CONSTRUCTION
AND REMAINING WORK
Key Dates
3.1
The key dates related to the Storstrøm Bridge design and construction are as follows:
Contract award – 26 February 2018
Supplementary geotechnical investigations were completed early 2019
Basic Design completed February 2019
Detailed Design is currently underway
Contractor mobilization on site – October 2018 (start of earth works for yard)
Prefabrication yard construction – October 2018 to March 2020
Start of precast segments:
Precast pier foundations February 2020
Precast pier segments July 2020
Precast girders November 2020
Start of cast-in-place foundations & piers:
South viaduct - F23S December 2019
North viaduct – F21N March 2021
Start of cast-in-place spans:
South viaduct November 2020
North viaduct Not yet commenced
Start of precast 1C foundation June 2020
The project had a slow start. For example, it took about 2 years from signing the contract to
casting first precast foundation bottom slab (for 21S), which should have started on 2019 March
(delayed by 12 months).
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0015.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
9
3.2
Design Progress & Remaining Work
Basic Design for the bridge was completed in 2019. Table 1 summarizes the Detailed Design
progress to date and the remaining design work.
Table 1 - Detailed Design Progress (as of 14th September 2021)
Number of Design
Packages in
Progress (not yet
submitted DRD)
a
Number of Design
Packages in Review
(submitted to DRD but not
approved / being revised
by SBJV)
4
3
2
5
Number of
Approved
Design
Packages
Total
Pier Foundations
1
Pier Shafts
Girders
Pylon & cables
2
Land works & other
packages
Ancillary Works
Major Temporary
Works
Total
6
5
4
0
16
10
6
0
26
18
12
5
20
21
26
67
1
1
1
3
1
0
3
4
37
36
62
135
1) Including 1C and under-foundations (number may vary as some packages containing both
foundations and piers have been split in a later revisions). Abutment foundations not included
2) Pylon foundation 1C is included in pier foundations above
a) Numbers from SBJV's DDDP v6, uploaded 10.09.2021
The design status as of 14
th
September 2021 is summarized on Figure 8, where:
Green solid and dotted lines: approved
Yellow: approval process ongoing
Unboxed elements: DP not submitted yet
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0016.png
10
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
Figure 8 – Design Status as of 14 September 2021
The key take-away from Figure 8 is that the design is well ahead of construction and SBJV has
the opportunity to work on construction of many segments and on many construction fronts.
3.3
Construction Progress & Remaining Work
The casting facilities and erection equipment seem to be appropriate for the job. However, there
does not seem to be sufficient storage space for all the pieces if the production rate is increased
to levels initially planned for the project.
The prefabrication yard on Masnedø Island has the following facilities (see Appendix A for layout):
A concrete batching plant: main and back-up facilities capable of producing 80 m³ per hour
and 40 m³ per hour, respectively. The maximum rate of production to-date has been ~30
m³ per hour. A learning curve is expected to be able to consistently achieve production
rates significantly more than that needed to-date to meet the full production needs of in-situ,
offshore, and precast construction.
Shed 2 & yard: Precast girder production line. It is planned to work on four girders at the
same time in a production line fashion.
Shed 3 & yard: Precast pier foundation production facility. There are two beds inside the
shed for casting the bottom slab and ribs. The foundations are then moved outside for
construction of the pier elevation. In the yard, there are four stations for pier construction.
Shed 4 & yard: Precast pier segment production facility. One casting bed for each segment
type (C1, C2, C3, C4, H1, H2).
Shed 5: Rebar processing facility (cut & bend).
Quay (140 m) for loading pier foundations and segments on to barges.
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0017.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
11
Storage area for various falsework, SPMTs, materials etc.
Table 2 summarizes the construction progress to date and the remaining work.
Table 2 – Construction Progress (as of 31st August 2021)
Number of
Units
Fabrication /
Construction
underway
Abutments
In-situ Spans
Precast Pier
Foundations
Precast Pier
Shafts
Precast Pier
Tops
Precast
Segment 0
Precast Girders
Precast 1C
Foundation
Pylon
CSB Precast
Girders
Cable System
0
2
Number of
Units
Fabrication
completed
Number of
Units Erected
Total
Percent
complete
2
0
-
-
2
4
100%
~35%
2
5
4
40
~15%
1
12
8
104
~15%
2
0
0
45
~2%
0
0
0
40
0%
1
0
0
44
~1%
1
0
0
1
~90%
1
0
0
1
~15%
0
0
0
4
0%
0
0
0
1
0%
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0018.png
12
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
4
4.1
SBJV's DESIGN & CONSTRUCTION SCHEDULE
SBJV's Proposed & Updated versus Actual Schedule
The production rates for different units are given in Table 3. The production rates given in SBJV's
proposal appear to be reasonable and consistent with what is expected from an experienced
international design and build team. The actual production is, however, much slower than
proposed by SBJV.
