Transport-, Bygnings- og Boligudvalget 2016-17
TRU Alm.del Bilag 266
Offentligt
1739996_0001.png
Internal report
Version 1.5, 18 March 2017
External quality assurance of the Fehmarn Belt fixed link business case
too little, too late, and too unreliable
Hans Schjær-Jacobsen
1
RD&I Consulting
Dyssebakken 19
2900 Hellerup
Denmark
Abstract
The external quality assurance (EQA) of the Fehmarn Belt fixed link business case
commissioned by the Danish Ministry of Transport is critically analyzed regarding the
New Construction Budgeting
requirements as well as common practical criteria. A
time line of analyses, decisions and external quality assurance activities as well as
external criticism is established as a basis for analyzing the completeness, timeliness
and trustworthiness of the quality assurance. Information obtained per the Public
Records Act is included. It is found that the external quality assurance was grossly
incomplete with limited scopes and exclusion of major elements of the project. The
overall financial performance and financial uncertainty analyses were not subject to
external quality assurance at all. The bulk of external quality assurance was carried
out only after the decision-to-build was made, preparatory construction activities
initiated or major economic commitments made, thus jeopardizing the timeliness.
The trustworthiness of the external quality assurance is limited for different reasons:
Bad timing of activities, lack of independence of consultancies, and controversial
findings of opposing analyses. The external quality assurance is found to be too little,
too late, and too unreliable. The status of the project as a high-risk business case is
not improved by the external quality assurance.
Keywords: External quality assurance, Fehmarn Belt, New Construction Budgeting,
high-risk, business case.
1
Former professor, director, and rector at the Copenhagen University College of Engineering and professor, director and
vice-dean at the Technical University of Denmark.
1
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
1. Introduction
The Fehmarn Belt fixed link project, currently put on hold due to lacking German approval, has a long and
turbulent history, of which a short account is given. (In the Appendix, a detailed timeline is presented). Way
back in 1991 in connection with the Danish
Swedish agreement to build the Øresund fixed link the project
was put on the official political agenda of the Danish Parliament. Denmark announced that the possibility of a
fixed link crossing the Fehmarn Belt should be further investigated as an important element in the direct
connection between Stockholm and Paris. Some of the early investigations may be found in FTC (1999), TRM
(1999) and Femern A/S (2003). In 2000 the Ministries of Transport of Germany and Denmark launched an
inquiry of commercial interest (ECI
to i estigate the pri ate se tor s i
terest in implementing a fixed link for
road and railway traffic across the Fehmarn Belt, State Memorandum (2000), and the results were published,
FDJV (2002). The forecasted income from the project was considered too low and uncertain to support a
private sector investment, in part due to the competition from other links, such as ferry services and the Great
Belt fixed link. The conclusion from the ECI is that the project can only be realized with substantial public
support either in the form of guarantees or direct government support. The Ministers of Transport agreed on
13 June 2002 to review some of the most important questions regarding the commercial risks involved in the
project, including the traffic forecasts and the revenues from both the road and railway traffic, TRM (2003).
Another memorandum confirming German and Danish cooperation was agreed upon, State Memorandum
(2004). The Danish Ministry of Transport published quite a lot of positive information about the project, COWI
(2004), TRM (2006b), however, in vain. On 19 June 2007, the state-owned shipping business Scandlines, jointly
owned by Denmark and Germany, was sold off to a consortium of German and British private investors,
Berlingske Business (2007). Only ten days later yet another memorandum was agreed upon, State
Memorandum (2007). However, the German government had already decided to pull out, except for building
and financing the German hinterland constructions, State Treaty (2008). The treaty followed a binding political
agreement between a majority of Danish political parties, Danish Parliament (2008). Still, the environmental
approval of the project part on German soil must be given by the local state government of Schleswig
Holstein, or more precisely by the organization: Landesbetrieb Strassenbau und Verkehr Schleswig
Holstein.
The agreement, Danish Parliament (2008), only two pages long, was unconditional. It merely stated the
political intention to build, finance and operate such a fixed link without mentioning any economic or other
conditions to be fulfilled. At the time, some initial financial analyses had been done, Femern A/S (2003), TRM
(2004), based on a recent traffic forecast, FTC (2003). Also, external criticism was exercised prior to the political
agreement, Jespersen (2007) and Vieregg-Rössler GmbH (2008). A new financial analysis was carried out,
Femern A/S (2008), however still using the traffic forecast from 2003.
As from 2008 the Danish political parties behind the project have continued the struggle to implement the
project despite the lack of commercial and German political support (except for the hinterland constructions)
and severe public criticism from sceptics. Following another binding political agreement on a green transport
poli , o also i ludi g the Da ish People s Part i the Feh ar Belt agree e t,
Danish Parliament
2
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
(2009a), a planning act was passed that allowed for the planning process to continue with increased intensity,
Danish Parliament (2009b). At the same time the State Treaty (2008) was ratified. The rivalry between a cable
stayed bridge, originally preferred, and a submersed tunnel was ended with a victory for the immersed tunnel,
Femern A/S (2010a, 2010b, 2010c), decided by the politicians behind the fixed link on 1 February 2011, Femern
A/S (2011a), and calculated by Femern A/S (2011d). A proposal to locate the tunnel element factory in
Rødbyhavn, Femern A/S (2011c) was also agreed upon on, TRM (2011b). Construction activities were advanced
by the approval of the Ministry of Finance, Danish Parliament (2011), and consolidated construction costs of
the immersed tunnel were put together, Femern A/S (2011d). To advance the bidding process for the tunnel
construction works the Ministry of Finance had to approve of yet another act, Danish Parliament (2013).
At the time, there was a lot of optimism concerning the implementation time schedule of the project, Femern
A/S (2012). It was planned that the application for German approval would be submitted by April 2013 and the
approval obtained by January 2015. Resolving of potential court cases was not considered. As of today, the
approval is expected by 2020 at the earliest, including the resolution of court cases. The building process was
expected to take 6�½ years, today 8�½ years are expected. Initially, the fixed link was expected to be inaugurated
by 2018, State Treaty (2008), now the expectation is 2028, at the earliest, Femern A/S (2016a).
In Section 2 an outline is given of the concept of
New Construction Budgeting
initiated by the Danish Ministry
of Transport in 2006, and how and to what extend external quality assurance should be applied to the Fehmarn
fixed link project. In the following sections the paper deals with quality assurance of elements of the Fehmarn
Belt fixed link project. Section 3 covers road traffic forecast quality assurance, which is of critical importance for
link economy. Special attention is devoted to the question of assumed road traffic transfer from the Great Belt
and discontinuation of the existing privately owned ferry service crossing Fehmarn Belt. Section 4 focuses on
quality assurance of the construction costs of hinterland constructions, tunnel construction and allocated
reserves and the delayed German approval process, including the contractual consequences. In Section 5 the
consolidated financial analysis is considered including financial uncertainties. Finally, the conclusion and
references follow.
This version of the paper was completed by 18 March 2017. Quite a substantial part of the information and
documents used in the paper has been obtained while the author and others were granted access to public
records in accordance with the Public Records Act. A few access applications are still pending.
2.
New Construction Budgeting,
quality assurance and reserves
After a couple of years with many serious cost overruns on projects run by the Ministry of Transport, an
analysis done by the Ministry of Finance revealed usage of inadequate budgeting methods and uncertainty
analyses. Consequently, in 2006 the Ministry of Transport launched a new approach by the name
New
3
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
Construction Budgeting
and informed the Ministry of Finance about it, TRM (2006a). Two new instruments are
introduced in the decision process:
1) External quality assurance carried out by an external and independent consultancy.
2) Experience-based correction supplements which are percentage reserves added on the cost side.
