JUDGMENT OF THE GENERAL COURT (Sixth Chamber)
13 December 2018
*
(State aid
Public financing of the Fehmarn Belt fixed link project
Individual
aid
Decision not to raise any objections
Decision finding no State aid and
declaring the aid compatible with the internal market
Definition of State aid
Adverse effect on competition and effect on trade between Member States
Conditions governing compatibility
Aid to promote the execution of an
important project of common European interest
Necessity of the aid
Incentive effect
Proportionality of the aid
Serious difficulties justifying the
initiation of the formal investigation procedure
Obligation to state reasons
Communication on State aid to promote the execution of important projects of
common European interest)
In Case T-631/15,
Stena Line Scandinavia AB,
established in Gothenburg (Sweden), represented
by P. Alexiadis, Solicitor, and L. Sandberg-Mørch, lawyer,
applicant,
supported by
Föreningen Svensk Sjöfart,
established in Gothenburg, represented by
L. Sandberg-Mørch and J. Buendía Sierra, lawyers,
intervener,
v
European Commission,
represented by L. Armati, L. Flynn and S. Noë, acting as
Agents,
defendant,
* Language of the case: English.
EN
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
supported by
Kingdom of Denmark,
represented initially by C. Thorning, and subsequently by
J. Nymann-Lindegren, acting as Agents, and by R. Holdgaard, lawyer,
intervener,
APPLICATION pursuant to Article 263 TFEU for annulment of Commission
Decision C(2015) 5023 final of 23 July 2015 on State aid SA.39078 (2014/N)
(Denmark) for the financing of the Fehmarn Belt fixed link project (OJ 2015
C 325, p. 5),
THE GENERAL COURT (Sixth Chamber),
composed of G. Berardis, President, D. Spielmann and Z. Csehi (Rapporteur),
Judges,
Registrar: P. Cullen, Administrator,
having regard to the written part of the procedure and further to the hearing on
26 April 2018,
gives the following
Judgment
Background to the dispute
The applicant
1
The applicant, Stena Line Scandinavia AB, is part of a ferry operator group
founded in 1962 engaged in the transport of passengers, cars, trains and freight. It
operates a number of ferry routes between Denmark, Germany, Latvia, Poland,
Sweden and Norway.
The project
2
The Fehmarn Belt fixed link project between
Denmark and Germany (‘the
project’) was approved by the treaty between the Kingdom of Denmark and the
Federal Republic of Germany concerning the Fehmarn Belt fixed link signed on
3 September 2008
and ratified in 2009 (‘the international agreement’).
The
project consists of, on the one hand, infrastructure (‘the fixed link’), and, on
the other, road hinterland connections in Denmark (‘the road connections’) and
rail hinterland connections in Denmark (‘the rail connections’) (together, ‘the
hinterland connections’).
The Federal Republic of Germany is responsible for the
3
2
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
financing of and modifications to the German hinterland connections, which are
not at issue in the present proceedings.
4
The fixed link takes the form of an immersed tunnel between Rødby on the island
of Lolland in Denmark and Puttgarden in Germany; it will be approximately 19
kilometres long and consist of an electrified railway line and a motorway. The rail
connections will include the expansion and upgrade of the existing rail link
between Ringsted (Denmark) and Rødby, covering approximately 120 kilometres,
which is owned by Banedanmark, the Danish State public rail infrastructure
manager.
The project was preceded by a planning phase. The Commission was given
notification of the financing of that phase, as regards the fixed link and the
hinterland connections, for reasons of legal certainty. By its decision of 13 July
2009 in Case N 157/2009
Financing of the planning phase of the Fehmarn Belt
fixed link (OJ 2009 C 202, p. 2,
‘the project planning decision’), the Commission
concluded, first, that the measures relating to the financing of the planning of the
project may not constitute State aid and, second, that those measures were in any
event compatible with the internal market. It therefore decided not to raise any
objections within the meaning of Article 4(2) and (3) of Council Regulation (EC)
No 659/1999 of 22 March 1999 laying down detailed rules for the application of
Article [88 EC] (OJ 1999 L 83, p. 1).
The estimated cost of the entire project, in fixed 2014 prices, is 64.4 billion
Danish krone (DKK) (approximately EUR 8.7 billion): DKK 54.9 billion
(approximately EUR 7.4 billion) for the planning and construction of the fixed
link, and DKK 9.5 billion (approximately EUR 1.3 billion) for the planning and
construction of the upgrading of the hinterland connections.
According to Article 1 of the international agreement, the Kingdom of Denmark
will be the sole owner of the fixed link and will have sole responsibility and bear
the full risk of financing the fixed link, as well as the upgrading of the Danish
hinterland connections.
Pursuant to Article 6 of the international agreement and the Lov n
o
575 om anlæg
og drift af en fast forbindelse over Femern Bælt med tilhørende landanlæg i
Danmark (Law No 575 on the construction and operation of the Fehmarn Belt
fixed link project and Danish hinterland connections) of 4 May 2015
(‘the
Construction Law’), two public undertakings were entrusted with the execution of
the project. The first, Femern A/S, established in 2005, is responsible for
financing, construction and operation of the fixed link. The second, A/S Femern
Landanlæg, established in 2009, is responsible for the construction, operation and
financing of the Danish hinterland connections. Femern Landanlæg is a subsidiary
of Sund & Bælt Holding A/S, which is owned by the Danish State. Femern
became a subsidiary of Femern Landanlæg following the latter’s establishment.
5
6
7
8
3
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
9
The works relating to the construction of the fixed link will be carried out by
Femern under construction contracts subject to public procurement procedures.
Once the fixed link is operational, Femern will collect fees paid by users for using
the link. Construction of the works necessary for upgrading the road connections
will be undertaken by the Danish Highways Directorate on behalf of the Danish
State. The latter will retain ownership of the hinterland road infrastructure, which
will be made available free of charge to all users. Femern Landanlæg will be
responsible for the construction and management, including maintenance, of the
rail connections. Ownership of the rail connections is to be shared between
Banedanmark (20%) and Femern Landanlæg (80%). Banedanmark will be
responsible for all the costs relating to the operation of the rail connections, while
the costs relating to the maintenance of the rail connection will be borne by
Femern Landanlæg and Banedanmark on a pro rata basis according to their
respective shares.
Femern and Femern Landanlæg have obtained loans to finance the project (see
paragraph 12 below). Those undertakings will be unable to obtain loans for
activities other than the financing, planning, construction and operation of the
fixed link and hinterland connections. In addition, Femern will receive the charges
paid by users of the fixed link in order to discharge its debt and will pay dividends
to Femern Landanlæg, which the latter will use to discharge its own debt. Femern
Landanlæg will also receive 80% of the fees paid by the railway operators for use
of the rail connections, charged by Banedanmark, as ownership of those
connections will be shared by it and Banedanmark.
The contested measures
10
11
The contested measures, notification of which was given by the Danish
authorities, include (i) a capital injection for the benefit of Femern and (ii) a State
guarantee and State loans for the benefit of Femern and Femern Landanlæg (‘the
measures at issue’).
More specifically, the planning, construction and operation of the fixed link and
the hinterland connections are financed by loans, raised on the international
financial markets and covered by the State guarantee, or, as an alternative method
of financing, by government-backed State loans from Danmarks nationalbank
(National Bank of Denmark).
Administrative procedure
12
13
During 2014 and 2015, the Commission received five complaints, the first lodged
on 5 June 2014, claiming that the Kingdom of Denmark had granted unlawful
State aid that was incompatible with the internal market to Femern and Femern
Landanlæg.
4
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
14
During that same period, the Commission’s departments sent several requests for
information to the Danish authorities, which replied and provided further
information on a number of occasions.
By letter of 22 December 2014, the Danish authorities gave the Commission
notification, pursuant to Article 108(3) TFEU, of the measures at issue.
The contested decision
15
16
On 23 July 2015, the Commission adopted Decision C(2015) 5023 final on State
aid SA.39078 (2014/N) (Denmark) for the financing of the Fehmarn Belt fixed
link project (OJ 2015 C 325, p. 5,
‘the contested decision’).
The operative part of that decision is divided into two parts.
In the first part, the Commission concluded that the measures granted to Femern
Landanlæg for the planning, construction and operation of the hinterland
connections do not constitute State aid within the meaning of Article 107(1)
TFEU.
In particular, the Commission concluded, in the first place, that the upgrading of
the road links did not constitute an economic activity and, in the second place, (i)
that the national rail network was operated and managed on a market that is not
open to competition and (ii) that the financial support granted to Femern
Landanlæg is not liable to affect trade between Member States, as its activities
were carried out on a national, separate and geographically closed market.
In the second part, the Commission concluded that, even if the measures granted
to Femern for the planning, construction and operation of the fixed link did
constitute State aid within the meaning of Article 107(1) TFEU, they are
compatible with the internal market pursuant to Article 107(3)(b) TFEU.
More specifically, the Commission took the view that the aid allegedly granted to
Femern was compatible with Article 107(3)(b) TFEU and with the
Communication of 20 June 2014 on the criteria for the analysis of the
compatibility with the internal market of State aid to promote the execution of
important projects of common European interest (OJ 2014 C 188, p. 4,
‘the IPCEI
Communication’), as well as with the Notice on the application of Articles [107]
and [108 TFEU] to State aid in the form of guarantees (OJ 2008 C 155, p. 10,
‘the
Guarantee Notice’), for the following reasons:
first, in accordance with Section 3.1 of the IPCEI Communication, the
construction of the fixed link (and hinterland connections) is a specific,
precise and clearly defined project;
second, in accordance with Section 3.2 of the IPCEI Communication, the
project is, on the one hand, a project of European interest and, on the other,
an important project which benefits the European Union as a whole;
17
18
19
20
21
5
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
third, in accordance with paragraph 28 of the IPCEI Communication, the aid
is necessary because no private investor would carry out the project without
public support;
fourth, in accordance with paragraph 31 of the IPCEI Communication, the
aid is proportional since: (i), its intensity is below the project’s funding gap;
(ii), it is limited in scope and time and covers only the debt related to the
planning, construction and operation of the fixed link until that debt is fully
repaid; and (iii), the Danish authorities undertook to limit the guarantee and
State loans to loans obtained no later than 55 years after the opening of the
fixed link, to give fresh notification of any subsequent measure, and to
report annually on progress in the repayment of Femern’s debt;
fifth, in accordance with paragraph 40 of the IPCEI Communication, the
significant positive effects of the project for the European Union as a whole
outweigh the limited negative effect on competition and trade between
Member States;
sixth, in accordance with paragraph 49 of the IPCEI Communication, the
Kingdom of Denmark has undertaken to submit annual reports regarding
progress in the repayment
of Femern’s debt;
seventh, in accordance with Section 5.3 of the Guarantee Notice, the
mobilisation of the State guarantees is contractually linked to specific
conditions, which may go as far as the compulsory declaration of bankruptcy
of the beneficiary undertaking.
22
The Commission therefore decided not to raise any objections to the measures at
issue.
Procedure and forms of order sought
23
24
25
By application lodged at the Court Registry on 11 November 2015, the applicant
brought the present action.
On 18 February 2016, the Commission lodged its defence. The reply and the
rejoinder were lodged within the period prescribed.
By document lodged at the Court Registry on 6 April 2016, the Kingdom of
Denmark sought leave to intervene in the present proceedings in support of the
Commission. By order of 29 June 2016, the President of the Ninth Chamber of the
Court granted such leave. The Kingdom of Denmark lodged its statement in
intervention and the main parties submitted their observations on that statement
within the period prescribed.
Following a change in the composition of the Chambers of the Court, pursuant to
Article 27(5) of the Rules of Procedure of the General Court, the President of the
26
6
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
Court reallocated the case to another Judge-Rapporteur, who was assigned to the
Fifth Chamber.
27
By document lodged at the Court Registry on 7 April 2016, Föreningen Svensk
Sjöfart sought leave to intervene in the present proceedings in support of the
applicant. By order of 30 November 2016, the President of the Fifth Chamber of
the Court granted such leave. Föreningen Svensk Sjöfart lodged its statement in
intervention and the main parties submitted their observations on that statement
within the periods prescribed.
