Selected Acquisition Report (SAR)
RCS: DD-A&T(Q&A)823-549
F/A-18E/F Super Hornet Aircraft (F/A-18E/F)
As of December 31, 2012
Defense Acquisition Management
Information Retrieval
(DAMIR)
May 21, 2013
16:04:14
UNCLASSIFIED
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0002.png
F/A-18E/F
December 31, 2012 SAR
Table of Contents
Program Information
Responsible Office
References
Mission and Description
Executive Summary
Threshold Breaches
Schedule
Performance
Track To Budget
Cost and Funding
Low Rate Initial Production
Foreign Military Sales
Nuclear Cost
Unit Cost
Cost Variance
Contracts
Deliveries and Expenditures
Operating and Support Cost
3
3
3
4
5
6
7
10
13
14
21
22
22
23
26
29
33
34
May 21, 2013
16:04:14
UNCLASSIFIED
2
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0003.png
F/A-18E/F
December 31, 2012 SAR
Program Information
Program Name
F/A-18E/F Super Hornet Aircraft (F/A-18E/F)
DoD Component
Navy
Responsible Office
Responsible Office
CAPT Frank Morley, USN
Program Executive Officer (PMA265)
Bldg 2272, Suite 445 NAVAIRSYSCOMHQ
47123 Buse Road, Unit IPT
Patuxent River, MD 20670-1547
[email protected]
Phone
Fax
DSN Phone
DSN Fax
301-757-7669
301-757-7520
757-7669
757-7520
Date Assigned
July 14, 2011
References
SAR Baseline (Production Estimate)
Navy Acquisition Executive (NAE) Approved Acquisition Program Baseline (APB) dated September 17, 2000
Approved APB
Navy Acquisition Executive (NAE) Approved Acquisition Program Baseline (APB) dated February 15, 2011
May 21, 2013
16:04:14
UNCLASSIFIED
3
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0004.png
F/A-18E/F
December 31, 2012 SAR
Mission and Description
The F/A-18E/F Super Hornet is the second major model upgrade since the inception of the F/A-18 aircraft program.
The single-seat F/A-18E and the two-seat F/A-18F are high performance, twin-engine, mid-wing, and multi-mission
tactical aircraft designed to replace the F/A-18C (single-seat) and F/A-18D (two-seat) aircraft as they reach the end
of their service lives and retire. The F/A-18E/F is designed to meet current Navy fighter escort and interdiction
mission requirements, to maintain F/A-18 fleet air defense and close air support roles, as well as an increasing
range of missions, including Forward Air Controller (Airborne) and Aerial Tanking, as the F/A-18E/F has proven
capability to replace the S-3 as an aerial tanker. F/A-18E/F enhancements include increased range and improved
carrier suitability required for the F/A-18 to continue its key strike fighter role against the advanced threats of the 21st
century.
May 21, 2013
16:04:14
UNCLASSIFIED
4
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0005.png
F/A-18E/F
December 31, 2012 SAR
Executive Summary
The program continues to excel. Cost, schedule, and performance were superb during this reporting period, and the
program continues to deliver aircraft ahead of schedule. As of March 27, 2013, the program has delivered 506
aircraft to the fleet (62 Low Rate Initial Production (LRIP) and 444 Full Rate Production (FRP)). This report solely
reflects the domestic Program of Record (PoR) quantities.
As of January 30, 2013, Super Hornet aircraft have flown over 1,131,122 hours.
The F/A-18E/F and EA-18G are software-intensive systems that share a common Operational Flight Program
(OFP). The current OFP is the H6E System Configuration Set (SCS), which was released to the fleet in October
2011. The H8E SCS represents the latest software upgrade that will replace the H6E SCS following Operational
Test (OT). The program office delayed H8E entry into OT by four months to correct weapon integration and
interoperability issues. The issues were resolved, and OT began in June 2012. H8E fleet release is scheduled
for July 2013. Therefore, there are no significant software-related issues with this program at this time.
Because the program is more than 90 percent delivered, this is the final SAR submission for the F/A-18E/F Super
Hornet Aircraft program (pursuant to section 2432 of title 10, United States Code).
