GRU, Alm.del - 2017-18 - Bilag 25: Oversendelse af notater om Servicekontrakten på Thulebasen, i forlængelse af samrådet den 18. december 2017 om samrådsspørgsmål A og B, fra udenrigsministeren
Introduction
Background
This report provides a review of Danish participation in United States (US) Defense
Projects at Thule Air Base (AB), Greenland during US Government Fiscal Year 2016
(FY16) - 1 October 2015 through 30 September 2016. This report is used as a basis for
discussion at the annual Permanent Committee meetings between the Kingdom of
Denmark and the US.
Part I
of this report provides a narrative analysis of expenditures made to Danish and
US vendors during FY16. Additionally, historical data is provided in table and figure
format for FY15 through FY16. An itemization, which provides a comparison between
the FY15 and FY16 elements, is provided in narrative form in Part I.
Part II
of this report includes a summary of expenditures for FY16. The Parts covered
are: (a) Base O&M; (b) Other Appropriated Funds; (c) Non-Appropriated Funds; (d)
Construction, Repair and Maintenance.
Part III
provides the future construction projections to include projected special base
construction, repair, maintenance and minor construction projects. The estimates for
FY17 through FY19 are based on the Danish Kroner (DKK) planning rate of DKK
6.7076 for FY17 and DKK 6.7738 for FY18 and FY19 = $1.00.
Exchange Rates
Generally, contract awards are made and funding is obligated in the market currency.
Figures contained in this report are based on then-year Danish Kroner (DKK) or US
Dollars (USD).
For Department of Defense (DoD) funding that is covered by the Foreign Currency
Fluctuations Defense program, the Office Secretary of Defense (OSD) establishes
foreign currency exchange rates to be used. The OSD exchange rate is established
prior to the beginning of the fiscal year, but can also be updated during the year of
execution. In FY16 the OSD established exchange rate was DKK 5.5561=$1.00. OSD
updated the exchange rate for obligations made after 1 February 2016 to DKK
6.7523=$1.00. The mid-year updated exchange rate was closer to the daily currency
exchange rates observed in FY16.
Summaries of total expenditures consist of multiple exchange rates and may not divide
evenly by any single exchange rate. The historical exchange rates for previous years
are provided in Part II of this report.
Page | 1
GRU, Alm.del - 2017-18 - Bilag 25: Oversendelse af notater om Servicekontrakten på Thulebasen, i forlængelse af samrådet den 18. december 2017 om samrådsspørgsmål A og B, fra udenrigsministeren
1855407_0003.png
Part I
Narrative Analysis
FY16 Danish participation in US Defense Projects at Thule AB totaled DKK
861,283,955 ($132,831,370 USD). This is a 9.83% decrease in DKK (2.92% decrease
in USD) from the FY15 figures of DKK 955,130,691 ($136,824,042 USD). The
decrease in DKK and USD was primarily due to the price change of the base
maintenance contract, some of which was offset due to the increase in construction
projects awarded to Danish firms.
The overall US participation at Thule AB for FY16 was $58,997,019 which was a
160.55% increase from the FY15 amount of $22,643,016. This increase was due to the
award of the High Altitude Electromagnetic Pulse (HEMP) Protection project at the Early
Warning Radar site to a US firm.
FY01-FY16 Data
Table 1 provides a comparison of Danish and US participation in percentages.
Table 1. Danish and US Participation
(Percentage comparison)
FY01
Danish
US
82%
18%
FY09
Danish
US
79%
21%
FY02
81%
19%
FY10
82%
18%
FY03
80%
20%
FY11
80%
20%
FY04
75%
25%
FY12
82%
18%
FY05
75%
25%
FY13
82%
18%
FY06
78%
22%
FY14
86%
14%
FY07
81%
19%
FY15
89%
11%
FY08
80%
20%
FY16
69%
31%
FY16 Itemization
Part II(a) Base Operation and Maintenance (O&M) Services
FY16 Danish Base O&M Services totaled DKK 406,257,784 ($64,807,677 USD). This
is a 51.08% decrease in DKK (44.08% decrease in USD) from the FY15 figure of DKK
830,389,542 ($115,894,182 USD). The difference in cost from FY15 was primarily due
to contract change which significantly reduced the cost of O&M services. The FY16
base contract cost was for DKK 392,784,867 ($62,811,159 USD). Additional funds
Page | 2
GRU, Alm.del - 2017-18 - Bilag 25: Oversendelse af notater om Servicekontrakten på Thulebasen, i forlængelse af samrådet den 18. december 2017 om samrådsspørgsmål A og B, fra udenrigsministeren
1855407_0004.png
were added throughout FY16 for additional supplies and materials at DKK 13,472,917
($1,996,518 USD). There were no O&M contract projects performed in FY16.