The aim is to improve cost control and prioritizing of projects. The principles should be used in all larger
infrastructure projects within the domain of the Ministry of Transport and apply to the appraisals at the two
points in the decision process labeled Level 1 and Level 2. At Level 1 it is decided which projects are taken
forward and at Level 2 the decision-to-build is made. The standard for experience-based correction supplement
is 30% of the base budget, TRM (2010a).
In the main memorandum, TRM (2010a), the principles for implementation are laid out. Terms of reference for
the external quality assurance at Level 1 is found in TRM (2010b) and Level 2 in TRM (2011b). We will focus on
Level 2 external quality assurance that should be carried out as a basis for the political decision-to-build to be
taken by Parliament, usually by passing a construction act.
The financing of the fixed link across the Fehmarn Belt is based on a state guarantee model. This model entails
financing of the project via loans guaranteed by the Danish Government, and which are to be repaid via
revenue from the users of the fixed link. These and further details of the Fehmarn Belt immersed tunnel
project are available from the subsidiary project company, Femern A/S (2017b) fully owned by a state
company, Sund & Bælt Holding (2017a), which in turn is fully owned by the Danish state.
New Construction Budgeting
is applicable to the Danish land works but, surprisingly enough, not to the
immersed tunnel construction or to the entire fixed link project. It is argued by the Ministry of Transport, TRM
(2015b), that this is the case because the construction of the land works is done by Banedanmark and the
Danish Road Directory, respectively, while the immersed tunnel construction is the responsibility of Femern
A/S. Apparently, state-owned companies are exempted from
New Construction Budgeting.
This does not make
much sense when it comes to the consolidated finances of the total project where income from the users plays
a major role. In fact, no external quality assurance of income and consolidated project finances, including
uncertainties, was ever carried out.
Despite the fact that
New Construction Budgeting
is not applicable to the tunnel construction and the entire
project, it was the guiding principle for some of the external quality assurance carried out. It is therefore
interesting to study the timing in relation to the decision process, see Table 1. Following the guideline of
New
Construction Budgeting,
external quality assurance at Level 2 should be carried out before the decision-to-build
is taken in Parliament, usually represented by the passing of the construction act. Obviously, in the Fehmarn
Belt case the decision process is creeping. It is a mix of unconditional and conditional decisions taken over time,
4
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
1739996_0005.png
constantly increasing the cost incurred and approved while confirming the commitment to build. The decision-
to-build was in fact taken already on 2 September 2008 by the binding political agreement because it was
unconditional: No matter how costs and other consequences develop the agreeing political parties wanted to
build. This decision was reconfirmed several times during the following years. The phenomenon is
characteristic of a particular culture in the Danish Parliament: Once a binding political agreement has been
reached it will be practically unbreakable independent of changing circumstances. Furthermore, there are no
obligations to take down minutes of meetings between members of Parliament or to make them available to
the public.
Date
19 June 2007
29 June 2007
2 September
2008
3 September
2008
29 January 2009
15 April 2009
23 June 2011
26 April 2012
8 June 2012
20 March 2013
20 April
21
May 2015
28 April 2015
1 October 2015
21 October
2015
1 June 2015
10 November
2015
12 November
2015
24 January 2016
28 January 2016
Decision
Scandlines sold off
Memorandum of understanding between
Denmark and Germany
Binding political agreement to build fixed
link
Agreement between Denmark and
Germany
Binding political agreement: Green
transport policy
Parliament passes Planning Act No. 285
Construction activities advanced, Act No.
149
External Quality Assurance (EQA)
Reference
Berlingske Business
(2007)
State Memorandum
(2007)
Danish Parliament
(2008)
State Treaty (2008)
Danish Parliament
(2009a)
Danish Parliament
(2009b)
Danish Parliament
(2011)
EQA of railroad constructions published
EQA of E47 South Motorway published
Authorization of call for tenders, Act No. 97
Work program for EQA of Fehmarn traffic
developed
Parliament passes Construction Act L141
conditionally
Due dilige e of reser es a d risk
distribution
Commissioning of EQA of tunnel
construction reserves and risks
EQA of competition by ferry services
started
EQA of road traffic forecasts published
EQA of road traffic transfer from the Great
Belt requested
EQA of competition by ferry services
published
EQA of tunnel construction costs, reserves
and German approval process published
KPMG (2012)
Deloitte (2012)
Danish Parliament
(2013)
COWI (2015a)
Danish Parliament
(2015)
TRM (2015a)
Ernst & Young
(2016)
KPMG (2016)
COWI (2015b)
TRM (2015d)
KPMG (2016)
Ernst & Young
(2016)
5
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
1739996_0006.png
Date
4 March 2016
4 March 2016
30 May 2016
17 March 2017
17 March 2017
Decision
Binding political agreement about future
development
Upgrading of existing rail track begins
Conditional tunnel construction contracts
signed
Contracts signed with engineering
consultants
External Quality Assurance (EQA)
Reference
Danish Parliament
(2016)
Ingeniøren (2016a)
Femern A/S (2016d)
Femern A/S (2017d)
EQA of road traffic transfer from Great Belt
not yet completed
Sund & Bælt Holding
(2017b)
Table 1. Timeline of decision process and external quality assurance. Extracted from the Appendix.
Obviously, it is seen from Table 1 that none of the external quality assurance activities was timed in accordance
with the guidance of
New Construction Budgeting.
The earliest attempts were made in 2012 and concerned the
land works, KPMG (2012) and Deloitte (2012), but at that time construction works had already begun, Danish
Parliament (2011), and construction costs already incurred. The rest of external quality assurance activities
were all begun after the construction act had been passed, Danish Parliament (2015), some are even not
completed yet, TRM (2015d). Additional spending was authorized by another binding political agreement,
Danish Parliament (2016). In March 2016 costs totaling DKK 13.2 billion had been spent or allocated while still
awaiting German approval, Ingeniøren (2016a, 2016c). In practice, Danish politicians have made the project
too ig to fail
, Bent Flyvbjerg in Ingeniøren (2016c), translated by the author. Since then, major contracts
representing a value of approximately DKK 30 billion were conditionally signed with the tunnel contractors,
Femern A/S (2016d). Consequently, it is fair to conclude that the timing of external quality assurance has been
inadequate in relation to the practical decision process and the accelerating economic commitment. Some
initial investigations by the author on the external quality assurance were presented, Schjær-Jacobsen (2016d).
A status of the Fehmarn Belt fixed link may be found in TRM (2017a).
3. Road traffic forecasts
The consulting company COWI was chosen to perform external quality assurance of the road traffic forecasts.
Since COWI has a major interest in the realization of the Fehmarn Belt fixed link and is a consulting partner of
the consortium Fehmarn Link Contractors that won the Tunnel North Contract, the Tunnel South Contract and
the Tunnel Portals and Ramps Contract (only the Tunnel Dredging and Reclamation Contract was won by
another consortium), Ingeniøren (2016b) and Femern A/S (2016d), it is obvious that COWI is disqualified as an
independent, external quality assurance consultancy as required by
New Construction Budgeting
and by
common sense as well.
6
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
During April and May 2015, the work program, COWI (2015a), for an external quality assurance of the road
traffic forecasts was negotiated between The Ministry of Transport and COWI simultaneously with the
preparatory work of the construction act. The method adopted for the quality assurance was
New Construction
Budgeting,
TRM (2006a, 2010a, 2010b, 2011a). When the report came out, COWI (2015b), the initiative had
not been announced publicly, and the timing was peculiar considering that the subject of traffic forecasts was
not considered to be critical in relation to the passing of the construction act, Danish Parliament (2015). The
early traffic forecasts, FTC (1999, 2003), had been criticized by Jespersen (2007) and Vieregg-Rössler GmbH
(2008) and Andersen (2014) and the updated forecasts, Intraplan (2014a, 2014b, 2015a) and Femern A/S
(2014a), by Andersen (2015) and DIW Econ (2015a, 2015b, 2015c). The criticism was answered, Femern A/S
(2015a), but the matter was not closed. Consequently, at the time of Parliament passing the construction act
there was plenty of evidence that the traffic forecasts were under heavy external criticism. Nevertheless, the
construction act was passed without mentioning any doubts concerning the validity of the traffic forecasts.