May 21, 2013
16:04:14
UNCLASSIFIED
5
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0006.png
F/A-18E/F
December 31, 2012 SAR
Threshold Breaches
APB Breaches
Schedule
Performance
Cost
RDT&E
Procurement
MILCON
Acq O&M
O&S Cost
Unit Cost
PAUC
APUC
Nunn-McCurdy Breaches
Current UCR Baseline
PAUC
None
APUC
None
Original UCR Baseline
PAUC
None
APUC
None
May 21, 2013
16:04:14
UNCLASSIFIED
6
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0007.png
F/A-18E/F
December 31, 2012 SAR
Schedule
May 21, 2013
16:04:14
UNCLASSIFIED
7
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0008.png
F/A-18E/F
December 31, 2012 SAR
Milestones
Milestone IV/II
First Engine to Test
Preliminary Design Review (Airframe)
Critical Design Review (Airframe)
Production Readiness Review (Airframe)
Preliminary Flight Qualification (Engine)
First Flight
Long Lead Release for LRIP
LRIP Decision Milestone
Limited Production Qualification (Engine)
LRIP Contract Award
Full Production Qualification (Engine)
LRIP First Delivery
Milestone III
Full Rate Production Contract Award
DT&E
DT-IIA
DT-IIB
DT-IIC
DT-IID
DT-IIE
IOT&E
OT-IIA
OT-IIB
OT-IIC
O-Level Maintenance Capability
(OPEVAL)
IOC
I-Level Maintenance Capability
WRA TPS and Modified TPSs (IOC)
New SRA TPS (IOC + one year)
Material Support Date
Navy Support Date
D-Level Maintenance Capability
SAR Baseline
Prod Est
MAR 1992
APR 1993
APR 1993
JAN 1994
APR 1995
MAR 1995
OCT 1995
DEC 1995
MAR 1997
MAR 1997
JAN 1997
AUG 1998
DEC 1998
JAN 2000
JAN 2000
OCT 1995
NOV 1996
NOV 1997
JUL 1998
OCT 1998
NOV 1997
DEC 1997
MAR 1999
MAR 1999
JUN 2001
SEP 2000
SEP 2001
OCT 2002
OCT 2003
OCT 2003
Current APB
Production
Objective/Threshold
MAR 1992 SEP 1992
APR 1993 OCT 1993
APR 1993 OCT 1993
JAN 1994
JUL 1994
APR 1995 OCT 1995
MAR 1995 SEP 1995
OCT 1995 APR 1996
DEC 1995 JUN 1996
MAR 1997 SEP 1997
MAR 1997 SEP 1997
JAN 1997
JUL 1997
AUG 1998 FEB 1999
DEC 1998 JUN 1999
JAN 2000
JUL 2000
JAN 2000
JUL 2000
OCT 1995
NOV 1996
NOV 1997
JUL 1998
OCT 1998
NOV 1997
DEC 1997
MAR 1999
MAR 1999
JUN 2001
SEP 2000
SEP 2001
OCT 2002
OCT 2003
OCT 2003
APR 1996
MAY 1997
MAY 1998
JAN 1999
APR 1999
MAY 1998
JUN 1998
SEP 1999
SEP 1999
DEC 2001
MAR 2001
MAR 2002
APR 2003
APR 2004
APR 2004
Current
Estimate
MAY 1992
MAY 1993
JUN 1993
JUL 1994
AUG 1995
SEP 1995
NOV 1995
MAR 1996
MAR 1997
APR 1997
MAY 1997
DEC 1998
DEC 1998
JUN 2000
JUN 2000
NOV 1995
DEC 1996
DEC 1997
OCT 1998
APR 1999
NOV 1997
JUN 1998
MAY 1999
MAY 1999
SEP 2001
SEP 2000
SEP 2001
APR 2003
MAR 2004
MAR 2004
May 21, 2013
16:04:14
UNCLASSIFIED
8
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0009.png
F/A-18E/F
December 31, 2012 SAR
Acronyms And Abbreviations
DT - Developmental Testing
DT&E - Developmental Test and Evaluation
IOC - Initial Operational Capability
IOT&E - Initial Operational Test and Evaluation
LRIP - Low Rate Initial Production
OPEVAL - Operational Evaluation
OT - Operational Testing
SRA - Shop Replaceable Assembly
TPS - Test Program Set
WRA - Weapon Replaceable Assembly
Change Explanations
None
May 21, 2013
16:04:14
UNCLASSIFIED
9
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0010.png
F/A-18E/F
December 31, 2012 SAR
Performance
SAR Baseline
Prod Est
Achieve all
IERs
Current APB
Demonstrated Current
Production
Performance Estimate
Objective/Threshold
Achieve all Achieve all Achieve all
Achieve all
IERs
Critical
Critical IERs
Critical IERs
IERs
<= 1.4
>=425
<1.5
>=410
1.46
462
1.46
434
Characteristics
Interoperability of the
F/A-18E/F
Communications & Data
Link Suite
Deck Spot Factor (F/A-
18A/B/C/D =1.2)
Fighter Escort Radius
(F/A-18E)(internal fuel)
(Nm)
Interdiction Mission
Radius (Nm)
2 external tanks
(retained)
3 external tanks
(retained)
Combat Ceiling (max
thrust) (ft)
Launch: Catapult WOD
(C-13-1 Catapult
MAXTOGW (kts))
Recovery: WOD (MK-
7MOD 3) (kts)
Recovery Payload (lbs)
Usable Load Factor
(Subsonic; Nz) (G's)
Specific Excess Power
(Max Thrust, .9M, 1G,
10kft) (fps)
Acceleration (.8M to
1.2M at 35kft) (sec)
Additional Internal Fuel
Capacity (lbs) (greater
than C/D)
Mean Time Between
Operational Mission
Failure (MTBOMF)
(Replaces MFHBF)
Direct Maintenance
Manhours per Flight
Hour (DMMH/FH)
(Replaces MH/FH)
<= 1.4
>=425
>=400
>=450
>50000
<=25
>=400
>=450
>50000
<=25
>=390
>=430
>=50000
<=30
444
489
52,300
19
419
463
51,948
19
<=10
>9000
>= +7.5
>=650
<=10
>9000
>= +7.5
>=650
<=15
>=9000
>= +7.5
>600
8
9494
+7.5
648
8
9327
+7.5
631
<=60
>=3000
<=60
>=3000
<70
>=3000
65
4090
69
4090
>=3.2
>=3.2
>=2.6
10.0
9.3
<=5.0
<=5.0
<=9.0
6.4
5.9
May 21, 2013
16:04:14
UNCLASSIFIED
10
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0011.png
F/A-18E/F
December 31, 2012 SAR
Speed (Mach) Fighter
Escort Mission
Configuration @10,000
ft with Intermediate
Rated Thrust
Empty Weight (lbs)
Built-In Test (All Avionics)
Fault Detection (%)
Fault Isolation (%)
False Alarm Rate (%)
Approach Speed (kts)
.98
.98
.96
.96
.96
29950
75
90
30
<=140
29950
75
90
30
<=140
31950
65
85
45
<=150
30801
94.5
90.5
33.5
142
30968
98.9
97.6
39.6
142
Requirements Source:
Operational Requirements Document (ORD) dated March 22, 2000
Acronyms And Abbreviations
fps - feet per second
Ft - Feet
G - Gravitational Acceleration
IER - Information Exchange Requirement
kft - Thousand Feet
kts - knots
lbs - pounds
M - Mach Number
MAX TOGW - Maximum Take Off Gross Weight
MFHBF - Mean Flight Hours Between Failure
MH/FH - Maintenance Hours per Flight Hour
Nm - Nautical Mile/s
Nz - Normal Load Factor, Normal Acceleration
sec - second
WOD - Wind Over Deck
Change Explanations
None
Memo
Interdiction Mission Radius, Recovery Payload, Specific Excess Power, Additional Internal Fuel Capacity, Launch
Wind Over Deck and Acceleration Time are estimates based on the F/A-18E aircraft.