Table 3 – Construction / Fabrication Production Rates
SBJV Proposal
Work Schedule
F (months)
Work Schedule G
(C2) (months)
5.0
Actual (first/
average)
14.7 (P23S)
Cast-in-place
pier
Cast-in-place
girder
Precast Pier
foundations
Precast Pier
shafts
2 piers worth per
month
2 units per month
2.5 months
11.1
5.3
4.5
12 (est.) first
girder
2 (first cycle)
1.6 (first cycle)
9.4 (F21S)
Included with
precast pier
foundations
Included with
precast pier
foundations
Included with
precast pier
foundations
1.0
Incomplete
Precast Pier Tops
Included in Pier
shafts
Included with
precast pier
foundations
Incomplete
Precast Reduced
Deck Segments
Precast Girders
Included in
Precast Girders
2 months (2
spans per month)
0.7
Not commenced
3.0 (first cycle)
2.0 (first cycle)
5.4 (est.) first
girder
Precast 1C
Foundation
Pylon
CSB Precast
Girders
Cables
Already in place in
2021
25 months
19 months
8.4
5.0
15
19.2
22.3
Not commenced
Not commenced
3 months
3.1 (phase 1&2)
3.5 (phase 1&2)
Not commenced
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0019.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
13
5
SITE VISIT & OBSERVATIONS
The site visit included an inspection of the main
Masnedø
Nedim Alca of COWI North America visited the site and interviewed the DRD and COWI site staff
between 13
th
& 16
th
September 2021.
yard, Sheds 2 through 5, and the abutments and in-situ spans at Falster and
Masnedø. A
summary of the site visit and interviews is provided below. This is not intended to be a
comprehensive list; it provides a flavour of the Project status, what has been working well, what
can be improved, and concerns going forward.
General
SBJV mainly engages subcontractors to perform the work on site. Initially the
subcontractor supervision by SBJV was inadequate, but this has improved through the
use of Site Supervisors. SBJV has also experienced difficulty retaining staff and
subcontractors and as a consequence of frequent staff changes, there has been
inconsistent production rates and quality. SBJV has recently started to employ ‘blue
collar’ staff to work directly under their control.
Subcontractors' lack of sufficient proficiency in English, which is the main language for
all site paperwork such as work methods and QA/QC documentation, is leading to
subcontractors not understating and/or not addressing project requirements. This is
resulting in inconsistencies in construction quality and speed.
SBJV increased technical, quality, supervision, and claim staff in Spring 2021, however,
still lacking experienced leaders.
Decision making process within SBJV seems to be slow. All decisions seem to be taken
above the project director level, making it difficult to resolve issues at the site.
After a slow start and change of the lead Designer, the design and the design review
process has become efficient. Currently, design is well-ahead of construction and
approved designs are available for a significant portion of the bridge. Completion of the
design is not expected to be critical.
The relationship between SBJV and DRD design teams appears to be well, however,
SBJV is not open to suggestions for design improvements which might improve
construction speed. Designers and Independent Checkers are talking to each other and
the weekly design meetings are productive and open.
Construction interface & planning are lacking, which is affecting production rate and
quality.
The number of construction workers appears to be very low for a project of this scale.
Most of the production is performed during one shift per day. Workers on site are
moved from one area or production line to another to address priority-of-the-day, which
is affecting productivity and quality.
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0020.png
14
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
The main construction site at Masnedø Island has limited storage space to store
completed precast components. If and when the precast unit production rate is
increased, this might become an issue if there are delays with installation offshore.
Offshore work such as precast pier shaft stitch casting, Segment 0 production, precast
girder placement, main pylon casting, Power Joint casting, and all operations for the
main span construction have not commenced yet and will have learning curves. It might
be possible to use the area currently occupied by the Pier 1C foundation to store precast
pier foundations, precast pier segments, and/or precast girders. Barges can be rented
to store precast girders.