By separate document lodged at the Court Registry on 25 May 2016, the applicant
submitted an application for confidential treatment in relation to the Kingdom of
Denmark and Föreningen Svensk Sjöfart. On the same day, the applicant also
lodged a non-confidential version of the application.
On 10 January 2017, pursuant to Article 27(2) of the Rules of Procedure, the
President of the Court reallocated the case, for reasons relating to the fact that the
cases are connected, to another Judge-Rapporteur, assigned to the Sixth Chamber.
The applicant, supported by Föreningen for Svensk Sjöfart, claims that the Court
should:
31
annul the contested decision;
order the Commission to pay the costs.
28
29
30
The Commission, supported by the Kingdom of Denmark, contends that the Court
should:
Law
;dismiss the application;
.order the applicant to pay the costs.
32
The applicant puts forward four pleas in law in support of its action.
the first plea alleges infringement of Article 107(1) TFEU in so far as the
Commission erred in finding that the measures granted to Femern
Landanlæg for the planning, construction and operation of the rail
connections do not constitute State aid;
the second plea, divided into five parts, alleges infringement of
Article 107(3)(b) TFEU in so far as the Commission erred in finding that the
aid measures granted to Femern for the planning, construction and operation
of the fixed link are compatible with the internal market;
7
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
the third plea, alleging breach of Article 108(2) TFEU in so far as the
Commission infringed its obligation to initiate the formal investigation
procedure, is made up of two parts, the first alleging infringement of the
obligation to initiate the formal investigation procedure on account of the
length of the procedure and certain circumstances connected with the
conduct of the procedure, and the second alleging such infringement on
account of an insufficient and incomplete analysis of certain aspects of the
contested decision concerning (i) the measures granted to Femern
Landanlæg and (ii) the measures granted to Femern;
the fourth plea alleges failure to state adequate reasons.
33
The Court considers it appropriate to examine the pleas in the following order:
first, the fourth plea, alleging an inadequate statement of reasons;
second, the first plea and the second part of the third plea in so far as it
concerns the measures granted to Femern Landanlæg;
third, the second plea and the second part of the third plea in so far as it
concerns the measures granted to Femern.
The fourth plea, alleging failure to state adequate reasons
34
By its fourth plea, the applicant claims that the Commission failed to provide an
adequate explanation in the contested decision regarding a number of matters it
considered. That matters concern: (i) the analysis of the market for the operation
of railway infrastructure in Denmark; (ii) the assessment of the common European
interest of the project, the reasons given in the contested decision being, in its
view, contradictory as regards the taking into account of competition from ferries;
(iii) the examination of the incentive effect of the project; (iv) the analysis of the
proportionality of the aid; and (v) the assessment of the negative effects of the aid
on competition.
As a preliminary point, it should be noted that, according to settled case-law, the
statement of reasons required by Article 296 TFEU must be appropriate to the act
at issue and must disclose in a clear and unequivocal fashion the reasoning
followed by the institution which adopted the measure in question in such a way
as to enable the persons concerned to ascertain the reasons for the measure and to
enable the competent court to exercise its power of review. The requirements to be
satisfied by the statement of reasons depend on the circumstances of each case, in
particular the content of the measure in question, the nature of the reasons given
and the interest which the addressees of the measure, or other parties to whom it is
of direct and individual concern, may have in obtaining explanations. It is not
necessary for the reasoning to go into all the relevant facts and points of law, since
the question whether the statement of reasons meets the requirements of
Article 296 TFEU must be assessed with regard not only to its wording but also to
35
8
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
its context and to all the legal rules governing the matter in question (see judgment
of 8 July 2010,
Freistaat Sachsen and Land Sachsen-Anhalt
v
Commission,
T-396/08, not published, EU:T:2010:297, paragraph 143 and the case-law cited).
36
It should also be noted, with regard to the nature of the measure in question, that
the contested decision was adopted at the end of the preliminary stage of the
procedure for reviewing aid under Article 108(3) TFEU, the sole purpose of
which is to enable the Commission to form a prima facie opinion on whether the
aid concerned is wholly or partially compatible with the internal market, without
opening the formal investigation procedure laid down in Article 108(2) TFEU,
which, in turn, is designed to enable the Commission to be fully informed of all
the facts pertaining to that aid (see judgment of 11 October 2016,
Søndagsavisen
v
Commission,
T-167/14, not published, EU:T:2016:603, paragraph 110 and the
case-law cited). Such a decision, which is taken within a short period of time,
must simply set out the reasons why the Commission takes the view that it is not
faced with serious difficulties in assessing the compatibility of the aid at issue
with the internal market (see judgment of 11 October 2016,
Søndagsavisen
v
Commission,
T-167/14, not published, EU:T:2016:603, paragraph 111 and the
case-law cited).
It is in the light of those principles that it is necessary to examine the applicant’s
arguments.
In the first place, it should be noted that, in recitals 53 to 55 of the contested
decision, the Commission sets out the reasons why it took the view that the market
for the operation of Danish railway infrastructure is not open to competition.
Thus, the Commission concluded, in essence, that the rail connections owned by
Femern Landanlæg would be operated by Banedanmark on the same conditions as
those of other parts of the Danish railway system and that, given that the
management and operation of the Danish national railway is carried out on a
national, separate and geographically closed market, which is not open to
competition, the public financial support made available to Femern Landanlæg for
the rail connections was not liable to affect trade between Member States.
In the second place, it should be noted that, in recitals 88 to 93 of the contested
decision, the Commission sets out the reasons why it took the view that the project
has a common European interest.
The Commission relied essentially on four factors. First, it noted, in recital 89 of
the contested decision, that the common European interest of the project had been
recognised in the project planning decision. Second, it observed, in recital 90 of
the contested decision, that the fixed link is a trans-European transport network
project (‘TEN-T’), in particular, a priority TEN-T
project (No 20), and will
contribute to improving the connection between the Nordic countries and central
Europe as well as providing greater flexibility and time savings for road and rail
traffic. Third, it stated, in recital 91 of the contested decision, that the project
37
38
39
40
41
9
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
involves two Member States and will bring benefits which have been defined and
quantified in a profitability study prepared for the Danish ministry of transport,
which showed that the project will produce an economic return of 4.7%. Fourth, it
observed, in recital 92 of the contested decision, that the project had received EU
funding for the planning activities and an application had been submitted for EU
funding for the construction phase.
42
43
In the third place, in recitals 98 to 105 of the contested decision, the Commission
sets out the reasons why it considered that the project had an incentive effect.
The Commission observed, in essence, that the Danish authorities, while stating
that there was no viable counterfactual scenario, provided information concerning
a scenario in which no public support was granted to Femern, and that the analysis
carried out in the preliminary phases as well as an inquiry as to commercial
interest conducted
in 2001 (‘the 2001
inquiry
as to commercial interest’) had
concluded that the project could be realised only with substantial public support
and that the private sector was interested in participating in the project on
condition that support well in excess of that envisaged by the project, as approved,
was granted. The Commission also stated that, according to the information
provided by the Danish authorities, the internal rate of return (‘the IRR’) of the
project, on a debt-free basis, was 4.2% over the expected repayment period of 55
years and was therefore below the weighted average cost of capital (‘the WACC’)
that a private investor would be expected to require, estimated at 11.0%.
In the fourth place, in recitals 106 to 111 of the contested decision, the
Commission set out the reasons why it took the view that the aid was proportional.
After calculating the project’s funding gap ratio at 54.9%, the Commission stated
that the aid element granted to Femern was below that ratio. It also noted that the
aid was limited in time and scope, because the guarantee covers only debt relating
to the planning, construction and operation of the fixed link until the debt is fully
repaid, and the Danish authorities had undertaken to limit the State guarantee and
loans to the loans obtained in order to finance eligible costs no later than 55 years
after the opening of the fixed link, to give fresh notification of any public
financing measure granted after that period and to report annually on progress in
the repayment
of Femern’s debt.
In the fifth place, in recital 116 of the contested decision, the Commission
examined the negative effects of the aid on competitors.
The Commission took the view that the opening of the fixed link would have a
negative impact on ferry operators and probably, as a consequence, also on the
ports used by the ferries in terms of traffic volume and revenue. Nonetheless, the
Commission considered that those effects were inherent in the project, which
seeks to offer a quicker and more convenient alternative to ferry services.
In the light of the foregoing, it must be concluded that the statement of reasons in
the contested decision meets the requisite legal standard.
44
45
46
47
48
10
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
49
It should also be added that, by its fourth plea, the applicant refers, on certain
specific points, to the arguments put forward in the first and second pleas
concerning the merits of the Commission’s findings.
Suffice it to observe in this regard that, according to settled case-law, the
obligation to state reasons is an essential procedural requirement, as distinct from
the question whether the reasons given are correct, which goes to the substantive
legality of the contested measure (judgments of 22 March 2001,
France
v
Commission,
C-17/99, EU:C:2001:178, paragraph 35, and of 18 January 2005,
Confédération nationale du Crédit mutuel
v
Commission,
T-93/02, EU:T:2005:11,
paragraph 67).
Lastly, it should also be noted that the applicant has been able to develop its
arguments in support of the first, second and third pleas and that the Court is in a
position to conduct its review in the light of all the arguments raised by the
applicant.
The fourth plea must therefore be rejected.
The first plea and the second part of the third plea, alleging infringement of
Article 107(1) TFEU and infringement of the obligation to initiate the formal
investigation procedure in so far as concerns the analysis of the measures
granted to Femern Landanlæg for the planning, construction and operation of
the rail connections
50
51
52
53
In the first plea, the applicant submits that the Commission made an error of fact
and of law by concluding that the measures granted to Femern Landanlæg
concerning the rail connections did not constitute State aid as they were not liable
to distort competition or to affect trade between Member States within the
meaning of Article 107(1) TFEU.
In the first complaint in the second part of the third plea, the applicant refers to the
errors alleged in the first plea, arguing that those errors show that the Commission
conducted an incomplete and insufficient examination, which brought to light
serious difficulties that should have prompted it to initiate the formal investigation
procedure.
The Commission disputes the applicant’s arguments. The Kingdom of Denmark
also raises doubts concerning the admissibility of the action, in so far as it relates
to measures granted to Femern Landanlæg, on the basis that the applicant is not
individually affected.
It is appropriate to examine first of all whether the applicant’s arguments are well
founded.
Article 107(1) TFEU states as follows:
54
55
56
57
11
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
‘Save
as otherwise provided in the Treaties, any aid granted by a Member State or
through State resources in any form whatsoever which distorts or threatens to
distort competition by favouring certain undertakings or the production of certain
goods shall, in so far as it affects trade between Member States, be incompatible
with the internal market.’
58
Classification of a measure as aid incompatible with the internal market, within
the meaning of Article 107(1) TFEU, requires all the conditions laid down in that
provision to be fulfilled.
With regard, in particular, to the conditions relating to the effect on trade between
Member States and the distortion of competition, it should be noted that,
according to established case-law, the Commission is not required to establish that
the aid will in fact have an impact on trade and that competition will actually be
distorted and is required only to examine whether the aid is liable to affect such
trade and distort competition (see judgment of 9 June 2011,
Comitato ‘Venezia
vuole vivere’ and Others
v
Commission,
C-71/09 P, C-73/09 P and C-76/09 P,
EU:C:2011:368, paragraph 134 and the case-law cited). In particular, according to
case-law, the fact that an economic sector has been liberalised at EU level may
serve to determine that the aid has a real or potential effect on competition and
affects trade between Member States (see judgment of 15 December 2005,
Unicredito Italiano,
C-148/04, EU:C:2005:774, paragraphs 56 and 57 and the
case-law cited). Moreover, it is not necessary for the recipient undertaking itself to
take part in intra-EU trade. Aid granted by a Member State to an undertaking may
help to maintain or increase domestic activity, with the result that undertakings
established in other Member States have less chance of penetrating the market of
the Member State concerned (see judgment of 14 January 2015,
Eventech,
C-518/13, EU:C:2015:9, paragraph 67 and the case-law cited).
