ANNEX
The work programme relating to the development and
deployment of the electronic systems provided for in the Union
Customs Code
I. Introduction to the Work Programme
1. The Work Programme provides an instrument to support the application of the Code
relating to the development and deployment of the electronic systems envisaged therein.
2. The purpose of the Work Programme is also to specify periods during which the
transitional measures are applicable until the deployment of the new or upgraded electronic
systems as referred to in Delegated Regulation (EU) 2015/2446, Delegated Regulation
(EU) XXX/XXX [TDA] and Implementing Regulation (EU) 2015/2447.
3. The 'key milestone' in terms of target date of the technical specifications, shall be
understood as the date by which a stable version of the technical specifications is made
available. For the national systems or components, this date will be communicated as part
of the published national project planning.
4. The Work Programme establishes the following 'dates of the deployment' of the trans-
European and national systems:
(a) the start date of the deployment window for the electronic systems, to be understood as
the earliest date to start operations of the electronic system;
(b) the end date of the deployment window for the electronic systems, to be understood as
-the latest date by which the systems need to be operated by all Member States and
used by all economic operators, and as well as
-the end date of the validity of the transitional period.
For the purposes of point (b), the date will be the same as the start date in case no actual
(deployment or migration) time-window is envisaged.
5. For purely national systems or specific national components of a wider Union project,
the Member States may decide on the 'dates of deployment' as well as on the start date and
on the end date of a deployment window in accordance with their national project planning.
The following national systems or specific national components are covered by the first
paragraph:
(a) UCC AES Component 2 (National Export Systems upgrade) (point 10 of Part II);
(b) UCC Special Procedures (SP IMP/SP EXP) (point 12 of Part II);
2
L 99 - 2015-16 - Endeligt svar på spørgsmål 1: Spm. om ministeren vil redegøre for de økonomiske og administrative konsekvenser for henholdsvis det offentlige og erhvervslivet ved indførelsen af EU-toldkodeksen, til skatteministeren
(c) UCC Arrival Notification, Presentation Notification, Temporary Storage (point 13
of Part II);
(d) UCC National Import Systems upgrade (point 14 of Part II);
(e) UCC Guarantee Management (GUM) - Component 2 (point 16 of Part II).
6. For trans-European systems with an actual deployment window without a single
implementation date, the Member States may start the deployment at an appropriate date
within this window and may allow a time-period for the economic operators to migrate
within this deployment window, where such time-period is deemed appropriate. The start
and end dates shall be communicated to the Commission. Careful examination of the
common domain aspects will need to be considered.
The following trans-European systems are covered by the first paragraph:
(a) UCC Proof of Union Status (PoUS) (point 8 of Part II),
(b) UCC NCTS upgrade (point 9 of Part II);
(c) UCC AES (Component 1) (point 10 of Part II).
7. In view of the implementation of the Work Programme, the Commission and the
Member States will need to manage carefully the complexity in terms of dependencies,
variables and assumptions. The principles set out in the MASP will be used to manage the
planning.
The projects referred to in points will be rolled out in different phases from elaboration to
construction, testing and migration to final operation. The role of the Commission and the
Member States in these different phases will depend on the nature and architecture of the
systems and its components or services, as described in the detailed project fiches of the
MASP. Where appropriate, common technical specifications will be defined by the
Commission, in close cooperation with and subject to review with the Member States, with a
view to provide them 24 months prior to the target date of deployment of the electronic
system. Technical specifications drawn up nationally for the national systems or components
need to be made available, at least concerning the parts related to the external communication
with the economic operators, in a timely manner in order to enable the economic operators to
plan and adjust their systems and interfaces accordingly.
The Member States and, where appropriate, the Commission will engage in the development
and deployment of the systems in line with the defined system architecture and
specifications. The activities will be carried out in respect of the milestones and dates
stated in the Work Programme. The Commission and the Member States will also
collaborate with the economic operators and other stakeholders.
