Transportudvalget 2020-21
L 220 Bilag 22
Offentligt
2398761_0001.png
Lynetten Aqueduct
Consideration of aqueduct for Margretheholm Harbour
Yacht Club Lynetten
19 May 2021
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0002.png
Project
Client
Lynetten Aqueduct
Yacht Club Lynetten
Document
Status
Date
Reference
Lynetten Aqueduct, Consideration of aqueduct for Margretheholm Harbour
Final version
19 May 2021
126592/21-007.855
Project code
Project Leader
Project Director
126592
ir. A.J.T. Luttikholt
ir. R.P. Herrema
Author(s)
Checked by
Approved by
ing. S.J. Wolbrink
ir. A.J.T. Luttikholt MSc
ir. A.J.T. Luttikholt MSc
Initials
Address
Witteveen+Bos International Projects B.V.
Leeuwenbrug 8
P.O. Box 233
7400 AE Deventer
The Netherlands
+31 570 69 79 11
www.witteveenbos.com
CoC 58093818
The Quality management system of Witteveen+Bos International Projects B.V. has been approved based on ISO 9001.
© Witteveen+Bos
No part of this document may be reproduced and/or published in any form, without prior written permission of Witteveen+Bos International Projects
B.V., nor may it be used for any work other than that for which it was manufactured without such permission, unless otherwise agreed in writing.
Witteveen+Bos International Projects B.V. does not accept liability for any damage arising out of or related to changing the content of the document
provided by Witteveen+Bos International Projects B.V.
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
TABLE OF CONTENTS
1
1.1
1.2
1.3
INTRODUCTION
General information
Definition of the problem
Witteveen+Bos
5
5
5
6
2
2.1
2.2
2.3
2.4
2.5
PRACTICE OF AQUEDUCTS
Appearance
Benefits of an aqueduct
Phasing
Water sealing
Highlighted Aqueducts
2.5.1
2.5.2
2.5.3
Project example Margaretha Zelle
Project example Eco-aquaduct Zweth en Slinksloot
Project example Geeuwaquaduct
8
8
10
10
11
14
14
15
16
3
3.1
3.2
3.3
3.4
AQUEDUCT FOR THE MARGRETHEHOLM HARBOUR
Introduction to the conceptual design
Construction principle
Benefits
Disadvantage
18
18
19
20
20
4
5
COST ESTIMATION
CONCLUSIONS
23
25
Last page
25
Number of
pages
4
APPENDICES
I
Cost estimate
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
1
INTRODUCTION
1.1
General information
The Yacht Club Lynetten in Copenhagen have asked Witteveen+Bos to assess the feasibility of an aqueduct
design in the Margretheholm harbour knowing the design, cost estimate and time schedule for an aqueduct
prepared by Sejlklubben Lynetten. Witteveen+Bos answer is given in the following including the
characteristics of aqueducts in general. By showing the design of some of the aqueducts constructed in The
Netherlands the pros and cons will become clear. This should explain why in the last twenty years more and
more aqueducts were built in favor of bridges. Were in the early years of aqueduct construction they were
purely built to limit road traffic disruptions, the last 20 years the importance of leisure and recreational
sailing has become more important. With more attention going to recreational sailing the waiting times for
marine traffic became more of an issue. Also, with trade offs being assessed on the entire life cycle span the
movable bridges became less attractive from a cost perspective. In a number of cases the life cycle costs of
aqueducts turn out to be close to the cost of moveable bridges and together with the uninterrupted road
and marine traffic advantage the aqueduct was selected as the preferred option.
The report starts with an overview of aqueducts constructed in The Netherlands. To increase confidence and
show the robustness of the solution itself some specific details with regard to waterproofing are given. By
showing three different construction methods the versatility and applicability is demonstrated. At last a cost
estimate of an aqueduct for the Margretheholm harbour is given.
1.2
Definition of the problem
A new temporary road for transportation of soil to a land reclamation in the Northern part of Copenhagen
will be established. This road towards the land reclamation called Lynetteholmen will cross the current
navigation channel to the Margretheholm harbour as shown in the figure below.
5 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0005.png
Figure 1.1 Location of the Lynetteholmen and the construction road
Land Reclamation
Lynetteholmen
Construction road
The developer of the land reclamation and their engineer proposed an embankment for the construction
road and a bascule bridge so there will be access to the Margretheholm harbour. Unfortunately the bascule
bridge has only limited opening hours.
1.3
Witteveen+Bos
Witteveen+Bos is a firm of engineering consultants, established in the Netherlands 1946, with over
1,300 professionals across the Netherlands and 14 branch offices worldwide.