In the present case, in recitals 53 to 55 of the contested decision, first, the
Commission expressed the view that the measures granted to Femern Landanlæg
would not give rise to any distortion of competition, as the rail connections owned
by Femern Landanlæg would be upgraded and operated by Banedanmark, the
national railway infrastructure manager, under the same conditions as the other
parts of the Danish national rail network, and that there was no
competition ‘on’
or ‘for’ the market for the operation and management of the national rail network.
Second, it found that those measures were not liable to affect trade between
Member States, as the management and operation of the network in question were
carried out on a national, geographically closed and separate market, which was
not open to competition.
It is in the light of the principles outlined in paragraphs 57 to 59 above and the
wording of the contested decision that the applicant’s arguments must
be
examined.
59
60
61
12
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
The preliminary finding that the fixed link and rail connections constitute a single
integrated project
62
The applicant claims, as a preliminary point, that the fixed link and the rail
connections constitute a single integrated project and that, given that the
Commission confirmed that the aid relating to the fixed link was liable to distort
competition and to affect trade between Member States, it follows that the aid
relating to the rail connections was also liable to distort competition and to affect
such trade.
That claim is incorrect. It cannot be concluded that the measures granted to
Femern Landanlæg in relation to the rail connections constitute State aid for the
sole reason that they were adopted in connection with the same project which
granted measures for Femern in relation to the fixed link, and that those measures
were categorised as State aid by the Commission. Those are two separate aid
measures which, admittedly, concern the same project, but they have a different
purpose and different beneficiaries.
Moreover, the applicant claims that there is a contradiction between, on the one
hand, the conclusion that the financing of the costs relating to the hinterland
connections does not constitute State aid for the benefit of Femern Landanlæg
and, on the other, the fact that the costs relating to the hinterland connections were
taken into account for the purpose of determining whether the aid received by
Femern for the fixed link was compatible with the internal market.
In that regard, a distinction must be made between the measures granted to
Femern Landanlæg in connection with the cost of the hinterland connections and
the measures granted to Femern in connection with the costs of the project as a
whole.
First, as is apparent from paragraphs 69 to 102 below, the measures granted to
Femern Landanlæg for the hinterland connections do not constitute State aid
because they produce their effects on a market that is closed to competition.
Second, the measures granted to Femern for the project as a whole may constitute
State aid because those measures have an impact, in the main, on the management
and operation of infrastructure that is in competition with other transport services,
in particular ferry services.
Against that background, whether the aid granted to Femern is compatible with
the internal market must be established in the light of all the measures granted to
that company, including those covering the costs of the rail connection. In other
words, the fact that the indirect financing of the hinterland connections by
dividends paid by Femern to Femern Landanlæg does not constitute State aid for
the benefit of the latter company does not mean that the arrangements for the
financing of the entire project cannot be examined, in the light of the measures
granted to Femern, to determine whether the aid granted to the latter is
compatible.
63
64
65
66
67
68
13
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
The finding that the rail connections form part of the main Danish national rail
network
69
The applicant maintains that the mere fact that the rail connections will be
operated by Banedanmark is not sufficient to establish that they form part of the
main Danish national rail network.
In that regard, it should be noted that, as is apparent from recital 5 of the contested
decision, the rail connections entail the expansion and upgrading of the existing
rail link between Ringsted and Rødby, which belongs to Banedanmark, and that,
as is made clear in recital 55 of that decision, they will be managed by the latter in
accordance with rules applicable to the entire national network. Therefore,
according to the provisions governing the project, the rail connections simply
connect the fixed link to the existing national network and will thus form an
integral part of it.
In any event, the applicant’s argument is ineffective
because the claim that the rail
connections do not form part of the main rail network, even if it were established,
is not, of itself or in conjunction with the arguments that will be dealt with below,
capable of proving that those connections form part of a network the management
or operation of which are open to competition.
Competition on the markets for the operation and management of the Danish
railway infrastructure
72
As regards the distortion of competition, the applicant maintains that the measures
at issue granted to Femern Landanlæg affect the markets for the operation and
management of the Danish railway infrastructure and that those markets are,
de
lege and de facto,
open to competition.
The Court must therefore examine whether the Commission committed errors of
fact or of law or encountered serious difficulties when it stated, in recitals 53 to 55
of the contested decision, that there was no competition ‘on’ or ‘for’ the market
for the management and operation of the national railway network.
74
Preliminary considerations as to the relevant terminology
70
71
73
As a preliminary point, it should be noted that the words ‘operation’ and
‘management’, as used in connection with the railway network, are not used very
precisely in the contested decision or in the parties’
pleadings, which, moreover, is
a reflection of the fact that there is no specific definition of those terms in the
relevant EU legislation, in particular Council Directive 2012/34/EU of the
European Parliament and of the Council of 21 November 2012 establishing a
single European railway area (OJ 2012 L 343, p. 32).
According to the Commission’s interpretation in these proceedings, the contested
decision distinguishes between the operation of the railway infrastructure, in the
75
14
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
sense of the making available of the infrastructure to railway undertakings for
consideration, and the management of that infrastructure, in the sense of
establishing and maintaining the physical infrastructure. As the Commission
acknowledges, that terminology does tally exactly with that used in Directive
2012/34.
76
Article 3(2)
of Directive 2012/34 defines ‘infrastructure manager’ as ‘any body or
firm responsible in particular for establishing, managing and maintaining railway
infrastructure, including traffic management and control-command and
signalling’, while at the same time specifying that ‘the functions of the
infrastructure manager on a network or part of a network may be allocated to
different bodies or firms’.
The second subparagraph of Article 7(1) of Directive 2012/34 defines the
‘essential functions’ of the infrastructure manager as follows:
‘(a)
decision-making on train path allocation, including both the definition and
the assessment of availability and the allocation of individual train paths;
and
(b)
78
decision-making on infrastructure charging, including determination and
collection of the charges …’.
77
The third subparagraph of Article 7(1) of Directive 2012/34 states as follows:
‘Member States may, however, assign to railway undertakings or any other body
the responsibility for contributing to the development of the railway infrastructure,
for example through investment, maintenance and funding.’
79
Moreover, Article 3(12)
of Directive 2012/34 defines an ‘operator of service
facility’ as ‘any public or private entity responsible
for managing one or more
service facilities or supplying one or more services to railway undertakings
referred to in points 2
to 4 of Annex II’, namely access to infrastructure (point
2 of
Annex II) and additional and ancillary services (points 3 and 4 of Annex II).
After the contested decision was adopted, Article 1(2)(a) of Directive (EU)
2016/2370 of the European Parliament and of the Council of 14 December 2016
amending Directive 2012/34 as regards the opening of the market for domestic
passenger transport services by rail and the governance of the railway
infrastructure (OJ 2016 L 352, p. 1)
altered the definition of ‘infrastructure
manager’ in
Article 3(2) of
Directive 2012/34, which is now defined as ‘any body
or firm responsible for the operation, maintenance and renewal of railway
infrastructure on a network, as well as responsible for participating in its
development as determined by the Member State within the framework of its
general policy on development and financing of infrastructure’.
Furthermore, Article 1(2)(b) of Directive 2016/2370 added a paragraph 2b to
Article 3 of Directive 2012/34, which introduces a definition of the term
80
81
15
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
‘operation of the railway infrastructure’, namely ‘train path allocation, traffic
management and infrastructure charging’.
82
As a further preliminary point, it should be noted that, notwithstanding the fact
that Directive 2012/34 does not give a definition, the interpretation of the notion
of ‘maintenance’ of railway infrastructure does not give rise to any doubt, as that
term may be equated with ‘works intended to maintain the condition and
capability of existing infrastructure’, which corresponds to the definition
introduced, after the contested decision was adopted, by Article 1(2)(b) of
Directive 2016/2370, which added paragraph 2c to Article 3 of Directive 2012/34.
According to the applicant, that activity is included in the activity of ‘operation’ in
the broader sense.
83
The
opening ‘de lege’ of the relevant markets by Law
No 1249
The applicant submits that, from a legal standpoint, the operation of the railway
infrastructure, including its maintenance, and the management of that
infrastructure were opened up to competition by the Bekendtgørelse af lov n
o
1249
om jernbane (Law No 1249 on railways) of 11 November 2010 and that there are
in fact a number of railway infrastructure management companies which have
been granted a licence as well as various companies active in the railway
infrastructure operating sector.
The applicant based its arguments on Sections 2 and 3 of Sub-Chapter 3 of
Chapter 3 of Law No 1249,
entitled ‘Authorisation to operate railways and
manage railway infrastructure’, which are worded as follows:
Section
2: ‘Management of the railway infrastructure requires authorisation
and a safety certificate issued by the Transport Authority’;
Section 3: ‘Permits issued by other Member States of the European Union
under EU rules are valid in Denmark’.
84
85
However, contrary to what is claimed by the applicant, Section 2 of Sub-Chapter 3
of Chapter 3 of Law No 1249 simply provides that, in order to manage railway
infrastructure, it is necessary to obtain authorisation and a safety certificate issued
by the transport authority and does not imply, in any event, that railway
infrastructure is open to competition.
Indeed, it should be noted that, as stated in recital 71 of Directive 2012/34,
railway infrastructure is a natural monopoly and EU directives on the
liberalisation of the railway sector have not required Member States to open up
the management of that infrastructure to competition.
In that context, it should be noted, as observed by the Commission, that the fact
that an undertaking that meets certain conditions can obtain a licence to manage
railway infrastructure and that there are in fact companies in possession of
licences to manage such infrastructure does not mean that there is competition
86
87
16
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
‘on’ or ‘for’ the market for the operation and management of the Danish national
railway network, including the rail connections at issue in the present dispute. The
fact that such companies may operate on sections of the railway network which
form a kind of natural monopoly, separate from the national railway network, is
not sufficient to show that the latter, which is managed by Banedanmark under a
statutory monopoly, is open to competition. The same applies with regard to the
rail connections, which involve the expansion and upgrading of the existing
infrastructure held by Banedanmark and will be jointly owned by it and Femern
Landanlæg (see paragraphs 4 to 9 above).
88
Moreover, Section 3 of Sub-Chapter 3 of Chapter 3 of Law No 1249 simply
allows undertakings established in other EU Member States to rely on permits
issued by their country of origin in Denmark, which does not mean, of itself, that
the market for the management and operation of railway infrastructure in that
country is open to competition.
It should also be noted that, as observed by the Commission, Sub-Chapter 16 of
Chapter 5 of the Jernbanelov n
o
686 (Law No 686 on the railways) of 27 May
2015, which was in force at the date of the contested decision, provides that
Banedanmark is responsible for the management of the State railway
infrastructure and rail connections.
The same considerations justify the dismissal of the arguments alleging, first, that
Law No 686 dispensed with the obligation to obtain a licence, merely requiring
infrastructure managers to obtain security approval, and, second, that that law
does not impose Banedanmark as manager of railway infrastructure that is owned
by others than the Danish State, merely providing for such a possibility, subject to
the prior agreement of the infrastructure owner.
Any dispensation from the requirement to hold a licence and the fact that it is
possible for railway infrastructure that is owned by third parties to be managed by
operators other than Banedanmark do not show that the markets for the
management and operation of the State infrastructure and, in particular, the rail
connections, are open to competition.
The ‘de facto’ opening of the relevant markets, as evidenced by the
presence of network management companies
92
The applicant submits that the markets for the management and operation of
railway infrastructure in Denmark are de facto open to competition. It relies on the
existence of a number of companies other than Banedanmark which operate as
managers of certain sections of the Danish railway network under a licence or
which are appointed as infrastructure managers in connection with certain projects
in which they participate, in particular the Great Belt Bridge, the Øresund tunnel-
bridge and the Fehmarn Belt fixed link tunnel itself.
89
90
91
17
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
93
As the Commission and the Kingdom of Denmark have acknowledged, there are
admittedly local railway networks in private hands which do not have to be
managed by Banedanmark. Moreover, that situation is envisaged by Directive
2012/34, in particular in Article 2(4), which allows Member States to exclude
from the scope of Article 8(3) of the directive, concerning the financing of the
infrastructure manager, ‘local and regional railway infrastructures which do not
have any strategic importance
for the functioning of the rail market’ and to
exclude from the scope of Chapter IV, concerning the levying of charges for the
use of infrastructure and the allocation of railway infrastructure capacity, ‘local
railway infrastructures which do not have any strategic importance for the
functioning of the rail market’.
