Grønlandsudvalget 2015-16
GRU Alm.del Bilag 32
Offentligt
1593352_0001.png
North Atlantic Energy Network
January 2016
Orkustofnun (OS) - National Energy Authority of Iceland
Norges Arktiske Universitet (UiT) - The Arctic University of Norway
Energy Styrelsen - Danish Energy Agency
Jarðfeingi - Faroese Earth and Energy Directorate
Shetland Islands Council - Economic Development Service
Greenland Innovation Centre
1
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
2
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
EXECUTIVE SUMMARY
The aim of the North Atlantic Energy Network project was to investigate how isolated energy systems
in the North Atlantic can be connected to Norway and Greenland to form an electrical grid in the North
Atlantic. Representatives of Greenland, Iceland, Faroe Islands, Shetland and Norway met in
Copenhagen in the end of February 2015 to formulate how to tackle this question. Each country
documented its status regarding energy production and potentials in the fields of renewable energy
and the technological aspects were investigated.
Greenland has a big hydropower and solar energy potential, which is not known in detail. Further work
is needed to map the potentials. Due to lack of infrastructure and experience a cable connection
between Greenland and the neighbouring countries is not realistic in the nearest future.
It is technically possible to connect all of the neighbouring countries around Iceland with subsea cables.
Iceland now produces about 18 TWh of electricity per year and could have the potential to double the
production from geothermal and hydropower alone. There are many unclear aspects that need to be
investigated further to draw a full picture of the pros and cons of interconnectors from Iceland. The
legal and regulatory framework must be in place before a project of this kind can be realized and
extensive grid reinforcements are needed to support export through a cable at a single connection
point in Iceland.
A 100 MW cable between Iceland and Faroe Islands is possible but might not be economically
competitive. Faroe Islands and Shetland have offshore wind conditions on land and large windfarms in
Faroe Islands need powerful interconnectors. A large cable from Iceland to Scotland could be laid via
the Faroes and Shetland and could possibly transmit energy from Iceland, Shetland and Faroe Islands
to Scotland and Europe. A probable synergy effect could be to transmit hydropower from Iceland in
summer and windpower from Faroes and Shetland in winter.
The submission of Scottish Hydro Electric Transmission’s (SHE-T) needs case for developing a 600 MW
transmission cable between Shetland and the UK national grid, is expected to be submitted to the UK
electricity regulator Ofgem in 2016. The Shetland to UK interconnector project has been in process for
over a decade and is the main focus for harnessing Shetland’s exceptional wind resource. The North
Atlantic Energy Network has highlighted the potential for Iceland and Faroe Islands to export
renewable energy to electricity markets in the UK, Norway and connect to the wider European grid.
Cable routes from Iceland to the UK are currently being investigated and Faroe Islands also have an
interest in securing a supply of renewable energy from Iceland.
Although the NAEN project has the potential for localized introduction of electricity from renewable
resources for both Shetland and oil platforms along the cable route, the economic benefit seems
reduced with respect to Norwegian interest. This especially so with the new HVDC subsea
interconnector to Great Britain to be finished in 2021.
The North Atlantic Energy Network has explored the potential of connecting some of the best
renewable energy sources in the Arctic, Nordic and northern European regions to the large energy
markets of the UK and European continent. The project has allowed informative exchange of
knowledge between the participating regions and organisations.
Access and utilization of renewable energy is a key element in fighting global warming. The countries
behind the NAEN project could benefit from integrated future cooperation regarding exporting energy
and knowledge in this field in the widest sense. A platform to develop this cooperation and mapping
the possibilities for future development in this area could be beneficial for all of Europe.
3
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
4
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Table of Contents
Introduction............................................................................................................................................. 7
Conclusion ............................................................................................................................................... 7
Energy markets in Europe ....................................................................................................................... 8
The North Atlantic Energy network......................................................................................................... 9
Financing cables ................................................................................................................................ 10
Installation cost ................................................................................................................................. 10
Bipolar v.s. Monopol ..................................................................................................................... 10
Cable size ....................................................................................................................................... 10
Depths ........................................................................................................................................... 11
Prices ............................................................................................................................................. 11
Ships .............................................................................................................................................. 11
Timescale ....................................................................................................................................... 12
Alternating Current (AC) technology ............................................................................................. 12
Transformers, Converter stations ................................................................................................. 12
Surveys .......................................................................................................................................... 12
Operation cost ................................................................................................................................... 12
Lifetime.............................................................................................................................................. 13
Technologies.......................................................................................................................................... 13
Submarine cable faults ...................................................................................................................... 13
Total number of submarine faults reported 1990 to 2005 ........................................................... 13
Windfarms .......................................................................................................................................... 15
Land-based windfarms ...................................................................................................................... 15
Windturbines of different wind classes ............................................................................................ 16
Optimal grid integration .................................................................................................................... 17
Wind energy converters (WEC technology) ...................................................................................... 17
Annular generator ............................................................................................................................. 17
SCADA System ................................................................................................................................... 18
Closed-loop control of the wind farm at the point of connection .................................................... 18
Reactive power capability ................................................................................................................. 18
Power-frequency control .................................................................................................................. 18
Inertia Emulation ............................................................................................................................... 19
Fault Ride Through ............................................................................................................................ 19
Storm control .................................................................................................................................... 19
Offshore Wind Turbines .................................................................................................................... 20
Floating wind turbines in deep water environment ............................................................................. 20
5
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Substructures, station keeping and anchoring.................................................................................. 21
Rated power and rotor size ............................................................................................................... 22
Windfloat Portugal ............................................................................................................................ 23
Electricity usage on oil platforms ...................................................................................................... 25
Connecting oil platforms to the network .............................................................................................. 26
Benefits.............................................................................................................................................. 29
Cost .................................................................................................................................................... 29
CO
2
emission...................................................................................................................................... 29
Impact Assessment................................................................................................................................ 29
What can we learn from other projects ............................................................................................ 30
The IceLink Projcet ........................................................................................................................ 30
The Isles project ............................................................................................................................ 31
References ............................................................................................................................................. 32
Acronyms ............................................................................................................................................... 33
Appendix A
Appendix B
Appendix C
Appendix D
Appendix E
North Atlantic Energy Network Faroe Islands
North Atlantic Energy Network Greenland
North Atlantic Energy Network Iceland
North Atlantic Energy Network Norway
North Atlantic Energy Network Shetland
6
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Introduction
The North Atlantic Energy Network Project aims to investigate how small isolated energy systems can
be connected to an electrical network grid and onwards to the European market. The Project focuses
on Greenland, Iceland, the Faroe Islands, Shetland, Norway and offshore companies in the area.
The purpose of the Project is to examine whether it is possible to connect these communities via
undersea electric cables. Greenland, Iceland and Norway have a high potential for hydro power and all
of the countries have potential for other types of renewable energy. Faroe Islands and Shetland are
today heavily dependent on oil for their energy supplies. Greenland is today also dependent on oil,
despite its possibilities as this large islands is scarcely populated and lacking the necessary
infrastructure to harvest all of its abundant renewable energy potential.
An electric cable connection, in addition to reducing overall oil dependency, will open up the
opportunity for exploitation of the wind potential that is available in the Faroe Islands and Shetland
and other potential renewable energy sources, such as tidal energy.
Norway, Greenland and Iceland have a large, hydropower capacity, that can become a kind of battery
to regulate production from wind and the tides, which are very fluctuating energy sources. The
interconnection of the electricity supply systems between the Faroe Islands, Iceland and Shetland also
creates the opportunity to operate the oil platforms in the area with renewable energy, and the
creation of offshore wind farms in one of the world's best areas for wind power generation.
The principle focus of the Project is to identify the interests and opportunities that the different parties
see in such a network, and to examine the technical and economical aspects.
Conclusion
The European energy market is very complicated and the greatest risk involved in connecting to this
market are energy politics. The European Union creates and develop regulations regarding
interconnectors and each country also influences their energy market with country specific emphasis.
The installed generating capacity of wind power is showing rapid growth in Europe and when there is
a lot of wind, prices go down. More flexibility and storage is needed and hydro power reservoirs offer
flexibility and storage possibilities.
For the past five years energy prices have been going down and a lot of power plants can’t survive the
current prices that are close to 3 Eurocents pr. kWh. What the future may hold in terms of prices and
politics is hard to predict.
Norway has led the way in interconnectors and finished a new connection to Denmark in 2014.
Interconnector’s are seen as an important and integrated part of the power system in Norway and
Denmark. Two additional interconnectors are planned in the near future; one to Germany to be up
and running in 2019 and another to the United Kingdom to be finished in 2021.
A connector between Iceland and the Faroese Isands has been up for discussion for decades but has
not been seen as financially feasible for just that purpose. In correlation with the NAEN project a
cooperation between a cable project between Iceland and the UK (IceLink) and a Faroe Islands
connection was discussed. The IceLink connection would probably have to pass Faroe Island waters
and it was discussed as a possibility that the cable could be taken ashore in the islands. This might be
an advantage for both Faroe Islands and the cable owner as Faroe Islands could import and export
energy from both UK and Iceland and cable faults could be easier to locate.