Around the world, both public- and private-sector clients call on Witteveen+Bos to help resolve the
challenges they face. We provide advice to contractors, engineering and architectural firms, energy and
water companies, railway and port authorities, and industry. In the public sector, we work for national
governments, water boards, and provincial and local authorities. Our activities cover the entire chain, from
policy-making and design to contracting and supervising construction. Witteveen+Bos aims to establish
long-term relationships with her clients that enables us to meet their needs and expectations as effectively as
possible while delivering maximum added value.
The many international projects that we have successfully completed over the years are evidence of our
effective expertise and ability to adapt to local requirements. Witteveen+Bos has been involved in the design
of the following aqueducts:
- Margaretha Zella aqueduct (Western ring road Leeuwarden) (paragraph 2.5.1).
- Richard Hageman aqueduct (Leeuwarden).
- M.C. Escher Akwaduct (Drachtsterweg, Leeuwarden).
- Hendrik Bulthuis aqueduct (Bergum).
- Geeuw aqueduct (Sneek) (paragraph 2.5.3).
- A4 Midden Delfland (paragraph 2.5.2).
6 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0006.png
Currently Witteveen+Bos is involved in the following projects with similar civil structures:
- Maasdeltatunnel and Hollandtunnel (Rotterdam).
- the Scheldt tunnel (Antwerp).
- Fehmarnbelt tunnel (Denmark-Germany).
- ViaA15 roadway (deepened road way in between sheet-piles).
Infrastructure and Mobility
Deltas, Coasts and Rivers
-
-
-
-
-
-
Civil Structures for Railways
Construction Management
Infrastructural Engineering
Smart Infra Systems
Traffic and Roads
Underground Infrastructure
-
-
-
-
-
-
-
Ecology
Coasts, Rivers and Land
Reclamation
Flood Protection and Land Development
Hydraulic and Geotechnical Engineering
Ports and Waterways
Water Management
The engineers of Witteveen+Bos worked on a lot of tunnels, viaducts and aqueducts in the Netherlands but
also abroad. Three of these project (A4 Midden Delfland, Geeuwaquaduct and Haak om Leeuwarden) are
highlighted in chapter 2.
7 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0007.png
2
PRACTICE OF AQUEDUCTS
2.1
Appearance
In the Netherlands aqueducts are quite common, especially in the northern part of the country. Due the
number of waterways and lakes and the importance of sailing to the local tourism industry aqueducts are
more and more selected in favor of movable bridges. From figure 2.1 the rapid increase in aqueducts in the
last 10 years is shown.
Aqueducts are mainly constructed at the crossing of roads with canals and small rivers. Large river crossings
are constructed with tunnels for which different techniques (other than aqueducts) are utilised. The main
problem of the canals is not the professional shipping traffic but the recreational traffic. The fixed standing
rigging (mast, or the tall upright post carrying the sails) of those ships would lead to exceptional high
bridges or to an unacceptable amount of bridge openings.
Figure 2.1 Number of aqueducts constructed in The Netherlands
Table 2.1 shows a list with the 10 last build aqueducts. A few of these aqueducts are highlighted in the
following paragraphs.
8 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0008.png
Table 2.1 Aqueducts constructed in the last 10 years
Name of the Aqueduct
Dampoort aqueduct
Amstel aqueduct
Limesaquaduct
Margaretha Zelle akwadukt*
Richard Hageman akwadukt*
Aqueduct Steenbergen aan Zee
Eco-aquaduct Zweth en Slinksloot*
Boxemtunnel
Hendrik Bulthuis akwadukt*
Aquaduct Vechtzicht
M.C. Escherakwadukt
Aquaduct Van Harinxmakanaal*
Geeuwaquaduct*
* projects Witteveen+Bos participated
Year of Execution
2011
2014
2014
2014
2014
2014
2015
2015
2016
2016
2017
2017
2008
Usually the ramps of aqueduct are less than 250 m and the closed section of the aqueducts rarely exceeds
50 m. This means that it is not classified as a tunnel and therefore no electrical and mechanical installations
(i.e. ventilation) and emergency egress facilities are required. Needless to say is that a pump sump and
lighting is required.
Aqueducts have been constructed in highways with 2x5 lanes and in local roads with 2x1 lane (and
bidirectional traffic in one tube). The first aqueducts where constructed in highways in the densely populated
western part of The Netherlands. Later on, smaller aqueducts with 2x1 lanes were constructed as well.
A rule of thumb used up to the nineties was that an aqueduct was around 3 times as expensive as an
moveable bridge. Due to increased experience and optimalisations in construction methods a factor of 1.5 is
now used.
Figure 2.2 Large (left) and small aqueduct (right)
9 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0009.png
2.2
Benefits of an aqueduct
There are a lot of benefits of building an aqueduct instead of a (movable) bridge, the most important
benefits are summed up below:
- Road traffic is not disrupted (bridge will disrupt road traffic in opened position).