Interdiction Mission Radius Nautical Miles payload with:
a. 2 external tanks + 2 Airborne Intercept Missile (AIM) -9 + 4 MK 83 Low Drag (LD) on Low Drag Pylons + Forward
Looking Infrared Radar/Navigation Forward Looking Infrared Radar (FLIR/NAVFLIR).
b. 3 external tanks + 2 AIM-9 + 4 MK 83 LD on Low Drag Pylons + Forward Looking Infrared Radar/Navigation
Forward Looking Infrared Radar (FLIR/NAVFLIR).
MK is part of a serial number; it is not an acronym or an abbreviation.
May 21, 2013
16:04:14
UNCLASSIFIED
11
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0012.png
F/A-18E/F
December 31, 2012 SAR
Current estimated performance is based on Lot 35 Full Rate Production (FRP) 12 configuration as of January
2013.
Recovery Payload: F/A-18F: 44,000 Carrier Landing Design Gross Weight (CLDGW). The F/A-18E/F at Initial
Operating Capability (IOC) provided for a threshold/objective of 9,000 pounds of recovery payload.
Specific Excess Power: F/A-18E: (2) AIM-9 + (2) AIM-120 + Gun and Ammo with 60% internal fuel; and the
equivalent design gross weight for the F/A-18F.
May 21, 2013
16:04:14
UNCLASSIFIED
12
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0013.png
F/A-18E/F
December 31, 2012 SAR
Track To Budget
RDT&E
APPN 1319
BA 07
Project E2130
PE 0204136N
(E2130) F/A-18
Squadrons/Follow-on Variant
(Navy)
(Sunk)
Procurement
APPN 1506
BA 01
ICN 0145
PE 0204136N
APN 1 F/A-18E/F (Fighter)
Hornet (MYP)
PE 0204136N
APN 6 Spares
(Navy)
(Shared)
(Navy)
APPN 1506
BA 06
ICN 0605
May 21, 2013
16:04:14
UNCLASSIFIED
13
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0014.png
F/A-18E/F
December 31, 2012 SAR
Cost and Funding
Cost Summary
Total Acquisition Cost and Quantity
BY2000 $M
BY2000 $M
TY $M
Current APB
Current APB
SAR Baseline
Current
SAR Baseline
Current
Appropriation
Production
Production
Prod Est
Estimate
Prod Est
Estimate
Objective/Threshold
Objective
RDT&E
Procurement
Flyaway
Recurring
Non Recurring
Support
Other Support
Initial Spares
MILCON
Acq O&M
Total
5889.4
32995.3
27850.7
27001.3
849.4
5144.6
4304.8
839.8
0.0
0.0
38884.7
5895.2
41460.3
--
--
--
--
--
--
0.0
0.0
47355.5
6484.7
45606.3
--
--
--
--
--
--
--
--
N/A
5895.2
39880.5
32673.3
31211.1
1462.2
7207.2
6091.1
1116.1
0.0
0.0
45775.7
5574.0
36063.3
30453.8
29575.6
878.2
5609.5
4709.4
900.1
0.0
0.0
41637.3
5557.6
5557.6
46347.3 44501.0
-- 36368.0
-- 34773.6
--
--
--
--
0.0
0.0
1594.4
8133.0
6920.3
1212.7
0.0
0.0
51904.9 50058.6
Confidence Level for Current APB Cost 50% - The Program of Record&nbsp;(PoR) decreased from 565 to 552
due to a reduction in procurement quantities in President's Budget (PB) Congress added an additional 11 F/A-
18E aircraft to the program profile. These additional aircraft will be incorporated into the PoR with the next
budget submission.
Quantity
RDT&E
Procurement
Total
SAR Baseline
Prod Est
0
458
458
Current APB
Production
0
565
565
Current Estimate
0
552
552
The Program of Record (PoR) decreased from 565 to 552 due to a reduction in procurement quantities in
President's Budget (PB) 2014.
Congress added an additional 11 F/A-18E aircraft to the program profile. These additional aircraft will be
incorporated into the PoR with the next budget submission.
May 21, 2013
16:04:14
UNCLASSIFIED
14
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0015.png
F/A-18E/F
December 31, 2012 SAR
Cost and Funding
Funding Summary
Appropriation and Quantity Summary
FY2014 President's Budget / December 2012 SAR (TY$ M)
Appropriation
RDT&E
Procurement
MILCON
Acq O&M
PB 2014 Total
PB 2013 Total
Delta
Prior
5557.6
42173.0
0.0
0.0
47730.6
47761.0
-30.4
FY2013 FY2014 FY2015 FY2016 FY2017 FY2018
0.0
2083.7
0.0
0.0
2083.7
2083.7
0.0
0.0
244.3
0.0
0.0
244.3
1154.0
-909.7
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
To
Complete
0.0
0.0
0.0
Total
5557.6
0.0
0.0
0.0 44501.0
0.0 50058.6
0.0 50998.7
0.0
-940.1
Program funding and production quantities listed in this SAR are consistent with the FY 2014 President's
Budget (PB). The FY 2014 PB did not reflect the enacted DoD appropriation for FY 2013, nor sequestration; it
reflected the President's requested amounts for FY 2013.