Quality Management, Inspection, Checking, and Re-work
SBJV's approach to quality management needs to be improved. Procedures and
documentation for the quality management system, work methods, team meetings etc.
are inadequate. Handling of NCR's and remedial & corrective actions do not seem to be
effective and do not seem to lead to corrective actions. Communication and
collaboration between SBJV's construction and QA/QC teams needs to be improved.
The SBJV does not operate their own Project specific document management system
(for example, Aconex) but relies upon ProjectWise (managed by the DRD), Microsoft
Teams and emails. This mixed use of systems by SBJV, and SBJV not providing
sufficient number of Document Controllers, have been challenging for smooth and
efficient flow of documents and information between parties to the Contract.
Construction quality in general is satisfactory for components constructed to date,
however, construction quality remains a concern due to high rate of workforce turnover.
Method statements and working procedures are prepared by inexperienced staff and
lacking details, except those prepared by specialist subcontractors, such as Fagioli,
which are appropriate. The persons nominated as Checker and Approver of these
documents need to review these documents more closely. The documents do not
appear to be used on site by the non-English speaking subcontractors due to the
language barrier.
Many Site Query Changes (SQC's) are not closed but this is not causing any work
stoppages.
DRD and COWI teams are working closely with SBJV's QA/QC team to avoid construction
delays despite unsatisfactory level of quality system documentation, however, the
concerns raised in the previous bullets can lead to work stoppages, rework, and delay.
When the production rate increases, special attention needs to be paid to integration of
QA/QC process and construction.
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0021.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
15
Embankments
Construction of the embankments is on-going, however, there seems to be lack of
planning leading to rehandling of the material placed. This is not only a quality concern
but is also inefficient and costly for the SBJV. Regardless, the work on the
embankments is not expected to be on the critical path.
Abutments and in-situ spans
Both abutments are substantially complete. The construction of the
Masnedø
and
Falster in-situ spans is not expected to be on the critical path as the erection sequence,
temporary restraints, and closure procedures of the spans next to them can be modified
to suit if necessary.
Construction of the Falster in-situ spans is underway. There are some cracks and
honeycombs in concrete, however, overall quality of construction is good. The
construction of the two Falster spans started ~11 months ago (the initial plan was to
construct both
Masnedø
and Falster in-situ spans in 10 months). Falsework design and
approval in accordance with the Danish Handbook on Falsework (due to SBJV's lack of
planning and lack of sufficient workforce) are some of the challenges.
Once the Falster in-situ spans are completed, the falsework will be moved to the north
side to construct the
Masnedø in-situ spans.
Dredging and foundation preparation & placement
The dredging and foundation preparation for placement of precast pier foundations is
not expected to be on the critical path. The learning curve is complete and the
appropriate equipment and subcontractors are on site.
All dredging for the foundations has been completed. It takes one week per pier to
perform the final preparations to place a precast pier foundation.
The inclusion piles for Pier 1C are complete. The inclusion piles for the remaining piers
(1N, 1S, 12S) are expected to start in October 2021.
Pier 21S precast foundation had issues during placement because the survey boat had
calibration error. Surface of the ballast was undulating above tolerance. NW corner has
a gap of 2-3 cm tall in a 4mx4m area. The foundation will be lifted, the screeding layer
corrected and then replaced.
Precast Pier Foundations & Piers
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0022.png
16
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
Shed 3 contains two stations for precast pier foundation bottom slab & rib fabrication. A
third station is currently being prepared in the yard just outside of Shed 3, which will
help improve the production rate.
Method statements for work in Sheds 3 & 4 are appropriate.
It seems feasible to achieve production rates indicated in SBJV's stand-alone schedule
for the precast pier foundations with the facilities on site, however, there must also be
an adequate workforce.
The catamaran has lifting (currently certified for 2,550 tonnes) and height limitations.
These limit the height of pier shaft that can be cast on top of the precast pier
foundations. Employing cranes with higher weight capacity and higher reach would
minimize number of stitch joints for the pier shafts.
SBJV is considering eliminating stitches and cast all upper piers in-situ. This might be a
reason why there is currently no production of pier segments.
Precast Girders
The precast girder production line in Shed 2 is sophisticated and well-suited to produce
quality segments.
Method statements for work in Shed 2 are appropriate.
