Udenrigsudvalget 2018-19 (1. samling)
URU Alm.del
Offentligt
2004438_0001.png
+
Benpower SA: Dual Fuel HFO/NG
power plant, Maria Gleta, Benin
SUMMARY
The project will increase the overall capacity installed in the country of Benin and thus satisfy currently
unmet demand for electricity. Electrification provides a viable alternative to highly polluting private
generators, running on diesel. Thus, despite the application of rather carbon-intensive fuels, the
project can still feasibly provide GHG savings based on detailed analysis. It shall also be noted that the
installed electric capacity of Benin has been growing over the past 2 years and has gradually expanded
into less carbon intensive generation sources, including hydroelectricity. Two scenarios were analysed
with the power plant operating on heavy fuel oil (HFO) and operating on HFO for 2 years, before
transitioning to natural gas.
In the first scenario, mate
iality of a o sa i gs is o side ed
low’
with an associated net benefit of
24 tCO
2
e/DKK million invested.
With social cost of carbon incorporated, this is equivalent to 0.019
DKK/DKK invested.
In the second scenario, should the plant switch to natural gas in the third year of operation, materiality
of carbon savings is still
o side ed
low
ith a highe
associated net benefit of
257 tCO
2
e/DKK
million invested.
With social cost of carbon incorporated this is equivalent to 0.2089 DKK/DKK
invested.
1
URU, Alm.del - 2018-19 (1. samling) - Endeligt svar på spørgsmål 103: MFU spm., om ministeren vil oversende rapporterne med beregninger af klimaeffekten for de to kraftværker i Mali og Benin, som IFU gik ind i i 2016, til ministeren for udviklingssamarbejde
DATA AVAILABLE
The installed capacity will be 144 MW, consisting of 127 MW dual fuel power
plants and 17 MW steam turbines. (BWSC Dual Fuel HFO/NG power plant,
October 2018).
The actual working capacity is 91.3% of maximum capacity (BWSC Dual Fuel
HFO/NG power plant, October 2018).
The project life considered for the analysis is 15 years, as per the power purchase
agreement (PPA) signed with the primary offtaker for the energy
the national
utility
So iete Be i oise d E e gie Ele t i ue SBEE .
ASSUMPTIONS
The following is assumed:
Marie Gleta, Benin, is a brownfield site. Since the plan entails dismantling some
existing capacity and building new one, construction emissions are accounted for.
The estimation of construction emissions is conservative and leans towards the
more carbon-intensive infrastructure for heavy fuel oil.
The electricity produced by the dual fuel plant will increase the total capacity of
the country and will supposedly reduce the use of diesel private generators.
The plant will utilize heavy fuel oil, with the option of switching over to a less
carbon intensive option of natural gas.
Impacts are determined based on EcoInvent LCA data for construction impacts of
conventional oil and natural gas power generation and.
It is assumed that currently part of unmet demand in the country of Benin is
supplied by private generators running on diesel, in accordance with existing
practices in other countries in the region of West Africa.
The baseline scenario considered reflects the marginal emission factor, rather
than the grid capacity mix. This considers the likely fuel sources required to
generate currently unmet demand, rather than replacing current generation.
It is assumed that the working hours of a HFO power plant would be 8760 hours
per annum.
RATIONALE OF FUNDING THE PROJECT
In Benin, West Africa, there is an increasing demand for electricity, which is currently unsatisfied.
Access to power in Benin remains at a low 29% and the unreliability of supply is one of the key
constraints faced by economic actors and investors (BWSC Dual Fuel HFO/NG power plant, October
2018).
2
URU, Alm.del - 2018-19 (1. samling) - Endeligt svar på spørgsmål 103: MFU spm., om ministeren vil oversende rapporterne med beregninger af klimaeffekten for de to kraftværker i Mali og Benin, som IFU gik ind i i 2016, til ministeren for udviklingssamarbejde
IFU is considering an investment developing a HFO to help meet this need and increase access to
electricity.
The optimal opportunity for carbon reductions relates to renewable energy rather than continued
development of fossil fuel based power generation. However, given that the energy demand is
increasing at a high rate and it is easier and reliable to expand the energy generation from thermal
power plant, HFO electricity generation is investigated as an alternative to current private generator
and carbon intensive grid generation.
INTRODUCTION
In 2006, because of structural deficiencies to electricity supply, the Beninese Government decided to
build a new power plant by installing eight gas turbines with a combined capacity of 80 MW on the
site of Maria Gléta on the outskirts of Cotonou. The power plant was commissioned in 2013.