- Marine traffic is not disrupted (bridge will disrupt marine traffic is in a closed position) .
·
Vertical clearance of vessels/ships/boats is infinite.
·
Vessels can sail in and out without waiting.
- No fendering works for waiting vessels required.
- No hydraulics needed for opening a bridge.
·
Reduces amount of maintenance.
·
No risk of malfunctioning.
- Low visual impact.
- Reduced noise impact.
Disadvantages of aqueducts:
- Water safety. Flooding can occur when the ground level of the hinterland is lower than the water level. In
the unlikely event of leakage of the aqueduct the hinterland will be flooded. A flood barrier or dike
around the entrance will prevent floods in these circumstances.
- Construction cost. The initial investment (direct cost) of building an aqueduct is generally higher than the
cost of building a bridge.
2.3
Phasing
For constructing an aqueduct there are two common methods. The first one is to construct the ramp and the
aqueduct in two phases, for example first constructing the right side so vessels can use the other half. After
finishing the ramp and the aqueduct the vessels can use the aqueduct and the left part can be build. This
principle is shown in the image below. Minor dredging might be required to provided sufficient depth for
the diverted temporary shipping lane.
Figure 2.3 Principle building an aqueduct in 2 phases
When it is not possible to divert the axis of the channel an aqueduct can be made by using an immersed
tunnel. The tunnel element will be transported to the location and sunk in the channel. After the element is
in place the vessels can cross the channel and the ramps can be built on either side.
10 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0010.png
Figure 2.1 Principle immersion technique for aqueducts Figure 2.2 Immersed aqueduct in Harlingen
When the immersion technique is utilised the element is usually precast in one of the ramps. No access
channel is required and the transport distance is limited. However, when construction time is important an
aqueduct could be constructed elsewhere. This has however for aqueduct construction never been used.
2.4
Water sealing
One of the most important issues in constructing an aqueduct is water tightness. Water tightness of the
concrete or sheet piles is usually not a problem. Concrete itself is water tight when the usual detailing rules
are applied. Sheet piles can leak through the joint but this can be solved by applying bituminous sealings in
the joints or, in case that’s not working, by welding the joints together. Attention has to be paid to the joint
between the concrete segment, the joints between sheet piles and concrete and the joints between the
aqueduct and the ramps. To assure a waterproof construction a couple of solutions can be used, the most
common used solutions at tunnels and aqueducts are described below.
W9U-profile
When concrete structures are submitted to outside water pressures, in tunnels, cellars, off-shore
reservoirs, etc., the joints between concrete sections are made watertight with water stops. For
normal purposes standard rubber water stop with vulcanised steel strips alongside (type
W9U) can be applied. This water stop will give water tightness between the concrete and the steel strips.
However in practice, caused by shrinkages in the concrete and errors while pouring, in the area around the
water stop the concrete can show fissures, gravel spots and the like. These issues can accommodate water
seeping through the concrete. To prevent this leakage, a special type of water stop is developed type W9UI.
This type of water sealing is most used in underground structures of concrete. In tunnels and deepened road
or train sections constructed from concrete these seals are used. This seal is also used in sealing the joint
between a concrete part and a steel part. Therefore, the steel part of the W9U is welded to, for example, a
sheet pile.
11 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0011.png
Figure 2.3 W9U profile in 3D view (left) and in cross-sectional view in structural slab (right)
GINA-profile
The Gina gasket and Omega seal can be used to make the water tight connection between the immersed
aqueduct element and the ramps of the aqueduct. This combination of seals not only allows for sealing but
also for the transfer of the hydrostatic loads and movements between the tunnel ends due to soil settlement,
creep of concrete, temperature effects and if required earthquakes. The designs are generally based on the
expected tunnel lifetime of 100 years. The GINA seal is used as a temporary water seal directly after
immersion of an element. By the hydrostatic pressure the seal is compressed by itself. The omega-profile is
the final water stop and is installed after immersion. In general the combination of GINA- and omega-seals is
not used in aqueduct construction.
Figure 2.4 GINA-profile in immersed elements
Inflatable-seal
A more common method to water tight connect an immersed aqueduct to the ramps of the aqueduct is by
making us of an inflatable seal. The rubber seal is installed on the embankment of the ramp and the first part
of the aqueduct is immersed in between the embankment. After immersion the seal is inflated and a water
tight connection is established. The connection is regarded as only temporarily. The final water stop is
created by applying an omega seal over the joint. This methods has been successfully utilised in aqueduct
construction.
12 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0012.png
Figure 2.5 Schematic sketch of inflatable seal (left)
Figure 2.6 Inflated seal on construction site (right)
Stop log recess
A stop log recess can be used for closing the gap between a immersed tunnel and the cut -and-cover part
(embankment of the ramp). A concrete slab surrounded by rubber profiles will be placed in pre-made
recesses. This method guarantees the waterproofness between these elements.