That being the case, even if there was competition ‘for’ the market for the
management of certain local networks, for which concession contracts are
awarded, it must be noted, first, that those networks are natural monopolies
separate from the national railway infrastructure, including the railway
connections (see paragraph 86 above) and, second, that according to paragraph 2
of Chapter 1 of the Construction Law, Femern Landanlæg is ‘authorised
to
construct and operate the Danish hinterland connections and to take the measures
necessary to carry those tasks out’ —
tasks which are mentioned in that
company’s articles of association as forming part of its objects. Therefore, the
documents before the Court do not show that Femern Landanlæg is active or may
be active on other markets, such as those for which contracts are awarded for the
management of local railway networks.
In conclusion, the existence of local infrastructure managed by operators other
than Banedanmark does not show that the rail connections are also operated as a
result of competitive tendering procedures or that Femern Landanlæg is active on
markets open to competition.
The opening of the markets for the construction and maintenance of the
railway infrastructure
94
95
96
The applicant argues that the activities of constructing and maintaining the
railway network, which are open to competition, are part of the activities included
in the concept of ‘railway network operation’, activities
with which Femern
Landanlæg is entrusted by the Construction Law, as acknowledged by the
Kingdom of Denmark and that company’s articles of association.
It is, admittedly, common ground between the parties that the markets for the
construction and maintenance of the railway infrastructure are open to
competition. Nevertheless, those markets, on which Femern Landanlæg is not
active, are separate from the market for the management and operation, in the
strict sense, of the railway infrastructure. Those markets are not therefore affected
by the measures at issue.
97
18
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
98
The Lov n
o
285 om projektering af fast forbindelse over Femern Bælt med
tilhørende landanlæg i Danmark (Law No 285 on the planning of the Fehmarn
Belt fixed link and Danish hinterland connections) of 15 April 2009
(‘the Planning
Law’), referred to in recital 13 of the contested decision, confines the activities of
Femern Landanlæg to planning the hinterland connections, whereas the
Construction Law, referred to in recital 50 of that decision, adds the activities
relating to the construction and operation of the hinterland connections.
In particular, paragraph 2 of Chapter 1 of the Construction Law, referred to by the
applicant, provides that Femern Landanlæg is ‘authorised to construct and operate
the Danish hinterland connections and to take the measures necessary to carry out
those tasks’ and that company’s articles of association refer to the same tasks as
forming part of the company’s objects. Moreover, as observed by the Kingdom of
Denmark, under Article 2(1) of the Bekendtgørelse n
o
1222 om Banedanmarks
opgaver og beføjelser (Regulation No 1222 on the tasks and powers of
Banedanmark) of 21 November 2014, Banedanmark is responsible for, inter alia,
the construction, upgrading and maintenance of public railway infrastructure.
99
100 Accordingly, while the provisions referred to in paragraphs 98 and 99 above
confer responsibility on Femern Landanlæg for ensuring that the rail connections
are constructed and operated, it is not apparent from those provisions that that
company is in a position to carry out the tasks of constructing and maintaining the
network itself in competition with other operators
a claim which is not,
moreover, made by the applicant.
101 In those circumstances, the existence of companies that construct and maintain
certain parts of the Danish railway network, including following a competitive
tendering procedure, does not demonstrate that the activities of managing or
operating the railway infrastructure, as referred to in the contested decision and
performed by Femern Landanlæg, are open to competition.
102 Therefore, irrespective of whether the activity of maintaining the railway network
is technically part of the activity of operating the network, it is clear, first, that
Femern Landanlæg does not directly perform that activity, or indeed that of
constructing the network, and, second, that the references in the contested decision
to the activities of managing and operating the railway network do not go so far as
to include the exercise of the construction and maintenance activities described to
above.
The effect on trade between Member States
103 With regard to the effect on trade between Member States, the applicant submits
that the measures at issue granted to Femern Landanlæg may prevent
infrastructure operators established in other Member States from penetrating the
Danish market and strengthen that company’s competitive position on railway
infrastructure markets in other Member States.
19
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
104 In the first place, it is clear that it is the fact that there is no competition on the
market for the management of the Danish railway infrastructure which prevents
other companies established in other Member States from penetrating that market,
so that the measures granted to Femern Landanlæg cannot affect the entry of non-
Danish operators onto the Danish market.
105 In the second place, it should be noted that the Planning Law, referred to in recital
13 of the contested decision, does not allow Femern Landanlæg to engage in
activities other than those relating to the planning of the hinterland connections,
whereas the Construction Law, referred to in recital 50 of that decision, does not
allow Femern Landanlæg to engage in activities other than those relating to the
construction and operation of the hinterland connections (see paragraphs 98 to 100
above).
106 It follows that the applicant has not succeeded in showing that Femern Landanlæg
was authorised to carry out activities other than those relating to the project and
that it could therefore penetrate markets in other Member States.
107 Moreover, the claim that Banedanmark maintains the Danish railway network in
competition with other companies and that it may penetrate other national
markets, even if established, does not show, first, that the measures granted to
Femern Landanlæg, but not to Banedanmark, constitute indirect aid for the benefit
of Banedanmark
a claim not made by the applicant
or, second, that such
measures are liable to distort competition on a market on which Femern
Landanlæg operates.
Conclusion
108 In the light of all the foregoing, it must be concluded that there is no basis for the
applicant’s claim that the Commission’s examination is vitiated by an error of fact
or of law, and that it has failed to demonstrate that the Commission encountered
serious difficulties which should have prompted it to initiate the formal
investigation procedure.
109 As a consequence, the Court rejects as unfounded the first plea and the first
complaint in the second part of the third plea, in so far as concerns the analysis of
the measures granted to Femern Landanlæg for the planning, construction and
operation of the rail connections.
The second plea and the second part of the third plea, alleging infringement of
Article 107(3)(b) TFEU and infringement of the obligation to initiate the formal
investigation procedure in so far as concerns the compatibility with the internal
market of the measures granted to Femern for the planning, construction and
operation of the fixed link
110 The second plea alleges infringement of Article 107(3)(b) TFEU in so far as the
Commission concluded that the aid measures granted to Femern were compatible
20
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
with the internal market. That plea is made up of five parts, by which the applicant
alleges errors of law and manifest errors of assessment in respect of: (i) the
common European interest of the project; (ii) the necessity of the aid; (iii) whether
the aid was proportional; (iv) the distortion of competition; and (v) the conditions
for mobilising State guarantees.
111 The second part of the third plea alleges infringement of the obligation to initiate
the formal investigation procedure, for the purpose of Article 108(2) TFEU, in so
far as the Commission conducted an insufficient or incomplete assessment of the
compatibility of the aid measures. That part of the plea is made up of five
complaints, the first of which has been dealt with at the same time as the first plea.
The second to fifth complaints concern: (i) the common European interest of the
project; (ii) the necessity of the aid; (iii) the proportionality of the aid l; and (iv)
distortion of competition.
112 The Court considers it appropriate to examine first the first four parts of the
second plea together with the corresponding complaints in the second part of the
third plea and, afterwards, the fifth part of the second plea.
The relevant case-law
113 As a preliminary point, with regard to the arguments alleging failure to initiate the
formal investigation procedure, it should be borne in mind that, according to
settled case-law, the procedure under Article 108(2) TFEU must be followed
whenever the Commission encounters serious difficulties in determining whether
aid is compatible with the internal market. It follows that the Commission, when
taking a decision in favour of aid, may restrict itself to the preliminary
examination under Article 108(3) TFEU only if it is able to satisfy itself after an
initial examination that the aid is compatible with the internal market. If, on the
other hand, the initial review leads the Commission to the opposite conclusion or
even if it does not enable the Commission to overcome all the difficulties involved
in determining whether the aid is compatible with the internal market, the
Commission is under a duty to obtain all the requisite opinions and, for that
purpose, to initiate the procedure under Article 108(2) TFEU (see judgment of
27 September 2011,
3F
v
Commission,
T-30/03 RENV, EU:T:2011:534,
paragraph 53 and the case-law cited).
114 Although it has no discretion in relation to the decision to initiate the formal
investigation procedure, where it finds that such difficulties exist, the Commission
nevertheless enjoys a certain margin of discretion in identifying and evaluating the
circumstances of the case in order to determine whether or not they present
serious difficulties (see judgment of 27 September 2011,
3F
v
Commission,
T-30/03 RENV, EU:T:2011:534, paragraph 54 and the case-law cited).
115 According to case-law, the concept of serious difficulties is an objective one. The
existence of such difficulties must be sought both in the circumstances in which
the contested measure was adopted and in its content, in an objective manner,
21
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
comparing the grounds of the decision with the information available to the
Commission when it took a decision on the compatibility of the disputed aid with
the internal market. It follows that judicial review by the Court of the existence of
serious difficulties will, by its nature, go beyond simple consideration of whether
or not there has been a manifest error of assessment. The applicant bears the
burden of proving the existence of serious difficulties and may discharge that
burden by reference to a body of consistent evidence, concerning, first, the
circumstances and the length of the preliminary examination procedure and,
second, the content of the contested decision (see judgment of 27 September 2011,
3F
v
Commission,
T-30/03 RENV, EU:T:2011:534, paragraph 55 and the case-
law cited).
116
Furthermore, with regard to the applicant’s pleas concerning the application of
Article 107(3)(b) TFEU, it should be borne in mind that that article confers on the
Commission a discretion, the exercise of which involves complex economic and
social assessments (see judgment of 22 December 2008,
Régie Networks,
C-333/07, EU:C:2008:764, paragraph 78 and the case-law cited). Judicial review
of the manner in which that discretion is exercised is confined to establishing that
the rules of procedure and the rules relating to the duty to give reasons have been
complied with and to verifying the accuracy of the facts relied on and that there
has been no error of law, manifest error in the assessment of the facts or misuse of
powers (judgment of 22 December 2008,
Régie Networks,
C-333/07,
EU:C:2008:764, paragraph 78 and the case-law cited). In particular, it is not for
the Court to substitute its own economic assessment for that of the author of the
decision (judgment of 25 June 1998,
British Airways and Others
v
Commission,
T-371/94 and T-394/94, not published, EU:T:1998:140, paragraph 79).
The common European interest of the project
117 By the first part of the second plea, the applicant raises two complaints, alleging
(i) a manifest error of assessment in calculating the socio-economic return of the
project and (ii) misapplication of Article 107(3)(b) TFEU and of the IPCEI
Communication. The second complaint in the second part of the third plea alleges
infringement of the obligation to initiate the formal investigation procedure in so
far as concerns the calculation of the socio-economic return of the project.
118 The Commission disputes
the applicant’s arguments.
119
It is appropriate to examine, first, the Commission’s assessment concerning the
calculation of the socio-economic return of the project in terms of the alleged
manifest error of assessment and infringement of the obligation to initiate the
formal investigation procedure and, second, the Commission’s assessment
concerning the alleged misapplication of Article 107(3)(b) TFEU in terms of
manifest error of assessment.
22
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
The calculation of the socio-economic return of the project
120 In the contested decision, the Commission based its assessment of the common
European interest of the project on four factors. First, in recital 89 of the decision,
it stated that the common European interest of the project had been recognised in
the project planning decision. Second, in recital 90, it observed that the fixed link
was a priority TEN-T project (No 20) and contributed to improving the connection
between the Nordic countries and central Europe. Third, in recital 91, it stated that
the project will produce a positive economic return and, lastly, in recital 92, that
the project had obtained EU funding for the planning activities and that an
application had been submitted for EU funding for the construction phase.
121 In particular, recital 91 of the contested decision, which is disputed in the
complaint under consideration, states as follows:
‘The Project involves two Member States, i.e. Denmark and Germany, and the
benefits go beyond those two Member States. The benefits of the Project were
clearly defined and quantified in a cost benefit study prepared for the Danish
Ministry of Transport. The cost benefit analysis shows that the Project will have
wide benefits for Europe. Despite significant investment costs, the Fixed Link will
return a net benefit and
produce an economic return of 4.7 [%].’