7
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0008.png
During the process of this cooperation between all of the countries involved in the NAEN project
representative of Shetland reported that there will possibly be a new 600 MW cable connection
between Shetland and UK in the near future. The plan is to export windpower from Shetland to the UK
grid from the Viking Energy wind farm project. The Viking Energy wind farm has planning consent and
would be built if the Shetland to UK grid connection is approved. (http://www.vikingenergy.co.uk/the-
project).
The Viking Energy project originally got planning consent from the Scottish energy minister
Fergus Ewing in April 2012 and was reaffirmed in February 2015.
Most of the studies regarding estimates of hydro power potential in Greenland have focused on
Western Greenland. These studies indicate possibilities of 14 TWh/year. A theoretical maximum
potential taking into account all natural water from the locality where it is formed and via turbines
resulted in an estimation of 470 TWh/year potential. This theoretical estimation was conducted in
1994 and might reveal a higher potential if it were recalculated today as the ice in Greenland is melting
much faster today. This theoretical value would never be the end result but it depicts the abundant
resources that are available.
The necessary infrastructure to harvest Greenland’s abundant power sources has not yet been
developed. Greenland will not be using subsea interconnectors to other parts of the world in the near
future. This does not prevent them from exporting their power in some other form. Iceland has been
exporting power in the form of aluminum for half a century and Norway started its export the same
way before Iceland did. Possibly Greenland could build up infrastructure and knowledge the same way
as Iceland and Norway have done in the past by attractking industry that needs a lot of power.
Access and utilization of renewable energy is a key element in fighting global warming. The countries
behind the NAEN project could benefit from integrated future cooperation regarding exporting energy
and knowledge in this field in the widest sense. A platform to develop this cooperation and mapping
the possibilies for future development in this area could be beneficial for all of Europe.
Energy markets in Europe
To decide upon the financial feasibility of a network of this kind and its connection to Europe through
Norway is a very complicated task.
Energy markets in Europe are integrating and through this integration prices are expected to be
levelized in an ideal market. The European energy market has not reached this state as there are
bottlenecks in the system and therefore huge price differences. Prices to different areas of the market
like home and industry also differ between countries. The market is complicated and therefore it is
difficult to determine the prerequisites for detailed calculations.
Interconnection of power markets is supposed to lead to more economic distribution of energy than
without the interconnectors. Interconnectors can contribute to security of supply; less need for
investment in production and reserve power, better utilisation of electricity and less cost involved in
balancing the systems.
Interconnection cables for island systems are expensive and will have lasting effects both on
production of electricity and prices. Technologically it is possible to lay sea cables to create a North
Atlantic Energy Network (NAEN) but there are many risk factors that need to be considered. The
economic risks involved in the installation and operational cost of the interconnectors and market
prices for electricity.
8
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0009.png
The North Atlantic Energy network
Likely connection points for the countries involved in the NAEN project have not been decided for a
possible network. Each interconnector would need a thorough survey of the seabed as well as indepth
analysis of various aspects of each project before connection points can be decided.
Approximate length of each cable as depicted on the front page give an idea of the distances in
question. These are just shortest routes estimated through Google earth or large scale maps and the
depths are assumptions that should be reviewed as such.
Link
Eastern Iceland – Faroes
Faroes – Shetland
Faroese – Scotland
Faroese – Norway
Shetland – Norway
Iceland – Greenland
Iceland – Scotland
Iceland – UK
Shetland - Scotland
Approximate length [km]
450
350
400
650
300
470
900
1200
250
Approximate depth [m]
500
1100 - 1200
1100 - 1200
1500
350
800
1100 - 1200
1200
100
Bathymetry Nordic Seas - Borrowed from Landsvirkjun webside – ORIGINALLY FROM
MATHEMATICS, UNIVERSITY OF OSLO 1995.
Rated power of the interconnectors in question were not established, but indications are that for long
distances losses rule out the benefits of cables with low capacity.
9
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Financing cables
Initiating subsea projects involves deciding which type of contract the operating entity should follow.
In submarine cable projects three types of structure are common:
1. Private ownership
2. Consortium
3. Public Private Partnership
It is rather common that cable projects adopt more sophisticated structures mixing some of the above
mentioned structure types in order to optimize the projects.
Different cable projects, in the planning phase or operating, illustrate this. One of the cables between
the UK and Norway is owned by Statnett (NO) and National Grid (UK) with investment costs for Statnett
of 1.5-2 billion euro. Another example is one of the cables between Norway and Germany- the
NORDLINK with a different owner structure. 50% is owned by Statnett and 50% by TenneT and KfW in
Germany. The investment costs for Statnett equals the investments for the cable between the UK and
Norway. Both these projects are in the construction phase. An increase in capacity for the countries
involved to exchange electrical energy will probably give a more stable reliability of electric supply,
contribute to added labour and a future of climate friendly energy systems. Another aspect of this is
the financing model within each nation in the study. In a project like the North Atlantic Energy Network,
there has to be enough power delivered from renewable sources and willingness to invest in electricity
grids.
The costs of financing cables will most likely be implemented as a model where the different nations
involved will divide the costs between them. If we look at two other similar projects, with a Norwegian
starting point, with only two countries involved there are at least two different models of dividing the
costs. The cable between the UK and Norway is owned by Statnett (NO) and National Grid (UK) with
investment costs for Statnett of 1.5-2 million euroThe cost for investing for Statnett equals the
investments for the cable between UK and Norway.
Installation cost
Bipolar v.s. Monopol
It is possible to use just one cable instead of two (bipolar) and let the current flow in
the earth and/or sea between two specially designed earth electrodes. This arrangement is a type
of single wire earth return system and is often called monopol.
According to ABB specialists Mr. Ola Hanson and Darren Fennel they would not recommend a
monopolar connection as a solution, as there is a great opposition regarding environmental effects of
electrode stations. The seabed will be disturbed where you place the electrodes and small amount of
chlorine is developed. Chlorine is toxic and can be leathal to some organisms (2014. IGRC. Balsle).
Laying a bundled bipolar costs about the same as laying a monopole so the savings of starting off with
a monopole are only what you save by delaying the cost of one cable. The extra cost of the electrodes
which will be obsolete once the second cable has been laid and the laying of the second cable later on,
cost so much that it outweighs the benefits of starting out with a monopol. If the plan is to lay a bipolar
they would recommend laying a bundled bipolar in one go as it would be cheaper and more acceptable
environmentally.
Cable size
For long cable stretches the loss in the cable is considerable and for a 200 MW cable you can have 30
MW of losses or about 15%. Larger the cables and higher the voltages give relatively less transmission
10
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
losses. For long cables you should go for high capacity. Cable prices are related to cable weight and the
price depends mostly on price of aluminium and copper. If you go up by 20% in power you have about
10% heavier cable so you go 10% up in price. All indications are that when laying a cable it is most cost
effective to lay as large a cable as possible with current technology.
Other things that need to be considered is that losses are less in a copper conducter but copper is very
expensive so for long stretches a cable would probably be aluminium. Installation is mainly decided by
the nature of the route and the cost of laying a 200 MW cable is about 70% of the cost of laying of a
1000 MW cable. There are more losses in extruded cables but they are less expensive. It must be
studied what is optimal for each solution.
Depths
In deep waters cables won’t get damaged by anchors, trolls or floating icebergs so the cables don’t
need to be buried and that saves some money. Close to shore you need to bury or cover the cables to
protect them. Taking cables ashore can be expensive if you have to drill cable routes through bedrock.
Cables have been installed at great depths and cable tunnels have been created as long as 1600m. It
saves a lot of money if they can be avoided so cable routes and landfalls should be chosen with great
care.
It may be necessary to survey the seabed after cables have been laid to make sure they are sitting
where they are supposed to be and that material has not moved from under them.
A 525 kV cable has not yet been qualified for a 1000 m depth, but it might be before IceLink or some
parts of the NAEN project will be realized. A cable with aluminium conductor is likely to have an
advantage when laying at greater depths due to the lower cable weight compared to a cable with
copper conductor
It is no problem to leave a cable in deep waters between cable stretches, it’s no problem to pick it up
again for splicing when you come again with the next stretch
Prices
A price of 2000 DKK/m for a monopole cable was mentioned but that is only for the cable itself and
not the laying of the cable or the converter stations at each end. This means 4 M DKK /km for a cable
pair.
To answer how much it will cost to lay the cable depends on the nature of the cable route which must
be researched properly so it can be estimated how much it will cost.
Price of metal is the deciding factor in cable prices.
Recently there was an article (Ing.dk. 2015) regarding a 740 km long submarine cable from Denmark
to UK. The cable should be able to transport 1400 MW and the cost estimate is for 15.000 million DKK
or 20 million DKK pr km which is almost exactly 2 million pounds pr. km.