Quantity
Development
Production
PB 2014 Total
PB 2013 Total
Delta
Undistributed Prior FY2013 FY2014 FY2015 FY2016 FY2017 FY2018
0
0
0
0
0
0
526
526
526
0
0
26
26
26
0
0
0
0
13
-13
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
To
Total
Complete
0
0
0
0
0 552
0
0 552
0
0 565
0
0
-13
May 21, 2013
16:04:14
UNCLASSIFIED
15
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0016.png
F/A-18E/F
December 31, 2012 SAR
Cost and Funding
Annual Funding By Appropriation
Annual Funding TY$
1319 | RDT&E | Research, Development, Test, and Evaluation, Navy
Non End
End Item
Non
Item
Total
Fiscal
Recurring
Recurring
Quantity
Recurring
Flyaway
Year
Flyaway
Flyaway
Flyaway
TY $M
TY $M
TY $M
TY $M
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
Subtotal
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
Total
Support
TY $M
--
--
--
--
--
--
--
--
--
--
--
--
Total
Program
TY $M
349.5
842.1
1396.2
1246.0
801.1
345.4
234.6
195.6
132.1
13.9
1.1
5557.6
May 21, 2013
16:04:14
UNCLASSIFIED
16
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0017.png
F/A-18E/F
December 31, 2012 SAR
Annual Funding BY$
1319 | RDT&E | Research, Development, Test, and Evaluation, Navy
Non End
End Item
Non
Item
Total
Total
Total
Fiscal
Recurring
Recurring
Quantity
Recurring
Flyaway
Support
Program
Year
Flyaway
Flyaway
Flyaway
BY 2000 $M BY 2000 $M BY 2000 $M
BY 2000 $M
BY 2000 $M
BY 2000 $M
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
Subtotal
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
391.7
922.4
1501.2
1314.4
831.0
354.0
238.5
196.5
130.8
13.6
1.1
5895.2
May 21, 2013
16:04:14
UNCLASSIFIED
17
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0018.png
F/A-18E/F
December 31, 2012 SAR
Annual Funding TY$
1506 | Procurement | Aircraft Procurement, Navy
Non End
End Item
Non
Item
Fiscal
Recurring
Recurring
Quantity
Recurring
Year
Flyaway
Flyaway
Flyaway
TY $M
TY $M
TY $M
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
Subtotal
--
12
20
30
36
39
48
45
42
42
38
37
37
23
18
31
28
26
--
552
233.5
1471.5
1678.7
2237.9
2230.9
2377.2
2651.8
2684.5
2529.2
2560.9
2209.2
2175.7
2190.6
1396.5
1043.9
1703.4
1859.3
1538.9
--
34773.6
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
200.0
163.4
195.5
85.9
63.4
72.7
71.0
168.0
75.8
44.6
39.8
56.7
88.6
36.2
70.5
67.3
95.0
--
1594.4
Total
Flyaway
TY $M
233.5
1671.5
1842.1
2433.4
2316.8
2440.6
2724.5
2755.5
2697.2
2636.7
2253.8
2215.5
2247.3
1485.1
1080.1
1773.9
1926.6
1633.9
--
36368.0
Total
Support
TY $M
--
436.8
331.0
451.3
580.3
524.0
531.2
482.1
503.6
401.1
514.2
474.8
537.5
404.0
399.6
467.0
400.4
449.8
244.3
8133.0
Total
Program
TY $M
233.5
2108.3
2173.1
2884.7
2897.1
2964.6
3255.7
3237.6
3200.8
3037.8
2768.0
2690.3
2784.8
1889.1
1479.7
2240.9
2327.0
2083.7
244.3
44501.0
May 21, 2013
16:04:14
UNCLASSIFIED
18
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0019.png
F/A-18E/F
December 31, 2012 SAR
Annual Funding BY$
1506 | Procurement | Aircraft Procurement, Navy
Non End
End Item
Non
Item
Total
Total
Total
Fiscal
Recurring
Recurring
Quantity
Recurring
Flyaway
Support
Program
Year
Flyaway
Flyaway
Flyaway
BY 2000 $M BY 2000 $M BY 2000 $M
BY 2000 $M
BY 2000 $M
BY 2000 $M
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
Subtotal
--
12
20
30
36
39
48
45
42
42
38
37
37
23
18
31
28
26
--
552
239.3
1495.2
1686.1
2219.3
2183.4
2299.1
2532.7
2513.7
2307.4
2272.3
1907.4
1835.6
1820.7
1144.3
836.3
1332.7
1426.9
1158.7
--
31211.1
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
203.2
164.1
193.9
84.1
61.3
69.4
66.5
153.3
67.3
38.5
33.6
47.1
72.6
29.0
55.2
51.6
71.5
--
1462.2
239.3
1698.4
1850.2
2413.2
2267.5
2360.4
2602.1
2580.2
2460.7
2339.6
1945.9
1869.2
1867.8
1216.9
865.3
1387.9
1478.5
1230.2
--
32673.3
--
443.8
332.5
447.5
567.9
506.8
507.4
451.4
459.4
355.9
443.9
400.6
446.8
331.1
320.2
365.4
307.4
338.7
180.5
7207.2
239.3
2142.2
2182.7
2860.7
2835.4
2867.2
3109.5
3031.6
2920.1
2695.5
2389.8
2269.8
2314.6
1548.0
1185.5
1753.3
1785.9
1568.9
180.5
39880.5
May 21, 2013
16:04:14
UNCLASSIFIED
19
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0020.png
F/A-18E/F
December 31, 2012 SAR
Cost Quantity Information
1506 | Procurement | Aircraft Procurement, Navy
End Item
Recurring
Flyaway
Fiscal
(Aligned
Quantity
Year
with
Quantity)
BY 2000
$M
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
Subtotal
--
12
20
30
36
39
48
45
42
42
38
37
37
23
18
31
28
26
--
552
--
1493.4
1839.1
2200.2
2132.9
2359.9
2545.6
2516.7
2311.8
2274.7
1908.2
1864.4
1826.4
1141.1
837.4
1372.3
1379.6
1207.4
--
31211.1
May 21, 2013
16:04:14
UNCLASSIFIED
20
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0021.png
F/A-18E/F
December 31, 2012 SAR
Low Rate Initial Production
Initial LRIP Decision
3/26/1997
62
Milestone II ADM
1997
1999
Current Total LRIP
3/26/1997
62
Milestone II ADM
1997
1999
Approval Date
Approved Quantity
Reference
Start Year
End Year
The Current Total LRIP Quantity is more than 10% of the total production quantity due to the Quadrennial Defense
Review (QDR). As a result of the QDR, the total procurement quantity for the program was reduced to a range of 548
to 785 aircraft, but there was not a change to the LRIP quantity. The LRIP quantity was approved during the LRIP
Defense Acquisition Board (DAB) in March 1997.