It seems feasible to achieve production rates indicated in SBJV's stand-alone schedule
for the precast girders with the facilities on site, however, there must also be an
adequate workforce.
Segment 0 is key to be able to install fabricated precast girders, however, there are no
forms on site currently. In order to speed-up construction and reduce offshore work, it
would be beneficial to re-evaluate the Segment 0 construction process. If large crane(s)
with sufficient capacity and reach are brought on site, Segment 0 can be cast in its
entirety (except for the "wings").
Pier 1C and Cable Stayed Bridge
Pier 1C precast foundation is almost complete and planned to be installed in early
October 2021.
Currently, no drawings or method statements have been submitted for Power Joint and
Upper Pylon.
The current plan for offshore casting involves the use of static mixers on a barge. The
batched concrete is loaded into mixers for transportation to the quay, and then
transferred to the static mixers. The barge is then towed offshore to where the concrete
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0023.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
17
is needed, such as the pier body stitches, the pier heads, the Lower and Upper Pylon
and the Power Joint. The double handling of concrete, instead of pumping directly from
the concrete trucks, could lead to concrete waste (due to rejecting batches) and cold
joints & honeycombing. Significant learning curve related to offshore in-situ casting is
expected.
The Lower Pylon is planned to be cast in 4m lifts, which is similar to other cable stayed
bridges.
Only preliminary design drawings are available for the temporary works related to the
cable stayed bridge main span girder installation.
Stay anchor boxes design package and stay cable lengths & stressing information have
been received.
The current design for the Power Joint requires many construction joints, which is not
desirable for areas with congested reinforcement. It is recommended that the Power
Joint be cast with as few construction joints as possible.
Other
Waterproofing system is currently being discussed. The current plan is to install water
proofing in the winter, which has been raising quality concerns.
The bearing design has changed, which is affecting bearings already on site. In total
eight bearings will be discarded, and 56 bearings will be returned to the manufacturer
for rehabilitation.
The last full programme to be formally submitted by SBJV to the DRD was Work
Schedule Revision F on 13
th
October 2020. The SBJV is now in excess of five months
behind this schedule and because of this, it cannot be used with any confidence to
determine the SBJV’s future activities.
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0024.png
18
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
6
ANALYSIS OF SCHEDULE FOR THREE SCENARIOS
Three different design and construction scenarios are considered to assess whether the bridge
can be open to road traffic and be ready for installing catenary system for railway in the second
half of 2024. In this section, the scenarios and the analysis performed are discussed.
Using the progress to date to predict the future is not meaningful as only a few precast segments
for different parts of the bridge have been produced and extrapolating their production duration
would lead to an unrealistically long construction period. There is no doubt that it is feasible to
increase the construction speed, however, it will take some time to improve the production rate
(referred to as "ramp-up") and the actual production rate would depend on many factors, e.g.
level & skill of workforce, planning of activities, number of work fronts and more.
The three scenarios considered in this study are (see Figure 8 for a graphical representation):
Scenario 1: Pessimistic case – slow ramp-up and slow progress. This scenario has progress
faster than that observed to date but still very slow compared to that expected from a well-
organized and experienced design & build team.
Scenario 2: Realistic case – ramp-up and progress between Scenarios 1 and 3.
Scenario 3: Optimistic case – rapid ramp-up and progress expected from a well-organized
and experienced design & build team and all parties working collaboratively.
Scenario 3
Production Rate
Scenario 2
Scenario 1
Time
Figure 8 – Graphical representation of the three scenarios
The main assumptions and the assumed production (fabrication and installation) rates used for
the three scenarios are shown on Tables 4 and 5, respectively.