At a meeting with National Grid in Faroe Islands in June 2015 a similar price was also mentioned.
Ships
A cableship can lay 500 to 600 m/h on seabed but it can only handle 200 m/h if you need to trench the
cable through soft bed rock or sand. Clay and hard bedrocks can add to difficulties and hence the cost.
Necessary research for thorough preparation only costs about 1% of the total cost of laying a cable.
Extra ships are needed both to guide the way, make sure that other traffic is not in the way and a ship
11
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
is needed to clean the route of junk and obstacles that could harm the trenching equipment or the
cable.
Timescale
The capacity of cable factories will be a bottleneck, since the demand is high and growing.The ABB
factory f.ex. is today booked for 3 years. It is realistic to extimate that itmay take 4 to 7 years from
bidding until commissioning.
It is possible to lay 2 bundled cables at a time in 85 km stretches in 30 to 35 days. This is the overall
time for loading cable onto ship, sailing, laying and going back for more cable.
This means that 4*85 = 340 km of cable can be laid in one summer or each year. It would therefore
take two summers to lay a cable to the Faroe Islands from Iceland.. However, production capacity is
also important. No manufacturer will allow any project to virtually block for other orders for the time
it will take to manufacture e.g. the IceLink cables.
To set up connector stations would take 3 to 4 years.
Alternating Current (AC) technology
For long distances Direct current (DC) cables are the only technical solution but AC cables can be used
for shorter distances. ABB has provided an AC cable to Goliat oil field 100 km off shore.
Transformers, Converter stations
It takes at least 6 months to get a new transformer if there is a breakdown. Therefore it is sensible to
use three single line transformer for each end and have one spare transformer at each end to shorten
the outage because of transformers. One reserve transformer costs about 8% of a converter station.
Surveys
Extensive surveys are needed to find the most appropriate route for a submarine cable. It is necessary
to do a comprehensive Marine Survey and Landing Site study to map the geology and physical
geography in the area.
Hazardous environmental phenomena need to be investigated. Among other things it is essential that
the cable is not layed in sediments with high thermal resistivity as it decrease the capacity of the cable.
Seabed conditions must be investigated for conditions that might lead to requirements for heavy
armouring of cables, movemetnts of sediment, earthquakes, fishing, shipping, floating icebergs,
wrecks etc.
Manufacturers of cables have specified what type of surveys are necessary and money is well spent on
thorough preparations. Surveys cost a fragment of the total cost and it is very expensive to find the
obstacles during installation.
Operation cost
Possibilities for shutdown for new installations can hardly be estimated. However, based on experience
and statistics, there will be a probability for a breakdown one or more times during the life span. This
can either be as a breakage of the cable itself, or in converter structures. If the repairing has to take
place in deep water, this will be a highly expensive operation. In addition, normal maintenance for the
different systems has to be performed. Experience from operational costs estimate this to
approximately 5% of investment costs.
Operational cost includes costs for operation and maintenance of the subsea cable and converter
stations, as well as onshore costs due to losses and increased cost for running and managing the
12
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0013.png
onshore grid. There will be electrical losses depending on the total length and number of converter
stations. As basis for further work, electrical losses can be estimated to about 1% per 100 km, and 1 %
per converter station.
Finally the repair cost for subsea cables should be taken into account, due to a risk evaluation.
Estimated cost for one cable repair is 2-5 million Euro. In addition the value of downtime (estimated
to 30-100 days per subsea repair) should be calculated.
Lifetime
The submarine cable technology is well established, and has been used for energy transmission in more
than 100 years. The principles with paper tape insulated cables today are more or less the same as
those used for decades, and the service experience is extremely good.
Generally, high voltage power cables have a proven life span of more than 70 years, and a large number
of the cables in services today are more than 50 years old.
Due to the route length, the transmission must be by utilizing high voltage direct current (HVDC).
Submarine cables made for HVDC transmission have somewhat shorter history, and literature estimate
the life span of a submarine HVDC cables to be approximately 30 – 40 years. Equipment for plant
control is most likely to be changed after 20 years due to development of technology.
A HVDC system will consist of two main sub-systems, the submarine cable, and the converter system.
All this is passive, robust and well-proven equipment, and consist of simple structures.
Technologies
Submarine cable faults
A Cigré report from 2009 is interesting regarding shedding light on submarine cable faults.
Total number of submarine faults reported 1990 to 2005
According to Cigré report from 2009, 49 failures in submarine cables were reported during that period:
The faults reported are mainly external faults, with immediate breakdown or an unplanned
outage of the cable system.
Six answers, classified as unknown, failed to specify whether the failure was instantaneous or
not. These failures are reported to have been caused by anchor and trawling and as
consequence are considered to be instantaneous. Therefore 40 cases may be classified as
instantaneous failures and 9 cases may be classified as occurrence requiring unplanned
outage.
13
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0014.png
Eight of the nine cases requiring unplanned outage were reported on SCOF type cable. The
remaining case was termination related (hydraulic system) on MI cable. Six of these failures
were reported to be on terminations, joints and other components. Oil leaks are expected to
be the main reason in these cases.
Owing to the fact that few replies were received from utilities and that manufacturers may not
be aware of all failures, the number of faults reported may be slightly understated. If so, this
is most likely to be the case for the lowest voltage levels of XLPE and EPR cables installed in
short lengths in shallow water.
Repair joints for armoured submarine cables are not available off the shelf from accessory
suppliers. Such accessories are designed and type tested by the submarine cable suppliers.
Therefore it is rather unlikely that the submarine cable suppliers would not be informed about
damage and repairs requiring joints. Installation of cable in long lengths and / or in deep water
will require assistance from the supplier. Therefore, the reported number of failures, repairs
and joints are assumed to be fairly accurate (information from the suppliers has been used to
compensate for unsatisfactory response from utilities in parts of the world).
In total 49 faults were reported, 55% on AC cable systems and 45% on DC cable.
7 cases (14%) are reported to have an unknown cause of failure.
16 faults (33%) are reported to have been caused by “other” reasons. This is rather higher than
expected. “Other” was defined as physical external parameters excluding anchors, trawling or
excavation and could include for example subsidence, increased burial depth resulting in
overheating or an abnormal external system (e.g. lightning)
The origin of the undefined faults (reported as “Other” or “Unknown” has been investigated
to try to clarify the type of fault, internal or external.”
49 cases over a fifteen year period or just over three cases a year does not give a very reliable statistics
to estimate failure in the future. Predicting the likelihood for failure of a cable is therefore a rather
uncertain.
Analysing failures categorized as “Other” is according to the same Cigré report as follows:”
Failures reported as being caused by incidents other than trawling, anchoring and excavation
may have not been specified.
63 % of these failures are reported on AC-SCOF cable and 31% on DC – MI cable.
14
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0015.png
19% of these failures have occurred in landfall troughs where wave induced movement and
thermal effects may cause lead sheath fatigue and failure of paper insulated cables with lead
sheath.
44 % of these failures are reported to have occurred at locations with unprotected cable.
It is assumed that a significant part of this group is related corrosion, mechanical impact from
wave action, unplanned thermal exposure etc in landfall area during time in operation.
The major part of these failures occurred after nearly 10 years and more in operation.
Supporting information regarding potential lightning and switching over voltages has not been
given.”
In the report a comparison is made with older Cigré reports on cable failures. It states that the number
of reported faults are significantly lower today than in 1950-1980. It is stated that the reason is
probably because of improved methods for surveying and finding optimal routing, laying and
protecting the cables.
The report goes through many statistical aspects of submarine faults and outage times at different
voltage levels. The outage times are half the time, less than 2 months, but over 20% last more than 6
months.
Repair can be difficult if not impossible in the winter time in the North Atlantic, so failures could cause
long outage times if they happen in the worst of times.
Windfarms
In the two following chapters there will be some information on landbased and
offshore windfarms, mostly in connection with production of energy to
interconnectors in the North Atlantic.
This means, that focus will be on the special challenges in the north Atlantic
region with its very good wind conditions.
Land-based windfarms
Windfarms in the north Atlantic region have only been in production for the last
ten years, and only the last three years have given some experience and results
from windturbines specially designed for high wind speeds and rough wind
conditions.
In the table below you can see the capacity factor for windturbines in Shetland, Faroe Islands and
Iceland.
Site
Capacity factor
Shetland Burradale
52%
Faroe Islands Neshagi
42% (*)
Iceland
44%
(*) This figure is an underestimate, since the simultanous production from hydro, heavy fuel and wind
in some periods of low demand implies a downregulating of the production from the windtubines.
Small electricity systems such as in the Faroe Islands and Shetland set very high demands to the quality
of the energy from the windturbines to the grid.
15
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0016.png
Also the very high windspeeds that are in the area are a challenge to the windturbines.
These conditions are not very common in most parts of the world, and therefore the range of suitable
turbines is not high.
In particular turbines from one company have been choosen in all three countries mentioned.