The economic operators will have to take the necessary steps to be able to make use of the
3
L 99 - 2015-16 - Endeligt svar på spørgsmål 1: Spm. om ministeren vil redegøre for de økonomiske og administrative konsekvenser for henholdsvis det offentlige og erhvervslivet ved indførelsen af EU-toldkodeksen, til skatteministeren
systems once in place and at the latest by the end dates defined in this Work Programme or,
where applicable, defined by the Member States as part of their national plan.
4
L 99 - 2015-16 - Endeligt svar på spørgsmål 1: Spm. om ministeren vil redegøre for de økonomiske og administrative konsekvenser for henholdsvis det offentlige og erhvervslivet ved indførelsen af EU-toldkodeksen, til skatteministeren
1603992_0005.png
II. List of projects related to the development and deployment of electronic systems
A. Full list
UCC Projects and related Electronic Systems
Legal basis
Key
milestone
Dates of deployment of the
electronic systems
End date of the
deployment window
Start date of the
of the electronic
deployment window
system
5
of the electronic
=
system
4
End date of the
transitional period
1. UCC Registered Exporter System (REX)
Article 6(1),
Articles 16 and
The project aims to make available up-to-date information on
64 of Regulation
Registered Exporters established in GSP countries exporting goods
(EU) No 952/2013
to the Union. The system will be a trans-European system and also
include data about EU economic operators for the purpose of
supporting exports to GSP countries. The required data will be
inserted in the system in a gradual manner until 31 December 2017.
4
5
Target date of
technical
specifications
= Q1 2015
01/01/2017
01/01/2017
This date for starting the deployment window of the electronic systems equals the earliest date for Member States to start operations.
This date for ending the deployment window of the electronic systems equals to the latest date by which the system should be fully deployed and the latest date by which all
economic operators should be migrated; where applicable, the date will be established by the Member States and equals the end date of the validity of the transitional period.
This date shall not be later than 31 December 2020.
6
L 99 - 2015-16 - Endeligt svar på spørgsmål 1: Spm. om ministeren vil redegøre for de økonomiske og administrative konsekvenser for henholdsvis det offentlige og erhvervslivet ved indførelsen af EU-toldkodeksen, til skatteministeren
1603992_0006.png
2. UCC Binding Tariff Information (BTI)
The project aims at providing an upgrade of the existing trans-
European EBTI-3 system and Surveillance 2 systems to ensure the
following:
(a) alignment of the EBTI-3 system to the UCC requirements;
(b) extension of under-surveillance-required declaration data;
(c) monitoring of the compulsory BTI usage;
(d) monitoring and management of BTI extended usage.
Article 6(1),
Articles 16, 22,
23 26, 27, 28, 33
and 34 of
The project will be implemented in two phases.
The first phase will, firstly, provide the functionality to receive the
Regulation (EU)
UCC required declaration dataset (i.e. step 1) as of 1 March 2017 in
No 952/2013
a gradual manner until the implementation of the projects listed in
points 10 and 14 hereof (and at the latest by 31 December 2020),
and, secondly, fulfil the obligation of BTI usage control on the basis
of the newly required declaration dataset and the alignment to the
customs decisions process (i.e. step 2).
The second phase will implement the electronic form of the BTI
application and decision and provide for the economic operators an
EU harmonised trader interface to submit the BTI application and
receive the BTI decision electronically.
