Udenrigsudvalget 2018-19 (1. samling)
URU Alm.del
Offentligt
2004437_0001.png
HFO power plant in Mali, Africa
SUMMARY
Trucost, part of S&P Global was commissioned to conduct analysis of the potential CO
2
e savings
relating to a heavy fuel oil (HFO) power plant installation in Mali (Africa).
This African HFO project can feasibly provide GHG savings based on detailed analysis and
materiality of carbon savings. These are considered
low
with an associated net benefit of 15
tCO
2
e/DKK million invested. With social cost of carbon incorporated, this is equivalent to 0.012
DKK/DKK invested.
DATA AVAILABLE
The maximum working capacity of the new HFO power plant in Kayes, Mali is 81
MWe (IFU, 2016b)
The actual working capacity is 81% of maximum capacity for the HFO power
plant in Mali (IFU, 2016b)
The guaranteed output for Mali power plant is 578,160 MWh/annum (IFU,
2016b) and based on this it was calculated that the plant operates for 24
hours/day
Kayes, Mali HFO plant is a greenfield project, thus construction emissions are
included
The project life considered for the analysis is 20 years
Ecoinvent factors were used for calculating the lifetime emissions of both
alternative and baseline scenario (EcoInvent, 2016)
RATIONALE OF FUNDING
In Mali as well as generally in Africa, there is an increasing demand for electricity, which needs to
be met. The annual demand for energy is increasing at the rate of 10% per annum in Mali (African
Development Bank, 2015). IFU is considering an investment developing a HFO power plant to help
meet this need.
The optimal opportunity for carbon reductions relates to renewable energy rather than continued
development of fossil fuel based power generation. However, given that the energy demand is
increasing at a high rate and it is easier and reliable to expand the energy generation from thermal
1
URU, Alm.del - 2018-19 (1. samling) - Endeligt svar på spørgsmål 103: MFU spm., om ministeren vil oversende rapporterne med beregninger af klimaeffekten for de to kraftværker i Mali og Benin, som IFU gik ind i i 2016, til ministeren for udviklingssamarbejde
2004437_0002.png
power plant, HFO electricity generation is investigated as an alternative to current private
generator and carbon intensive grid generation.
INTRODUCTION
Mali Investment:
The developer of the Mali HFO plant is Albatros Energy Mali SA. It made a concession agreement
with the Government of Mali back in 2011 that has later been amended and now covers the
construction and operation of an 81.5 MWe HFO thermal power plant with a guaranteed output
corresponding to 66 MW.
Burmeister & Wain Scandinavian Contractor (BWSC) has been selected as Engineering,
Procurement and Construction (EPC) supplier as well as Operations & Maintenance (O&M)
contractor with a 13-year full O&M contract.
Table 1: Details of Investment made in Mali HFO power plant
Units
City
Location
Power Type
Maximum Capacity
Actual working capacity
Guaranteed output
Working Hours/day
Working Hours/annum
Total MWH
MW
%
MWh/annum
hours
hours
MWh/annum
Investment
City of Kayes
Western Mali
HFO thermal power plant
81
81%
578,160
24
8,760
578,160
METHODOLOGY
The focus of the proposed HFO power plant is to increase the current capacity rather than replace
it. Therefore, the impacts from alternative and baseline scenarios were compared with respect to
providing electricity to satisfy a part of unmet demand from the individual national grids. In the
absence of a HFO power plant, it is assumed an equal amount of electricity would have been
provided by thermal power plants (50%) and private generators (50%), based on current energy
mixes.
To capture impacts arising from both supply chain and operations of alternative and baseline
scenarios, carbon impacts were derived from LCA values from EcoInvent (EcoInvent, 2016) to
account for entire upstream activities associated with different electricity producing
technologies. All EcoInvent records used in this study have been mentioned in detail in the
reference section.
Life expectancy of the project is estimated to be 20 years. The results have been consequently
contrasted with the proposed fund participation in an effort to get a more holistic view of the carbon
savings of the project with respect to the investment.
2
URU, Alm.del - 2018-19 (1. samling) - Endeligt svar på spørgsmål 103: MFU spm., om ministeren vil oversende rapporterne med beregninger af klimaeffekten for de to kraftværker i Mali og Benin, som IFU gik ind i i 2016, til ministeren for udviklingssamarbejde
2004437_0003.png
Mali Project GHG emissions profile
The proposed plant in Mali has a capacity of 81 MW and its output is 66 MW which translates to a
working capacity of 81%. The LCA factor identified was scaled appropriately to fit the detail of the
Mali plant.