However, because of a chronic shortage of natural gas, the high cost of the alternative fuel Jet A1 as
well as design and maintenance problems, the plant could not fulfill its intended role as a steady
supplier of electricity to the grid. As a result, the Government of Benin launched an open Request for
Proposal (RFP) to invite specialized companies to submit their technical and financial proposals for
the rehabilitation, expansion and operation of the plant.
The consortium of IFU-AIIM-BWSC-Enpower has emerged as the final concessionaire for the IPP,
afte a halle gi g p o ess. The o so tiu s Spe ial Pu pose Vehi le SPV ill sig a Co essio
Agreement (CA) and Power Purchase Agreement (PPA) with the Government of Benin (GoB) to
construct a 144 MW combined cycle dual fuel HFO/Natural Gas plant (127 MW thermal duel-fuel
power plant and 17 MW steam turbine). The project will provide baseload power during a
concession period of 15 years following which the plant will be transferred to GoB. (BWSC Dual Fuel
HFO/NG power plant, October 2018).
The CA allows for a 16+4 month construction period followed by a 15 year operation period on a
build-own-operate-transfer (BOOT) basis. The power plant (Benpower SA, the project) is to be built
on a 20 hectar site in Maria Gleta, 20 km north-west of Cotonou the main commercial city and port
of Benin. (BWSC Dual Fuel HFO/NG power plant, October 2018).
Benpower SA will be operational in April 2020. Initially the plant will run on Heavy Fuel Oil (HFO)
which will be delivered by truck from storage facilities in the Port of Cotonou close by. SBEE has the
responsibility to deliver the HFO. The plant which will the be first Independent Power Producer (IPP)
in Benin will be the most fuel efficient and environmentally friendly power plant in the country.
Benpower SA, anticipated to add approximately up to 40-50%
of Be i s u e t ele t i ity apa ity,
will play a critical role in a market with a 7-8% annual increase in demand, which cannot be met due
to lack of production capacity. (BWSC Dual Fuel HFO/NG power plant, October 2018).
3
URU, Alm.del - 2018-19 (1. samling) - Endeligt svar på spørgsmål 103: MFU spm., om ministeren vil oversende rapporterne med beregninger af klimaeffekten for de to kraftværker i Mali og Benin, som IFU gik ind i i 2016, til ministeren for udviklingssamarbejde
2004438_0004.png
TABLE 1: DETAILS OF INVESTMENT
BENPOWER SA, DUAL HFO/NG POWER PLANT BENIN
UNIT
Project
City
Location
Power Type
Total Investment
IFU investment
Maximum Capacity
Actual working capacity
Guaranteed output
Working Hours/day
Working Hours/annum
Total MWH
-
-
-
-
DKK
DKK
MW
%
MWh/annum
hours
hours
MWh/annum
INVESTMENT
Benpower SA
Marie Gleta
near Cotonou, Benin
HFO/NG thermal power plant
1,392,000,000
122,500,000
144
91.3%
1,151,695
24
8,760
1,151,695
METHODOLOGY
The focus of the proposed HFO power plant is to increase the current capacity rather than replace it.
In the absence of a HFO power plant, it is assumed an equal amount of electricity would have been
provided by thermal power plants (50%) and private generators (50%), based on the current energy
mix and assumed near-future generation possibility. It shall be noted that the current energy mix of
Benin supposedly has hydroelectricity and some solar capacity installed. However, due to
unreliability of the grid, in a more conservative fashion it is assumed that diesel run private
generators contribute a higher share than prescribed. IFU should also consider future increase in
renewable energy generation could potentially reduce the benefit achieved by a fossil fuel based
plant which brings immediate gain. No further consideration of future energy scenarios has been
considered in this analysis.
To capture impacts arising from both supply chain and operations of alternative and baseline
scenarios, carbon impacts were derived from LCA values from EcoInvent to account for entire
upstream activities associated with different electricity producing technologies.
Project life is considered 15 years, in accordance with the signed PPA.
Two main scenarios were analysed: with the plant running on HFO for the entire life of the project and
for the plant running on HFO for 2 years, before being transitioned to natural gas.
Benpower SA Project GHG emissions profile
The proposed plant in Benin has a nameplate capacity of 144 MW and an assumed working capacity
ratio of 91.3% was applied. While the plant will be constructed to use both HFO and natural gas, the
infrastructure required for storing and delivering HFO is more carbon intensive. Thus the construction
emissions in both scenarios, consider the initial stage of putting up infrastructure for HFO.