Figure 2.7 Stop log recess
13 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0013.png
2.5
Highlighted Aqueducts
In this paragraph three aqueducts are shown which show the versatility of this kind of structure.
Witteveen+Bos has been involved in the design and construction of all of these three aqueducts.
2.5.1
Project example Margaretha Zelle
The aqueduct Margaretha Zelle was part of the project Haak om Leeuwarden. This city in the north of the
Netherlands was struggling with traffic jams almost daily. An additional road was made to connect two
highways. This project contained a lot of viaducts, bridges and also an aqueduct. This aqueduct provides a
crossing from the Johannes Brandsmaweg to the center of Leeuwarden over the Van Harinxmakanaal
without traffic jams due to the opening of a bridge.
As can be seen on the photo’s below two lanes for cyclist
have been included. The inclination for the cyclists has been reduced compared to the inclination for the
road traffic by elevating the lane at the deepest section.
Table 2.2 Haak om Leeuwarden
General information
Overview
Location
Cliënt
Country
Location
Construction completed
Construction type
Google.Maps link
Provincie Friesland
the Netherlands
Leeuwarden
2020
Aqueduct
https://goo.gl/maps/A7EkpdCRw9Lu5yN39
images/pictures: www.google.com/maps / own picture
Construction principle
To construct the aqueduct a sheet pile wall was placed and the ground was excavated. Afterwards an
underwater concrete floor was cast and ground anchors were placed. After establishing a waterproof box ,
the reinforced concrete floors and walls where made. At the channel also a deck was constructed. The
concrete floors and walls secure a waterproof tunnel in the user phase.
The sheet piles are only required temporarily to create a dry environment to built the final concrete
structure. Also the underwater concrete is only required temporarily. For the Margretheholm harbour
aqueduct the sheet piles can be used as final construction and no final concrete walls are required. It
becomes more common to use the sheet piles also in the final phase and let them retain ground and water
during the entire service life. In case aesthetically the sheet piles are unwanted concrete panels are placed in
front of the sheet piles.
14 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0014.png
Figure 2.8 Cross-section of the open part of the aqueduct
2.5.2
Project example Eco-aquaduct Zweth en Slinksloot
The construction of the A4 Delft Schiedam motorway includes the construction of a 7-kilometer motorway
that is built below ground level, a 2-kilometer long land tunnel, an aqueduct and a new connection to the
Kethelplein traffic junction. The aim is to reduce the amount of traffic jams at the highway A13.
Table 2.3 A4 midden Delfland Eco-aquaduct Zweth en Slinksloot
General information
Overview
Location
Cliënt
Country
Location
Construction completed
Construction type
Google.Maps link
Heijmans N.V.
the Netherlands
Schiedam
2015
Eco- Aqueduct
https://goo.gl/maps/8XUYnxx9H7YAsZJx8
images/pictures: www.google.com/maps
15 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0015.png
Construction principle
At the A4 project the sheet pile wall is not only used in the temporary situation but also in the user phase.
Inside the dry construction pit (formed with sheet piles) a concrete floor is casted anchored with GEWI-
anchors. In this design underwater concrete was not necessary. At the side of the road a cladding is placed
against the sheet piles, this wall provides the fire safety.
Compared to the Margaretha Zelle aqueduct less material is used and therefore a cheaper construction is
obtained. In this design a water tight connection between the structural floor with the sheet piles is required.
Figure 2.9 Section of the open part of the aqueduct
2.5.3
Project example Geeuwaquaduct
This aqueduct was part of a project to upgrade a regional road to a freeway nearby the city of Sneek in the
province of Friesland. The existing drawbridge caused long waiting times for car traffic but also for the boats
and ships. Due to five grade-separated viaducts and an aqueduct the traffic can cross the river Greeuw, a
Railway and other roads without being disrupted.
16 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0016.png
Table 2.4 Geeuwaquaduct
General information
Overview
Location
Cliënt
Country
Location
Construction completed
Construction type
Google.Maps link
Provincie Friesland.
the Netherlands
Sneek
2008
Aqueduct
https://goo.gl/maps/75Yed4ZKAbW89J2R6
images/pictures: www.google.com/maps / own picture
Construction principle
To construct this aqueduct the dry pit was made with two principles, one part with a sheet pile wall and the
other part with a foil construction. After creating a dry pit the underwater concrete floor was cast and
ground anchors where placed. After establishing a waterproof box, the reinforced concrete floors and walls
where made. At the channel also a deck was constructed. The concrete floors and walls secure a waterproof
tunnel in the user phase. The sheet piles where pulled after the concrete box was finished and could be uses
somewhere else in the project.