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0025.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
19
Table 4 – Scenario Main Assumptions
Scenario 1
Ramp-up (full
production rate
achieved by)
Fabrication
Twice as long as
Scenario 3
Installation
Twice as long as
Scenario 3
1
st
July 2022
Scenario 2
1
st
April 2022
Scenario 3
1
st
January 2022
Between Scenario 1
and Scenario 3
Between Scenario 1
and Scenario 3
Fabrication durations
equal to SBJV proposal
Installation durations
equal to SBJV proposal
Table 5 – Assumed Production (Fabrication and installation) Rates for Scenarios
Scenario 1
Precast Pier
foundations
Precast Pier shafts
1 unit per month
(total = 34 months)
1 pier worth per
month (34 months)
Precast Pier Tops
Included in Pier
shafts
Precast Segment 0
Included in Precast
Girders
Precast Girders
1 span per month
(total = 40 months)
Precast 1C
Foundation
Pylon
Cable Stayed
Bridge Main Span
Precast Girders
Cables
12 months
Already in place in
2021
48 months
38 months
Scenario 2
1.5 units per month
(total = 26 months)
1.5 piers worth per
month (26 months)
Included in Pier shafts
Scenario 3
2 units per month
(total = 17 months)
2 piers worth per
month (17 months)
Included in Pier shafts
Included in Precast
Girders
1.5 spans per month
(total = 30 months)
Already in place in
2021
36 months
29 months
Included in Precast
Girders
2 spans per month
(total = 20 months)
Already in place in
2021
24 months
4 months
9 months
6 months
The high-level schedules for the three scenarios are shown on Figures 9 through 11 (also included
in Appendix B for printing larger format).
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0026.png
20
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
2021
O N
2022
J J
2023
J J
2024
J J
2025
J J
2026
J J
2027
M A M
Activity
Precast Foundations
Design
Fabricate
Install
Offshore Work
Precast Pier Shaft Segments
Design
Fabricate
Install
Offshore Work
Precast Superstructure
Design
Fabricate
Install
Offshore Work
Precast 1C Foundation
Design
Fabricate
Install
Offshore Work
Cast-in-place 1C Pylon
Design
Offshore Work
Cable-stayed Superstructure Construction
Design
Fabricate
Install superstructure
Offshore Work related to superstructure installation
Install cable-stays
Finishing Works
Design
Asphalt Overlay
Track Slab Installation
Track Installation
S
D
J
F
M
A M
A
S
O
N
D
J
F
M
A M
A
S
O
N
D
J
F
M A M
A
S
O
N
D
J
F
M A
M
A
S
O
N
D
J
F
M
A M
A
S
O
N
D
J
F
J
Figure 9 – Scenario 1 High-Level Schedule
Activity
Precast Foundations
Design
Fabricate
Install
Offshore Work
Precast Pier Shaft Segments
Design
Fabricate
Install
Offshore Work
Precast Superstructure
Design
Fabricate
Install
Offshore Work
Precast 1C Foundation
Design
Fabricate
Install
Offshore Work
Cast-in-place 1C Pylon
Design
Offshore Work
Cable-stayed Superstructure Construction
Design
Fabricate
Install superstructure
Offshore Work related to superstructure installation
Install cable-stays
Finishing Works
Design
Asphalt Overlay
Track Slab Installation
Track Installation
S
2021
O N
D
J
F
M
A M
2022
J J
A
S
O
N
D
J
F
M
A M
2023
J J
A
S
O
N
D
J
F
M A M
2024
J J
A
S
O
N
D
J
F
M A
M
2025
J J
A
S
O
N
D
J
F
M
A M
2026
J J
A
S
O
N
D
J
F
2027
M A M
J
Figure 10 - Scenario 2 High-Level Schedule
Activity
Precast Foundations
Design
Fabricate
Install
Offshore Work
Precast Pier Shaft Segments
Design
Fabricate
Install
Offshore Work
Precast Superstructure
Design
Fabricate
Install
Offshore Work
Precast 1C Foundation
Design
Fabricate
Install
Offshore Work
Cast-in-place 1C Pylon
Design
Offshore Work
Cable-stayed Superstructure Construction
Design
Fabricate
Install superstructure
Offshore Work related to superstructure installation
Install cable-stays
Finishing Works
Design
Asphalt Overlay
Track Slab Installation
Track Installation
S
2021
O N
D
J
F
M
A M
2022
J J
A
S
O
N
D
J
F
M
A M
2023
J J
A
S
O
N
D
J
F
M A M
2024
J J
A
S
O
N
D
J
F
M A
M
2025
J J
A
S
O
N
D
J
F
M
A M
2026
J J
A
S
O
N
D
J
F
2027
M A M
J
Figure 11 - Scenario 3 High-Level Schedule
Figures 9 to 11 suggest that precast girder production is the critical activity and interrupting the
viaduct precast girder production to fabricate the cable stayed bridge main girders will likely
adversely affect the overall schedule due to learning curve involved (blue shaded durations).
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0027.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
21
The analysis and conclusions for the three scenarios are summarized on Table 6.