3. UCC Customs Decisions
The project aims at harmonising the processes related to the
application for a customs decision, the decision-taking and the
decision management through standardisation and electronic
management of application and decision/authorisation data across
Article 6(1),
Articles 16, 22,
23, 26, 27 and 28
of Regulation
(EU) No 952/2013
Target date of
technical
specifications
=Q2 2016
(phase 1)
01/03/2017
01/03/2017
(phase 1 – step 1) (phase 1 – step 1)
01/10/2017
01/10/2017
(phase 1 – step 2) (phase 1 – step 2)
=Q3 2016
(phase 2)
01/10/2018
(phase 2)
01/10/2018
(phase 2)
Target date of
technical
specifications
=Q4 2015
02/10/2017
02/10/2017
7
L 99 - 2015-16 - Endeligt svar på spørgsmål 1: Spm. om ministeren vil redegøre for de økonomiske og administrative konsekvenser for henholdsvis det offentlige og erhvervslivet ved indførelsen af EU-toldkodeksen, til skatteministeren
1603992_0007.png
the Union. The project relates to national and multi-Member State
decisions defined by the Code and will cover system components
developed centrally at Union level and cover integration with
national components where opted for by Member States. This
trans- European system will facilitate consultations during the
decision taking period and the management of the authorisations
process.
This trans-European system consists of an EU trader portal, a
customs decisions management system and a customer reference
4. Direct trader access to the European Information Systems
(Uniform User Management & Digital Signature)
The goal of this project is to provide working solutions for a direct
and EU harmonised trader access as a service for user-to-system
interfaces to be integrated in the electronic customs systems as
defined in the specific UCC projects. The Uniform User
Management and Digital Signature will be integrated in the portals
of the concerned systems and includes support for identity, access
and user management compliant with the necessary security
policies.
The first deployment is foreseen together with the UCC Customs
Decisions system.
Afterwards, this technical enabler for authentication and user
management will be made available for usage in other UCC projects
such as the UCC BTI, UCC AEO upgrade UCC Proof of Union
Status system and potentially also the UCC Information Sheets
(INF) for Special Procedures system. See the different projects for
the dates of deployment.
Article 6(1) and
Article 16 of
Regulation (EU)
No 952/2013
Target date of
technical
specifications
=Q4 2015
02/10/2017
02/10/2017
8
L 99 - 2015-16 - Endeligt svar på spørgsmål 1: Spm. om ministeren vil redegøre for de økonomiske og administrative konsekvenser for henholdsvis det offentlige og erhvervslivet ved indførelsen af EU-toldkodeksen, til skatteministeren
1603992_0008.png
5. UCC Authorised Economic Operators (AEO) upgrade
Article 6(1),
The project aims to improve the business processes related to AEO
Articles 16, 22,
applications and authorisations taking into account the changes of
23, 26, 27, 28, 38
and 39 of
the legal provisions of the UCC.
In the first phase, the project aims at implementing the major
enhancements to the AEO system in view of the harmonisation to
the customs decision taking procedure.
In the second phase, the project will implement the electronic form
of the AEO application and decision and provide for the economic
operators an EU harmonised interface to submit the AEO
application and receive the AEO decision electronically.
Regulation (EU)
No 952/2013
Target date of
technical
specifications
=Q1 2016
01/03/2018
(phase 1)
01/03/2018
(phase 1)
Target date of
technical
specifications
=Q3 2017
1/10/2019
(phase 2)
1/10/2019
(phase 2)
6. UCC Economic Operator Registration and Identification
System upgrade (EORI 2)
This project aims at providing a minor upgrade of the existing trans-
European EORI system that enables the registration and
identification of economic operators of the Union and third
country operators that are active on customs matters in the Union.
Article 6(1) and
Article 9 of
Regulation (EU)
No 952/2013
Target date of
technical
specifications
=Q2 2016
01/03/2018
01/03/2018
9
L 99 - 2015-16 - Endeligt svar på spørgsmål 1: Spm. om ministeren vil redegøre for de økonomiske og administrative konsekvenser for henholdsvis det offentlige og erhvervslivet ved indførelsen af EU-toldkodeksen, til skatteministeren
1603992_0009.png
7. UCC Surveillance 3
This project aims at providing an upgrade of the Surveillance 2+
system to ensure its alignment to the UCC requirements such as the
standard exchange of information by electronic data-processing
techniques and the establishment of adequate functionalities needed
for processing and analysing the full surveillance dataset obtained
from Member States.