Figure 2.10 section of the Aqueduct
17 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0017.png
3
AQUEDUCT FOR THE MARGRETHEHOLM HARBOUR
3.1
Introduction to the conceptual design
As an alternative to the proposal by By & Havn for a bascule bridge across the navigation channel to the
Margretheholm Harbour, the Yacht Club Lynetten have prepared the present conceptual design for an
aqueduct with ramps. The aqueduct and ramps have the same road alignment as proposed by By & Havn for
the bascule bridge. The ramps down to the aqueduct have a slope of 6 % following maximum gradients
according to regulation for Danish state roads. Witteveen+Bos was asked to review the design of the Yacht
Club and propose potential improvements.
In the design of Yacht Club Lynetten a caission at the location of the fairway is included. A caisson shall only
be used in case the fairway during construction cannot be diverted. In case of the Margretheholm harb our a
temporary diversion of the fairway is possible and therefore a phased construction is preferred. Although the
construction at the location of the fairway shall now be phased it is not believed that the total construction
time
being approximately 1�½ year from construction start - is affected.
A 3D-view of the construction principle including all mayor structural parts is given in the figures below.
Figure 3.1 Construction principle for aqueduct in Margretheholm harbour
18 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0018.png
Figure 3.2 Construction principle for aqueduct in Margretheholm harbour (longitudinal section)
3.2
Construction principle
For the phasing of the construction it is assumed that the aqueduct is made in two phases as shown in
paragraph 2.3. The ramps for the aqueduct are designed as a Cut-and-cover sections. First the sheet piles
will be driven into the ground of the channel and the soil in between will be excavated. In the next phase the
underwater concrete will be cast and the ground anchors will be places to prevent the floor from floating. To
reduce materials and costs the underwater concrete is only placed at the lowest points of the underpass, at
the higher points of the ramp only a reinforced concrete floor is required.
A reinforced floor will be made on top of the underwater concrete at the lower parts. The sheet piles,
concrete floor will provide a waterproof box. In between the concrete floor and the sheet pile a rubber
profile will ensure water tightness.
The sheet piles are provided with a fire-retardant coating, by applying this principle it is not needed to place
a cladding. Without the cladding it is possible to reduce the width of the aqueduct, this will have a p ositive
effect on the cost. The fire-retardant coating is also used at the Veluwemeer aqueduct in The Netherland as
shown in figure 3.3.
19 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0019.png
Figure 3.3 Rire-retardant coating on sheet piles
3.3
Benefits
By choosing an aqueduct and not a movable bridge it would be possible to access the Margretheholm
harbour for vessels and ships without limitation. Also the transport of soil to the Lynetteholmen will not be
disrupted by the opening of a bridge. Due to a limited amount of hydraulic parts in an aqueduct in
comparison to a bridge the risk of failing of the mechanism is reduced.
3.4
Disadvantage
Future use of the aqueduct
The current horizontal alignment and in particular the radius might pose a problem if it is decided to allow
regular traffic in the future. The radius is quite narrow, so there is al possibility it would be a problem to see
traffic in the other direction on time. A solution for this issue is to adjust the horizontal alignment into a
straight alignment (possible since the aqueducts is not required to cross the fairway perpendicular).
Figure 3.4 Horizontal alignment
Due to the fact that the road will only be used as a construction road, barriers and other utilities would not
be needed. By not applying barriers in the design the width of the aqueduct can be reduced to a minimum .
20 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0020.png
30 years instead of 100 years
When the cost are compared from a bridge and an aqueduct normally reduced maintenance is a big positive
point for an aqueduct. In the lifespan of 100 years a lot of the movable parts of the bridge should be
replaced so this is an expensive solution. Due to the fact that this is a temporary road this is not that big of
an argument as it would have been if the construction was made for 100 years.
Comparison with Van Harinxma aqueduct
In the figure below the vertical alignment of the Harlingen aqueduct is shown. This aqueduct is wider than
the aqueduct required for the Margretheholm harbour but is perfect to show the construction principle.
On the right side at a relative deep point the concrete box is transferred into an open excavation (with foil to
avoid uplift). On the left side the concrete floor in between sheet piles continues into a deepened section
with a length of 1.50 km.
Figure 3.5 Vertical alignment of Van Hanrinxma aqueduct in Harlingen
At the shallow section the underwater concrete is not present and only a final concrete slab is required. At
the deep sections a final reinforced concrete slab is present on a temporary under water concrete slab.
Concrete panels in front of the steel sheet piles are used for aesthetic reasons. In the Margretheholm
aqueduct the concrete panels can be omitted.