Apparently, the Ministry of Transport had second thoughts, as it decided to commission the external quality
assurance, COWI (2015a, 2015b).
During the years 1999
2015 the estimated construction costs of the fixed link had escalated considerably by
almost 100%, thereby jeopardizing the entire project (see Section 4). It is interesting to observe that the road
traffic forecast during the same period underwent a substantial growth in volume, FTC (1999), FTC (2003),
Intraplan (2014a, 2014b, 2014c) and Femern A/S (2014a).
The external assurance report, COWI (2015b, p. 9) has a main conclusion in two parts (translated by the
author):
The ai o lusio is that COWI assesses that the traffi fore ast of the ai s e ario is a realisti
estimate
of the traffic volume on a Fehmarn Belt fixed link provided the ferry operation Rødby
Puttgarden is
discontinued. The forecasted growth over time corresponds to the historical growth in later years. The
assumptions are considered reasonable and the forecast models are consistent with the professional practice
of traffic forecasts. However, we think that there are elements in the forecast that appear to be difficult to
substantiate. Particularly, the expected transfer of passenger car traffic from the Great Belt is difficult to
substantiate due to a lack of data concerning the actual traffic pattern crossing the Great Belt fixed link. The
forecast is conservative in estimating the creation of new traffic due to the lack of tools for forecasting the
pote tial d a i effe ts of the fi ed li k .
In the report COWI does not address several fundamental questions of great importance for the
trustworthiness of the traffic forecasts, such as the inability of the forecasting method, FTC (2003) and
Intraplan (2014a, 2014b), applied to handle the complexity created by two different segments of passenger
cars (Europe travelers and border shoppers) and two competing transport modes (tunnel and ferry). Likewise,
the lack of evaluating the degree of uncertainty in data for the traffic forecasts is ignored. However, the
7
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
estimated transfer of passenger car traffic from the Great Belt is explicitly addressed. This is particularly
important because the estimated volume amounts to approximately 800,000 one-way cars per year,
corresponding to approximately 25% of the expected tunnel traffic.
Despite the reservation in the main conclusion and the weaknesses mentioned above the Minister of Transport
is quoted as saying on 12 November 2015
tra slated the author : COWI has fou d that the traffi fore ast
is thorough and presents a realistic estimate of the tunnel traffic. This is an important conclusion and then we
politicians can concentrate on the remainder of the
proje t , T‘M
). The
i ister s o issio
was
pointed out, Bredsdorff (2015b) and Schjær-Jacobsen (2015b), but even more interestingly: On the very same
day, namely 12 November 2015, as the Minister of Transport approved the traffic forecast quality assurance, it
turned out that the Ministry of Transport requested an analysis, TRM (2015d) and Sund & Bælt Holding (2016),
of the traffic transfer from the Great Belt which has not yet been delivered although announced to be finished
by 1 February 2017, at the latest. 16 months after being requested, the analysis has not yet been completed
and results have not even been exchanged between Sund & Bælt Holding, Femern A/S and the Ministry of
Transport, Sund & Bælt Holding (2017b). Being the exclusive owner of the project company Femern A/S and
the future operator of the Fehmarn Belt fixed link on behalf of the Danish state, Sund & Bælt Holding does
certainly not qualify as an independent external consultancy for quality assurance.
The transfer of passenger car traffic from the Great Belt fixed link to the Fehmarn Belt fixed link had already
caused some controversy, COWI (2011), Andersen (2015), Femern A/S (2015c, 2015c), Sund & Bælt Holding
(2015), and Intraplan (2015b), but no trustworthy forecast has been produced so far.
Although the growth of traffic crossing the Fehmarn Belt during the period 2011
2019 is markedly lower than
presumed in the traffic forecasts, the long-term growth assumption is maintained by the Ministry of Transport,
Ingeniøren (2016e).
Commissioned by the Ministry of Transport and unknown to the public, a consulting company had already
started a business analysis of the Scandlines ferry business by 1 June 2015, and the confidential report was
finished by 14 January 2016, KPMG (2016). Prompted by a leakage of the report to a German journalist, the
report was made public by the Ministry of Transport by 14 March 2016. As to be expected, Scandlines was
furious about having been kept ignorant of the work and the content of the report as well, TRM (2016b), and
commissioned a response report, Deloitte (2016). The two reports arrive at completely opposite conclusions.
The former concludes (translated
the author : After
opening of the fixed link in 2026 Scandlines will be a
loss-ge
erati g usi ess . The latter o ludes: I our opi io , there are sig ifi a t u ertai ties related to
conclusion in the KPMG report that the Rødby
Puttgarden ferry service be loss-making from 2026. We
consider it more likely that the Rødby
– Puttgarde ferr ser i e ill o ti ue to e profita le i
.
To the
author s k o ledge the o l atte pts to ase this
discussion on a genuine competitive theory were DIW Econ
(2015c) and Aigner (2016). Particularly the latter suggests that the ferry is a much stronger competitor to the
8
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
1739996_0009.png
fixed link than assumed and that one should not take it for granted that the ferry will exit the market. In fact, it
seems more likely that the ferry will make positive profits in equilibrium and stay in the market. This is quite a
challenge for the fixed link because the results also suggest that if the ferry competes, the tunnel will not be a
profitable business, Aigner (2016).
4. Reserves and risk distribution of tunnel constructions
Already in 2012, the external quality assurance of the Danish land works was carried out according to the
procedures laid out in
New Construction Budgeting,
TRM (2006a), for the railroad constructions, KPMG (2012),
and the E47 South Motorway, Deloitte (2012). No serious problems were uncovered and these subprojects of
the Fehmarn belt fixed link are non-controversial, partly because they are standard technology. The estimates
of the land works construction costs have been stable over time and reserves have been allocated in
accordance with
New Construction Budgeting,
see Table 2.
Base Case construction costs
(DKK billion)
Price level
Danish land works
Construction costs excl. reserves
Correction allowance (10%)
Reserves (20%)
Sum reserves
Sum reserves (%)
Sum construct. costs incl. reserves
Coast-to-coast construction
Construction costs excl. reserves
Reserve for contractor risk
Other reserves:
Client reserve
Extra reserves (16.4%)
Total other reserves
Sum reserves
Sum reserves (%)
Project preparation, organisation etc.
Sum construction costs incl. reserves
Total project
Total construction costs excl. reserves
Total reserves
Total reserves (%)
Total construction costs incl. reserves
Base Case Payback Period (Years)
Partial sensitivity analysis (Years)
Femern A/S
(2014b)
Main Scenario
2014
7.3
0.7
1.5
2.2
30%
9.5
40.5
1.8
3.7
3.7
5.5
14%
46.0
47.8
7.7
16%
55.5
32
[28; 41]
Femern A/S
(2014b)
Table 20
2014
7.3
0.7
1.5
2.2
30%
9.5
40.5
1.8
3.7
6.7
10.5
12.3
30%
52.7
47.8
14.5
30%
62.2
37
NA
Femern A/S
(2015b)
2014
7.3
0.7
1.5
2.2
30%
9.5
49.4
1.8
3.7
3.7
5.5
11%
54.9
56.7
7.7
14%
64.4
39
NA
Femern A/S
(2016a)
L141
2015
7.3
0.7
1.5
2.2
30%
9.5
45.8
Femern A/S
(2016a)
2015
7.3
0.7
1.5
2.2
30%
9.5
38.9
3.7
8%
5.6
55.1
53.1
5.9
11%
64.6
39
NA
7.3
19%
6.4
52.6
52.6
9.5
18%
62.1
36
[31; 48]
Table 2. Estimates of Base Case construction costs of the Fehmarn Belt fixed link.