Therefore it will include further data mining capabilities and
reporting functionalities to be made available to Commission and
Member States.
8. UCC Proof of Union Status (PoUS)
The project aims at the creation of a new trans-European system to
store, manage and retrieve the following electronic Proofs of Union
Status: T2L/F and the customs goods manifest (issued by a non-
authorised issuer).
Article 6(1),
Articles 16 and
153 of Regulation
(EU) No 952/2013
Target date of
technical
specifications
=Q1 2017
Article 6(1),
Articles 16 and
56(5) of
Regulation (EU)
No 952/2013
Target date of
technical
specifications
=Q3 2016
01/10/2018
01/10/2018
01/03/2019
01/10/2019
9. UCC New Computerised Transit System (NCTS) upgrade
The aim of this project is to align the existing trans-European NCTS
system to the new UCC requirements such as the registration of "en
route" events and the alignment of information exchanges to UCC
data requirements and the upgrade and development of interfaces
with other systems.
Article 6(1),
Articles 16 and
226 - 236 of
Regulation (EU)
No 952/2013
Target date of
technical
specifications
=Q3 2017
01/10/2019
02/03/2020
10
L 99 - 2015-16 - Endeligt svar på spørgsmål 1: Spm. om ministeren vil redegøre for de økonomiske og administrative konsekvenser for henholdsvis det offentlige og erhvervslivet ved indførelsen af EU-toldkodeksen, til skatteministeren
1603992_0010.png
10. UCC Automated Export System (AES)
This project aims to implement the UCC requirements for export
and exit.
Component 1 - "AES":
The aim of the project is to further develop
the existing trans-European Export Control System in order to
implement a full AES that would cover the business requirements
for processes and data brought about by the UCC, inter alia the
coverage of simplified procedures, split exit consignments and
centralised clearance for export. It is also envisaged to cover the
development of harmonised interfaces with Excise Movement
System (EMCS) and NCTS. As such, AES will enable the full
automation of export procedures and exit formalities. AES covers
parts to be developed centrally and nationally.
Component 2 – "National Export Systems upgrade":
In addition,
not being part of the scope of AES but closely linked, separate
national systems are to be upgraded for specific national elements
related to export and/or exit formalities. As far as these elements do
not have an impact on the common domain for AES, they can be
covered under this component.
11. UCC Information Sheets (INF) for Special Procedures
The aim of this project is to develop a new centralised system to
support and streamline the processes of INF data management and
the electronic handling of INF data in the domain of Special
Procedures.
Article 6(1),
Articles 16 , 215,
237 – 242 and 250
- 262 of
Regulation (EU)
No 952/2013
Article 6(1),
Articles 16, 179
and 263 - 276 of
Regulation (EU)
No 952/2013
Target date of
technical
specifications
=Q3 2017
(component 1)
01/10/2019
(component 1)
02/03/2020
(component 1)
Target date of
technical
specifications
=to be defined by
MS
(component 2)
01/03/2017
(component 2)
02/03/2020
(component 2)
Target date of
technical
specifications
=Q1 2018
02/03/2020
02/03/2020
11
L 99 - 2015-16 - Endeligt svar på spørgsmål 1: Spm. om ministeren vil redegøre for de økonomiske og administrative konsekvenser for henholdsvis det offentlige og erhvervslivet ved indførelsen af EU-toldkodeksen, til skatteministeren
1603992_0011.png
12. UCC Special Procedures
This project aims at accelerating, facilitating and harmonising
Special Procedures across the Union by means of providing
common business process models. The national systems will
implement all UCC changes required for customs warehousing, end-
use, temporary admission, inward and outward processing.
Article 6(1),
Articles 16, 215,
Target date of
237 - 242 and 250
This project will be implemented in two parts.
technical
- 262 of
specifications
Component 1 - "National SP EXP":
provide the required national
Regulation (EU)
=to be defined by
01/03/2017
electronic solutions for the export related special procedures
MS (for
(component 1)
No 952/2013
activities.
component 1 and
2)
Component 2 - "National SP IMP":
provide the required national
To be defined by
electronic solutions for the import related special procedures
MS as part of the
activities.
national plan
(component 2)
The implementation of these projects is directly linked to the
projects listed in points 10 and 14 hereof.