Danish and Greenlandic O&M labor decreased from
positions total in FY15 to
positions in FY16. As part of that total, part-time positions increased from
positions
in FY15 to
positions in FY16. The Base Maintenance Contract (BMC) is a non-
personal services, performance-based contract and the BMC contractor is solely
responsible for the number of personnel needed to perform the service.
Part II(b) Other Appropriated Funds
Other Appropriated Funds included expenditures for passenger and subsistence, airlift
with Air Greenland, ocean transportation with Royal Arctic Lines and telecommunication
services with TeleGreenland. Total Danish, participation in Appropriated Funds
expenditures for FY16 was DKK 42,426,518 ($6,805,069 USD), representing a 6.96%
decrease in DKK (9.09% decrease in USD) from the FY15 amounts of DKK 45,600,047
($7,485,653 USD). The decrease was primarily due to the fact that the US Government
reached the ceiling established in the Danish Sealift contract (shipping from Denmark to
Thule).
US participation in Appropriated Funds expenditures for US airlift and sealift for the
transportation of passengers and cargo from the US to Thule Air Base in FY16 was
$8,938,250 USD, a 27.24% decrease from the FY15 amount of $12,283,958 USD. The
decrease was partially due to the airfield runway project and the use of US Government
airlift versus the use of the airlift service contract during a period of time in FY16, and an
overall decrease in the cargo shipped to Thule using these US services contracts.
Part II(c) Non-Appropriated Funds
All items procured with Non-Appropriated Funds were in support of the Top of the World
(TOW) Club, Billeting, Morale, Welfare and Recreation activities, and the Base
Exchange (BX). Danish participation in Non-Appropriated Funds totaled DKK 6,895,979
($1,023,688 USD) in FY16, a 10.02% decrease in DKK (25.85% decrease in USD) from
the FY15 amount of DKK 7,663,988 ($1,380,526 USD).
US participation in Non-Appropriated Funds totaled $2,008,945 USD in FY16, a 22.02%
increase from the FY15 amount of $1,646,430 USD.
In FY16 the use of individual services contracts for TOW club food service workers was
ceased due to US Air Force regulations. This resulted in a direct decrease of Danish
expenditures. Other changes in the procurement of goods was based upon customer
demand.
Part II(d) Construction, Repair and Maintenance
FY16 Danish participation in Construction, Repair and Maintenance expenditures
increased from the FY15 expenditures of DKK 71,477,114 ($12,063,681 USD) to DKK
Page | 3
GRU, Alm.del - 2017-18 - Bilag 25: Oversendelse af notater om Servicekontrakten på Thulebasen, i forlængelse af samrådet den 18. december 2017 om samrådsspørgsmål A og B, fra udenrigsministeren
1855407_0005.png
405,687,406 ($60,194,937 USD), an increase in DKK of 467.58% (398.98% increase in
USD). This was due to the increase of new construction project activities such as the
construction of Thule Consolidation 1, renovations for dormitory Building 97, and repairs
of airfield pavement. These contracts were all awarded in FY16 and some will span
over two or more years with decreasing cost in the later years.
US participation in FY16 Construction, Repair and Maintenance expenditures was
$38,218,708 and an award was made to a United Kingdom (UK) based vendor for
$796,828, making the total non-Danish expenditures $39,015,536. This significant
increase from the FY15 expenditures of $0 was due to an award of a major construction
project, the High Altitude Electromagnetic Pulse (HEMP) Protection project at the Early
Warning Radar site. The award to the UK vendor was accomplished due to a lack of
Danish or Greenlandic bids received for a specific fuel hose product needed for
operations at Thule.
Part III Projected Special Base Construction, Repair, Maintenance and Minor
Construction Projects
Projected construction projects for FY17 through FY19 are summarized in Part III of this
year’s report. This includes new facilities construction, flattop renovations, mission
upgrades, consolidation efforts and other facility infrastructure projects. These
projections are merely estimates and are subject to change depending upon availability
of funding and prioritization of projects.
Employment
Total FY16 Danish employment represented in this report consisted of
employees
of which
were part-time/seasonal employees. Total FY16 US employment
represented in this report consisted of
employees of which none were a part-time.
Contracts at Thule are non-personal services, performance-based contracts and the
contractors are solely responsible for the number of personnel needed to perform the
service.
Summary
Thule’s location and support capabilities make it suitable to operate the Air Force’s vital
space superiority missions as well as conduct a variety of resupply and arctic research
operations by agencies of the US, Danish and Canadian Governments, academia, and
private organizations. Our enduring relationship with the Kingdom of Denmark makes it
possible for us to continue our partnership and accomplish critical missions.
On a daily basis, four cultures, American, Danish, Greenlandic and Canadian, work
together to ensure mission success. This requires quality work and tremendous effort
from each and every member of Team Thule in one of the most challenging
environments anywhere on Earth. Thule AB is an extraordinary base, with an
extraordinary mission, operated and maintained by extraordinary people.