Based on Schjær-Jacobsen (2016c).
9
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
Otherwise, see Table 2 for the coast-to-coast tunnel constructions. Even though New Construction Budgeting
did not apply, two alternative calculations made in 2014, one with reserves of only 14% and one with 30%,
Femern (2014b). The former was based on estimates from the tunnel construction consortia, the latter on
requirements from New Construction Budgeting. Only a few months later the construction costs exclusive of
reserves had risen from DKK 40.5 to 49.4 billion due to new incoming bids from the tunnel construction
consortia, Femern A/S (2015a, 2015b). This was essentially the financial calculations behind the presentation of
the construction act L141 to Parliament, Danish Parliament (2015). The act was passed conditionally, meaning
that construction work startup had to await a negotiated reduction of construction costs, a clarification of the
amount of EU subsidies that could be obtained, and an acceptable time schedule for the German
environmental project approval. It turned out that negotiations with the tunnel construction consortia resulted
in a lower bid, a prolonged construction period, and a redistribution of risks between the master builder and
the construction consortia, Femern A/S (2016b). The question about EU subsidies was clarified by 29 June
2015, resulting in much lower subsidy than expected, Børsen (2015). A time schedule for the German approval
process has not yet been presented by the Germans, Femern A/S (2016f).
On 1 October 2015, the Danish Ministry of Transport decided to have a due diligence made, TRM (2015a) and
on 21 October 2015, the agreeing political parties, Danish Parliament (2009a), decided to commission an
external assessment and quality assurance of the Fehmarn Belt fixed link reserves and risk distribution
between the master builder and the main contractors of the tunnel construction works, including a perspective
of the delay of the German approval process, Ernst & Young (2016). This initiative was taken after the
construction act was conditionally passed by the Danish Parliament, Danish Parliament (2015). The task was to
answer four questions (translated and edited by the author):
1.
Ho are toda s risks distri uted et ee the aster uilder a d
the construction consortia and how
were they distributed earlier? 112 risks were identified, 9 of which changed the risk allocation and 12
aused a ha ge of Feh ar A/“ s risk e posure. O l
-15% of the reported cost reduction is caused
by change of risk distribution while 85-90% is caused by a reduction of tasks and an increase of the
building period.
2. Does the risk distribution correspond with the common praxis of construction contracts for large
projects? The actual distribution is comparable with international standards of other large international
projects. The risk distribution should be supported by an improved risk management process.
3. What are the risks connected with the German approval plan? Are there sufficient reserves to cover
additional costs of the German approval plan and special approval conditions, that may cause
additional costs, delays etc. in the construction phase? It is highly likely that the construction work can
be started during the period medio 2018
medio 2020. Approximately 25% of the actual reserves are
related to the German approval process. There are still several unknown circumstances connected to
the German approval process.
10
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
4. How many reserves should be included in the construction budget based on the binding bids? Since 75-
80% of the total construction costs are covered by the bids, a reserve of minimum 15-20% at a P80
level gives a greater confidence that the reserves are sufficient. Benchmarking with other projects
indicates reserves of 10-20%. The necessary reserves are calculated to be DKK 7.3 billion at a P80 level,
Femern A/S (2016a).
In Ernst & Young (2016) it is further observed that the risk categories applied by Femern A/S (2014b, 2016a) are
not in compliance with the recommendations in
New Construction Budgeting,
TRM (2010a). This could lead to
a problem in relation to the Ministry of Transport reporting process. It is further observed that uncertainty of
revenue is ignored and missing in the risk analyses, Femern A/S (2014b, 2016a).
The statistical approach applied by Ernst & Young (2016) to arrive at a forecast of the date of the German
approval is criticized, Ingeniøren (2016d). Actually, the approval has already been delayed by another 6 months
since the forecast was published, TRM (2016c). Consequently, it is highly likely that construction work
cannot
be started before medio 2020. The delay of the German environmental approval has got the political attention
of the Danish Minister of Transport. Bypassing the political parties behind the project as well as the state
government of Schleswig
Holstein he addresses the federal government in Berlin directly to find ways of
speeding up the approval process, TRM (2017b).
5. Financial analysis and uncertainty
The financing of the fixed link across the Fehmarn Belt is based on a state-guaranteed model. The model entails
financing of the project via loans guaranteed by the Danish Government which are to be repaid via revenue
from the users of the fixed link. These and further details of the Fehmarn Belt immersed tunnel project are
available from the project company, Femern A/S (2017b), fully owned by the state company, Sund & Bælt
Holding A/S (2017).
The political criteria for the go/no-go of the project were expressed at the first readings of the construction act
L141 on 18 March 2015, Danish Parliament (2015), by the spokesman of the Liberal Party of Denmark using the
metaphor of traffic lights, Lorentzen (2015): With the actual economic assumptions, the expected payback
period is 39 years. This means that we are still in the green zone. The Liberal Party does not want to go into the
yellow or red zone, thereby taking the risk that the taxpayers must pay part of the project . When asked about
what lengths of the payback period he associated with the colored zones mentioned, he responded: We have
the rule of thumb in the Liberal Party
and I think this is also the case elsewhere
that as long as we are under
40 years we are in the green zone, then we are on safe ground regarding the taxpayers avoiding to pay. When
we are between 40 and 50 years we are in the yellow zone, then it begins to be on shaking ground. When we
are over 50 years we are in the red zone and we must stay completely out of that one, that is what I mean
,
quoted from Schjær-Jacobsen (2016b, 2017).
11
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
1739996_0012.png
Based on alternative calculations, Bredsdorff (2015a), Schjær-Jacobsen (2015a), Rasmussen (2015), the
finances of the Fehmarn Belt business case were criticized prior to the passing of the construction act on 28
April 2015.
Although of immense importance for the financial feasibility of the fixed link project, the external quality
assurance efforts carried out as described in this paper did not address such vital items as:
Inability of the traffic forecasts methods to handle a business case subject to competition.
Transfer of road traffic from the Great Belt to the tunnel (quality assurance requested 16 months ago).
Uncertainty analysis of road traffic volume.
Tariffs for tunnel road traffic.
Uncertainty analysis of road traffic income.
Amount of EU subsidies.
Economic consequences of needed renegotiations of main tunnel construction contracts.
Maintenance and administration costs of the fixed link.
Consolidated financial analysis of the business case.
Financial risk and uncertainty analysis of the business case.
Genuine uncertainty analyses beyond simple partial sensitivity analyses applied by Femern A/S can be found in
Table 3. By comparison with Table 2 it turns out that the financial uncertainties are much larger than the
impression left by the official financial reports conveyed to Parliament and the public. Clearly, the likelihood
that the Payback Period will be in the green zone is practically equal to zero.
Payback Periods and uncertainties
Road traffic income/volume
Tunnel construction costs excl. reserves (DKK billion)
EU subsidies (DKK billion)
Base Case Payback Period (Years)
Likelihood of Payback Period in green zone
Likelihood of Payback Period in yellow zone
Likelihood of Payback Period in red zone
Worst and Best Case (Years)
Base Case 1
Femern A/S (2014b)
40.5
10.3
37
7.5%
55.9%
36.6%
[37; >60]
Base Case 2
DIW Econ GmbH (2015b)
49.4
4.4
>60
0.0%
12.3%
87.7%
[48; >60]
Table 3. Payback periods and uncertainty analyses, extracted from Schjær-Jacobsen (2016b, 2017).