13. UCC Notification of Arrival, Presentation Notification and
Temporary Storage
The goal of this project is to define the processes for Notification of
Arrival of the means of transport, Presentation of the goods
(Presentation Notification) and Declaration for Temporary Storage
as described in the UCC and to support harmonisation in this respect
02/03/2020
(component 1)
To be defined
by MS as part
of the national
plan
(component 2)
Article 6(1),
Target date of
Articles 16 and
To be defined
technical
133 - 152 of
To be defined by by MS as part
specifications
Regulation (EU)
MS as part of the of the national
=to be defined by
No 952/2013
national plan
plan
MS
12
L 99 - 2015-16 - Endeligt svar på spørgsmål 1: Spm. om ministeren vil redegøre for de økonomiske og administrative konsekvenser for henholdsvis det offentlige og erhvervslivet ved indførelsen af EU-toldkodeksen, til skatteministeren
1603992_0012.png
across the Member States as regards the data exchange between
trade and customs and, where required, between customs
administrations.
The project covers the automation of processes at national level.
14. UCC National Import Systems upgrade
The project aims at implementing all process and data requirements
deriving from the UCC which relate to the import domain (and
which are not covered by one of the other projects defined in the
Work Programme). It relates mainly to the changes for the "Release
for free circulation" procedure (standard procedure +
simplifications), but covers also the impact arising from other
system migrations. This project relates to the national import
domain covering the national customs declarations processing
systems as well as other systems such as national accountancy and
payment systems.
15. UCC Centralised Clearance for Import (CCI)
Article 6(1),
Article 16(1)and
Articles
53, 56, 77-80, 83- Target date of
To be defined
technical
To be defined by by MS as part
87, 101-105, 108-
109, 158-187,194- specifications
MS as part of the of the national
=to be defined by
national plan
plan
195 of Regulation
MS
(EU) No 952/2013
Article 6(1),
This project aims to allow for goods to be placed under a customs
Articles 16 and
procedure using centralised clearance, allowing economic operators
179 of Regulation
to centralise their business from a customs viewpoint. The
(EU) No 952/2013
processing of the customs declaration and the physical release of the
goods should be coordinated between the related customs offices. It
concerns a trans-European system containing components
developed centrally and nationally.
Target date of
technical
specifications
=Q2 2018
01/10/2020
Roll-out plan to
be defined as part
of the CCI project
documentation
13
L 99 - 2015-16 - Endeligt svar på spørgsmål 1: Spm. om ministeren vil redegøre for de økonomiske og administrative konsekvenser for henholdsvis det offentlige og erhvervslivet ved indførelsen af EU-toldkodeksen, til skatteministeren
1603992_0013.png
16. UCC Guarantee Management (GUM)
This project aims to assure the effective and efficient management
of the different types of guarantees.
Component 1 – "GUM":
The trans-European system will cover
the management of the comprehensive guarantees that may be used
in more than one Member State and the monitoring of the reference
amount for each customs declaration, supplementary declaration or
an appropriate information of the particulars needed for the entry in
the accounts for the existing customs debts for all customs
procedures as provided for in the Union Customs Code, except
Transit which is handled as part of the NCTS project.
Component 2 – "National Guarantee Management":
In addition,
the electronic systems existing at national level to manage the
guarantees valid in one Member State are to be upgraded.
17. UCC Import Control System upgrade (ICS 2)
The goal of this project is to strengthen the safety and security of the
supply chain for all modes of transport and especially air cargo, by
means of improving data quality, data filing, data availability and
data sharing as regards the entry summary declaration and related
risk and control information (ENS+ lifecycle).