These are the relatively small turbines E-44 from the German company Enercon, V47 and V52 turbines
from Danish company, Vestas. Recently a 3MW, E82 E4 Enercon wind turbine has been erected in
Shetland.
It can be a good lesson to describe in some details the features of these turbines that make them
usable in the mentioned small and vulnerable grids in these countries with very challenging
weatherconditions.
Windturbines of different wind classes
Some sites are windier than others. A lowland site in the middle of southern England might have an
average wind speed of 6 m/s, whereas an exposed site in the North Atlantic might have an average
wind speed of more than 10 m/s.
Because the ‘power in the wind’ is proportional to the cube of the velocity, this means that the wind
turbine on the 10 m/s site would on average be exposed to well over three-times the loads compared
to the 6 m/s site.
There is also a second dimension that affects wind class which is ‘turbulence intensity’or wind shear,
which is basically a measure of how turbulent the wind is at a site. This is important because complex
topography can cause turbulence, and turbulence can cause varying loads on wind turbines which
causes them to wear down more quickly. In extreme cases, if a site is just too turbulent the wind
turbine manufacturer will refuse to supply a wind turbine because they will know that the turbine will
not operate reliably for the full design life at such a site.
Basically, for wind class 2 and wind class 1 sites on-site wind monitoring is essential to determine the
exact annual average wind speed and the turbulence intensity, so that the optimum turbine can be
specified to ensure long term, reliable operation.
Wind Class 1 turbines are designed to cope with the tough operating conditions experienced at sites
with average wind speeds above 8.5 m/s. Typically these turbines have smaller rotors (i.e. shorter
blades) and are on shorter towers to minimise structural loads. They are also heavier-duty in design,
which makes them more expensive.
The table here shows the International Electrotechnical Commission (IEC) Wind Classes and the wind
speeds that the turbine must be designed to withstand.
IEC Wind Class
1 (High Wind)
2 (Med. Wind)
3 (Low Wind)
16
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0017.png
Reference Wind Speed
50 m/s
42.5 m/s
7.5 m/s
Annual Average Wind Speed (Max)
10 m/s
8.5 m/s
7.5 m/s
50-year Return Gust
70 m/s
59.5 m/s
52.5 m/s
1-year Return Gust
52.5 m/s
44.6 m/s
39.4 m/s
With regard to 1-year Return Gust it can be mentioned, that the turbines situated in Faroe Islands
already after two years in operation have been exposed to windspeeds above 80 m/s.
There is an extension for windclass 1, namely an S, which stands for “site specific”. The new turbines
on Faroe Islands have this extension. They have therefore been specially designed after the turbine
company has made a thorough examination from one year quality wind measurements at the specific
site.
Optimal grid integration
The share of wind energy in the electricity generation is on the rise in many countries electricity
systems. That is why the technical requirements of local grid operators regarding the electrical
performance of wind energy converters (WECs) and wind farms (WFs) are also getting more extensive
and challenging.
Wind energy converters (WEC technology)
In Enercon turbines the rotor is directly connected, that means without intermediate gearbox, to the
multi-pole, electrically excited annular generator. The electrical power produced by the generator is
fed via a full-scale power converter into the electric network. The converter system itself consists of a
rectifier, a DC link and several inverters.
In electrical terms the annular generator is completely decoupled from the grid. This enables a high
level of rotor speed variability and, in turn allows for a more mechanically robust design with fewer
moving parts. In addition to this the electrical properties of the WEC’s are solely determined by the
inverters used and the corresponding FACTS- (Flexible AC Transmission System) controller.
Advances in relation to the electrical grid
Contributes to maintaining grid voltage and frequency
Optimum power quality through an adapted control system and operating mode in accordance
with IEC standards and FGW (Federation of German Windpower) regulations
The idea behind the grid management system is to control and regulate power feed without
power peaks
FACTS properties enable the turbines to provide system services similar to those provided by
conventional power plants or beyond
Annular generator
The annular generator - comprising rotor and stator - forms the key component of the wind energy
converter design. Combined with the hub, it provides optimal energy flow. The sophisticated wind
17
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
energy converter technology means maximum running smoothness, low sound emissions and a long
service life. One special feature is that, thanks to the externally excited annular generator, there is no
need for the use of permanent magnets that are manufactured from highly controversial neodymium
(rare earths). The magnetic fields required for power generation are created electrically.
SCADA System
The Supervisory Control and Data Acquisition (SCADA) system comprises all components for data
acquisition, remote monitoring and control of a wind farm. The adaptability of the standard topology
consisting of the WEC- and SCADA System allows complying with the most demanding grid codes and
additionally providing a multitude of system services. Provision of such system services allows wind
farm operators in many markets to generate additional income, and ensure optimal operation.
Closed-loop control of the wind farm at the point of connection
A wind farm controller can be used to accurately control the active and reactive power of a wind farm
at the point of connection (PoC). In conjunction with the wide reactive power range of the WECs, a
wind farm controller can be used for rapid control of the voltage at the network connection point.
With these wind farm regulation, the setpoints for control can not only be programmed specifically
into the relevant device but also be received dynamically from the grid operator via a communication
interface. This enables optimal integration of the wind farm into existing grids.
At last in this chapter we will descibe in some details the capability of these mentioned WEC’s to
cooperate with and stabilize the receiving grid, which as mentioned above has limited size and
strenght.
Reactive power capability
Power-frequency control
Inertia Emulation
Fault Ride Through
Storm control
De-Icing
Reactive power capability
Reactive power is needed in order to keep the grid’s voltage within the required limits and compensate
for electrical equipment connected to the grid. Due to the full-scale converter concept, the WECs can
provide reactive power flexibly.
The Q+ option extends the reactive power range i.e. the maximum reactive power available from an
ENERCON WEC.
The STATCOM option enables an ENERCON WEC to provide the full reactive power range regardless of
the active power production. Even when idle, the full reactive power of the WEC will be available.
The Q+ option and the STATCOM option can be configured project specifically onto meet the
requirements of certain grid codes. Both options are installed in the WEC eliminating the need for
external STATCOMs, capacitor banks or choke coils.
Power-frequency control
For any electric power system, generation and consumption of power have to be balanced at all times.
If this balance is disturbed, the grid’s frequency will deviate from its nominal value. In case a grid fault
leads to temporary over frequency, the WECs will reduce their power infeed according to certain set
18
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0019.png
parameters. In addition, reserve power can be retained during normal operation in order to
compensate for an event of under frequency.
Inertia Emulation
The WECs equipped with the Inertia Emulation option can increase their active power output in the
event of frequency drops without setting aside reserve power. For a certain period of time, a power
greater than that contained in the wind is fed into the grid.
Fault Ride Through
TheWECs are capable of remaining in fully operational and connected to the grid for 5s in case of
overvoltages or undervoltages caused by grid faults. Furthermore the Fault Ride Through (FRT) option
enables an adjustable current to be fed in during the fault in order to dynamically support the grid
voltage.
Storm control
The wind energy converters run with a special storm control feature. This slows the wind turbine down
so that it can continue to operate even at high wind speeds. Numerous shutdowns which lead to
considerable losses in power output can thus be avoided. When storm control is activated, the rated
speed is linearly reduced starting at a predetermined wind speed for each turbine type. When wind
speeds surpass 32 m/s the Storm Control System does not shut down the turbine abruptly, but rather
reduces the power by continuously pitching the rotor blades. The output is only reduced to zero at
wind speeds of approx. 40 m/s. This strategy improves electrical behaviour in the grid at the same time
increases output.
Rotor blade de-icing system
The de-icing system shortens thawing time. A fan heater installed in the blade root is activated and
starts heating the air inside the rotor blade using air recirculation. The temperature of the blade
surface warms up to above 0°C and the ice build-up melts off.
19
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
The rotor blade de-icing system can be operated at sites with low icing potential even when the WEC
is in operation. Thin layers of ice are thawed off at an early stage thus maximising energy yield and
reducing downtime.
Offshore Wind Turbines
Worldwide offshore wind is accepted as the central focus to increase energy production from
renewable sources over the next decade. But there are still major challenges ahead, since the industry
is not yet mature in either technology or supply chain. It is still a young technology facing considerable
challenges and political and economic support is needed to live up to the strategy and to ensure that
it can meet its potential.
The move to sites further offshore will give access to improved wind resources.
Offshore wind is a strong asset in European maritime economy and is one of the fastest growing
maritime sectors. It is a promising industry with great potential to transform and decarbonise the
electricity system. The global installed capacity at the beginning of 2014 was 6.5 GW and in 2020 it is
expected, that 4% of the European electricity demand (40GW) could come from offshore wind. By
2030, offshore wind capacity could total 150GW and meeting 14% of the EU consumption.
The bottom fixed foundations used today are limited to depths less than 40-50 m due to today´s
technical and economic restrictions. And as the sector is growing, the areas with suitable conditions
become increasingly limited and the engineers are looking for solutions, where floating wind power
turbines could be installed. This technology could play a vital role towards a greener power generation.