Consequently, the external quality assurance was rather incomplete leaving large areas of continued doubt
concerning the financial performance of the fixed link.
12
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
Since the most recent financial analysis, Femern A/S (2016a), exhibiting a Base Case Payback Period of 36 years
and a partial sensitivity range of [31, 48] years (see Table 2) and the external quality assurance of reserves and
risk distribution, Ernst & Young (2016), was published, a lot of things have happened, for example:
Tunnel contractors have been appointed, Femern A/S (2016c), and conditional tunnel construction
contracts have been signed, Femern A/S (2016d). Thus, extra costs will be incurred due to stand-by fees
until construction start-up and additional costs for keeping Femern A/S operating over an extended period,
estimated in total to DKK 0.5 billion per year.
A renewed application for German approval has been completed and submitted, Femern A/S (2016e),
replacing the previous one, Femern A/S (2013). This has incurred extra costs.
The German approval process has been delayed by another 6 months, TRM (2016c). Consequently, the
tunnel construction contracts must be renegotiated because the German approval will probably not be
obtained before the contracts expire. The amount of extra costs is unknown.
Answers to 12,600 German objections to the fixed link projects have been completed and submitted,
Femern A/S (2017a). This has been a cumbersome and costly affair, costs being unknown.
“ a dli es a ou es lo g ter o petitio ith the Feh ar Belt fi ed li k upgradi g the Gedser −
Rostock ferry connection, Børsen (2017a). This initiative may cut away a substantial part of the forecasted
traffic transfer from Gedser
Rostock to the Fehmarn tunnel.
Scandlines announces a possible court case concerning obstruction of ferry operations during the tunnel
construction period, Børsen (2017b).
Femern A/S signs contracts with two consortia of engineering consultants, Femern A/S (2017d).
On 27 February 2017, Femern (2017c), it is claimed that the financial analysis from 3 February 2016, Femern
(2016a), is still valid. No new financial analyses are presented, only one-year old key figures are repeated.
Apparently, all the above-mentioned potential costs are expected to be accommodated in the budget without
depleting the reserves and jeopardizing the economy of the project. Particularly notable is the absence of any
kind of risk or uncertainty analysis, not even partial sensitivity analyses are included.
I the author s opi io ,
the Fehmarn Belt fixed link business case is still a financial high-risk project, as pointed out by Schjær-Jacobsen
(2016a, 2017), despite the efforts of the project owners to rationalize the decisions and the economic
commitments made by performing external quality assurance.
6. Conclusion
In summary, the external quality assurance dealt with in this paper includes the following official reports (in
chronological order) as well and the contexts in which they were created, published, and received:
KPMG (2012). EQA of railroad constructions.
Deloitte (2012). EQA of E47 South Motorway.
13
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
COWI (2015). EQA of road traffic forecasts.
KPMG (2016). EQA of competition by ferry services.
Ernst & Young (2016). EQA of tunnel construction reserves, risk distributions and German approval process.
Sund & Bælt Holding A/S, EQA of road traffic transfer from the Great Belt to Fehmarn Belt (in process since
12 November 2015).
The paper finds that the quality assurance concerning the Danish land works is carried out in compliance with
the principles laid out in
New Construction Budgeting
concerning completeness, timeliness and
trustworthiness.
This is not the case concerning the tunnel construction work and the entire business case including Danish land
works. Paradoxically,
New Construction Budgeting
is claimed not to apply but nevertheless it is invoked,
however in general not complied with. The quality assurance commissioned and carried out is not complete,
since large and important issues are not dealt with and left out of the analyses. The quality assurance is not
timely since it is carried out at times when decisions and large economic commitments have already been
made. Largely, the quality assurance is limited in trustworthiness, partly due to bad timing, partly due to lack of
independence of consultancies, and partly due to findings of opposing analyses. In other words, the external
quality assurance of the Fehmarn Belt fixed link business case is too little, too late, and too unreliable. Thus,
the Fehmarn Belt fixed link project is still a high-risk business case, which contrasts with the impression created
by official communications. The political majority of Parliament has decided to continuously promote the
Fehmarn Belt fixed link project despite the large likelihood of a financial project failure. Generally, the external
quality assurance efforts have not contributed to verification of the financial viability of the project.
14
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
References
Aigner, R. (2016). The Fehmarn Belt duopoly
Can the ferry compete with a tunnel? 13 pp., discussion paper
1539, DIW Berlin, January 2016.
Andersen, K.E. (2014). The Fehmarn Belt fixed link
made in Denmark, Copenhagen: Praxis, June 2014. (In
Danish).
Andersen, K.E. (2015). Analysis of new traffic forecasts for the Fehmarn Belt fixed link, 2014. 72 pp.,
Copenhagen: Praxis, January 2015. (In Danish).
Berlingske Business (2007). Scanlines sold for DKK 11.6 billion, 19 June 2007.
Bredsdorff, M. (2015a). The tax payers will have to pay part of the Fehmarn bill,
Ingeniøren,
2 October 2015,
based on work by H. Schjær-Jacobsen. (In Danish).
Bredsdorff, M. (2015b). Large uncertainty about every fourth car in the Fehmarn tunnel,
Ingeniøren,
20
November 2015. (In Danish).
Børsen (2015). Femern-shock: New Minister of Transport misses DKK 4 billion, 29 June 2015. (In Danish).
Børsen (2017a). Scandlines warms up to Fehmarn showdown by venturing billions, 14 March, 2017. (In Danish).
Børsen (2017b). Criticism from shipping company can take Femern A/S to court, 14 March 2017. (In Danish).
COWI (2004). Economic assessment of a fixed link across the Fehmarn Belt
Summary report, 20 pp., 29 March
2004. (Commissioned by the Danish Ministry of Transport).
COWI (2011). Customer survey of Fehmarn Belt, 26 pp., 16 February 2011.
COWI (2015a). External quality assurance of the updated traffic forecast of the Fehmarn Belt project, 8 pp., first
draft of work program 20 April 2015, last draft 21 May 2015 10:52. (In Danish).
COWI (2015b). External quality assurance of the updated traffic prognosis of the Fehmarn Belt project. Ministry
of Transport, 39 pp., 10 November 2015. (In Danish).
Danish Parliament (2008). Binding political agreement between the Government (the Liberal Party and the
Co ser ati e Part , the “o ial De o rats, the “o ialist People s Part a d the “o ial Li eral Part a out a
Fehmarn Belt fixed link, 2 pp., 2 September 2008. (In Danish)
Danish Parliament (2009a). Binding political agreement between the Government (the Liberal Party and the
Co ser ati e Part , the “o ial De o rats, the “o ialist People s Part , the “o ial Li eral Part a d Li eral
Alliance: A green transport policy, 30 pp., 29 January 2009. (In Danish).
Danish Parliament (2009b). Planning of a fixed link crossing Fehmarn Belt with connecting land works in
Denmark. Planning Act No. 285. April 2009. (In Danish, also available in English translation).
Danish Parliament (2011). Act No. 149, 6 pp., passed by the Finance Committee on 23 June 2011. (In Danish).
Danish Parliament (2013). Act No. 97, 4 pp., passed by the Finance Committee on 20 March 2013, confidential
until 26 February 2015. (In Danish).
Danish Parliament (2015). Construction and operation of a fixed link crossing Fehmarn Belt with connecting
land works in Denmark. Construction Act L141 passed on 28 April 2015. (In Danish).
Danish Parliament (2016). Binding political agreement between the Government (the Liberal Party), the Social
De o rats, Da ish People s Part , Li eral Allia e, the “o ial Li eral Part , the “o ialist People s Part a d the
15
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
1739996_0016.png
Conservative Party concerning: The continued process of the Fehmarn belt fixed link, 3 pp., 4 March 2016. (In
Danish).