4
URU, Alm.del - 2018-19 (1. samling) - Endeligt svar på spørgsmål 103: MFU spm., om ministeren vil oversende rapporterne med beregninger af klimaeffekten for de to kraftværker i Mali og Benin, som IFU gik ind i i 2016, til ministeren for udviklingssamarbejde
2004438_0005.png
Benin Baseline GHG emissions profile
Be i s g id ele t i ity ai ly o es f o fuel oil
(IEA, 2016), a part of remaining unmet demand is
catered through private diesel generators, assumed to be 29% and a small share of capacity of hydro
energy is installed (3%). Considering this energy mix ( IEA,2016) and using emission factors (Ecoinvent,
2016) a current emission factor of national energy is calculated to be 0.900 kgCO
2
e/kWh (Ecoinvent,
2016).
There is currently significant unmet demand in Benin, and this is increasing annually. Therefore, the
country energy composition has been adjusted to reflect a higher share of private generators and thus
increasing the average emission factor to 0.934 kgCO
2
e/kWh. Table 4 below presents the total
contribution by each power generation type.
TABLE 2: NATIONAL MARGINAL ENERGY SCENARIO, BENIN (IEA,2016, ADJUSTED BY TRUCOST)
POWER
TYPE
Thermal
Private
generators
FUEL
TYPE
HFO
Diesel
ESTIMATED
CONTRIBUTION
%
50%
50%
GRID EMISSION FACTOR
(Kg CO2e/KWh)
0.460
0.474
0.934
COUNTRY
GHG/KWh
0.920
0.948
Total
Benin
Here the baseline is electricity generation through thermal power plants and private generators to
produce power equivalent to 1,151,695 MWh
total generation of the project.
RESULTS
The total emissions were calculated per typical year and total project life for the project in two fuel
scenarios, compared to a baseline case. Using the client provided investment details (in Table 1), the
GHG savings or emissions avoided per Million Danish Krone (DKK) invested in the HFO plant were
calculated.
5
URU, Alm.del - 2018-19 (1. samling) - Endeligt svar på spørgsmål 103: MFU spm., om ministeren vil oversende rapporterne med beregninger af klimaeffekten for de to kraftværker i Mali og Benin, som IFU gik ind i i 2016, til ministeren for udviklingssamarbejde
2004438_0006.png
SCENARIO 1: The plant operates on HFO for the entire project life
TABLE 3: GHG SAVINGS FROM INVESTMENT MADE IN BENIN HFO POWER PLANT
SCENARIO 1
TYPICAL YEAR
Project emissions (tCO
2
e)
Baseline emissions (tCO
2
e)
1,050,342
1,075,356
TOTAL PROJECT LIFE
15,755,134
16,130,338
GHG savings (tCO
2
e)
25,014
375,204
GHG savings (tCO
2
e per Total DKK mn
Investment)
GHG savings (tCO
2
e per IFU DKK mn
investment)
N/A
270
N/A
24
IFU saving (DKK/DKK invested)
N/A
0.019
For every million DKK IFU is investing in the Benin HFO power plant, 24 tonnes of GHG is being
saved. When considering the social cost of carbon, this is equivalent to 0.019 DKK/DKK invested,
considered low materiality for carbon saving.
SCENARIO 2: The plant operates on HFO for 2 years and on natural gas for the remaining 13 years
TABLE 4: GHG SAVINGS FROM INVESTMENT MADE IN BENIN HFO POWER PLANT
SCENARIO 2
TYPICAL YEAR
Project emissions (tCO
2
e)
Baseline emissions (tCO
2
e)
804,300
1,075,356
TOTAL PROJECT LIFE
12,064,500
16,130,338
GHG savings (tCO
2
e)
271,056
4,065,839
GHG savings (tCO
2
e per Total DKK mn
Investment)
GHG savings (tCO
2
e per IFU DKK mn
investment)
N/A
2,921
N/A
257
IFU saving (DKK/DKK invested)
N/A
0.209
For every million DKK IFU is investing in the Benin HFO power plant, 257 tonnes of GHG is being
saved. When considering the social cost of carbon, this is equivalent to 0.209 DKK/DKK invested,
considered low materiality for carbon saving.
6
URU, Alm.del - 2018-19 (1. samling) - Endeligt svar på spørgsmål 103: MFU spm., om ministeren vil oversende rapporterne med beregninger af klimaeffekten for de to kraftværker i Mali og Benin, som IFU gik ind i i 2016, til ministeren for udviklingssamarbejde
The carbon savings in a natural gas scenario are higher, yet it shall be emphasized that in order to
achieve absolute carbon savings, the overall direction shall be towards lowering the dependence on
fossil fuels and expanding renewables capacity.