Floating wind power technology is derived from deep water offshore oil & gas structures used in this
sector for a long time. And there is an opportunity to use the synergy and the expertise from this area
to establish an industry around this segment.
Floating wind turbines in deep water environment
Offshore floating wind turbines may hold the key to large-scale offshore wind energy. They can operate
in deep waters, far from shore where visual impacts are negated and where the wind resource is
generally strong and consistent. However, floating turbines have significant challenges as well, in
particular the increased loading on the blades and tower due to the higher inertial and gravitational
forces caused by the motion of the floating platform.
If we take Faroe Islands as an example, we can say, that although there still is plenty of areas onshore
Faroe Island where wind parks can be installed, the big potential and hence the future may lie in the
water surrounding the islands.
Floating wind represents a new and significant renewable energy source that will complement an
existing and expanding array of alternative energy projects in North Atlantic.
In 2013, the global installed capacity for offshore wind was around 6.5 GW, almost all of this built on
bottom fixed foundations. Many coastal areas of the world the waters are too deep for this technology.
Floating wind turbine technology offers a new opportunity to provide clean energy to countries and
coastal regions with deep water coastlines. Floating wind turbines can be deployed in deep to ultra-
deep waters, in the 1,000 metres range and beyond.
Hywind, a new demonstration project in Scotland, consists of a wind turbine placed on top of a
ballasted steel cylinder. This pilot project is expected to demonstrate the feasibility of multiple floating
wind turbines in a region that has optimal wind conditions, a strong supply chain within oil and gas
20
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
and supportive public policies such as enhanced support for floating offshore wind pilot parks under
the Renewables Obligation (Scotland).
Statoil’s Hywind concept combines known technologies in a completely new setting and opens up the
possibility for capturing wind energy in deep-water environments. Based on Statoil’s background in
design, installation and operation of floating offshore oil and gas platforms, Hywind has been designed
as a slender cylinder structure, chosen as the most feasible and economical concept for a floating wind
turbine.
The floating turbine technology was first conceptualized in 2001, a scale-model was used to test the
concept in 2005 and the world’s first floating full-scale wind turbine Hywind Demo was installed in
2009. Hywind is turbine independent and, in principle, any offshore wind turbine generator can be
used as long as the combined weight of the nacelle and rotor is within the requirements for marine
stability.
Statoil's proprietary Hywind-specific pitch motion controller is integrated with the turbine’s control
system and mitigates excessive motions of the structure. This also eliminates the loss of energy due to
aerodynamic or hydrodynamic movements and maximizes the power output from the turbine. The
structure is ballast-stabilized and anchored to the seabed. The mooring system consists of three
mooring lines attached to anchors suited to the seabed conditions on site.
The water depth around the coastline of the Faroe Island, Iceland, Greenland and Norway is much
deeper than it is in the central North Sea, where until now the majority of offshore wind farms are
installed. And the conditions regarding wind, waves and current are much harsher and more
challenging. Hence the countries lack extensive areas of shallow water suitable for conventional
offshore wind farms. Norway is in a similar situation and is concentrating on solutions based on floating
offshore wind. The first test turbine Hywind was installed outside the Norwegian coast in 2009. But
today the activity regarding offshore wind in Norway is very low due to lack of economic incentives.
There is an oversupply of almost CO
2
free hydro production and the motivation is limited.
But Norway, as well as Great Britain, has an extensive offshore expertise from the oil & gas industry.
And with the low activity at the moment due to low oil prices, these two countries are in a situation
where companies could benefit from this and becoming a world leader within offshore renewable and
at the same time diversify the economy by export of the offshore wind supply chain. But this could
only be implemented with a strong subsidy and a clear long-term national plan in order to reduce the
financial risk and attract investors.
Due to these circumstances, it is very unlikely, that we will see any Offshore Wind Projects
outside the
central North Sea
in the nearest future. It is possible to install Wind Turbines on land for a fracture of
the cost for offshore turbines. Turbines which could produce the same amount of power as offshore
turbines
Substructures, station keeping and anchoring
The number of developers and substructure concepts is constantly growing. Even though alternative
designs are suggested, the industry is currently dominated by the three key design philosophies: SPAR,
Semi-Submersibles and Tension Leg Platforms (TLPs), all well-known from the offshore oil & gas
industry.
Future systems will be correlated to developments in turbine design, the introduction of new materials
like polyester, graphene and carbon fibre for mooring lines and tendon systems. Going towards
21
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0022.png
increasingly deeper waters and larger arrays is likely to lead to new innovative mooring and anchoring
solutions.
Graphic from DNV - GL showing connections (mooring lines) between floating offshore
turbines (2015. DNV- GL)
Rated power and rotor size
The trend is towards increases in turbine rated power and rotor size, leading to higher energy yield
and improvement in LCOE. Turbines installed offshore in 2013 had an average size of 4 MW and
demonstration projects for floating wind turbine systems currently under development are applying
turbine sizes of 6-7 MW.
Most likely the turbine size is bound to increase in the coming decades. Some developers beleive that
10 MW offshore turbines, with a hub height of 130 metres and a rotor diameter of 200 meters, will be
commercially available in the early 2020s. For 2030-2050, the average size could grow to sizes of 10-
15 MW and up to 20 MW for new installations in the later part of the period.
22
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0023.png
Growth in size of wind turbines since 1980 and future prospects according to EWEA
(2015. DNV- GL)
After the Fukushima nuclear disaster in Japan, causing a meltdown of three reactors, many of the
country´s nuclear power plants have been shut down and alternative energy supply is needed. One of
the focus areas is wind power, and since Japan is a crowded and mountainous country, the main option
is floating turbines in deep water off the rugged coastline.
Fukushima Forward is a trial project for offshore wind power plant conducted by the Japanese Ministry
of Economy, Trade and Industry. In the first phase a floating 2 MW turbine was installed.
The second phase is ongoing and include installation of two 7 MW turbines. A Swedish company is
selected to provide the distributed buoyancy modules, dynamic stiffeners and connectors, cable
protectors etc. (2015. Trelleborg.)
Windfloat Portugal
In October, 2011, Principle Power deployed a full-scale prototype WindFloat 5km off the coast of
Aguçadoura, Portugal. To date the system has produced in excess of 9 GWh of electricity delivered by
sub-sea cable to the local grid. The structure was completely assembled and commissioned onshore
before being towed some 400km along the Portuguese coast (from it's assembly facility near Setubal,
Portugal). Additionally, certification (or class) was an area of focus in the prototype design as it will be
a future requirement for commercial projects. Principle Power continues to operate the prototype
system gaining priceless operational data and experience for use in future WindFloat systems world-
wide (2015. Principle)
23
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0024.png
WindFloat of the Portuguece coast (2015. Cleantechnica)
Fukushima (Japan) Floating Offshore Wind Farm (2015. Fukushima forward)
More information about cable ship (laying & repair) can be found:
24
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0025.png
https://www.iscpc.org/ The International Cable Protection Committee (ICPC) is dedicated to
the sharing of information for the common interest of all seabed users. ICPC represents all
who operate, maintain and work in every aspect of both the telecommunication and power
cable industry. All areas of this site are available for public viewing except for the Members
area which is reserved for administration of the ICPC.
Electricity usage on oil platforms
The areas of the North Sea and the Norwegian Sea has a high density of oil fields – both on
the Norwegian-, Danish- and the UK shelf we find installations potentially to be included in an
electric subsea grid . At present only two fields on the Norwegian shelf are fully electrified,
including British Petroleum’s (BP) Valhall field. The discussion of electrification of fields on the
Norwegian shelf started itwenty years ago. After three reports and impact assessments
Norway has still not decided fully on electrification. This only shows some of the obstacles in
the electrification debate.
Ellen Hambro, the director in the Norwegian Environmental Authorities said in a statement
“that Norway’s climate goals will not be possible to achieve unless we will see large cuts in
discharges from the Norwegian shelf” implying that all new projects in the North Sea will have
to be electrified. New fields are planned and developed in several of the countries in this
study, and oil and gas possibilities will be in focus in the years to come. The North Sea and the
Norwegian Sea will possibly be important regions for oil and gas production for many years,
even with the oil prices we have seen in 2015. “Utsira høgden” is a large area with some of
the largest findings of oil and gas in Norway’s history. One of the fields on Utsira, the Johan
Sverdrup field will be fully electrified as it is set in production in 2019. In the whole of the
North Sea Area there are about 61 fields in production (www.norskpetroleum.no).
The decision of electrification of Utsira came in 2014 and other fields on the Norwegian shelf, as the
Goliat field in the Barents Sea will be supplied with electrical power from land, which will reduce
Goliat’s CO
2
emissions by half (
www.eninorge.com
).
25
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0026.png
CO
2
emissions from the oil and gas industry in the period 1997-2010 and prognoses to
2025.