Deloitte (2012). External quality assurance
E47 South Motorway Sakskøbing-Rødbyhavn, 29 pp., 8 June 2012,
commissioned by the Danish Ministry of Transport. (In Danish).
Deloitte (2016). Scandlines Rødby-Puttgarden: Review of KPMG report dated 24 January 2016, 34 pp., 24 June
2016. Commissioned by Scandlines.
DIW Econ GmbH (2015a). Comments to new traffic forecast for the Fehmarn Belt fixed link, 14 pp., 20 January
2015. Commissioned by Scandlines. (In German).
DIW Econ GmbH (2015b). Investigation of the recent cost-benefit analysis of the Fehmarn Belt fixed link, 19
pp., 19 February 2015. Commissioned by Scandlines. (In Danish).
DIW Econ GmbH (2015c). How robust are the financial analyses of the Fehmarn Belt fixed link? 76 pp.
Commissioned by Scandlines. (In German).
Ernst & Young (2016). External quality assurance of the Fehmarnbelt fixed link including Danish land works, 69
pp., February 2016. Commissioned by the Danish Ministry of Transport and Building. (In Danish).
FDJV
Fehmarn Development Joint Venture (2002). Finances and organization, 156 pp., June 2002. (In Danish,
originally in English).
Femern A/S (2003). Financial analysis
February 2003, 20 pp., March 2003.
Femern A/S (2008). Financial analysis, 27 pp., September 2008. (Available in Danish).
Femern A/S (2010a). Construction cost estimate of a cable sustained bridge
comparison with the Planning
Act, 6 pp., 1 November 2010. (In Danish).
Femern A/S (2010b). Construction cost estimate of an immersed tunnel
comparison with the Planning Act, 6
pp., 1 November 2010. (In Danish).
Femern A/S (2010c). Consolidated construction cost estimate of the Fehmarn Belt fixed link, 8 pp., 1 November
2010.
Femern A/S (2011a). Backing of immersed tunnel, news release, 21 February 2011. (In Danish).
Femern A/S (2011b). Traffic across the Great Belt between Zealand and Germany, 2 pp., 21 April 2011. (In
Danish).
Femern A/S (2011c). Nomination of Rødbyhavn as production site, 6 pp., 25 May 2011. (In Danish).
Femern A/S (2011d). Consolidated construction estimates of the Fehmarn Belt fixed link, 9 pp., 24 August 2011.
(In Danish).
Femern A/S (2012). Time schedule for the Fehmarn Belt project, 5 pp., 17 April 2012. (In Danish).
Femern A/S (2013). German plan approval documents for the Fehmarn Belt fixed link, 1 October 2013.
http://femern.com/en/Tunnel/Milestones-for-the-project/Approval-process-in-Germany/The-German-plan-
approval-procedure.
(In German).
Femern A/S (2014a). Traffic forecast for a fixed link crossing the Fehmarn Belt, 74 pp., November 2014. (In
Danish).
16
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
1739996_0017.png
Femern A/S (2014b). Financial analysis of the Fehmarnbelt fixed link including Danish land works, 56 pp.,
November 2014. (Available in Danish).
Femern A/S (2015a). Analysis of Fehmarn forecast based on misinterpretation, 8 pp., 16 January 2015. (In
Danish).
Femern A/S (2015b). Status of construction budget for the fixed link across the Fehmarnbelt, 3 pp., February
2015. (Available in Danish).
Femern A/S (2015c). What is the status of the work in Femern A/S with the tunnel crossing Fehmarn Belt?
News release, 26 February 2015. (In Danish).
Femern A/S (2015d). Note: Road users on the Great Belt
en route
between Zealand and Germany, 2 pp., 21
April 2015. (In Danish).
Femern A/S (2016a). Financial analysis of the Fehmarnbelt fixed link including Danish land works, 74 pp., 3
February 2016.
Femern A/S (2016b). Memo
Financial analysis for the Fehmarnbelt project: Assumptions and results February
2016, 3 pp., 10 February 2016.
Femern A/S (2016c). Fehmarn Belt tunnel contractors appointed, 3 April 2016. (In Danish).
Femern A/S (2016d). Femern A/S signs conditional contracts with the prequalified construction consortia
concerning the four large tunnel contracts, press release by Femern A/S, 30 May 2016. (In Danish).
Femern A/S (2016e). Revised plan approval documents for the Fehmarn Belt fixed link, 13 June 2016.
http://pfu.femern.com/.
(In German).
Femern A/S (2016f). Work in progress, Status report from the Ministry of Transport in Schleswig-Holstein
regarding the German approval. Memo to the Transport and Building Committee of the Danish Parliament,
appendix No. 83, 4 pp., 15 November 2016. (In Danish).
Femern A/S (2017a). Femern A/S delivers answers to Germany. Press release, 15 February 2017. (In Danish).
Femern A/S (2017b). Link to home page
http://femern.com/en,
accessed on 6 March 2017.
Femern A/S (2017c). The economy of the Fehmarn Belt project, 2 pp., 27 February 2017. (In Danish).
Femern A/S (2017d). Femern A/S signs contracts with engineering consultants, news release, 17 March 2017.
FTC
Fehmarn Belt Traffic Consortium (1999). Fehmarn Belt traffic demand study
final report, 350 pp.,
January 1999.
FTC
Fehmarn Belt Traffic Consortium (2003). Fehmarn Belt forecast 2002
final report, 150 pp., 1 April 2003.
Ingeniøren (2016a). Fehmarn surprise: The commuters in eastern Denmark now get a railroad worth DKK 7.5
billion, 4 March 2016. (In Danish).
Ingeniøren (2016b). COWI is the big winner of the Fehmarn invitation to tender, 4 March 2016. (In Danish).
Ingeniøren (2016c). Political feint: Denmark spends DKK 13 billion on the Fehmarn Belt fixed link before
German approval, 11 March 2016. (In Danish).
Ingeniøren (2016d). Top-lawyers: The Danish Fehmarn decision is based on fortune telling, 21 March 2016. (In
Danish).
17
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
1739996_0018.png
Ingeniøren (2016e).
Mi istr : That s h toda ´s traffi rossi g Feh ar Belt ea s othi g for the tu el.
Five questions to the Ministry of Transport from journalist Frede Vestergaard, Weekend Avisen, 31 March
2016. (In Danish).
Intraplan Consult GmbH and BVU Beratergruppe GmbH (2014a). Fehmarnbelt forecasts 2014
Update of the
FTC-Study of 2002, 196 pp., November 2014.
Intraplan Consult GmbH and BVU Beratergruppe GmbH (2014b). Fehmarnbelt forecasts 2014
Update of the
FTC-Study of 2002, Annex, 156 pp., November 2014.
I
trapla Co sult G H a d BVU Beratergruppe G H
a . Adde du to the Feh ar elt fore asts
2014
Update of the FTC-Study of 2002 referring to additional data and statements provided by Scandlines in
January 2015, 3 pp., February 2015.
Intraplan Consult GmbH and BVU Beratergruppe GmbH (2015b). Fehmarnbelt forecasts 2014
Update of the
FTC-Study of 2002
Treatment of the Great Belt in the forecast, 2 pp.
Jespersen, P.H. (2007). Road freight transport across Fehmarn Belt fixed link, 7 pp., presented at
Traffic Days,
Aalborg University, August 2007.
KPMG (2012). Quality assurance of railroad constructions in connection with the Fehmarn Belt fixed link, 74 pp.
Commissioned by the Ministry of Transport. (In Danish).
KPMG
Busi ess a al ses of the ferry
link Rødby-Puttgarden, 76 pp., 24 January, 2016. Confidential 14
January 2016 edition published 14 March 2016 after leakage to German journalist. Commissioned by the
Ministry of Transport and Building. (In Danish).