7
URU, Alm.del - 2018-19 (1. samling) - Endeligt svar på spørgsmål 103: MFU spm., om ministeren vil oversende rapporterne med beregninger af klimaeffekten for de to kraftværker i Mali og Benin, som IFU gik ind i i 2016, til ministeren for udviklingssamarbejde
2004438_0008.png
REFERENCES
Ecoinvent, 2016. [Online]
Available at:
https://v33.ecoquery.ecoinvent.org/
IEA, 2016.
Benin Electrciity Statistics.
[Online]
Available at:
https://www.iea.org/statistics/?country=BENIN&year=2016
US AID, Benin Installed Energy Capacity
https://www.usaid.gov/sites/default/files/documents/1860/BeninPACFSDEC2017.pdf
8
URU, Alm.del - 2018-19 (1. samling) - Endeligt svar på spørgsmål 103: MFU spm., om ministeren vil oversende rapporterne med beregninger af klimaeffekten for de to kraftværker i Mali og Benin, som IFU gik ind i i 2016, til ministeren for udviklingssamarbejde
NOTICE
Copyright © 2017
S&P T u ost Li ited T u ost , a affiliate of S&P Do Jo es I di es LLC. All ights ese ed.
Redistribution or reproduction in whole or in part is prohibited without written permission. All information provided by
Trucost is impersonal and not tailored to the needs of any person, entity or group of persons. This publication and related
materials are not intended to provide and do not constitute financial or investment advice.
DISCLAIMER
Copyright © 2017
S&P T u ost Li ited T u ost , a affiliate
of S&P Dow Jones Indices LLC. All rights reserved.
This publication and related materials are not intended to provide and do not constitute financial or investment advice.
The information in this publication should not be construed or relied upon in making, or refraining from making, any
investment decisions with respect to a specific company or security or be used as legal advice. Trucost is not an
investment advisor, and Trucost makes no representation regarding the advisability of investing in any investment fund or
other investment vehicle. A decision to invest in any investment fund or other investment vehicle should not be made in
reliance on any of the statements set forth in this document.
This pu li atio a d elated
ate ials I fo
atio
ha e ee p epa ed solely fo i fo
atio al pu poses o ly ased
upon information generally available to the public from sources believed to be reliable. The Information may not be
reproduced or disseminated in whole or in part without the prior written permission of Trucost. The information may not
be used to verify or correct other data, create indexes, risk models, or analytics or in connection with issuing, offering,
sponsoring, managing, marketing any securities, portfolios, financial products, or other investment vehicles.
Historical data and analysis should not be taken as an indication or guarantee of any future performance, analysis, forecast
or prediction.
Trucost, its affiliates, or its and their third-party data providers and licensors (colle
ti ely T u ost Pa ties do ot
guarantee the accuracy or completeness of the Information. Trucost Parties are not responsible for any errors or
omissions, regardless of the cause, for the results obtained from the use of the Information. THE TRUCOST PARTIES MAKE
NO WARRANTIES OR REPRESENTATIONS, AND, TO THE MAXIMUM EXTENT PERMITTED BY LAW, EACH TRUCOST PARTY
HEREBY EXPRESSLY DISCLAIMS ALL IMPLIED WARRANTIES, INCLUDING WARRANTIES OR MERCHANTABILITY AND FITNESS
FOR A PARTICULAR PURPOSE. WITHOUT LIMITING ANY OF THE FOREGOING AND TO THE MAXIMUM EXTENT PERMITTED
BY LAW, IN NO EVENT SHALL ANY OF THE TRUCOST PARTIES HAVE ANY LIABILITY REGARDING ANY OF THE INFORMATION
FOR DIRECT, INDIRECT, SPECIAL, PUNITIVE, CONSEQUENTIAL (INCLUDING LOST PROFITS) OR AN OTHER DAMAGES EVEN IF
NOTIFIED OF THE POSSIBILITY OF SUCH DAMAGES. The foregoing shall not exclude or limit any liability that may not by
applicable law be excluded or limited.
T u ost is the t adi g a e of S&P T u ost Li ited a li ited o pa y egiste ed
in England company number 3929223
whose registered office is at 20 Canada Square, London E14 5HL, UK.
CONFIDENTIALITY & COPYRIGHT
The information contained in this report is confidential and is submitted by Trucost on the understanding that it will be
used only by your staff and consultants. Where consultants are [self] employed, the use of this information is restricted to
use in relation to your business. In particular, the contents of this report may not be disclosed in whole or in part to any
other party without the prior written consent of Trucost.
9