The project will also facilitate the collaboration amongst Member
States in the process of risk analysis. It will lead to a
complete new architecture of the existing trans-European ICS
system.
Article 6(1),
Articles 16, 46
and 127 - 132 of
Regulation (EU)
No 952/2013
Article 6(1),
Articles 16 and
89 - 100 of
Regulation (EU)
No 952/2013
Target date of
technical
specifications
=Q2 2018
(component 1)
01/10/2020
(component 1)
01/10/2020
(component 1)
Target date of
To be defined by
technical
MS as part of the
specifications
national plan
=to be defined by
(component 2)
MS (component 2)
To be defined
by MS as part
of the national
plan
(component 2)
Target date of
technical
specifications
=Q2 2018
01/10/2020
Roll-out plan to
be defined as part
of the ICS2
project
documentation
14
L 99 - 2015-16 - Endeligt svar på spørgsmål 1: Spm. om ministeren vil redegøre for de økonomiske og administrative konsekvenser for henholdsvis det offentlige og erhvervslivet ved indførelsen af EU-toldkodeksen, til skatteministeren
1603992_0014.png
B. Overview of the list
UCC Projects related to electronic systems
1. UCC Registered Exporter System (REX)
2. UCC Binding Tariff Information System (BTI)
3. UCC Customs Decisions
4. Direct trader access to European Information Systems
(Uniform user management & digital signature)
5. UCC Authorised Economic Operators System (AEO) upgrade
6. UCC Economic Operator Registration and Identification
System upgrade (EORI 2)
7. UCC Surveillance 3
8. UCC Proof of Union Status (PoUS)
9. UCC New Computerised Transit System (NCTS) upgrade
10. UCC Automated Export System (AES) –
Component 1: Trans-European AES
10. UCC Automated Export System (AES) –
Component 2: National Export Systems upgrade
11. UCC Information Sheets (INF) Special Procedures
12. UCC Special Procedures –
Component 1: National SP EXP
12. UCC Special Procedures –
Component 2: National SP IMP
13. UCC Notification of arrival, presentation notification and
temporary storage
14. UCC National Import Systems upgrade
Dates of deployment /
Deployment windows
01/01/2017
01/03/2017 (phase 1 – step 1)
01/10/2017 (phase 1 – step 2))
01/10/2018 (phase 2)
02/10/2017
02/10/2017
01/03/2018 (phase 1)
01/10/2019 (phase 2)
01/03/2018
01/10/2018
01/03/2019 – 01/10/2019
01/10/2019 – 02/03/2020
01/10/2019 – 02/03/2020
01/03/2017 – 02/03/2020
02/03/2020
national planning
01/03/2017-02/03/2020
- see also project 10
national planning for SP IMP
- see also project 14
national planning
national planning
SP IMP
SP IMP
SP EXP
SP EXP
SP EXP
SP EXP
SP EXP
SP EXP
SP EXP
Phase 1
Phase 2
Phase 1
(step 1)
Phase 1
(step 2)
Phase 2
S1 2016
S2 2016
S1 2017
S2 2017
S1 2018
S2 2018
S1 2019
S2 2019
S1 2020
S2 2020
SP IMP
SP IMP
SP IMP
SP IMP
SP IMP
SP IMP
SP IMP
SP IMP
15
L 99 - 2015-16 - Endeligt svar på spørgsmål 1: Spm. om ministeren vil redegøre for de økonomiske og administrative konsekvenser for henholdsvis det offentlige og erhvervslivet ved indførelsen af EU-toldkodeksen, til skatteministeren
1603992_0015.png
15. UCC Centralised Clearance for Import (CCI)
16. UCC Guarantee Management (GUM) –
Component 1: Trans-European GUM
16. UCC Guarantee Management System (GUM) –
Component 2: National Guarantee Management
17. UCC Import Control System upgrade (ICS 2)
01/10/2020 – rollout plan
01/10/2020 – 01/10/2020
national planning
01/10/2020 – rollout plan
16