122 It is common ground between the parties that that conclusion is based on two
documents: the study of 5 January 2015 and the study of 27 March 2015, carried
out for the Danish Ministry of Transport.
123 The applicant puts forward three arguments in support of the complaints under
consideration.
124 By its first argument, the applicant maintains, in the first place, that it is not the
study of 5 January 2015 but the updated version of that study, namely that of
27 March 2015, which indicates a socio-economic return of 4.7% at European
level.
125 The Commission acknowledges that the figure of 4.7% is based on the new,
updated calculation carried out in the study of 27 March 2015 in response to the
applicant’s
observations.
126 It must
therefore be concluded that the Commission’s
statement in recital 91 and
footnote 31 of the contested decision that the figure of 4.7% is based on the study
of 5 January 2015 is incorrect, as it is common ground between the parties that the
source of that figure is the updated calculation given in the study of 27 March
2015.
127 However, although regrettable, that error did not, of itself, have any bearing on the
Commission’s examination. It is common ground between the parties that, as is
apparent from the wording of recital 91 of the contested decision and irrespective
23
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
of the merits of that assessment, which will be examined below, the Commission
based its decision on an economic return at European level of 4.7%.
128 In the second place, the applicant contends that the calculation of a socio-
economic return of 4.7% is based on the incorrect premiss that the fixed link will
not be in competition with ferries.
129 In that regard, it should be noted that in the contested decision the Commission
based that premiss on the conclusions of the study of 5 January 2015, as revised
by the study of 27 March 2015. That study does not take account of competition
from ferries, ‘in accordance with normal practice’ and the experience gained from
the Great Belt and Øresund bridge projects. Nevertheless, that study measures, in
the interests of prudence, the impact of competition from ferries operating at
reduced frequency. Under that scenario, the socio-economic return was estimated
at 4.1%.
130 The applicant maintains that it will continue with its activities, that the study is
based on a
‘simplistic simulation’ of ferry traffic and that the projects referred to
by the Commission do not support the premiss that the fixed link will not face
competition from ferries, which the Commission disputes.
131 Those arguments are not sufficient to show that the Commission made a manifest
error of assessment or that it carried out an insufficient or incomplete
examination.
132 First, the socio-economic return of 4.7% is just one of the four factors on which
the Commission based its assessment of the common European interest of the
project (see paragraph 120 above). It joins the other factors taken into account by
the Commission,
including the classification of the project as a ‘priority TEN-T’
project, which is a strong indication of the common European interest of the
project.
133 Second, it is reasonable, or at the very least not manifestly incorrect, to conclude
that the opening of the fixed link will lead to the disappearance of ferry services
on the line covered by the fixed link.
134 In any event, the 0.9% reduction, due to account being taken of the presumption
that the ferry services will continue in the sensitivity calculations, even if it
slightly reduced the socio-economic return of the fixed link to a level below the
4% threshold, is not in any event indicative of a manifest error of assessment on
the part of the Commission. As the Kingdom of Denmark observed, the applicant
cannot include the 0.9% negative sensitivity calculation in relation to the
assumption that ferries will continue to operate when all the positive and negative
sensitivity calculations have been disregarded. Moreover, the percentage figure of
4% is simply an indicative ceiling, and merely one of the factors taken into
account by the Commission, including the socio-economic return at Danish level,
which is above 4%.
24
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
135 By its second argument, the applicant submits that the socio-economic return
measured by the Commission does not take account of the costs incurred by the
project before 2015, which, according to the applicant, would give rise to a further
reduction in the return of 0.3%.
136 Nevertheless, as the Kingdom of Denmark observed, the applicant cannot take
account of the sensitivity calculations relating to the inclusion of costs incurred
before 2015 when all the other sensitivity calculations are disregarded. Moreover,
that argument does not alter the conclusion that the socio-economic return
demonstrates that the project is of common European interest.
137 By its third argument, the applicant submits that the Commission was not entitled
to conclude, as it did in recital 91 of the contested decision, that the ‘Project will
have wide benefits for Europe’, as the socio-economic
return of 4.7% at EU level,
even if it were established, is only slightly above the Danish threshold of 4% and
considerably below the 14% threshold of the Great Belt fixed link.
138 In that regard, as the Commission argues, it is sufficient to note that the fact that
the anticipated return of the project, which is above the Danish threshold, is below
that of other projects does not, of itself, show that the project is not of common
European interest.
139 In conclusion, as regards the calculation of the socio-economic return of the
project, first, the applicant is not entitled to claim that the Commission’s
examination is vitiated by an error of law or a manifest error of assessment and,
second, the applicant has failed to show that there were difficulties of assessment
which should have prompted the Commission to initiate the formal investigation
procedure.
140 The first complaint in the first part of the second plea and the second complaint in
the second part of the third plea, concerning the calculation of the socio-economic
return of the project, must therefore be rejected.
The application of Article 107(3)(b) TFEU and the IPCEI Communication
141 As a preliminary point, it should be noted that the concept of common European
interest inherent in Article 107(3)(b) TFEU must be interpreted strictly and that a
project may be so classified only if it forms part of a transnational European
programme jointly supported by a number of Member State governments or arises
from concerted action by a number of Member States to combat a common threat
(see judgment of 6 October 2009,
Germany
v
Commission,
T-21/06, not
published, EU:T:2009:387, paragraph 70 and the case-law cited).
142 The concept of common European interest was explained by the Commission in
the IPCEI Communication, in the light of which that concept must be interpreted,
a point which the applicant does not dispute.
25
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
143 In recitals 89 to 92 of the contested decision, the Commission based its
examination of the common European interest of the project on the following
factors:
first, the common European interest of the fixed link was recognised in the
decision regarding the planning of the project;
second, the fixed link will contribute to the development of the TEN-T, in
particular by improving the connection between the Nordic countries and
central Europe;
third, (i) the project involves two Member States and its benefits go beyond
those two Member States and (ii) the benefits of the project were clearly
defined and quantified, the economic return of the project having been
assessed at 4.7%;
fourth, the project obtained EU funding for the planning activities and an
application for EU funding for the construction phase was submitted.
144 In support of the complaint under consideration, the applicant puts forward three
arguments.
145
In that regard, it is necessary, first, to dismiss the applicant’s first argument,
alleging, in essence, that the project planning decision and, more generally, the
Commission’s previous decision-making
practice, were irrelevant for the purpose
of examining whether the project was of common European interest.
146 Recital 40 of the project planning decision, which is echoed by the Commission in
recital 89 of the contested decision, simply stresses the importance of the fixed
link in the context of the TEN-T, a point which is repeated by the Commission in
recital 90 of the contested decision and, moreover, is not a decisive factor in the
Commission’s conclusion on the common European interest of the project, albeit
an important indication of the existence of such an interest. In that context, the
argument that the
Commission’s earlier decision-making
practice is irrelevant is
ineffective as the Commission did not base its conclusion on the project planning
decision or any other earlier decision.
147 Next, it is
appropriate to examine together the applicant’s second and third
arguments, alleging, in essence, that the importance of the project in the context of
the TEN-T and the joint funding of the project by the European Union are not
decisive factors for the purpose of establishing that the project is of common
European interest and do not justify disregarding the other cumulative conditions
set out in the IPCEI Communication.
148
It should be noted in that regard that the Commission’s assessment in the
contested decision of whether there is a common European interest is based on the
two factors mentioned in paragraph 147 above, which are not disputed by the
applicant, and on the fact that the project will provide benefits that go beyond the
26
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
two Member States directly concerned and that those benefits are clearly defined
and quantified, the economic return of the fixed link having been estimated at
4.7%.
149 Irrespective of the merits of the latter consideration, which was examined in
paragraphs 120 to 139 above, those three factors meet the conditions set out in the
IPCEI Communication, having regard to the common European interest test.
150
Indeed, those factors form part of the ‘general cumulative criteria’ in
paragraphs 14 to 19 of Section 3.2.1 of the IPCEI Communication and include one
of the ‘general positive indicators’, as set out in
paragraph 20(f) of the
communication.
151 Lastly, it is true that doubts may arise as to whether the condition laid down in
paragraph 18 of the IPCEI Communication, namely that the project must involve
co-financing by the beneficiary, which is disputed by Föreningen Svensk Sjöfart,
is fulfilled. However, as submitted by the Commission, the project is funded in
large part by the beneficiaries of the measures, on account of the fact that tolls and
fees will be charged to users of the fixed link and rail connections, which satisfies
that condition.
152 In conclusion, the Court finds, first, that there are no valid grounds for the
applicant’s claim that the Commission made a manifest error of assessment
in
concluding that the project was of common European interest and, second, that the
applicant has failed to show that the Commission’s examination disclosed serious
doubts which should have prompted it to initiate the formal investigation
procedure.
153 The first part of the second plea and the second complaint in the second part of the
third plea, concerning the common European interest of the project, must
therefore be rejected in their entirety.
The necessity of the aid
154 By the second part of the second plea, the applicant raises two complaints,
alleging an error of law and a manifest error of assessment in the assessment of
the necessity of the aid, in so far as concerns, first, the incentive effect of the aid
and, second, the counterfactual scenario, including
the calculation of the project’s
IRR. By the third complaint in the second part of the third plea, the applicant also
alleges infringement of the obligation to initiate the formal investigation
procedure in relation to those factors.
155 The Commission disputes those arguments.
27
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
The incentive effect of the aid
156 As a preliminary point, it is appropriate to set out the content of paragraph 28 of
the IPCEI Communication:
‘The aid must not subsidise the costs of a project that an undertaking would
anyhow incur and must not compensate for the normal business risk of an
economic activity. Without the aid the project’s realisation should be impossible,
or it should be realised in a smaller size or scope or in a different manner that
would significantly restrict its
expected benefits …’
157 Footnote No 24, in paragraph 28, of the IPCEI Communication states as follows:
‘The aid application must precede the start of the works, which is either the start
of construction works on the investment or the first firm commitment to order
equipment or other commitment that makes the investment irreversible, whichever
is the first in time …’
158 By its arguments, the applicant claims, in essence, that the aid, as referred to in
paragraph 28 of the IPCEI Communication, does not have any incentive effect, as
construction work on the fixed link had already started before an aid application
had been made or a commitment given by the Danish authorities to grant such aid.
159 It should be noted in that regard, first, that a certain number of preparatory works,
anticipated by the Planning Law, were authorised by the project planning
decision, and, as stated in recital 13 of the contested decision, the Danish
authorities confirmed that the standstill obligation had been observed, in
accordance with the measures laid down in the Construction Law, as required by
Article 108(3) TFEU.
160 Next, it is clear from the documents before the Court that Femern was established
for the sole purpose of constructing and operating the fixed link. It is therefore
required by its articles of association to do so.
161 Lastly, it is not disputed that Femern was not in a position to start work on the
project unless it was granted the aid at issue.
162 In those circumstances, a prior aid application or a prior commitment on the part
of the Danish authorities to grant aid are not prerequisites for demonstrating that
the aid had an incentive effect for the purpose of paragraph 28 of the IPCEI
Communication.
163 Moreover, the case-law relied on by the applicant does not alter that conclusion.
The judgments of 15 April 2008,
Nuova Agricast
(C-390/06, EU:C:2008:224),
and of 13 June 2013,
HGA and Others
v
Commission
(C-630/11 P to C-633/11 P,
EU:C:2013:387), concern aid schemes approved on the basis of the Guidelines on
national regional aid (OJ 1998 C 74, p. 9), the third subparagraph of Section 4.2 of
which states that ‘aid schemes must lay down that an application for aid must be
28
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
submitted before work is started on the projects’.
That is a very different context
from that of the present case and cannot be compared with it.
164 It must therefore be concluded that the applicant is not entitled to claim that the
Commission made a manifest error of assessment in concluding that the aid had
an incentive effect and that it has failed to show that the Commission’s
examination disclosed serious doubts which should have prompted it to initiate the
formal investigation procedure.
165 The first complaint in the second part of the second plea and the third complaint in
the second part of the third plea must therefore be rejected in so far as concerns
the examination of the incentive effect of the aid.