May 21, 2013
16:04:14
UNCLASSIFIED
21
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0022.png
F/A-18E/F
December 31, 2012 SAR
Foreign Military Sales
Country
Australia
Australia
Date of
Quantity
Sale
4/14/2011
5/2/2007
24
Total
Cost $M
Memo
357.9 This case was implemented for the sustainment
of 24 F/A-18F aircraft.
2474.0 The Program Office has a Foreign Military Sales
case with Australia for 24 F/A-18F aircraft. This
case was implemented for acquisition and initial
support.
Nuclear Cost
None
May 21, 2013
16:04:14
UNCLASSIFIED
22
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0023.png
F/A-18E/F
December 31, 2012 SAR
Unit Cost
Unit Cost Report
BY2000 $M
Current UCR
Baseline
(FEB 2011 APB)
47355.5
565
83.815
41460.3
565
73.381
BY2000 $M
Original UCR
Baseline
(JUN 1992 APB)
65944.7
1000
65.945
59976.8
1000
59.977
BY2000 $M
Current Estimate
(DEC 2012 SAR)
45775.7
552
82.927
39880.5
552
72.247
BY2000 $M
Current Estimate
(DEC 2012 SAR)
45775.7
552
82.927
39880.5
552
72.247
BY
% Change
BY
% Change
Unit Cost
Program Acquisition Unit Cost (PAUC)
Cost
Quantity
Unit Cost
Average Procurement Unit Cost (APUC)
Cost
Quantity
Unit Cost
-1.06
-1.55
Unit Cost
Program Acquisition Unit Cost (PAUC)
Cost
Quantity
Unit Cost
Average Procurement Unit Cost (APUC)
Cost
Quantity
Unit Cost
+25.75
+20.46
May 21, 2013
16:04:14
UNCLASSIFIED
23
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0024.png
F/A-18E/F
December 31, 2012 SAR
Unit Cost History
Original APB
APB as of January 2006
Revised Original APB
Prior APB
Current APB
Prior Annual SAR
Current Estimate
Date
JUN 1992
JUL 2003
N/A
JUL 2003
FEB 2011
DEC 2011
DEC 2012
BY2000 $M
PAUC
APUC
65.942
59.970
86.175
75.505
N/A
N/A
86.175
75.505
83.815
73.381
82.395
71.961
82.927
72.247
TY $M
PAUC
94.583
91.968
N/A
91.968
91.867
90.263
90.686
APUC
88.750
81.871
N/A
81.871
82.031
80.427
80.618
SAR Unit Cost History
Initial SAR Baseline to Current SAR Baseline (TY $M)
Initial PAUC
Dev Est
94.583
Changes
Eng
Est
-2.510 0.670
PAUC
Prod Est
90.911
Econ
-16.460
Qty
25.278
Sch
1.930
Oth
0.000
Spt
-12.580
Total
-3.672
Current SAR Baseline to Current Estimate (TY $M)
PAUC
Prod Est
90.911
Changes
Eng
Est
0.468 -2.520
PAUC
Current Est
90.686
Econ
0.460
Qty
-4.853
Sch
2.010
Oth
0.000
Spt
4.210
Total
-0.225
May 21, 2013
16:04:14
UNCLASSIFIED
24
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0025.png
F/A-18E/F
December 31, 2012 SAR
Initial SAR Baseline to Current SAR Baseline (TY $M)
Initial APUC
Dev Est
88.750
Changes
Qty
Sch
Eng
Est
Oth
Spt
18.461 2.200 -2.510 0.510 0.000 -12.580
APUC
Prod Est
78.741
Econ
-16.090
Total
-10.009
Current SAR Baseline to Current Estimate (TY $M)
APUC
Prod Est
78.741
Changes
Eng
Est
0.468 -2.533
APUC
Current Est
80.618
Econ
0.503
Qty
-2.781
Sch
2.010
Oth
0.000
Spt
Total
4.210 1.877
SAR Baseline History
SAR
Planning
Estimate (PE)
N/A
DEC 1991
DEC 1998
N/A
3974.4
N/A
N/A
SAR
Development
Estimate (DE)
N/A
MAR 1992
JAN 2000
SEP 2000
94583.0
1000
94.583
SAR
Production
Estimate (PdE)
N/A
MAR 1992
JAN 2000
JUN 2001
41637.3
458
90.911
Current
Estimate
N/A
MAY 1992
JUN 2000
SEP 2001
50058.6
552
90.686
Item/Event
Milestone I
Milestone II
Milestone III
IOC
Total Cost (TY $M)
Total Quantity
Prog. Acq. Unit Cost (PAUC)
May 21, 2013
16:04:14
UNCLASSIFIED
25
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0026.png
F/A-18E/F
December 31, 2012 SAR
Cost Variance
Summary Then Year $M
RDT&E
Proc
5574.0
36063.3
-23.7
--
--
--
+7.3
--
--
-16.4
--
--
--
--
--
--
--
--
-16.4
5557.6
5557.6
+170.6
+6942.6
+1109.4
+258.3
-1299.4
--
+2196.3
+9377.8
+107.0
-1076.1
--
--
-98.8
--
+127.8
-940.1
+8437.7
44501.0
44501.0
MILCON