Figure 3.6 Cross-section of shallow sections of Van Harinxma aqueduct in Harlingen
21 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0021.png
Figure 3.7 Cross-section of deep sections of Van Harinxma aqueduct in Harlingen
Figure 3.8 Photos of Van Harinxma aqueduct in Harlingen
22 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
4
COST ESTIMATION
Based on the main required dimensions for road and marine traffic an indicative sketch has been made to
derive to main quantities. Structural dimensions (sheet pile weight, reinforcement rates, concrete thickness
etc) have been estimated based on engineering judgement as no geotechnical nor structural calculations
have been made.
An important difference with a regular aqueduct is the reduced design lifetime. This structure is designed for
30 years (instead of 100 years).
A second important difference with a regular aqueduct is the fact this road in only allowed to be used by
construction traffic. In the design no future use by public traffic has been taken into account. The (rather
steep) slope of 6 % and narrow road profile cannot be adjusted to meet future road design regulations after
the construction period of 30 years.
With reference to appendix I we also believe the aqueduct is more expensive to construct than the simplified
bascule bridge. However, despite the advantages for both road and marine traffic, we also believe the
operational costs differ. An aqueduct has lower operational and maintenance cost and also lower costs of
energy.
As shown in figure 4.1 the bars show higher initial costs for the aqueduct (capex) than the bascule bridge.
Also the moveable bridge electrical component probably needs replacement within these 30 years.
Mechanical installations are uncertain to last for 30 years. This also depends on the frequency of bridge
openings we do not know. Yearly costs for both the bridge and aqueduct are hardly visible at this scale and
level of detail. However as shown with the dotted lines, cumulative costs are slowly closing the gap. That
means at a longer horizon the aqueduct might be cost efficient because of the lower re-investments
(replacement) costs and lower operational expenditures.
In this cost comparison no costs for decommissioning has been taken into account. Both the bridge and
aqueduct have large component and require specialised equipment in case of decommissioning. It is
uncertain if the structure has to be removed or if life extension after 30 years is required. In case the life time
of the crossing is extended to 50 or 100 years the aqueduct will become more cost efficient.
23 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0023.png
Figure 4.1 Capex and opex excluding VAT
.
.
.
.
€ .
€ .
.
.
-
2021 2023 2025 2027 2029 2031 2033 2035 2037 2039 2041 2043 2045 2047 2049 2051 2053 2055
.
.
.
.
.
.
.
.
.
.
-
2021 2023 2025 2027 2029 2031 2033 2035 2037 2039 2041 2043 2045 2047 2049 2051 2053 2055
Bridge COWI CAPEX + OPEX
Bridge COWI CAPEX + OPEX (cumulative)
Aqueduct CAPEX + OPEX
Aqueduct CAPEX + OPEX (cumulative)
€ .
-
.
.
.
.
.
.
.
€ .
-
.
.
.
.
.
.
.
.
.
.
.
.
.
.
€ 8.
€ .
.
.
.
€ 8.
€ .
€ .
€ .
For a more detailed description of all starting points and exclusions reference is made to the first page of
appendix I. An overview of costs is given in table 4.1.
Table 4.1 Estimated cost
Item
Direct costs
Direct costs including allowance
Costs foreseen (including contractors overhead)
Construction costs (including contingencies)
Total investment costs
Cost
12.475.231
14.346.515
18.871.980
22.646.376
25.665.893
24 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
cumulative costs (NPV)
.
yearly costs (NPV)
cumulative costs (nominal)
.
yearly costs (nominal)
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
5
CONCLUSIONS
On a conceptual level the options of constructing an aqueduct in the Margretheholm harbour are evaluated.
An underwater concrete slab in between two rows of sheet piles seems the best solution for constructing an
aqueduct. On the underwater concrete a structural floor is cast. Both floors are connected with the sheet
piles and anchored with GEWI-piles. As the fairway can be temporarily diverted no use needs to be made of
a caisson.
Although this structure seems new for Denmark, the different parts utilised in the design have all been used
in other projects in Denmark. Engineering firms, design institutes and contractors are familiar with the design
of the parts although they have never used them together in aqueduct construction. Therefore, the overall
risk of aqueduct construction is considered to be lower compared to moveable bridges were the electrical
and hydraulic installations complicate design.
The construction costs of an aqueduct are higher than the construction costs of a movable bridge. However,
due to the low operational cost and maintenance cost (compared to a moveable bridge) the total costs after
30 years are more or less similar.
At this conceptual level it cannot be concluded which construction is more cost efficient. What can be
concluded is that an aqueduct shall be taken into account when comparing alternatives. With the additional
benefits associated with an aqueduct this option shall be taken into account when making the trade off. A
moveable bridge in front of a marine full of pleasure yachts seems, at least in The Netherlands, as an illogical
solution.