The counterfactual scenario
166 As a preliminary point, it is appropriate to refer to the content of paragraphs 29
and 30 of the IPCEI Communication:
‘29.
The Member State must provide the Commission with adequate information
concerning the aided project as well as a comprehensive description of the
counterfactual scenario which corresponds to the situation where no aid is
awarded by any Member State. The counterfactual scenario may consist in
the absence of an alternative project or in a clearly defined and sufficiently
predictable alternative project considered by the beneficiary in its internal
decision-making, and may relate to an alternative project that is wholly or
partly carried out outside the Union.
30.
In the absence of an alternative project, the Commission will verify that the
aid amount does not exceed the minimum necessary for the aided project to
be sufficiently profitable, for example by making possible to achieve an IRR
corresponding to the sector or firm specific benchmark or hurdle rate.
Normal rates of return required by the beneficiary in other investment
projects of a similar kind, its cost of capital as a whole or returns commonly
observed in the industry concerned may also be used for this purpose. All
relevant expected costs and benefits must be considered over the lifetime of
the project.’
167 The applicant raises seven arguments in that regard. By the first and second, it
disputes, in essence, the Commission’s conclusion that there was no
counterfactual scenario, which is at variance with the conclusions of a cost-benefit
report commissioned in 2000 by the Danish and German Ministries of Transport
(‘the 2000 cost-benefit report’).
168 In that connection, recitals 99 and 100 of the contested decision read as follows:
‘99
[With regard to paragraph 29 of the IPCEI Communication] the Danish
authorities submit that there is no counterfactual or an alternative project.
The Danish Parliament has sole decision-making authority as regards the
29
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
project’s scope and its means of financing. Hence, [Femern] and [Femern
Landanlæg] have no power to decide to carry out an alternative project of a
different scale. Consequently, no realistic description of an alternative
project could be provided by Denmark.
100 However, the Danish authorities provided information regarding a scenario
where no public support is granted to [Femern]. The analysis conducted in
the preliminary phases shows that the Fehmarn Belt fixed link project can
only be realised with substantial public support either in the form of State
guarantees or direct grants.’
169 Recital 101 of the contested decision summarises the results of the 2001 inquiry as
to commercial interest, which shows that the project was not feasible without
public support.
170 It is apparent from recitals 99 to 101 of the contested decision that, in the
Commission’s view, the Danish authorities, while claiming that there was no
counterfactual scenario or any realistic alternative project, provided information
relating to a scenario in which no public support would be granted to Femern, a
scenario which confirmed that the project could be completed only with
substantial public support. Moreover, the 2001 inquiry as to commercial interest
confirmed that the private sector was interested in participating in the project on
condition that State subsidies far exceeding the support envisaged by means of the
RTE or State guarantees were granted.
171 It follows that, notwithstanding the ambiguous wording of recital 99 of the
contested decision, which states that ‘the Danish authorities submit that there is no
counterfactual or alternative project’, the Commission based its decision on the
premiss that there was no alternative project, not on the premiss that there was no
counterfactual scenario at all.
172 It should be noted in that regard that, according to paragraph 29 of the IPCEI
Communication, a counterfactual scenario may consist in the absence of an
alternative project.
173 What now remains to be considered is the argument that the Commission did not
take account of the 2000 cost-benefit report, which examined several alternatives
to the project, the most advantageous of which related to a scenario in which no
fixed link was constructed and the existing ferry services were modernised.
174 As the Commission stated, the 2000 cost-benefit report is one of the documents
which served as a basis for the 2001 inquiry as to commercial interest. The
conclusion of that study is as follows:
‘Evaluation results show that the relative efficiency of the investment in an
improved ferry system is considerably higher than for the best ranked fixed link
alternative, whereas the absolute magnitude of net benefits gained by the fixed
link solution is by far not achievable by an improved ferry system.’
30
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
175 Therefore, while it is true that, according to the 2000 cost-benefit report, in terms
of relative efficiency, improvement of the ferry system would be more
advantageous than construction of the fixed link, that report acknowledges that the
net benefits gained by the solution in the form of the fixed link would not be
achieved by improvements to the ferry system. That report cannot call into
question the Commission’s assessment, based
on the results of the 2001 inquiry as
to commercial interest, that report, moreover, having been used as one of the
references in that inquiry.
176 By its third argument, the applicant submits that the Commission has failed to
establish market failure in the present case and has relied solely on the 2001
inquiry as to commercial interest, which is several years old and relates to a
project which was different in scope and costs to those of the current project.
177 It is sufficient to note in that regard that the reference made by the Commission to
the 2001 inquiry as to commercial interest was simply intended to show that the
private sector would not have undertaken such a large project without State
financial support. The applicant has not explained the extent to which that
conclusion may be called into question by the changes in scope and cost in the
original project, by showing, for example, that in the meantime a counterfactual
scenario in which no aid was granted had become viable.
178 By its fourth to sixth arguments, the applicant criticises the lack of detail in the
calculation of the IRR and allege that it is incorrect. It maintains that the
calculation could not be based on a 55-year repayment period, contrary to what is
stated in the contested decision, in particular in footnote 35, in recital 104 thereof.
In particular, it disputes the claim that the IRR was calculated by reference to the
repayment period, estimated by the Commission at 55 years, and not by reference
to the lifetime of the project, which,
as stated in an extract from Femern’s website,
is 120 years. The Commission, it is alleged, applied a test relating to the
proportionality of the aid, not the necessity of the aid.
179 It is appropriate to examine first the arguments relating to the serious difficulties
encountered by the Commission when carrying out its preliminary examination.
180 As a preliminary point, it should be noted that the IPCEI Communication is not
very precise with regard to the analysis of the criteria of the necessity and
proportionality of aid. Paragraph 28 et seq. of the communication does not make a
distinction between those two criteria, as the Commission acknowledges, and even
confuses them.
181 In particular, with regard to the calculation of the profitability of a project,
paragraph 30
of the IPCEI Communication refers, inter alia, to ‘an IRR
corresponding to the sector or firm specific benchmark or hurdle rate’ and states
that, in order to calculate the IRR, ‘all relevant and expected costs and benefits
must be considered over the lifetime
of the project’. That would therefore suggest
a condition which seems to be based primarily on the necessity of the aid, as, if
31
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
the project is not profitable during its lifetime, the aid is necessary. However, the
beginning of paragraph 30 of the IPCEI Communication requires the Commission
to verify that ‘the aid amount does not exceed the minimum necessary for the
aided project to be sufficiently profitable’, which seems to relate to the different,
but complementary, condition that the aid must be proportional.
182 In recital 103 of the contested decision, the Commission applied the conditions
laid down in paragraph 30 of the IPCEI Communication when examining the
necessity of the aid. It took the view that, if the IRR was greater than the WACC,
the net present value of the project would be positive and the project profitable,
and that if, on the contrary, the IRR was lower than the WACC, the project would
not be profitable and aid would therefore be necessary.
183 However, in recital 104 of the contested decision, the Commission calculated the
IRR of the project ‘over the expected repayment period of 55 years’. Footnote 35
specifies that the calculation of the 55-year repayment period is based, inter alia,
on ‘the project planning and construction costs of
EUR
7.4 billion (2014 prices)’.
The figure of EUR 7.4 billion, according to Table 1 in recital 8 of the contested
decision, covers only the construction costs of the fixed link.
184 In that regard, first, the Court notes that, when referring to the repayment period
for the aid, the Commission failed to apply correctly paragraph 30 of the IPCEI
Communication, which states that the IRR is to be calculated taking into account
all expected costs and benefits ‘over the lifetime of the project’. Furthermore, to
base the calculation of the IRR on a very uncertain repayment period, as in the
present case, is also arbitrary, as that period may vary depending on subjective
factors, including the type of aid and the arrangements for repayment negotiated
between the beneficiary and the financial institution granting the loan.
185 Second, in the calculation of the IRR for the purpose of examining the necessity
of the aid, the Commission did not take account of the construction costs of the
fixed link, whereas it conducted its compatibility analysis by reference to the
project as a whole, including the construction costs of the hinterland connections
and the operating costs of the fixed link (see paragraph 208 below).
186 In its pleadings, the Commission states that the IRR was calculated over the
expected repayment period of 55 years, in accordance with paragraph 31 of the
IPCEI Communication, which indicates that the funding gap is defined as ‘the
difference between the positive and negative cash flows over the lifetime of the
investment’.
It adds that the lifetime of the investment refers to its economic
lifetime, in accordance with the Directorate-General (DG) for Regional and Urban
Policy’s document of December 2014 entitled ‘Guide
to Cost-Benefit Analysis of
Investment Projects’,
which
refers to a standard reference period of 25 to 30 years
for calculating the funding gap for the purpose of establishing the maximum
contribution from the European Regional Development Fund (ERDF) for
infrastructure projects for roads and railways, while at the same time stating that,
32
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
in the present case, given the exceptional nature of the project and the unusually
long construction period, it took a more conservative approach.
187 In that regard, it is clear that paragraph 31 of the IPCEI Communication does not
concern the calculation of the IRR but that of the funding gap, which relates
mainly to the different requirement that the aid must be proportional (see
paragraph 195 below). Next, it should be noted that the DG for Regional and
Urban Policy’s document
referred to by the Commission provides only guide
values as to the profitability of certain types of project, while at the same time
indicating that, in cases involving unusually long construction periods, longer
values may be used. In any event, that document cannot prevail over the wording
of the IPCEI Communication. Lastly, the Commission does not explain in the
contested decision in what way the lifetime of the investment corresponds to the
repayment period, on which the calculation of the IRR is based.
188 In conclusion, while it cannot be ruled out that, in principle, aid was necessary for
the realisation of such a large project, it must be nonetheless be found that the
Commission’s examination of the necessity of the aid in the contested decision
was, at the very least, insufficient and imprecise. This indicates that there were
serious difficulties, which should have prompted the Commission to initiate the
formal investigation procedure, and also means that it is not possible to examine
whether the Commission made a manifest error of assessment.
189 By its seventh and final argument, the applicant disputes the calculation of the
WACC. It maintains that the 11.0% WACC level assumed in the contested
decision is too high by comparison with the WACC for similar long-term
infrastructure projects, according to data provided by a Professor at the New York
University (New York, United States), which suggests a WACC level of between
5.68% and 6.71%.
190 As the Commission was correct to observe in that regard, the document referred to
in paragraph 189 above simply shows a one-page table containing figures, without
explanations or sources, which are, in any event, higher than the IRR of the
project. That evidence cannot therefore call into question the Commission’s
assessment.
191 In the light of all the foregoing, the third complaint in the second part of the third
plea must be upheld in so far as the Commission failed to have regard to its
obligation to initiate the formal investigation procedure when faced with serious
difficulties concerning its assessment of the necessity of the aid. It is not therefore
possible, in the light of the inadequate examination carried out by the
Commission, to rule on the second complaint in the second part of the second
plea, alleging a manifest error of assessment.
33
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
The proportionality of the aid
192 By the third part of the second plea, the applicant alleges an error of law and a
manifest error of assessment in the assessment of the proportionality of the aid. By
the fourth complaint in the second part of the third plea, which refers to arguments
set out in connection with the third part of the second plea, it submits that the
Commission’s analysis of whether the aid was proportional was insufficient and
incomplete.
193 It is appropriate to consider first the arguments relating to the serious difficulties
encountered by the Commission when carrying out its preliminary examination.
194 First, it should be noted that the principle of proportionality requires that measures
adopted by EU institutions should not exceed the limits of what is appropriate and
necessary in order to attain the objectives legitimately pursued by the legislation
in question; when there is a choice between several appropriate measures,
recourse must be had to the least onerous, and the disadvantages caused must not
be disproportionate to the aims pursued (see judgment of 8 April 2014,
ABN Amro
Group
v
Commission,
T-319/11, EU:T:2014:186, paragraph 74 and the case-law
cited). As a general principle of EU law, the principle of proportionality is a
criterion for determining whether any act of the institutions of the European Union
is lawful, including decisions taken by the Commission in its capacity as
competition authority (see judgment of 8 April 2014,
ABN Amro Group
v
Commission,
T-319/11, EU:T:2014:186, paragraph 75 and the case-law cited).