Mali Baseline GHG emissions profile
Mali gets its electricity on-grid from thermal power plants (47%) and hydro power (53%)
installations as of 2013 (African_Development_Bank, 2015). The unmet demand is fortified with
off-grid energy from private diesel generators and representing
40% of energy from EDM’s grid
electricity supply (Mali_Minstry_Of_Energy_and_Water, 2011). Using Ecoinvent factors, the total
emission from the Mali grid is determined to be 0.582 KgCO
2
e/KWh (EcoInvent, 2016).
The HFO electricity is unlikely to replace the grid generated electricity due to unmet demand, so it
is assumed energy will be in addition to the grid, replacing in part the private generation of energy
through diesel generators. The baseline scenario is therefore electricity generation through
thermal power plants (50%) and private generators (50%) to produce power equivalent to
alternative scenario (578,160 MWh/year). Hydro power generation is excluded as this is unlikely to
be further expanded and comparison is against unmet demand not current practice.
Table 2: Baseline energy scenario in Mali
Country
Power type
Thermal
Private.
generators
Fuel type
HFO + Diesel
Diesel
Estimated
contribution %
50%
50%
Total
Kg
CO
2
e/KWh)
(Anon., n.d.)
0.9200
0.9475
Kg CO
2
e component of
total baseline
0.460
0.474
0.934
Mali
(African Development Bank, 2015)
Assumptions:
It is assumed that while there is current unmet demand, should the project not take
place, 50% of additional electricity would be provided by thermal power plants as grid
production and the other 50% would be catered for by private generators assumed to be
operated by diesel combustion.
A size appropriate LCA for the construction of a HFO plant was not identified, and
therefore the GHG emissions associated with the construction phase were scaled down
accordingly. The emission from combustion is considered appropriate.
GHG emissions from combustion of HFO at power plant were used as a proxy for the
thermal plant output within the country’s grid mix.
RESULTS
The total emissions were calculated per typical year and total project life for both alternative and
baseline scenario. Using the client provided investment details (in table1) the GHG savings or
emissions avoided per million Danish Krone (DKK) invested in to HFO plants were found. IFU
investment was provided in Euros (EUR) and converted to DKK
1
.
1
Converted using UKFOREX (Average value for year 2015)
3
URU, Alm.del - 2018-19 (1. samling) - Endeligt svar på spørgsmål 103: MFU spm., om ministeren vil oversende rapporterne med beregninger af klimaeffekten for de to kraftværker i Mali og Benin, som IFU gik ind i i 2016, til ministeren for udviklingssamarbejde
2004437_0004.png
Table 3: GHG savings from investment made in Mali HFO power plant
Typical Year
Project emissions (tCO
2
e)
Baseline emissions (tCO
2
e)
527,120
539,837
Total Project Life
10,542,392
10,796,746
GHG savings (tCO
2
e)
GHG savings (tCO
2
e per Total DKK
mn Investment)
GHG savings (tCO
2
e per IFU DKK
mn investment)
IFU saving (DKK/DKK invested)
12,718
254,354
N/A
294
N/A
15
N/A
0.012
For every million DKK
2
IFU is investing in the Mali HFO power plant, 15 tonnes of GHG could
potentially be avoided. When considering the social cost of carbon, this is equivalent to 0.012
DKK/DKK invested, considered low materiality for carbon saving.
Mali relies upon hydro installations for its grid power and the energy output depends on the water
availability. Also expanding its potential would take more investment and time
(African_Development_Bank, 2015), suggesting expansion of this renewable technology would be
challenging. Hence HFO is being proposed as a short term solution rather than using other high
emission alternatives such as diesel generators. For a long term, sustainable solution, increasing
the renewable potential to achieve a less carbon intensive energy scenario would be preferable.
Limitations:
The EcoInvent records used in the study are only a proxy which are very comparable to the
power production technologies of interest. The values are global as country specific data
was not available, however they are adjusted based on regional grid mix.
Literature and online information available on Mali energy is limited, conflicting and in
places, outdated.