25 | 25
Witteveen+Bos | 126592/21-007.855 | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
Appendices
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
I
APPENDIX: COST ESTIMATE
Witteveen+Bos | 126592/21-007.855 | Appendix I | Final version
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0027.png
Client:
Project:
Copenhagen Yacht Club
Aqueduct review Margretheholm Harbour
Colofon
Price level:
Version:
Status:
2021
01
Final
Date:
Project code:
Author:
18-5-2021
126592
SCHE4
PROJECT:
ESTIMATE CLASS
AQUEDUCT REVIEW MARGRETHEHOLM HARBOUR
CLASS 5 CONCEPT SCREENING
Scope description and basis of estimate
Methodology and assumptions:
- Deterministic estimation of investment costs
- No technical drawings are available. Quantities are based on a sketch and the main required dimensions
- Private road (construction traffic only)
- Lifespan 30 years
- Road slopes allowed for 6 %
Risks:
- Risks are not quantified (probability x impact), no risk sessions are held. However, in the
cost estimate a contingecy of 20 % is included to cover technical risks.
- No additional contingency is included for project related risks, like: legal, organisation, political or financial risks.
The aim of this quick cost estimate is to compare alternatives. Differences are quantified for
comparison purposes only.
Exclusions:
Construction costs
- Barriers, asphalt (not required)
- Soil or groundwater contamination (e.g. PFAS,
asbestos etc.)
- Unexploded Ordnance (UXO)
Real estate
- Land plot acquisition
- Site clearance
- Claims due to urban planning decision
Remaining costs
Engineering
- Surveys (bathymetry, geotechnical, environmental)
- Relocate underground utilities (if any)
- Permitting
- Insurances (CAR)
Life cycle costs / OPEX
- Winter road maintenance (e.g. gritting rock salt)
- Decommissioning (end of life)
- Interests
Other (scope) exclusions
- Uncertainty reserve (e.g. P50 > P95)
- Reserve scope changes
- Costs most economical advantageous tender (MEAT)
- Financial costs
- Social costs/benefits (e.g. costs of waiting)
- VAT
Colofon
Project leader:
Project director:
Estimate standard:
Estimate model number:
A.J.T. Luttikholt MSc
R.P. Herrema MSc
CROW Publication137 (2010) www.crow.nl
W+B SSK-2010 Rekenmodel 3.05a (26-2-2020)
1 | 4 Witteveen+Bos | 126592 | Final 01
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0028.png
Client:
Project:
Copenhagen Yacht Club
Aqueduct review Margretheholm Harbour
Project summary
Price level:
Version:
Status:
2021
01
Final
Date:
Project code:
Author:
18-5-2021
126592
SCHE4
code
description
Known
Direct cost
Known
Direct cost
Preliminaries
Indirect
cost
cost
Contingency
Total
INVESTMENT COSTS (by category)
BK01
BK02
BK03
BK04
BK
VK
EK
OBK
Construction costs Dike with movable bridge (estimated by Cowi)
Construction costs Aquaduct (by Sejlklubben)
Construction costs Aquaduct (W+B, quick&dirty)
Construction costs Aquaduct (by Sejlklubben) reviewed by W+B
TOTAL CONSTRUCTION COSTS
TOTAL REAL ESTATE
TOTAL ENGINEERING
TOTAL REMAINING COSTS
-
-
12.475.231
-
12.475.231
-
3.019.517
-
-
-
1.871.285
-
1.871.285
-
-
-
-
-
4.525.465
-
4.525.465
-
-
-
-
-
18.871.980
-
18.871.980
-
3.019.517
-
-
-
3.774.396
-
3.774.396
-
-
-
-
-
22.646.376
-
22.646.376
-
3.019.517
-
INV
OORINV
SUBTOTAL INVESTMENT COSTS
Project related contingencies
INVESTMENT COSTS DETERMINISTIC
15.494.748
1.871.285
4.525.465
21.891.497
3.774.396
-
3.774.396
-
3.774.396
-
3.774.396
and
40%
17%
M€
25.665.893
-
25.665.893
-
25.665.893
-
25.665.893
35,9
15.494.748
1.871.285
4.525.465
21.891.497
SINV
Skewness
INVESTMENT COSTS PROBABILISTIC (Mu-value)
excluding
M€
21.891.497
-
21.891.497
15,4
BTW
VAT
INVESTMENT COSTS EXCLUDING VAT
Bandwidth: with 70% certainty investment costs excluding taxes lie between
Variation coëfficiënt (estimated)
Risks in relation to known costs
2 | 4 Witteveen+Bos | 126592 | Final 01
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0029.png
Client:
Project:
Sub-item:
Copenhagen Yacht Club
Aqueduct review Margretheholm Harbour
Aquaduct (W+B, quick&dirty)
Price level:
Version:
Status:
2021
01
Final
Date:
Project code:
Author:
18-5-2021
126592
SCHE4
code
3
WAAR
description
quantity
unit
unit rate
total
INVESTMENT COSTS
40
400310
400320
400330
400340
400350
400360
400370
400380
400390
400400
400410
Substructure
Aquaduct
Supply and install permanent sheet piles 136 kg/m²
Supply and install permanent sheet piles 136 kg/m²
Supply and install permanent sheet piles 169 kg/m²
Fire resistant coating
Temporary sheet piles 150 kg/m²
Supply and install girders
Supply and install steel struts
Supply and install GEWI-anchors, length 24 m
Supply and install GEWI-anchors, length 26 m
Supply and install tremie slab, thickness 1 m
Total Substructure
-
4.080,00
6.800,00
3.400,00
5.929,31
3.400,00
428,00
35,00
120,00
114,00
3.925,90
Kopje
m
pcs
pcs
pcs
-
400,00
400,00
425,00
75,00
310,00
250,00
10.000,00
3.200,00
3.500,00
125,00
9.026.435,44
-
1.632.000,00
2.720.000,00
1.445.000,00
444.698,10
1.054.000,00
107.000,00
349.999,84
384.000,00
399.000,00
490.737,50
50
500310
500320
500330
500340
500350
Earth works
Aquaduct and ramps
Excavate from building pit
Excavate from building pit ramps
Transportation and placement soil surplus (in nearby reclamation)
Dredge and dispose from access channel
Total Earth works
-
1.608,20
20.244,40
21.852,60
4.000,00
Kopje
-
5,00
5,00
7,50
10,00
313.157,50
-
8.041,00
101.222,00
163.894,50
40.000,00
60
600310
600320
600330
600340
600360
Concrete works
In situ concrete base slab between sheet pile walls (175 kg/m³)
In situ concrete capping beam (100 kg/m³)
In situ concrete elevated slab aquaduct (200 kg/m³)
In situ concrete exterior walls aquaduct (200 kg/m³)
Dewatering cellar
Total Concrete works
3.367,76
996,00
241,23
170,00
50.000,00
EUR
385,00
525,00
610,00
700,00
1,00
2.135.637,90
1.296.587,60
522.900,00
147.150,30
119.000,00
50.000,00
70
700310
700320
Misc
Mechanical and electrical installations pump cellar
Vessel guiding structures and beacons
Total Misc
1,00
120,00
EUR
m
100.000,00
7.500,00
1.000.000,00
100.000,00
900.000,00
Direct costs
12.475.231
NTD031
Additional items
Direct costs incl. allowance
15,0%
12.475.231
1.871.285
14.346.515
IK036
IK037
IK038
IK039
IK0310
Non-reoccurring costs (e.g. mob/demob)
Site facilities
Management (by building contractor)
Site organisation (eg. foreman, site managers)
General costs
2,0%
2,0%
2,0%
10,0%
8,0%
14.346.515
14.346.515
14.346.515
14.346.515
16.641.958
286.930
286.930
286.930
1.434.652
1.331.357
3 | 4 Witteveen+Bos | 126592 | Final 01
L 220 - 2020-21 - Bilag 22: Henvendelse af 20/5-21 vedrørende etablering af en akvædukt frem for en klapbro, fra Sejlklubben Lynetten
2398761_0030.png
Client:
Project:
Sub-item:
Copenhagen Yacht Club
Aqueduct review Margretheholm Harbour
Aquaduct (W+B, quick&dirty)
Price level:
Version:
Status:
2021
01
Final
Date:
Project code:
Author:
18-5-2021
126592
SCHE4
code
3
WAAR
IK0311
IK0312
description
quantity
unit
unit rate
total
Profit
Risk
Indirect costs ('contractors overhead')
3,0%
2,0%
32%
17.973.315
17.973.315
539.199
359.466
4.525.465
VZBK
Costs foreseen
18.871.980
RBK033
RBK
Contingency
Contingencies
20,0%
20%
18.871.980
3.774.396
3.774.396
BK03
Construction costs Aquaduct (W+B, quick&dirty)
22.646.376
VK03
Real estate Aquaduct (W+B, quick&dirty)
-
EK031
EK032
EK033
EK034
EK03
Detailed engineering contractor
Engineering consultancies (design)
Client's organisation (tendering, permitting)
Site supervision, site management
Engineering Aquaduct (W+B, quick&dirty)
4,0%
4,0%
4,0%
4,0%
16%
18.871.980
18.871.980
18.871.980
18.871.980
754.879
754.879
754.879
754.879
3.019.517
OK031
OK033
OBK03
Permits, insurances
Taxes, import duties etc
Remaining costs Aquaduct (W+B, quick&dirty)
0,0%
0,0%
0%
18.871.980
18.871.980
-
-
-
INV03
Total investment costs Aquaduct (W+B, quick&dirty)
25.665.893
4 | 4 Witteveen+Bos | 126592 | Final 01