Table 6 – Analysis and Conclusions of Scenarios
Scenario 1
Estimated
completion date
Critical path
items / issues to
resolve
Same as Scenario 2
Mid 2027
Scenario 2
End of 2025
Scenario 3
Mid 2024
Production rate,
workforce level, work
on multiple fronts,
offshore works
learning curve
Same as Scenario 2
Obstacles
Same as Scenario 2
but less impact
Concrete production
rate, precast segment
storage space, quality,
and safety
Same as Scenario 2
but more impact
Likelihood of
occurrence
Possible, however, will
still require significant
improvements to
current production
rates
Realistic only if radical
changes are
implemented (see
Section 7 for further
discussion)
Increase workforce (by
a factor of 4 or 5),
work on multiple work
fronts, consider
producing CSB main
span girders on a
second production line,
increase concrete
supply capacity, bring
more & larger marine
cranes
Unlikely unless radical
changes mentioned for
Scenario 2 are
implemented very fast
Potential
mitigations (also
see Section 7)
Similar to Scenario 2
Similar to Scenario 2
The main risks to schedule are segment production rate, Segment 0 and Power Joint construction,
offshore work, safety, and quality, all of which can add one additional year or more to the
durations estimated for the three scenarios.
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0028.png
22
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
7
SCHEDULE ASSESMENT & RECOMMENDED
IMPROVEMENT MEASURES
The site visit and interviews with DRD and COWI staff, and analysis of schedule scenarios
discussed in Section 6 indicate that:
If radical changes to construction are not implemented by January 2022, it will be unlikely to
be able to open the new bridge to road traffic and have it ready for installing catenary
system for railway by second half of year 2024.
The radical changes might include one or more of the following (each would take some time
to implement, hence, a decision needs to be made quickly regarding which one(s) to adopt:
Adding to the SBJV team a major international contractor with a large workforce
(including workers, foremen, engineers, and management staff experienced in similar
major bridge construction projects) and equipment.
SBJV increasing its own capacity with a large injection of workforce (including workers,
foremen, engineers, and management staff experienced in similar major bridge
construction projects) and equipment well beyond that currently on site.
Working on multiple fronts by switching to traditional in-situ construction for parts of the
bridge. This will require significant additional marine equipment (barges, cranes, tugs,
crew boats, etc.), falsework and formwork, and infrastructure suitable to allow a large
workforce performing offshore work.
Adding one more precast girder production facility, first to fabricate the main span
precast girders and then, if needed, fabricate some of the typical precast girders. The
precast girder production appears to be the critical activity and interrupting the typical
precast girder production to fabricate the main span precast girders potentially adds 8
months, 6 months, and 4 months to the durations of Scenarios 1, 2, and 3, respectively
(see Figures 9 to 11). The facility does not need to be as elaborate as that in Shed 2
and does not need to be a production line. It could occupy a space slightly larger than
the girder itself.
Significant investment has been made in the prefabrication yard (Sheds 2 to 5, concrete
batch plant etc.) and the equipment (SPMTs, catamaran, barges, cranes etc.). The segment
fabrication facilities and segment installation equipment are appropriate for the project;
however, they need to be utilized much more effectively than they have been to date. Even
if the facilities and equipment are used effectively, it will still be challenging to complete
construction by mid 2024.
Completion of design is not expected to be critical.
The following are additional measures are recommended to improve SBJV's operations and
construction schedule:
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0029.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
23
General Approach & Culture
Improve communication between the site office staff and the workforce. Take steps to
eliminate language barriers and to improve collaboration.
Improve safety and quality culture. Any accident and/or reduction in quality can lead to
significant delays.
Look for opportunities to work on multiple construction fronts including segment
fabrication and installation. Preparation of one additional precast pier foundation casting
bed is currently underway, which is useful. Similar actions are needed for all other
operations.
Planning & Scheduling
Employ additional experienced construction engineers on site to work on work methods,
planning, scheduling and QA/QC.
Prepare stand-alone schedules for every segment fabrication and every offshore
operation. Currently, stand-alone schedules are available only for precast pier
foundation and precast girder fabrication. These are not detailed enough and are based
on single work shift.
Based on the stand-alone schedules and the actual production rates, continuously revise
the construction means & methods and seek for efficiencies in every operation.
Revise the rebar details and rethink number and location of construction joints to
improve construction speed and to minimize prefabrication yard and marine operations.
These might require design changes, which will require approvals by DRD, and hence
will require action well ahead of construction.