The electrification of oil and gas fields is still a hot topic in Norwegian politics. Trond Lien, the
Norwegian minister of Petroleum and Energy has in the last year made several statements linked to
energy politics: “Stating that the world needs more energy and more sustainable energy, renewable
energy and a power grid developed to meet future challenges is a part of this picture. The use of
electricity will increase in the future for example through electrification of the shelf and increased
industrial production”. (2014. Miljødirektoratet)
Connecting oil platforms to the network
At present only two fields on the Norwegian shelf are fully electrified. Norway’s climate goals will not
be possible to achieve unless large cuts in discharges from the Norwegian shelf. The Norwegian shelf
is divided into regions and region I and II in the southern parts of Norway are most relevant to this
study. In both these regions there are several large oil fields in productions today, new fields are
planned and this will be an important region for oil and gas production for many years to come yet.
“Utsira høgden” is a large area with some of the largest findings of oil and gas in Norway’s history. One
of the fields on Utsira, the Johan Sverdrup field will be fully electrified as it is set in production in 2019.
In the whole of the North Sea Area there are about 61 fields in production (www.norskpetroleum.no).
The decision of electrification of Utsira came in 2014 and other fields on the Norwegian shelf
will be supplied with electrical power from land, which will reduce Goliat’s CO
2
emissions by
half (www.eninorge.com). The two figures below give an impression of the amount of oilfields
26
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0027.png
in the project area. There is a heavy density of oil and gas fields in particular on the Norwegian
shelf.
Map of the North Atlantic Oil and Gas production
27
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0028.png
.
Map of the North Sea area of the Norwegian Continental Shelf (www.npd.no)
28
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Benefits
Figure 2 and 3 give an impression of the Oil and Gas production fields in the study area. In addition
both the Faroe Islands and Iceland are developing the potential for an Oil and Gas industry. Given this
and the already existing fields in the study area, there should be a substantial potential for
electrification of some of the fields. Commitments with respect to CO
2
emissions for the countries in
this study could have a positive overall effect from such a project. The possible elictrification of new
Oil and Gas installations, can imply huge benefits for the CO
2
account within each country.
Cost
Cost estimates concerning electrification of the oil and gas fields vary a lot and are at least in Norway
the centre of attention in the electrification debate. British Petroleum’s (BP) Valhall field is one of the
fully electrified fields on the shelf. Cost estimates from BP show that the costs to electrify this field
were around 1.8 billion NOK. According to BP the electrification has been a success. The operation-
and maintenance costs are heavily reduced, and the emissions are reduced by 250 tons of NOx and
300.000 tons of CO
2
a year. This can be compared to the yearly emissions from 100.000 cars. These are
numbers from the oil producers – however there are several discussions at present related to the real
costs of electrifying oilfields.
CO
2
emission
Reports handling the issues of electrification of oil and gas installations on the Norwegian shelf give a
hint of the benefits related to CO
2
emissions. One of the largest oil production areas in Norway at
present is the Utsirahøgden. These areas consist of four different oil fields, and the total emissions are
approximately 800.000 tons of CO
2
pr. year. According to the Central Bureau of Statistics in Norway,
the emissions from some fields are larger than the total emissions of CO
2
from the larger Norwegian
cities (2015. Statistisk sentralbyrå)
Impact Assessment
Environment, natural and societal impact assessments is as a general rule applied to any project that
will have possible impacts on the natural or societal resources. The European Union Environmental
Impact Assessment (EU EIA) Directive applies to almost all countries in this study and gives a guidance
of the issues that needs focus. In addition, each country in the study has laws and regulations derived
from the EU directive that apply to environmental and social issues on a national level. The OSPAR (see
Acronyms) convention (agreement from 1992) applies to any operation affecting the environment in
the marine environment in the North-East Atlantic. OSPAR is the current legislative instrument
regulating international cooperation in these areas, including submarine cables and oil and gas
activities.
29
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0030.png
The North-East Atlantic and range of application of the OSPAR Convention (Norwegian
Environmental Agency).
The environmental and societal review in larger studies should start with a screening phase where the
present situation including available data and an overview of studies and reports from the study area
is documented. The Environmental and Societal impact assessment program (ESIAP), and hearings of
these, make the basis for the focus areas during the Environmental and Societal Impact Assessment
(ESIA).
The purpose of the assessment is to ensure that decision makers are conscious of the
environmental and societal impacts when deciding whether or not to proceed, or form, a project. The
ESIA has to include both the development- and the operational phase of the project. A proposal of a
surveillance program should also be outlined for the project. (2015 EU Environmental Impact Directive
and 2015. OSPAR)
What can we learn from other projects
It will be interesting to follow up on developments of similar projects, like the IceLink Project on a 1000
MW interconnector between UK and Iceland as this concerns a cable going through the same waters
as an Interconnector between Iceland and Faroe Island which is a part of the NAEN project concept.
The Isles project is looking at a meshed offshore network and coordination of various interconnections
like the NAEN project. It has been ongoing for a number of years and may lead the way for future
development in this area.
The IceLink Projcet
The IceLink project is a project designed to deliver renewable, flexible generation to Great Britain from
2024. The project aims to deliver more than 5 TWh of flexible renewable electricity per annum.
The interconnector will be approximately 1000 km long, 1000 MW HVDC transmission link, connecting
east Iceland to northern GB, and offering bi-directional flows.
The entire Icelandic hydro system will provide flexibility to GB after a number of hydro repowering
upgrades are completed along with the new assets.
The project is not economically viable without the support of UK Contract for Difference (CfD) and
getting a UK CfD will require political support from both countries and the CfD itself will need to be
adapted to the unique nature of the project.
30
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0031.png
An interconnector between Norway and Holland was established in 2008. The link has capcity of 700
MW and was at that time the longest in the world or 580 Km.
The cable between Shetland and UK is most likely to be realised in the near future. There is a lot of
indication that the Icelink cable might be realised and it is technically possible to take it ashore in the
Faroe Islands. All of the connections discussed for this project are most likely to happen one at a time
if all of the connection require more indepth analysis and as for Greenland the necessary infrastructure
is not in place for a subsea cable to be realistic in the near future.
The Isles project
According to the latest documentation regarding the Isles project (2015
www.islesproject.eu)
there is
a significant opportunity to take a coordinated approach to delivery of electricity generation and
transmission in the Irish Sea and around the western coastal waters of Scotland – the ISLES zone.
The study demonstrates that coordinated development of harnessing renewable resources in the ISLES
zone can benefit consumers in Ireland and Great Britain. The ISLES vision is a meshed offshore network
to harness the wind, wave and tidal resources in the area.
The benefits are seen to be reduction in cost of Governments and consumers, project developers,
system operators. Policy barriers, regulatory barriers and commercial and technological barriers could
stop a project of this kind.
A number of important challenges regarding this project remain to be resolved, including operation of
energy markets and promotion of innovation and investment, to facilitate major coordinated
development.
“The main recommendations of ISLES have key implications for governments, regulators and industry
at national and EU level. The ISLES partners consider that the study will contribute to understanding
at jurisdictional and EU levels of the challenges and opportunities for enhanced cross-border
cooperation on renewables and grid development.”
31
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0032.png
References
2010. CIGRE. A survey of the reliability of HVDC systems throughout the world during 2009-2010.
2015. Cleantechnica. http://cleantechnica.com/2012/06/18/floating-wind-turbine-installed-
portuguese-coast/
2015. DNV- GL . https://www.dnvgl.com/technology-innovation/broader-view/electrifying-the-
future/third-generation-wind-power.html
2013. Experience in transporting energy through subsea power cables: The case of Iceland. Svandís
Hlín Karlsdóttir
2015. Fukushima forward. http://www.fukushima-forward.jp/english/2014. IGRC. Balslev.
http://www.balslev.com/fileadmin/user_upload/billeder/Nyheder___events/TP5_37_Rosenberg_Pa
per_No_309_Balslev.pdf
2015. http://www.islesproject.eu/final-reports-published-and-available-to-download/
2014. Miljødirektoratet. Faglig grunnlag for videreutvikling av den nasjonale og internasjonale
klimapolitikken. M-133.