195 It should also be noted that paragraph 28 of the IPCEI Communication states that
aid will be deemed proportionate only if the same result cannot be achieved with
less aid. Paragraph 31 of that communication indicates that the maximum aid level
will be determined with regard to the identified funding gap in relation to the
eligible costs, the funding gap being defined as ‘the difference between the
positive and negative cash flows over the lifetime of the investment, discounted to
their current value on the basis of an appropriate discount factor reflecting the rate
of return necessary for the beneficiary to carry out the project notably in view of
the risks involved’. Aid
is therefore proportionate up to the amount at which the
project becomes profitable.
196 With regard in particular to State aid in the form of a guarantee, footnote 27, in
paragraph 36
of the IPCEI Communication, states that ‘aid in the form of
guarantees must be limited in time, and aid in the form of loans must be subject to
repayment periods’. Moreover, point (b) of the third subparagraph of Section 4.1
of the Guarantee Notice, concerning guarantees, states that guarantees must be,
inter alia, ‘limited in time’ and that ‘unlimited’ guarantees are incompatible with
Article 107 TFEU.
197 In the contested decision, the Commission stated that the aid intensity was below
the funding gap of the project. In recital 107 of the decision, the Commission
indicated that the funding gap was EUR 3.1 billion and that the net present value
34
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
of the eligible investment costs was EUR 5.6 billion, giving a funding gap ratio
for the project of 54.9%. In recital 108 of the decision, it stated that the aid
granted to Femern was EUR 2.8 billion, which gives aid intensity of 50.8%.
198 Furthermore, in recital 109 of the contested decision, the Commission added that
the State guarantee and State loans were limited in scope and time. According to
the Commission, the guarantee covers only the debt relating to the planning,
construction and operation of the fixed link until the debt is fully repaid and there
is no risk that the guarantee may be used to subsidise other non-eligible costs and
activities.
199 In recital 110 of the contested decision, the Commission also stated that the
Danish authorities had ‘committed to limit the guarantees and State loans to loans
obtained in order to finance eligible costs no later than 55 years after the opening
of the Fixed Link’, to give fresh notification of any public
financing measures
granted after that period and deemed necessary to ensure the sustainability of the
project and to report annually on progress in the repayment of Femern’s debt. The
Commission also indicated that the guarantee would terminate earlier if the
project debt was repaid before the end of that period.
200 The applicant claims, in essence, that the Commission erred in law or made a
manifest error of assessment in so far as concerns the calculation of the duration
of the aid and its scope, having regard to the eligible costs, and in therefore
concluding that the maximum aid level was permissible.
201 In the first place, it should be noted that the contested decision does not contain
any precise indications concerning the duration and end dates of the State
guarantees and loans. As is apparent from recitals 109 and 110 of the decision, the
grant of those measures is ‘limited’ to 55 years from the date —
which remains
uncertain
on which the fixed link will be opened, and those measures will
cover Femern’s
debt until it ‘is fully repaid’. In any event, a period of at least 55
years is, in itself, extremely long, especially as it relates only to the provision of
guarantees in respect of loans taken out up to that date and which will therefore be
repaid long after that date.
202 In its pleadings, the Commission argues that a temporal limitation is not,
according to the IPCEI Communication, an essential requirement when
determining proportionality, and states that, in recital 109 of the contested
decision, it gave a precise indication of the scope and duration of the aid merely
for the sake of completeness. According to the Commission, linking the use of the
guarantees to the repayment of the costs ensures, via a limitation that is as much in
scope as it is in time, that the project will not receive more aid than is needed.
203 The question therefore arises as to whether, in principle, the very long and
imprecisely determined duration of the measures referred to in paragraph 198
above has a bearing on the proportionality of those measures. That question must
be addressed in the light of the principles set out by the Commission in the IPCEI
35
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
Communication and in the Guarantee Notice, which expressly provide that
guarantees must be ‘limited in time’.
204 In those circumstances, first, it should be noted that those guarantees are linked to
an object that is specific but the precise cost of which has not been determined,
namely the loans and obligations relating to the debt connected with the planning,
construction and operation of the fixed link until that debt has been repaid in full
(recitals 31 and 109 of the contested decision). Second, it should also be noted that
the provision of those guarantees is, in principle, limited to a period of 55 years
from the opening of the fixed link, the Danish authorities having undertaken to
give fresh notification of any new measure granted after that period (recital 110 of
the contested decision), which, according to the Commission, is the expected
repayment
period of Femern’s debt, as explained in footnote 35, in recital 104 of
the contested decision. All guarantees still valid at that date will remain so until
they ‘naturally’ expire, that is, until the underlying debts have been repaid, which
may be long after that date.
205 Accordingly, the fact that the object is only partially determined and the extremely
long and indeterminate, or indeed unforeseeable, debt repayment period, which
determines the duration of the guarantees, should have prompted the Commission
to investigate more closely the proportionality of that aid measure.
206
In the second place, the assessment of the Commission’s analysis also raises
difficulties as to the scope of the aid in the form of State guarantees and loans, in
particular with regard to the account taken, as eligible costs, of the costs of the
hinterland connections.
207 It is clear from recital 18 of the contested decision and, what is more, it is not
disputed by the Commission, that it took into account the costs of the hinterland
connections, as eligible costs, among the relevant costs when calculating the
length of the repayment period and the funding gap.
208 It is true that, in the context of the project, as notified, the costs of the hinterland
connections are indirectly payable by Femern, which is obliged, inter alia, to pay
dividends to Femern Landanlæg to enable the latter to meet those costs. Those
costs could therefore, in principle, be taken into account when examining whether
the aid granted to Femern was compatible.
209 That said, the Commission fails to explain in the contested decision whether and
to what extent those costs were taken into account in its analysis of compatibility,
which, in principle, appears to concern only the funding measures for the fixed
link. Moreover,
the Commission’s assessment appears to be contradictory in that
regard. While, in recital 107 of the decision, the Commission indicates that the
calculation of the funding gap takes account of the financing of the hinterland
connections, footnote 35, in recital 104 of the decision, states that the calculation
of the repayment period, which is decisive for determining whether the measures
36
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
at issue are proportional, is based only on the construction costs of the fixed link
(see paragraph 183 above).
210 It follows
that the Commission’s examination of that aspect is incomplete, or even
contradictory, so that it was not entitled to take the view that it had overcome all
the serious difficulties raised by the analysis of the proportionality of the measures
at issue.
211 In the third place, it is apparent from the contested decision that the measures at
issue granted to Femern covered not only the debt connected to the planning and
construction of the fixed link but also that relating to the operation of the link,
until the debt has been repaid in full.
212 It should be borne in mind in that regard that, as the aid at issue covers the
operating costs of the fixed link, it cannot be ruled out that, to some extent, it may
constitute operating aid, that is, aid which is intended to release an undertaking
from costs which it would normally have had to bear in its day-to-day
management or ordinary activities (see, to that effect, judgment of 19 September
2000,
Germany
v
Commission,
C-156/98, EU:C:2000:467, paragraph 30, and the
case-law cited).
213
As observed by the applicant, the aid should have expired at ‘the point in time
when the beneficiary would be able, on the basis of its cash flow, to borrow on the
open market without the support of State guarantees or State loans’. That point
is
normally reached when the amount of the beneficiary’s debt has reached a level at
which its income is likely to exceed operating costs and debt repayments under
normal market conditions, and therefore before the debt has been repaid in full.
Aid in excess of that level may therefore be regarded as operating aid, for which
the Commission has not provided any justification in the contested decision.
214 That possibility was not even taken into account by the Commission, as the
contested decision makes no distinction, in the analysis of the compatibility of the
aid, on the basis of whether it covers, on the one hand, the costs relating to the
planning and construction of the fixed link, which may, in principle, be classified
as investment costs and, on the other, the costs of operating the link, which may,
by contrast, constitute operating aid.
215
It follows from all the foregoing that the Commission’s analysis in the contested
decision concerning the proportionality of the measures at issue granted to
Femern, in particular the calculation of the repayment period of the aid and of the
eligible costs, was, at the very least, insufficient and imprecise, or even
contradictory, which is indicative of the existence of serious difficulties that
should have prompted the Commission to initiate the formal investigation
procedure.
216 The Court therefore upholds the fourth complaint in the second part of the third
plea, in so far as the Commission failed to have regard to its obligation to initiate
the formal investigation procedure when it encountered serious difficulties
37
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
concerning the assessment of the proportionality of the aid, although it is not
possible, on account of the inadequate examination carried out by the
Commission, to rule on the third part of the second plea, alleging a manifest error
of assessment.
Undue distortion of competition and balancing test
217 By the fourth part of the second plea, the applicant contends that, contrary to the
requirements of the IPCEI Communication, the Commission failed to examine
whether the aid gave rise to undue distortion of competition. By the fifth
complaint in the second part of the third plea, the applicant also alleges
infringement of the obligation to initiate the formal investigation procedure in so
far as concerns those matters.
218 Paragraph 40
of the IPCEI Communication states that ‘the Member State should
provide evidence that the proposed aid measure constitutes the appropriate policy
instrument to address the objective of the project’ and that ‘an aid measure will
not be considered appropriate if other less distortive policy instruments or other
less distortive types of aid instrument make it possible to achieve the same result’.
219 Under Article 41
of the IPCEI Communication, ‘for the aid to be compatible with
the internal market, the negative effects of the aid measure in terms of distortions
of competition and impact on trade between Member States must be limited and
outweighed by the positive effects in terms of contribution to the objective of
common European interest’.
220 In accordance with those principles, paragraph 42 of the IPCEI Communication
states that ‘in assessing the negative effects of the aid measure, the Commission
will focus its analysis on the foreseeable impact the aid may have on competition
between undertakings in the product markets concerned, including up- or
downstream markets, and on the risk of overcapacity’.
Paragraph 43 of the
communication adds that ‘the Commission will assess the risk of market
foreclosure and dominance, in particular in case of absence of, or limited
dissemination, of the research results’ and that ‘projects involving the construction
of an infrastructure must ensure open and non-discriminatory access to the
infrastructure and non-discriminatory
pricing’.
221 In the present case, with regard to the positive effects of the project, the
Commission refers in recital 115 of the contested decision to recitals 88 to 93
thereof, concerning the analysis of the common European interest of the project,
and states that ‘the Fixed Link is part of a wider plan
to promote mobility, further
integration and cultural exchange of people living on both sides of the Fixed Link,
and to improve the connection between the Nordic countries and central Europe
for passengers as well as road and railway freight’, expected
benefits which have
been ‘recognised at a European level by including the Fixed Link in the list of
TEN-T
priority projects’. It refers, inter alia, to the ‘positive effects on a number
38
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
of economic sectors in the region, such as gas stations, retail, restaurants, hotels,
amusement parks and rail and bus transport’.
222 With regard to the negative effects, in recital 116 of the contested decision the
Commission states that the opening of the fixed link will have ‘a negative impact
on the ferry operators, both serving Rødby and Puttgarden routes as well as other
ferry routes in the region’, and that the decline in the number of ferry operations
‘may also have a negative impact on the ports used by those ferries in terms of
traffic volumes and revenues’. It adds that those effects ‘are inherent in the
project, which seeks to offer a quicker and more convenient alternative to the ferry
services’.
223 The Commission states in recital 117 of the contested decision that the Fehmarn
Belt fixed link will be open to all users on an equal and non-discriminatory basis
and that the pricing structure will be non-discriminatory and transparent.
224 In recital 118 of the contested decision, the Commission adds, relying on the study
of 5 January 2015,
that ‘the cost benefit analysis of the
Fehmarn Belt Fixed Link
project clearly shows that the expected socio-economic outcome of the Fehmarn
Belt Fixed Link in the long run is positive, regardless of the fact whether the ferry
service continues or is terminated’. It states that the study in
question calculated,
so far as possible, all possible gains and costs of the fixed link in comparison with
a situation involving the continuation of the ferry services, and concluded that,
despite the significant investment costs of the fixed link and the hinterland
connections, the project will return a net benefit and produce an economic return
of 4.7% for Europe (and an economic return of 5.3% for Denmark), a benefit
consisting mainly in time saving and greater flexibility in departure times for the
various users of the fixed link.