Segment Fabrication
Increase workforce and number of shifts per day, possibly in all sheds and operations.
Pre-fabricate reinforcement cages on several fronts in parallel before placing in the
formwork and stitching cages together.
Look for opportunities to modify rebar detailing for rapid construction. This will require
design changes and hence need proper planning.
Precast the pier foundations and piers in only one or two pieces to minimize offshore
operations.
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0030.png
24
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
Precast the cable stayed bridge main span girders on a separate production line. This
will avoid interrupting the typical girder production and allow construction of the main
span girders independent of the typical girders.
Precast the entire Segment 0 (instead of partial precasting). The current scheme for
construction of Segment 0 requires many construction joints and large quantities of
concrete casting offshore.
Revisit concrete production capacity and if needed increase concrete production capacity
either on site or by using local concrete suppliers, which might require use of standard
concrete instead of SCC.
Storage in the
Masnedø yard is very limited, especially for the precast girders. When the
segment production rate is increased or if offshore segment installation is delayed, storage will
become an issue. Investigate options and take measures to address potential storage area
shortage.
Offshore Operations
Increase the size and number of the cranes. This will allow installing larger precast pier
foundation & shaft segments, largest possible Segment 0 segments, and minimize the
number of offshore operations and minimize offshore concrete placement.
Transport concrete to offshore locations by driving concrete trucks on to barges. The
current proposal requires double handling of concrete instead of directly pumping of
concrete from concrete trucks, which could lead to concrete waste (due to rejecting
batches) and cold joints & honeycombing.
Fabricate additional temporary works to allow installing multiple precast girders at the
same time.
Revisit Power Joint detailing and construction joints. The current design requires
multiple horizontal construction joints across congested rebar. It is recommended that
the Power Joint be cast with as few construction joints as possible.
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0031.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
25
8
SUMMARY & RECOMMENDATIONS
In this study, the overall construction programme is reviewed with a fresh set of eyes, a site visit
was conducted, DRD and COWI site staff were interviewed, the construction schedule was
assessed by considering three scenarios, and suggestions on how to improve the schedule are
provided.
The three scenarios considered in this study are:
Scenario 1: Pessimistic case – slow ramp-up and slow progress.
Scenario 2: Realistic case – ramp-up and progress between Scenarios 1 and 3.
Scenario 3: Optimistic case – ramp-up and progress expected for a well-organized and
experienced design-build team working collaboratively.
This study finds that if radical changes to construction are not implemented by January 2022, it
will be unlikely to be able to open the new bridge to road traffic and have it ready for installing
catenary system for railway by second half of year 2024.
The radical changes might include one or more of the following (each would take some time to
implement, hence, a decision needs to be made regarding which one(s) to adopt quickly):
Adding a major international contractor with a large workforce (including workers, foremen,
engineers, and management staff experienced in similar major bridge construction projects)
and equipment to the SBJV team.
SBJV increasing its own capacity with a large injection of workforce (including workers,
foremen, engineers, and management staff experienced in similar major bridge construction
projects) and equipment well beyond currently on site.
Working on multiple fronts by switching to traditional in-situ construction for parts of the
bridge.
Adding one more precast girder production facility.
Significant investment has been made in the prefabrication yard and the equipment. The
segment fabrication facilities and segment installation equipment are appropriate for the project;
however, they need to be utilized much more effectively than they have been to date. Even if the
facilities and equipment are used effectively, it will still be very challenging to complete
construction by mid 2024.
Completion of design, including design approvals, is not expected to be critical. It is
recommended that SBJV be open to DRD's design improvement suggestions for increasing
construction speed.
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0032.png
26
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
Additional measures are recommended to improve SBJV's operations and construction schedule
related to the following areas (see Section 7 for more details):
General Approach & Culture
Planning & Scheduling
Segment Fabrication
Storage
Offshore Operations
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0033.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
A-1
Appendix A
Masnedø Yard Layout
TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren TRU, Alm.del - 2021-22 - Bilag 97: Orientering om tredjepartsvurdering af tidsplanen for byggeriet af den nye Storstrømsbro, fra transportministeren
2501644_0035.png
STORSTRØM BRIDGE
INVESTIGATION OF WORK PLAN AND TIME SCHEDULE FOR CONSTRUCTION
B-1
Appendix B High Level Schedules for Three Scenarios