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
SAR Baseline (Prod Est)
Previous Changes
Economic
Quantity
Schedule
Engineering
Estimating
Other
Support
Subtotal
Current Changes
Economic
Quantity
Schedule
Engineering
Estimating
Other
Support
Subtotal
Total Changes
CE - Cost Variance
CE - Cost & Funding
Total
41637.3
+146.9
+6942.6
+1109.4
+258.3
-1292.1
--
+2196.3
+9361.4
+107.0
-1076.1
--
--
-98.8
--
+127.8
-940.1
+8421.3
50058.6
50058.6
May 21, 2013
16:04:14
UNCLASSIFIED
26
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0027.png
F/A-18E/F
December 31, 2012 SAR
SAR Baseline (Prod Est)
Previous Changes
Economic
Quantity
Schedule
Engineering
Estimating
Other
Support
Subtotal
Current Changes
Economic
Quantity
Schedule
Engineering
Estimating
Other
Support
Subtotal
Total Changes
CE - Cost Variance
CE - Cost & Funding
Summary Base Year 2000 $M
RDT&E
Proc
5889.4
32995.3
--
--
--
--
+5.8
--
--
+5.8
--
--
--
--
--
--
--
--
+5.8
5895.2
5895.2
--
+5421.9
+998.1
+227.2
-953.7
--
+1968.9
+7662.4
--
-795.1
--
--
-75.8
--
+93.7
-777.2
+6885.2
39880.5
39880.5
MILCON
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
Total
38884.7
--
+5421.9
+998.1
+227.2
-947.9
--
+1968.9
+7668.2
--
-795.1
--
--
-75.8
--
+93.7
-777.2
+6891.0
45775.7
45775.7
Previous Estimate: December 2011
May 21, 2013
16:04:14
UNCLASSIFIED
27
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0028.png
F/A-18E/F
December 31, 2012 SAR
Procurement
Current Change Explanations
Revised escalation indices. (Economic)
Quantity variance resulting from a decrease of 13 FA-18E/F from 565 to 552. (Quantity)
(QR)
Additional quantity variance due to loss of 13 F/A-18E/F. (Quantity) (QR)
Adjustment for current and prior escalation. (Estimating)
Revised estimate to reflect actuals. (Estimating)
Revised estimate to reflect budget controls. (Estimating)
Adjustment for current and prior escalation. (Support)
Increase in Other Support costs due to additional Sustaining Engineering costs.
(Support)
Decrease in Initial Spares. (Support) (QR)
Procurement Subtotal
(QR) Quantity Related
$M
Base
Year
N/A
-609.4
-185.7
-54.5
-22.1
+0.8
-13.7
+110.7
-3.3
-777.2
Then
Year
+107.0
-824.7
-251.4
-70.9
-29.4
+1.5
-17.8
+148.8
-3.2
-940.1
May 21, 2013
16:04:14
UNCLASSIFIED
28
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0029.png
F/A-18E/F
December 31, 2012 SAR
Contracts
Appropriation: Procurement
Contract Name
Contractor
Contractor Location
Contract Number, Type
Award Date
Definitization Date
Initial Contract Price ($M)
Target
Ceiling
Qty
2770.5
2945.6
66
Airframe Multi-Year Procurement III (MYP III)
The Boeing Company
6200 JS McDonnell Blvd
St. Louis, MO 63134
N00019-09-C-0019, FPIF
December 04, 2008
September 28, 2010
Current Contract Price ($M)
Target
Ceiling
Qty
4506.6
4621.2
103
Estimated Price At Completion ($M)
Contractor
Program Manager
4506.6
4506.6
Cost And Schedule Variance Explanations
Cost and Schedule variance reporting is not required on this FPIF contract.
General Contract Variance Explanation
In accordance with Defense Federal Acquisition Regulation Supplement Subpart 234.2, Earned Value Management
System, a waiver was obtained and approved on June 10, 2010, by the Deputy Assistant Secretary of the Navy
(Acquisition and Logistics Management), to omit Earned Value Management requirements.
Contract Comments
The difference between the Initial Contract Price Target and the Current Contract Price Target is due to multiple
funded modifications and the incorporation of Engineering Change Proposals (ECPs).
The MYP III contract value and quantities represent only the F/A-18E/F portion of the contract and do not include the
EA-18G portion.