2
Converted using FOREX, at an exchange rate of 7.44DKK per EUR, as per average rate of 2015
4
URU, Alm.del - 2018-19 (1. samling) - Endeligt svar på spørgsmål 103: MFU spm., om ministeren vil oversende rapporterne med beregninger af klimaeffekten for de to kraftværker i Mali og Benin, som IFU gik ind i i 2016, til ministeren for udviklingssamarbejde
2004437_0005.png
REFERENCES
African_Development_Bank, 2015. Renewable Energy in Africa, Mali country profile,
EcoInvent, 2016. Database search. [Online] Available at:
https://v32.ecoquery.ecoinvent.org/Account/LogOn?ReturnUrl=%2fHome%2fIndex
[Accessed
2016].
IFU, 2016b. BWSC HFO power plant, Kayes, Mali, Clearance in Principle. (Provided by IFU)
Mali_Minstry_Of_Energy_and_Water, 2011. SREP MALI - INVESTMENT PLAN Scaling up
Renewable energy
5
URU, Alm.del - 2018-19 (1. samling) - Endeligt svar på spørgsmål 103: MFU spm., om ministeren vil oversende rapporterne med beregninger af klimaeffekten for de to kraftværker i Mali og Benin, som IFU gik ind i i 2016, til ministeren for udviklingssamarbejde
NOTICE
Copyright © 2018 S&P Trucost Limited (“Trucost”), an affiliate of S&P Market Intelligence. All rights reserved.
Trucost and EBoard are trademarks of Trucost. Redistribution or reproduction in whole or in part is prohibited
without written permission. This document does not constitute an offer of services in jurisdictions where Trucost
and its affiliates do not have the necessary licenses. All information provided by Trucost is impersonal and not
tailored to the needs of any person, entity or group of persons.
DISCLAIMER
Copyright © 2018 S&P Trucost Limited (“Trucost”), an affiliate of S&P Market Intelligence. All rights reserved.
Trucost and EBoard are trademarks of Trucost.
This document does not constitute an offer of services in jurisdictions where Trucost and its affiliates do not have
the necessary licenses. Trucost is not an investment advisor, and Trucost makes no representation regarding
the advisability of investing in any investment fund or other investment vehicle. A decision to invest in any
investment fund or other investment vehicle should not be made in reliance on any of the statements set forth in
this document. Prospective investors are advised to make an investment in any fund or other vehicle only after
carefully considering the risks associated with investing in such funds, as detailed in an offering memorandum or
similar document that is prepared by or on behalf of the issuer of the investment fund or other investment product
or vehicle.
The materials have been prepared solely for informational purposes only based upon information generally
available to the public from sources believed to be reliable. No content contained in these materials (including
credit-related analyses and data, research, valuation, models, software or other application or output therefrom)
or any part thereof (“Content”) may be modified reverse-engineered,
reproduced or distributed in any form or by
any means, or stored in a database or retrieval system, without the prior written permission of Trucost. The
Content shall not be used for any unlawful or unauthorized purposes. Trucost and its third-party data providers
and licensors (collectively “Trucost Parties”) do not guarantee the accuracy, completeness, timeliness or
availability of the Content. Trucost Parties are not responsible for any errors or omissions, regardless of the
cause, for the results obtained from the use of the Content. THE CONTENT IS PROVIDED ON AN “AS IS”
BASIS. TRUCOST PARTIES DISCLAIM ANY AND ALL EXPRESS OR IMPLIED WARRANTIES, INCLUDING,
BUT NOT LIMITED TO, ANY WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR
PURPOSE OR USE, FREEDOM FROM BUGS, SOFTWARE ERRORS OR DEFECTS, THAT THE CONTENT’S
FUNCTIONING WILL BE UNINTERRUPTED OR THAT THE CONTENT WILL OPERATE WITH ANY
SOFTWARE OR HARDWARE CONFIGURATION. In no event shall Trucost Parties be liable to any party for any
direct, indirect, incidental, exemplary, compensatory, punitive, special or consequential damages, costs,
expenses, legal fees, or losses (including, without limitation, lost income or lost profits and opportunity costs) in
connection with any use of the Content even if advised of the possibility of such damages.
The Content does not constitute or form part of any offer, invitation to sell, offer to subscribe for or to purchase
any shares or other securities and must not be relied upon in connection with any contract relating to any such
matter. ‘Trucost’ is the trading name of S&P Trucost Limited a limited company registered in England company
number 3929223 whose registered office is at 20 Canada Square, London E14 5HL, UK.
6