2015. NVE. www.nve.no Energy market, Norwegian Water Resources and Energy Directorate 2015.
Principle. http://www.principlepowerinc.com/products/windfloat.html
2015. Regjeringen. www.regjeringen.no. Facts- Energy and Water Resources
2015 28. September. Ing.dk. http://ing.dk/artikel/740-kilometer-elkabel-skal-sende-dansk-stroem-til-
england-179078?utm_source=nyhedsbrev&utm_medium=email&utm_campaign=daglig
2015. Statnett. http://www.statnett.no/en/News/News-archives/News-archive-2015/15-billion-
contracts-awarded-to-build-the-worlds-longest-interconnector/
2015. The Convention for the Protection of the Marine Environment of the North-East Atlantic-
OSPAR (www.ospar.org)
2015. The EU’s Environmental Impact Directive. (http://ec.europa.eu/environment/eia/home.htm)
2015. Trelleborg. http://www.trelleborg.com/en/offshore/Resources/Case--Studies/Renewables-
Bend--Control
2015. Wikipedia.
https://en.wikipedia.org/wiki/High-voltage_direct_current
32
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0033.png
Acronyms
Acronym
A
AC
DC
HVDC
V
Watt (W)
kW
MW
GW
TW
Wh
kWh
MWh
GWh
TWh
SCOF
XLPE
EPR
MI
IEC
CfD
OSPAR
EU EIA
Explanation
Ampere unit of current (I)
Alternating current
Direct Current
High Voltage Direct Current
Voltage (V)
Unit of power named after James Watt
1000 Watt
1000.000 Watt or 1000 kW
1000.000.000 Watt or 1000 MW
1000.000.000.000 Watt or 1000 GW
Unit of energy = power * time, 1 Wh is the energy produced by 1 W over a period of
one hour. In a year there 1 kW of power produces 8760 kWh
1000 Wh
1000.000 Wh or 1000 kWh
1000.000.0000 Wh or 1000 MWh
1000.000.0000.0000 Wh or 1000 GWh
Self Contained Oil-Filled (cable type)
Cross-linked polyethylene (cable type)
Ethylene propylene rubber (cable type)
Mineral insulated
International Electrotechnical Commission
Contract for Difference CO
OSPAR is the mechanism by which 15 Governments & the EU cooperate to protect
the marine environment of the North-East Atlantic.
European Union Environmental Impact Assessment
33
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
34
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0035.png
Appendix A
North Atlantic Energy Network
Faroe Islands
1
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Introduction
............................................................................................................................................. 3
Electrical Energy production
.................................................................................................................. 3
Production from wind ......................................................................................................................... 4
Production from hydropower ............................................................................................................. 4
Production from oil-fired power plants .............................................................................................. 5
Production from tidal current power plants ....................................................................................... 6
Solar energy ........................................................................................................................................ 7
Waste incineration .............................................................................................................................. 7
Biogas power plants ............................................................................................................................ 7
The Grid and Electric System
................................................................................................................. 8
The electric system and stability ......................................................................................................... 8
Grid development plan ....................................................................................................................... 8
Technical Procedures .......................................................................................................................... 9
Electrification ...................................................................................................................................... 9
Subsidy regimes and excise taxes ....................................................................................................... 9
Electrical market (prices) .................................................................................................................... 9
Energy storage - Pumped Hydro ....................................................................................................... 10
Cable possibilities involving Faroe Islands
.......................................................................................... 11
Connection point in the Faroes......................................................................................................... 12
Cable sizes and cable prizes .............................................................................................................. 12
Cable for supplement of Faroese electricity production or cable for import or cable for both
import and export ............................................................................................................................. 13
Conclusion ............................................................................................................................................. 16
2
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0037.png
Introduction
The project North Atlantic Energy Network is not the first investigation of the possibilities of
connecting countries in the North Atlantic with subsea electricity cables. The tema has been an issue
in Faroes for the last forty years. In 2007 an Icelandic/Faroes report “Indledende vurderinger af
muligheden for at lægge elkabel fra Island til Færøerne”
1
concluded, that a connecting cable was
technically and legally possible, and that the economy could be interesting, if the amount of electricity
transmitted was of a certain amount.
In 2012 the Icelandic and Faroese governments signed a Memorandum of Understanding on
cooperation in the energy sector, where they expressed their willingness to continue to explore the
possibility of developing an electricity interconnection between Iceland and the Faroe Islands.
The faroese interest in an undersea cable running between the Faroe Islands and Iceland or between
the Faroe Islands and Scotland is to establish a possibility to transmit electric power between the
countries.
Even if both Faroe Islands and Denmark are part of the main project, this part of the project deals only
with Faroese matters. The danish contributions are in form of input to technical matters in the main
report.
Electrical Energy production
Electricity demand in the Faroe Islands is met via power plants driven by oil, hydro and wind.
In 2012, total electricity consumption, including grid loss, was 292 GWh, with 181 GWh from oil,
100 GWh from hydro and 11 GWh from wind. In 2014, production from wind was 35 GWh and will
in all probability in 2015 grow to 56 GWh annually. Generally, there is a period in the summer in the
Faroes when rainfall is limited, coupled with periods when there is little or no wind. Ultimately, this
means that the Faroes must rely on oil-fired power plants to produce electricity with water and wind
playing a role in reducing the consumption of heavy oil. The Figure below shows electricity con-
sumption subdivided into oil, hydro and wind. It shows that in the summer months the contribution
from water and wind is very little and thus a greater portion of demand has to be met by production
utilizing heavy oil.
Figure 1. Distribution of electricity production between wind, hydro and oil in
Faroe Islands in 2014 and 2015
1
“Indledende vurderinger af muligheden for at lægge elkabel fra Island til Færøerne”, Jarðfeingi 2007.
3
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Production from wind
Wind turbines have been a part of the Faroese grid since 1993, but not until the five 900 kW wind
turbines erected at Nes came online in November 2012 did wind energy make a meaningful impact on
the net contribution between oil, water and wind.
When electric usage is low, e.g., at night, and wind is present, by year-end 2012 some 30% of
production was derived from wind. With such a large portion of production coming from wind,
several challenges arise, because wind energy is not stable.
These challenges grew even more complicated in 2014 when thirteen 900 kW wind turbines came
online. Now some 20 MW of wind energy is available, which corresponds to 40-50% of total annual
available power. When such a large portion of total power is derived from wind, this places new
demands on the grid, especially the small and vulnerable grids found in the Faroes.
Links into the resilient international grid infrastructure enables Denmark, for example, to export
electricity when its production is greater than its demand and to import electricity when production is
less. Therefore, Denmark can maximize production from wind (ca. 50% by 2020). At the same time,
such a well-integrated AC electric grid can provide the necessary stability across international
boundaries.
When wind turbines initially only contribute to a limited extent to the stability of the grid, any
subsequent increase in the input of the wind turbines into the grid necessitates an ever-increasing need
for grid stability from other sources. Here synchronverters and/or large flywheels at the hydropower
plants could contribute to maintaining the stability of the grid.
In connection with the erection of 13 new wind turbines in 2014, SEV determined that the first two
years of operation would be trial years during which the electricity grid and procedures could be
developed and refined so that an greater amount of wind energy could be integrated into the Faroese
grid.
It is intended that a comprehensive evaluation be conducted regarding the future expansion of wind
energy in the Faroe Islands.
Wind turbines have developed considerably over the last few years. With this in mind, it is
recommended that possible locations for new windfarms be identified.
The resultant map shall be used to determine where the new windfarms should be located and to assist
in planning how best to ensure that the grid can readily accept future wind production.
The government should assume the responsibility for arranging access to the designated areas, setting
up the appropriate weather stations, carrying out environmental impact assessments and gaining the
approvals necessary to implement a new option for wind energy potential.
The mapping of potential wind energy locations requires the participation of several government
authorities. Close collaboration can help to ensure that any new windfarm projects can be quickly
implemented.
Production from hydropower
The first hydroelectric plant was built at Botni in 1921. Since then, hydropower has become a good
supplement to the heavy oil power plants.
All the water turbines in the Faroes are considered to be base-load units, and thus can operate more
than 7,500 hours per year (85%), if sufficient water is available.
The water reservoirs scattered throughout the country are subdivided relative to the amount of water
required for normal operation and for emergencies. Thus, 45% of the reservoirs are for normal
operation, while 55% are set aside for emergency use. Water seldom runs out over the dams, thus
there is no wastage.
All hydropower plants have, however, limited water storage capacity, and under normal operations in
the Central Production Area the time required to drain the reservoir is between 7 hours (at Strond) and
up to 413 hours ~ 17 days (at Vestmanna). The power plant at Eiði has a joint reservoir for three
turbines with a drainage time under normal operations of 135 hours ~ 5.5 days.
Under normal operations, the drainage time in Suðuroy is between 77 hours ~ 3 days (turbine 2 at
Botni) and 217 hours ~ 9 days (turbine 1 at Botni).
The water catchment areas in the Faroe Islands are different from those in Sweden and Norway where
considerable amounts of water are contained in the snow accumulation, which melts in the spring.
This “reservoir” of water provides sufficient water for several months of production.
4
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Short drainage times and a relatively long period with little rainfall during the summer months means
that hydropower in the Faroes cannot be considered a source of “secure" power, but only as a
supplement to total electricity production. The various reservoirs and possible catchment areas can
thus contribute to reducing the consumption of heavy oil, but cannot lessen the need for other power
sources.
There is a potential for building larger reservoirs and thus making power from hydro more reliable
also in summermonths.
Production from oil-fired power plants
Oil-fired power plants have a long history and have always been a part of Faroese electricity
production. These types of power stations are considered to be reliable and secure sources of energy
because they are not dependent upon the external vagaries of wind and rain. Of course, there will be
periods when the power plants will stand idle during routine maintenance or repair, but otherwise
these power plants can operate on “stand-by” or generate a little or a lot of power depending on the
need.