May 21, 2013
16:04:14
UNCLASSIFIED
29
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0030.png
F/A-18E/F
December 31, 2012 SAR
Appropriation: Procurement
Contract Name
Contractor
Contractor Location
Contract Number, Type
Award Date
Definitization Date
Initial Contract Price ($M)
Target
Ceiling
Qty
255.9
N/A 224
F414 Engine Production Lots 11-15
GE Aircraft Engines
1000 Western Ave.
Lynn, MA 01905-2655
N00019-06-C-0088, FPEPA
April 26, 2006
September 26, 2007
Current Contract Price ($M)
Target
Ceiling
Qty
1308.5
N/A
305
Estimated Price At Completion ($M)
Contractor
Program Manager
1308.5
1308.5
Cost And Schedule Variance Explanations
Cost and Schedule variance reporting is not required on this FPEPA contract.
General Contract Variance Explanation
There is no contract performance reporting required on this Fixed Price Economic Price Adjustment (FPEPA)
contract.
Contract Comments
The difference between the Initial Contract Price Target and the Current Contract Price Target is due to exercising
contract options, incorporation of Engine Program Descriptions (EPDs) in support of the F414 Component
Improvement Program (CIP), and procurement of long lead material in support of FY 2010 and FY 2011 engines.
This contract is more than 90% complete; therefore, this is the final report for this contract.
The original quantity of 224 represents the total potential F/A-18E/F engine quantity. This quantity is based upon the
base contract (68) and all option year (156) engines to be procured. This report solely reflects the domestic Program
of Record (PoR) quantities.
May 21, 2013
16:04:14
UNCLASSIFIED
30
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0031.png
F/A-18E/F
December 31, 2012 SAR
Appropriation: Procurement
Contract Name
Contractor
Contractor Location
Contract Number, Type
Award Date
Definitization Date
Initial Contract Price ($M)
Target
Ceiling
Qty
6.6
N/A
0
F414 Engine Production Lots 16-17
GE Aircraft Engines
1000 Western Ave.
Lynn, MA 01905-2655
N00019-11-C-0045, FFP
April 20, 2011
September 26, 2012
Current Contract Price ($M)
Target
Ceiling
Qty
440.0
N/A
110
Estimated Price At Completion ($M)
Contractor
Program Manager
440.0
440.0
Cost And Schedule Variance Explanations
Cost and Schedule variance reporting is not required on this FFP contract.
Contract Comments
This is the first time this contract is being reported.
The difference between the Initial Contract Price Target and the Current Contract Price Target is due to the FY 2012
procurement of 56 engines and devices, two spare engines, one spare module as well as the FY 2013 procurement
of long lead material, 52 engines and devices. This report solely reflects the domestic Program of Record (PoR)
quantities.
The original contract value only reflects the procurement of FY 2013 F414 logistics and engineering support.
May 21, 2013
16:04:14
UNCLASSIFIED
31
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0032.png
F/A-18E/F
December 31, 2012 SAR
Appropriation: Procurement
Contract Name
Contractor
Contractor Location
Contract Number, Type
Award Date
Definitization Date
Initial Contract Price ($M)
Target
Ceiling
Qty
905.3
N/A
80
System Configuration Sets (SCS) Contract
The Boeing Company
6200 JS McDonnell Blvd
St. Louis, MO 63166
N68936-09-D-0002, IDIQ/CPIF/CPFF
December 19, 2008
December 19, 2008
Current Contract Price ($M)
Target
Ceiling
Qty
899.9
N/A
67
Estimated Price At Completion ($M)
Contractor
Program Manager
899.9
899.9
Cost And Schedule Variance Explanations
Cost and Schedule variance reporting is not required on this IDIQ/CPIF/CPFF contract.
General Contract Variance Explanation
In accordance with a contract addendum to Federal Acquisition Regulation Clause 52.234-4, Earned Value
Management (EVM) will be implemented on individual orders. As stated in the contract, EVM is not applicable at the
basic contract level.
Contract Comments
The difference between the Initial Contract Price Target and the Current Contract Price Target is due to a contract
modification realigning certain efforts from a Cost Plus Incentive Fee Contract Line Item Number (CLIN) to a Cost
Plus Fixed Fee Level of Effort CLIN.
The initial contract price target for the basic contract reflects the total negotiated value at contract award. The current
contract price target for the basic contract reflects the revised contract value.
The value, quantities, and funding for each delivery or task order, issued under this Indefinite-Delivery, Indefinite-
Quantity contract, are individually negotiated.
This contract includes shared costs and quantities for the F/A-18E/F and EA-18G platforms; therefore, all data is
duplicated in the EA-18G SAR.
May 21, 2013
16:04:14
UNCLASSIFIED
32
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0033.png
F/A-18E/F
December 31, 2012 SAR
Deliveries and Expenditures
Deliveries To Date
Development
Production
Total Program Quantities Delivered
Plan To Date
0
506
506
Actual To Date
0
506
506
Total Quantity
0
552
552
Percent
Delivered
--
91.67%
91.67%
Total Acquisition Cost
Expenditures To Date
Percent Expended
Total Funding Years
Expenditures and Appropriations (TY $M)
50058.6
Years Appropriated
42116.9
Percent Years Appropriated
84.14%
Appropriated to Date
23
Percent Appropriated
22
95.65%
49814.3
99.51%
The above data is current as of 3/26/2013.