Lorentzen, K.P. (2015). Quotation from speech in the Danish Parliament on the occasion of the first readings of
L141,
Folketingstidende,
18 March 2015, retrieved on 27 March 2015 at
http://www.folketingstidende.dk/RIpdf/samling/20141/forhandlinger/M65/20141_M65_helemoedet.pdf#nam
eddest=L141.
(In Danish).
Rasmussen, I.L. (2015). Fehmarn is the worst investment in the Danish history, feature article,
Ingeniøren,
9
March 2015. (In Danish).
Schjær-Jacobsen, H. (2015a). Financial uncertainty of Fehmarn Belt tunnel is systematically under estimated, 2
pp., communication to the Danish Ministry of Transport and members of the Commission of Transport and
Buildings, Danish Parliament, including response from Femern A/S, 2 March 2015. (In Danish).
Schjær-Ja
o se , H.
. The i ister egle ts the serious riti is
Børsen,
26 November 2015. (In Danish).
of Feh ar , dis ussio arti le,
Schjær-Jacobsen, H. (2016a
. The Feh ar fi ed li k is a fi a ial high risk proje t , feature arti le,
Børsen,
13
January 2016. (In Danish).
Schjær-Jacobsen, H. (2016b). Construction and operation of the Fehmarn Belt immersed tunnel is a high risk
business case. In: Grubbström, R.W., and Hinterhuber, H.H. (Eds.),
Pre-prints of the 19
th
International Working
Seminar on Production Economics,
Vol. 1, pp. 367-378, Innsbruck, Austria, 22-26 February 2016.
Schjær-Jacobsen, H. (2016c). Revisiting financial uncertainty of the Fehmarn Belt
usi ess ase , pp.,
presented at
Traffic Days 2016,
Aalborg University, Denmark, 22-23 August 2016.
Schjær-Jacobsen, H. (2016d). Financial uncertainty of the Fehmarn Belt fixed link, invited paper presented at
the Concept Symposium:
Governing the Front-End of Major Projects,
Symposium Program, p. 56, organized by
18
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
1739996_0019.png
the Norwegian Ministry of Finance and the Norwegian University of Science and Technology, Sola Strand Hotel,
Stavanger, Norway, 8-9 September 2016.
Schjær-Jacobsen, H. (2017). Construction and operation of the Fehmarn Belt immersed tunnel is a high-risk
business case,
Journal of Financial Risk Management,
Vol. 6, pp. 1-15, Scientific Research Publishing, 14
February 2017. Revised version of Schjær-Jacobsen (2016b).
State Memorandum (2000). The Danish German decision on the further development of a fixed link across
Fehmarn Belt, 1 p., 6 December 2000.
State Memorandum (2004). Joint memorandum concerning cooperation about further development of the
Fehmarn Belt fixed link between the Ministries of Transport of Germany and Denmark, 3 pp., 23 June 2004. (In
German and Danish).
State Memorandum (2007). Memorandum of understanding concerning a fixed link crossing Fehmarn Belt
between the Federal Republic of Germany and the Kingdom of Denmark, 2 pp., 29 June 2007. (In Danish and
German).
State Treaty (2008). Treaty between the Kingdom of Denmark and the Federal Republic of Germany on a fixed
link across the Fehmarnbelt, 16 pp., 3 September 2008. (In Danish and German).
Sund & Bælt Holding (2015). Estimate of foreign passages 2009-2013 across the Great Belt, 2 pp., 5 May 2015.
(In Danish).
Sund & Bælt Holding (2016). Project proposal: Analysis of international traffic on the Great Belt and transfer to
Fehmarn, 6 pp., 20 January 2016.
Sund & Bælt Holding (2017a). Link to home page
http://sundogbaelt.dk/en/frontpage/,
accessed on 6 March
2017.
Sund & Bælt Holding (2017b). Answer to the third request of access to public records regarding EQA of road
traffic transfer from the Great Belt, 17 March 2017. (In Danish).
TRM
Danish Ministry of Transport (1999). The Fehmarn Belt fixed link
Economic investigations, 70 pp.,
August 1999. (In Danish).
TRM
Danish Ministry of Transport (2003). Financial analysis, traffic forecast and analysis of railway payment,
summary report, 82 pp., March 2003. (Available in Danish, May 2003).
TRM
Danish Ministry of Transport (2004). Fixed link across Fehmarnbelt
Financial analysis, 30 pp., June
2004.
TRM
Danish Ministry of Transport (2006a). Act No. 16 on New Construction Budgeting, information to the
Finance Committee, 3 pp., 24 October 2006.
TRM
Danish Ministry of Transport (2006b). Fehmarn Belt
An overview, 15 pp., 19 December 2006. (In
Danish).
TRM
Danish Ministry of Transport (2010a). New Construction Budgeting
Main memorandum, 45 pp., 24
August 2009, revised 10 October 2010. (In Danish).
TRM
Danish Ministry of Transport (2010b). Terms of reference for external quality assurance of the basis for
decision making at Level 1, 7 pp., 1 September 2010. (In Danish).
19
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
TRM
Danish Ministry of Transport (2011a). Terms of reference for external quality assurance of the basis for
decision making at Level 2, 10 pp., 17 May 2011. (In Danish).
TRM
Danish Ministry of Transport (2011b). Production of standard elements for the Fehmarn Belt immersed
tunnel will be located in Rødbyhavn, press release, 1 June 2011. (In Danish)
TRM
Danish Ministry of Transport (2015a). Note:
Due dilige e of reser es a d risk distri utio , pp., .
October 2015. (In Danish).
TRM
Danish Ministry of Transport (2015b). Answers to questions from H. Schjær-Jacobsen concerning
application of
New Construction Budgeting
to the Fehmarn Belt fixed link project, e-mail exchange, 11
November 2015
25 February 2016.
TRM
Danish Ministry of Transport (2015c). Traffic forecast gives a realistic estimate on road traffic on the
Fehmarn Belt fixed link, press release, 12 November 2015. (In Danish).
TRM
Danish Ministry of Transport (2015d). Request of analysis of potential road traffic transfer from the
Great Belt to Fehmarn Belt fixed link, e-mail to Sund & Bælt Holding A/S, 12 November 2015 10:08. (In Danish).
TRM
Danish Ministry of Transport (2016a). Political agreement about the Fehmarn Belt project, news release,
4 March 2016. (In Danish).
TRM
Danish Ministry of Transport (2016b). Exchange of letters between Scandlines and the Ministry of
Transport concerning confidential EQA report, KPMG (2016), 9 pp., 10 March
18 March 2016. (In Danish).
TRM
Danish Ministry of Transport (2016c). German delay of environmental approval of Fehmarn Belt fixed
link, news release, 12 December 2016. (In Danish).
TRM
Danish Ministry of Transport (2017a). Status of construction and building projects
second half-year
2016, 119 pp. (In Danish).
TRM
Danish Ministry of Transport (2017b). Letter to the Federal Minister of Transport, 16 February 2017.
(Unauthorized Danish translation).
Vieregg-Rössler GmbH (2008). Expert report on the traffic forecasts and cost calculations of the proposed fixed
Fehmarnbelt link, 55 pp., Munich, January 2008. Commissioned by NABU.
20
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
1739996_0021.png
Appendix: Timeline
Fehmarn Belt fixed link analyses, decisions, external quality assurance (EQA), and external criticism. Extracted
from References.