225 Essentially, the applicant contends that the Commission failed to analyse the
effect of the aid on competition, with regard in particular to the creation of a
dominant position for Femern and possible abuse of that position, and the risk of
overcapacity on a market that is already saturated by ferry operators.
226 In that regard, in recital 116 of the contested decision, the Commission took into
account
admittedly succinctly
the negative effect of the opening of the fixed
link on ferry operators and the ports used by those operators, while at the same
time stating that those effects ‘are inherent in the project, which seeks to offer a
quicker and more convenient alternative to the ferry services’. Moreover, in recital
118 of the decision, the Commission stated that the expected socio-economic
outcome of the Fehmarn Belt fixed link will in the long run be positive, whether
or not the ferry services are discontinued.
227
The Commission’s conclusion in this respect is not vitiated by a
manifest error of
assessment. It is reasonable to conclude that a project involving the construction
of infrastructure that will provide an alternative to existing modes of transport
entails the risk that the latter will disappear and, as that project provides a solution
39
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
which, on the whole, has positive results, it is not for the Commission to call into
question the choice made by the public authorities.
228 Furthermore, the argument that the calculation of the socio-economic return is
incorrect because it does not take into account competition from ferries has
already been addressed and rejected in connection with the first complaint in the
first part of the second plea and the second complaint in the second part of the
third plea, which should be referred to (see, in particular, paragraphs 128 to 134
above).
229 It follows, first, that the Commission did not make any manifest error of
assessment in its examination of undue distortion of competition and of the
balance test and, second, that that examination did not give rise to serious doubts
which should have prompted it to initiate the formal investigation procedure.
230 The fourth part of the second plea and the fifth complaint in the second part of the
third plea must therefore be rejected.
The conditions for the mobilisation of State guarantees
231 The applicant contends that the Commission erred in law and made a manifest
error of assessment with regard to the conditions for the mobilisation of State
guarantees.
232 As a preliminary note, it should be observed that Section 5.3 of the Guarantee
Notice is worded as follows:
‘The Commission will accept guarantees only if their mobilisation is contractually
linked to specific conditions which may go as far as the compulsory declaration of
bankruptcy of the beneficiary undertaking, or any similar procedure. These
conditions will have to be agreed between the parties when the guarantee is
initially granted. In the event that a Member State wants to mobilise the guarantee
under conditions other than those initially agreed to at the granting stage, then the
Commission will regard the mobilisation of the guarantee as creating new aid
which has to be notified under Article [108(3) TFEU].’
233 As a further preliminary point, it should be noted that, in adopting rules of conduct
and announcing through their publication that they will henceforth apply to the
cases to which they relate, the Commission imposed a limit on the exercise of its
discretion and cannot depart from those rules without running the risk of suffering
the consequences of being in breach of general principles of law, such as equal
treatment or the protection of legitimate expectations, unless it can provide
reasons justifying its departure from its own rules, in view of those same
principles (see, to that effect, judgments of 28 June 2005,
Dansk Rørindustri and
Others
v
Commission,
C-189/02 P, C-202/02 P, C-205/02 P to C-208/02 P and
C-213/02 P, EU:C:2005:408, paragraph 211, and of 11 September 2008,
Germany
40
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
and Others
v
Kronofrance,
C-75/05 P and C-80/05 P, EU:C:2008:482,
paragraph 60).
234 In the specific field of State aid, the EU Courts have previously indicated that the
Commission may adopt guidelines on the exercise of its powers of assessment and
that, in so far as they do not contradict Treaty rules, the policy rules which they
contain are to be followed by that institution (see judgment of 13 June 2002,
Netherlands
v
Commission,
C-382/99, EU:C:2002:363, paragraph 24 and the
case-law cited).
235 By its first argument, the applicant claims, in essence, that the conditions for the
mobilisation of the guarantees had not been determined when the guarantees were
initially granted.
236
The Commission maintains that the applicant’s speculation that the Danish
authorities might have granted guarantees before the adoption of the contested
decision, without the Commission having been informed of the conditions for the
mobilisation of those guarantees, is not supported by any evidence.
237 It should be recalled that in recital 122 of the contested decision the Commission,
while acknowledging that the conditions for the mobilisation of the guarantees at
issue are not set out in the Construction Law itself, states that, as confirmed by the
Danish authorities, those conditions were determined by the Minister for Finance
before Femern and Femern Landanlæg obtained loans and other financial
instruments and form part of the loan agreements which those companies
concluded with financial institutions.
238 It must therefore be found that the conditions for the mobilisation of the
guarantees at issue, as referred to in Section 5.3 of the Guarantee Notice, were not
known at the time the aid was granted. Those conditions were nevertheless
determined, according to the Commission, by the Danish Minister for Finance
before the guaranteed loans were granted and were included in the loan
agreements concluded between Femern and the financial institutions concerned.
239 In that regard, it is nevertheless clear that the contested decision does not explain
how the Danish Minister for Finance will impose those conditions.
240 Furthermore, it is apparent from the contested decision that the Commission found
that the conditions for mobilisation were introduced, on a case-by-case basis,
when the loans were granted, but that it did not formally impose those conditions
as conditions for ensuring that the aid was compatible. There is therefore some
doubt as to whether the Commission can intervene in a situation where, when a
specific loan is granted, no condition for mobilisation may be imposed.
241 In any event, in the light of Section 5.3 of the Guarantee Notice, it is clear that the
Commission was not in a position to find that the guarantees at issue were
compatible with the internal market without knowing the conditions for
mobilisation attaching to the grant of the guarantees.
41
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
242 Accordingly, the Court finds that the Commission erred in law and made a
manifest error of assessment.
243 By its second argument, the applicant maintains, in essence, that, as regards the
State guarantees covering non-financial obligations, the Commission was content
to accept the assurance received from the Danish authorities that the principles of
Danish law ensure that the rules laid down in the Guarantee Notice will be
applied, without stating what those principles are or requiring an undertaking in
that regard from the Danish authorities.
244
The Commission disputes the applicant’s arguments.
245 It should be noted that in recital 123 of the contested decision the Commission
states that, with regard to State guarantees covering non-financial obligations, as
affirmed by the Danish authorities, the general principles of Danish law regarding
obligations require Femern or Femern Landanlæg to be declared bankrupt before
the guarantee can be mobilised.
246 It is true that the Commission has not provided any explanation concerning the
provisions of Danish law applicable in the present case. Nevertheless, as the
Commission itself observes, it had no reason to doubt the interpretation of the
principles of Danish law provided to it by the Danish authorities, an interpretation
which, moreover, the applicant has not disputed.
247
Therefore, there are no grounds to support the applicant’s claim that the
Commission made a manifest error of assessment in that regard.
248 That argument cannot therefore succeed.
249 In conclusion, the fifth part of the second plea must be upheld, as the Commission
did not impose any conditions in respect of the mobilisation of the guarantees
before the aid was granted.
Conclusion
250 In the light of all the foregoing, it must be concluded that the Commission (i)
failed to have regard to its obligation to initiate the formal investigation procedure
in so far as concerns the assessment of the necessity and proportionality of the aid
and (ii) erred in law and made a manifest error of assessment in so far as concerns
the examination of the conditions for the mobilisation of the State guarantees.
251 As a consequence, the Court upholds the second part of the third plea, without
there being any need to examine the first part of that plea, alleging infringement of
the obligation to initiate the formal investigation procedure on account of the
length of and certain circumstances connected with the conduct of the procedure,
and annuls the contested decision in so far as the Commission decided not to raise
any objections to the measures granted by the Kingdom of Denmark to Femern for
the planning, construction and operation of the Fehmarn Belt fixed link.
42
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
Costs
252 Under Article 134(1) of the Rules of Procedure, the unsuccessful party is to be
ordered to pay the costs if they have been applied for in the
successful party’s
pleadings. Since the Commission has been largely unsuccessful, it must be
ordered to pay the costs, in accordance with the form of order sought by the
applicant.
253 Under Article 138(1) of the Rules of Procedure, Member States which intervene
in the proceedings are to bear their own costs. Accordingly, the Kingdom of
Denmark, intervener in support of the Commission, must bear its own costs.
254 Article 138(3) of the Rules of Procedure provides that the Court may order an
intervener other than those referred to in paragraphs 1 and 2 of that article is to
bear its own costs. In the present case, the Court has decided that Föreningen
Svensk Sjöfart is to bear its own costs.
On those grounds,
THE GENERAL COURT (Sixth Chamber)
hereby:
1.
Annuls Commission Decision C(2015) 5023 final of 23 July 2015 on
State aid SA.39078 (2014/N) (Denmark) for the financing of the
Fehmarn Belt fixed link project (OJ 2015 C 325, p. 5) in so far as the
Commission decided not to raise any objections to the measures granted
by the Kingdom of Denmark to Femern A/S for the planning,
construction and operation of the Fehmarn Belt fixed link;
Dismisses the action as to the remainder;
Orders the Commission to bear its own costs and to pay the costs
incurred by Stena Line Scandinavia AB;
2.
3.
43
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
4.
Orders the Kingdom of Denmark and Föreningen Svensk Sjöfart to
bear their own costs.
Berardis
Spielmann
Csehi
Delivered in open court in Luxembourg on 13 December 2018.
E. Coulon
Registrar
President
44
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
S
TENA
L
INE
S
CANDINAVIA V
C
OMMISSION
Table of contents
Background to the dispute ....................................................................................... 2
The applicant........................................................................................................ 2
The project ........................................................................................................... 2
The contested measures ....................................................................................... 4
Administrative procedure .................................................................................... 4
The contested decision ......................................................................................... 5
Procedure and forms of order sought ....................................................................... 6
Law .......................................................................................................................... 7
The fourth plea, alleging failure to state adequate reasons .................................. 8
The first plea and the second part of the third plea, alleging infringement of
Article 107(1) TFEU and infringement of the obligation to initiate the formal
investigation procedure in so far as concerns the analysis of the measures
granted to Femern Landanlæg for the planning, construction and operation of
the rail connections ............................................................................................ 11
The preliminary finding that the fixed link and rail connections constitute a
single integrated project ................................................................................. 13
The finding that the rail connections form part of the main Danish national
rail network .................................................................................................... 14
Competition on the markets for the operation and management of the Danish
railway infrastructure ..................................................................................... 14
Preliminary considerations as to the relevant terminology .................. 14
– The opening ‘de lege’ of the relevant markets by Law No
1249 ......... 16
– The ‘de facto’ opening of the relevant markets, as evidenced by the
presence of network management companies ........................................... 17
The opening of the markets for the construction and maintenance of the
railway infrastructure ................................................................................. 18
The effect on trade between Member States .................................................. 19
Conclusion ..................................................................................................... 20
The second plea and the second part of the third plea, alleging infringement of
Article 107(3)(b) TFEU and infringement of the obligation to initiate the formal
investigation procedure in so far as concerns the compatibility with the internal
market of the measures granted to Femern for the planning, construction and
operation of the fixed link .................................................................................. 20
The relevant case-law .................................................................................... 21
The common European interest of the project ............................................... 22
The calculation of the socio-economic return of the project................ 23
45
TRU, Alm.del - 2018-19 (1. samling) - Bilag 143: Kopi af TRU alm. del - bilag 134, Orientering - EU-Rettens domme om statsstøttegodkendelse af Femern Bælt-projektet, fra transport-, bygnings- og boligministeren
J
UDGMENT OF
13. 12. 2018
C
ASE
T-631/15
The application of Article 107(3)(b) TFEU and the IPCEI
Communication .......................................................................................... 25
The necessity of the aid ................................................................................. 27
The incentive effect of the aid .............................................................. 28
The counterfactual scenario ................................................................. 29
The proportionality of the aid ........................................................................ 34
Undue distortion of competition and balancing test ...................................... 38
The conditions for the mobilisation of State guarantees................................ 40
Conclusion ..................................................................................................... 42
Costs....................................................................................................................... 43
46