May 21, 2013
16:04:14
UNCLASSIFIED
33
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0034.png
F/A-18E/F
December 31, 2012 SAR
Operating and Support Cost
F/A-18E/F
Assumptions and Ground Rules
Cost Estimate Reference:
Current Program: F/A-18 E/F
Flight Hours per aircraft per month: 28.2
Number of 12 Primary Authorized Aircraft (PAA) F/A-18E/F Squadrons in FY 2016: 19
Number of 10 PAA F/A-18E/F Squadrons in FY 2016: 11
Fleet Readiness Squadron (FRS) at 12-14 E & 29-31 F: 2
Consumption rate, gallons per hour: 1,291
Petroleum, Oil, and Lubricant (POL) Cost, JP-5 per Gallon FY 2000 $: 0.73
Number of Aircraft Operating Years: 9,128
Operational Service Life (OSL): 6,000 Flight Hours
Date of Estimate: February 2013
Source: Air-4.2 Operating & Support (O&S) Cost Estimate
Sustainment Strategy:
The F/A-18E/F support strategy is based on the following basing and utilization plans. The current Program of
Record (PoR) consists of 19 - 12 PAA F/A-18E/F squadrons and 11 - 10 PAA Carrier Air Wing (CVW) deployable
squadrons stationed at either Naval Air Station (NAS) Lemoore, CA, or NAS Oceana, VA. Two Fleet Replacement
Squadrons (FRS) - NAS Lemoore and NAS Oceana - are comprised of 85 aircraft. Twenty-two additional aircraft
are either currently stationed, or will be stationed at various test and training units throughout the Continental United
States (CONUS). Additionally, four fleet squadrons are forward deployed to Atsugi, Japan. The majority of the
airframe and engine components are supported via three-level maintenance plans. Avionics components, on the
other hand, are predominantly supported by two-level maintenance plans.
The total F/A-18E/F aircraft procurement quantity is 552, which have a service life of 20 years. Two of the aircraft
were used as EA-18G System Development and Demonstration (SDD) assets. Eight of the aircraft have been lost
through attrition as Category 1 strikes.
Antecedent Information:
Antecedent Program: F/A-18C/D
Consumption Rate, Gallons per Hour: 1,127
Number of Aircraft Operating Years: 9,128 (See Total O&S Cost Comments below)
Flight Hours per Aircraft per Month: 23.5
POL Cost, JP-5 per gallon FY 2000 $: 0.73
The variable components of the cost estimate, such as the Flying Hour Program (FHP), are based on the number of
aircraft operational years available and flight hours. Some elements, such as personnel and associated indirect
and training costs, are dependent on the number of squadrons and manning requirements. Other elements which
are fixed in nature, such as sustaining engineering, are based on a cost-per-aircraft. Modification, airframe,
support equipment and depot maintenance are estimated as the total requirement and applied on a cost-per-
aircraft basis.
O&S Cost Variance
Explanation
Variance Category
Causal Factor
Impact
May 21, 2013
16:04:14
UNCLASSIFIED
34
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0035.png
F/A-18E/F
December 31, 2012 SAR
Cost Estimating Methodologies
Cost Data Updates
Rates
Technical Inputs
Programmatics
N/A
Aviation Type/Model/Series Report
(ATMSR) weapons training
expendable stores and temporary
additional duty rates rose significantly.
The 2013 composite rates were lower
than the 2012 rates, primarily due to a
$1,880 reduction in the Medicare
Eligible Retiree Health Care
(MERHC) accrual rate.
The Aviation Depot Level Repairable
(AVDLR) pricing for components
previously managed Eligible Retiree
Health Care (MERHC) accrual rate
under F/A-18E/F Integrated
Readiness Support Teaming (FIRST)
rose significantly in 2013. This was
offset by a $663M reduction in
modifications during the FYDP.
The President's Budget (PB) 2014
removed 13 pipeline and attrition
aircraft, resulting in a loss of 40
aircraft operating years.
N/A
1.30%
-0.10%
-0.60%
-0.10%
Estimated Technical & Programmatic Updates
Aircraft inventory updated to remove 13 aircraft
– 11 during the Office of the Secretary of Defense (OSD) 2014 Bill Payer
– Two during President's Budget (PB) 2014 as an End Game Offset
Program of Record (PoR) life cycle end year changed to 2035
Number of aircraft operating years decreased
Unitized O&S Costs BY2000 $K
F/A-18E/F
Average Annual Cost per
Aircraft
1.122
0.497
1.760
0.084
0.518
0.227
0.000
4.208
Cost Element
Unit-Level Manpower
Unit Operations
Maintenance
Sustaining Support
Continuing System Improvements
Indirect Support
Other
Total
F/A-18C/D (Antecedent)
Average Annual Cost per
Aircraft
0.983
0.289
2.097
0.078
0.524
0.204
0.000
4.175
Unitized Cost Comments:
The Average Annual Cost Per Unit for the F/A-18E/F is calculated by dividing the total O&S cost by the total
operational aircraft years for the program.
May 21, 2013
16:04:14
UNCLASSIFIED
35
FOU, Alm.del - 2015-16 - Endeligt svar på spørgsmål 165: Spm. om en redegørelse for konklusionerne og beregningerne i de amerikanske SAR rapporter, der evaluerer omkostningerne på at flyve henholdsvis Boeings Super Hornet (2012) og Lockheed Martins F-35 (2014), til forsvarsministeren
1631841_0036.png
F/A-18E/F
December 31, 2012 SAR
Total O&S Cost $M
Current Production APB
Objective/Threshold
F/A-18E/F
36961.7
65103.8
Current Estimate
F/A-18E/F
F/A-18C/D (Antecedent)
38410.0
38112.0
67505.0
N/A
Base Year
Then Year
40657.9
N/A
Total O&S Costs Comments:
For comparison purposes, the base year antecedent total O&S costs are the product of the antecedent’s average
annual cost per aircraft and the operational aircraft years of the new F/A-18E/F aircraft.
Disposal Costs
While disposal costs are not part of the Cost Assessment and Program Evaluation (CAPE) 2007 O&S Cost
Element Structure (CES) and are not included in the totals above, the Life Cycle Cost (LCC) impact of disposal
costs has been estimated at $58.9M in Base Year (BY) 2000 dollars and $99.5M in Then Year (TY) dollars.
May 21, 2013
16:04:14
UNCLASSIFIED
36