Date
January 1999
August 1999
6 December 2000
June 2002
March 2003
March 2003
1 April 2003
29 March 2004
23 June 2004
June 2004
Financial analysis
Finances and
organization
Summary report
Financial analysis
Traffic forecast
Economic analysis
Cooperation,
Germany-Denmark
Germany and
DDenmark
Analysis
Traffic demand study
Economic investigations
Decision
External Quality
Assurance (EQA) External criticism
Reference
FTC (1999)
TRM (1999)
Further development
of fixed link
State Memo-
randum (2000)
FDJV (2002)
TRM (2003)
Femern A/S (2003)
FTC (2003)
COWI (2004)
State Memo-
randum (2004)
TRM (2004)
TRM (2006b)
19 December 2006 Overview of project
19 June 2007
29 June 2007
August 2007
January 2008
2 September 2008
3 September 2008
September 2008
29 January 2009
15 April 2009
1 November 2010
1 November 2010
1 November 2010
1 February 2011
Construction costs of a
cable sustained bridge
Construction costs of an
immersed tunnel
Construction costs of
bridge and tunnel
Backing of immersed
tunnel
Financial analysis
Binding political
agreement
Parliament passes
Planning Act No. 285
Binding political
agreement to build
Agreement Denmark-
Germany
Scandlines sold off
Memorandum of
understanding
Berlingske Business
(2007)
State Memo-
randum (2007)
Road freight transport Jespersen (2007)
Traffic forecasts and
cost calculations
Vieregg-Rössler
GmbH (2008)
Danish Parliament
(2008)
State Treaty (2008)
Femern A/S (2008)
Danish Parliament
(2009a)
Danish Parliament
(2009b)
Femern A/S
(2010a)
Femern A/S
(2010b)
Femern A/S
(2010c)
Femern A/S
(2011a)
21
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
1739996_0022.png
Date
16 February 2011
21 April 2011
25 May 2011
1 June 2011
23 June 2011
24 August 2011
17 April 2012
26 April 2012
8 June 2012
20 March 2013
1 October 2013
June 2014
November 2014
November 2014
November 2014
January 2015
16 January 2015
20 January 2015
17 February 2015
19 February 2015
2015
February 2015
2015
26 February 2015
2 March 2015
9 March 2015
Analysis
Customer survey of
Fehmarn Belt
Great Belt traffic
Zealand-Germany
Decision
External Quality External criticism
Assurance (EQA)
Reference
COWI (2011)
Femern A/S
(2011b)
Femern A/S
(2011c)
TRM (2011b)
Danish Parliament
(2011)
Femern A/S
(2011d)
Femern A/S (2012)
Proposal of
production site
Decision on
production site
Construction activities
advanced, Act No. 149
Construction costs of
immersed tunnel
Time schedule for tunnel
construction
EQA of railroad
published
EQA of E47 South
Motorway published
Call for tenders, Act
No. 97
Application for
German approval
Critical analysis of
2003 traffic forecasts
Update of traffic
forecasts from 2002
Traffic forecast
Financial analysis
Critical analysis of
2014 traffic forecasts
Analyses based on
misinterpretation
Comments to new
traffic forecasts
Status of construction
budget
Investigation of cost-
benefit analysis
Robustness of
financial analysis
Addendum to update of
traffic forecasts
Transfer of Great Belt
road traffic
Status of work in Femern
A/S
Under estimation of
financial uncertainty
Worst investment in
Danish history
KPMG (2012)
Deloitte (2012)
Danish Parliament
(2013)
Femern A/S (2013)
Andersen (2014)
Intraplan (2014a,
2014b)
Femern A/S
(2014a)
Femern A/S
(2014b)
Andersen (2015)
Femern A/S
(2015a)
DIW Econ GmbH
(2015a)
Femern A/S
(2015b)
DIW Econ GmbH
(2015b)
DIW Econ GmbH
(2015c)
Intraplan (2015a)
Intraplan (2015b)
Femern A/S
(2015c)
Schjær-Jacobsen
(2015a)
Rasmussen (2015)
22
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
1739996_0023.png
Date
20 April
21 May
2015
21 April 2015
28 April 2015
5 May 2015
1 June 2015
29 June 2015
1 October 2015
2 October 2015
21 October 2015
10 November 2015
11 November 2015
12 November 2015
12 November 2015
20 November 2015
26 November 2015
13 January 2016
20 January 2016
24 January 2016
28 January 2016
January 2016
3 February 2016
10 February 2016
22 February 2016
4 March 2016
4 March 2016
4 March 2016
Analysis
Decision
External Quality External criticism
Assurance (EQA)
Work program for
traffic EQA
Reference
COWI (2015a)
Femern A/S
(2015d)
Danish Parliament
(2015)
Sund & Bælt
Holding (2015)
Road users on the Great
Belt
Construction Act L141
passed conditionally
Foreign passages of the
Great Belt
EQA of ferry services
started
EU appropriates reduced
subsidy
Due dilige e of
reserves etc.
Financial uncertainty
analysis
EQA of tunnel
commissioned
EQA of road traffic
forecasts published
Appl. of
New
Construction Budgeting
Traffic forecast
approved by Minister
EQA of road traffic
transfer requested
Traffic transfer from
the Great Belt
Minister ignores
criticism from EQA
Financial high risk
project
Proposal of Great Belt
traffic analysis
EQA of competition
by ferry services
published
EQA of tunnel
published
KPMG (2016)
Børsen (2015)
TRM (2015a)
Bredsdorff (2015a)
Ernst & Young
(2016)
COWI (2015b)
TRM (2015b)
TRM (2015c)
TRM (2015d)
Bredsdorff (2015b)
Schjær-Jacobsen
(2015b)
Schjær-Jacobsen
(2016a)
Sund & Bælt
Holding (2016)
KPMG (2016)
Ernst & Young
(2016)
Competition between
Aigner (2016)
ferry and tunnel
Femern A/S
(2016a)
Femern A/S
(2016b)
High risk business
Schjær-Jacobsen
case
(2016b)
Danish Parliament
(2016)
TRM (2016a)
Ingeniøren (2016a)
Financial analysis
Memo: Financial
analyses
Binding political
agreement
Upgrading of existing
rail track begins
Upgrading of existing
rail track begins
23
TRU, Alm.del - 2016-17 - Bilag 266: Henvendelse af 2/4-17 vedrørende Femern Bælt forbindelsen, fra Hans Schjær-Jacobsen, Hellerup
1739996_0024.png
Date
4 March 2016
− 8 Mar h
2016
11 March 2016
21 March 2016
31 March 2016
3 April 2016
30 May 2016
13 June 2016
24 June 2016
22 August 2016
8 September 2016
Analysis
Decision
External Quality External criticism
Assurance (EQA)
COWI is the big
winner
Correspondence
Scandlines - Ministry
Proje t is too ig to
fail
Criticism of EQA of
German approval
Five questions
answered by TRM
Reference
Ingeniøren (2016b)
TRM (2016b)
Ingeniøren (2016c)
Ingeniøren (2016d)
Ingeniøren (2016e)
Femern A/S
(2016c)
Femern A/S
(2016d)
Femern A/S
(2016e)
Preferred tunnel
contractors appointed
Tunnel construction
contracts signed
Renewed application
for German approval
Review of KPMG
quality assurance
Revisiting financial
uncertainty
Financial uncertainty
Deloitte (2016)
Schjær-Jacobsen
(2016c)
Schjær-Jacobsen
(2016d)
Femern A/S (2016f)
TRM (2016c)
TRM (2017a)
Memo: German approval
status
German approval
12 December 2016
delayed by 6 months
Status of Fehmarn Belt
2017
construction project
14 November 2016
14 February 2017
15 February 2017
16 February 2017
27 February 2017
14 March 2017
17 March 2017
Engineering
consultants signed up
engineering
consultants
Confirmation of financial
analysis
12,600 German
objections answered
Letter to German
minister
High risk business
case
Schjær-Jacobsen
(2017)
Femern A/S
(2017a)
TRM (2017b)
Femern A/S
(2017c)
Scandlines announces
Børsen (2017)
possible court case
Femern A/S
(2017d)
24