Originally, the power plants were built as individual local plants, but over time they were linked into
the 60 kV grid and today they provide excellent electricity production security for the Faroe Islands as
a whole.
The oil-fired power plants can be subdivided into:
· Base-load units – more than 7,500 annual operational hours (85%)
· Peaking units – up to 1,000 annual hours (<12%)
· Emergency units (limited hours – only as needed)
Similar to the hydropower plants, oil-fired power plants have the capacity to ensure stability within
the electricity grid and can provide 5-6 times the normal power in the event of a power failure.
Because electricity production to date has been derived from hydropower and oil-fired power plants,
historically there has been excellent correspondence between consumption and capacity within the
Faroese electricity grid.
On Suðuroy, the new pelagic fish processing factory has resulted in the base-load engine (motor 3 at
the Vági power plant) running many hours under a heavy load, which increases the wear and tear on
the engine. Therefore, a quick solution to increased power production is necessary. There are two
possibilities: 1) lay a cable to the Central Production Area, or 2) increase the current capacity at the
Vági power plant. An AC cable connection has the advantage that the total electricity grid is rendered
bigger and the power plants in both Suðuroy and the Central Production Area could collectively
contribute to greater capacity and stability throughout the entire system. Thus, a cable connection
between Suðuroy and the Central Production Area would result in a stronger grid overall.
Today, in the Central Production Area there are several base-load motors (e.g. motors 3 and 4 at the
Sund power plant) that have run for many, many hours and therefore cannot be expected to remain
fully operational as base-load motors much longer. In future, these particular motors should be used as
peaking load units (i.e. during periods of momentary high consumption) or in special circumstances,
e.g., breakdowns.
Therefore, greater production capacity must be arranged that could replace these particular power
plant motors. SEV has taken the steps necessary to obtain the required approvals from the government
authorities and it is planned that a new power plant at Sund will be operational in 2017. This new
power plant will incorporate advanced leading-edge technology to ensure a viable, long-lived future
that will also include options for a variety of different fuel types.
At the same time as the new Sund power plant is readied, it is recommended that a future long-term
plan be drafted that addresses the inter-relationship between oil-fired electric power plants and wind
and hydropower plants relative to current and future, accelerated electrification as well as the
possibilities of storing power, e.g., in a Pumped Storage system. This study shall contribute to and
serve as a foundation for a more comprehensive plan for the expansion of the entire energy system in
the Faroe Islands, a plan that will ensure, as much as possible, the use of renewable energy resources
in the future.
5
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0040.png
Production from tidal current power plants
There are several places with excellent conditions for tidal power generation, i.e. the tidal current is
over 2.5 meters per second (5 nautical miles) and the depth is more than 40 m.
Moreover, peak tidal currents vary from place to place, meaning that the greatest potential for
electricity production does not occur at the same time at the different locations. Two excellent
locations are Skopun Fjord and Vestmanna Sound; the difference in peak tides is three hours.
Electricity production occurs in essentially the same manner as with wind turbines, except that the
advantage of tidal current production is its predictability. Such a power plant can be viewed partly as
back-up security and partly as a base-load unit.
The technology continues to be expensive to deploy, but its development should be closely followed.
It is recommended that the technical specifications for such a power plant be compiled and the
permitting requirements outlined so that it might be possible to launch several trials within the next
few years.
Figure 2
Tidal current tidalenergy potential in the Faroe Islands
6
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Solar energy
Solar energy can be utilized via solar panels that heat water or solar cells that produce electricity.
Both possibilities have been tried in small settings in the Faroe Islands, but, compared to the
investment, little is gained, especially in winter. Considerable development has occurred in solar
energy over the past few years and production per area has increased and the cost is less.
The future outlook for solar panels and solar cells built into the exterior facing of a building (climate
screens) appears good. When hydro and wind production is lowest in the summertime, solar energy
could serve as supplemental production during this particular time of the year.
Developments in this area should be closely followed.
Waste incineration
District heating was implemented in the Faroe Islands in 1988 when central heating pipes were laid
from the Sandvíkarhjalla waste incinerator to a new housing development above Hoyvík. In 2008, this
infrastructure was expanded by laying central heating pipes to the Sund power plant. Thus, the district
heating network was connected to two heat sources that in turn supported each other and increased
overall energy security.
More wind energy production results in less oil consumption at the Sund power plant, which in turn
reduces the production of heat from this power plant. It is recommended that the possibility of burning
waste be investigated to enhance the expansion of the district heating system in Tórshavn, and that
heat production be supplemented by large heat pumps so that operations can remain flexible and of
good quality.
Biogas power plants
There is considerable organic waste generated by the fishing industry and agriculture in the Faroe
Islands. This waste pollutes the environment and is difficult to dispose of safely. The fishing industry
has, however, discovered a clever way to handle a large portion of its “waste”. Another possibility is
to use this organic waste as the basis for biogas production that could otherwise be linked into the
district heating system.
It is recommended that the technical specifications for a biogas power plant be researched and
compiled in order to explore and study the potential and the operational conditions of such a power
plant.
7
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0042.png
The Grid and Electric System
The electric system and stability
The electricity system or infrastructure in the Faroes is, in the main, divided into two grids
(see Figure 3), a small grid on Suðuroy and a somewhat larger grid in the Central Production Area of
the Faroese electricity company SEV. In addition, there are some smaller islands that derive their
electricity from small, oil-fired plants.
Figure 3
Faroese electric system
Certain prerequisites must be in place in order to adequately operate a national electric system. The
system must have the requisite internal inertia that will ensure that everything operates as it should
even in the event of a malfunction, such as a short circuit.
For the Faroese grid, it is the hydropower plants and the motors at Sund especially that ensure
sufficient inertia within the system. The size of the flywheels on the water turbines are also of
importance, because a large and thus heavier flywheel makes a considerable difference.
On the other hand, wind turbines to a much lesser degree are able to ensure sufficient inertia in the
system, because they only supply a fifteenth of what the water turbines and the motors provide. This
means that, if many wind turbines were linked into the grid, it would be necessary to ensure stability
in another way, e.g., by having the motors and water turbines idling on standby or by linking
synchronverters into the grid.
The Faroese electric system is small, tenuous and vulnerable because it is not linked to the grids of
other countries. And this situation is compounded when even more wind turbines are linked into the
system. Thus, it was considered that at most only 30 – 40% of total production could come from wind
turbines. However, experience with the new wind turbines indicates that this percentage could be
higher. Therefore, it is recommended that a detailed technical and economic analysis with
recommendations be undertaken to ensure commercially reasonable investment when further wind
turbine expansion takes place.
Grid development plan
There is a need for a plan relative to the development and expansion of the electric system in the
coming years. A grid development plan would be a useful tool and it is recommended that a report be
prepared analysing the various development options and the level of investment required.
Moreover, the plan should also address the transmission power line net, both the high and low tension
lines, i.e. 60 kV, 20/10 kV and 230/240 V.
8
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Technical Procedures
In the future, more and more different types of electrical equipment will connect to the grid. In many
cases, this equipment will be owned by the customers themselves and therefore it will be necessary to
stipulate specific conditions and technical requirements relative to the connection of this equipment
into the grid to ensure equal treatment for all. It is recommended that a distinction be made between
production entities and large consumers, e.g., immersion heaters, heat pumps and other equipment
with varying electricity consumption. Approved regulations regarding connection to the grid should
be drafted.
Electrification
Electrification, coupled with increased wind energy production capacity and possibly other sources of
renewable energy, will enhance the potential use of electricity during periods of peak wind.
Otherwise, the potential production will be lost.
At present it is not possible to store significant amounts of electricity, because, in the main, electric
power must be consumed at the same moment it is produced. Thus, there must be a balance between
production and consumption.
If it were possible to connect and disconnect large consumers of electricity, this would help minimize
production loss. These consumers are, e.g., refrigeration compressors, immersion heaters and heat
pumps. In addition, it is possible to use over production to pump water back up to a hydropower
reservoir (Figure 4).
There should be an emphasis on how economic incentives could accelerate electrification efforts and
how these could be advanced in a reasonable and effective manner.
SEV is underway to shift out all the electric meters. This work will be completed in 2015 and thus it
will be possible to wirelessly measure all electricity usage. In this connection, it is recommended that
a study be carried out to determine if it would be desirable to adjust the price of electricity so that it
would vary throughout the day and would also be linked to annual usage and power consumption.
Also it should be studied whether the price of electricity could vary based on what the electricity is
used for, such that less would be charged for electricity for e.g.heat pumps.
Subsidy regimes and excise taxes
To hasten the shift to green energy resources, it is advisable to investigate various support initiatives
relative to the purchase and installation of more green products or equipment. It should be possible to
offer direct financial incentives, tax allowances, VAT-free or similar programmes to encourage the
general public to invest in the latest and greenest technology.
Excise and similar taxes or surcharges could also be used as an effective tool to promote a more
“greening” trend. For example, an excise tax could be levied on petrol for vehicles or on oil-burning
furnaces. The VAT on heat pumps could be reduced and it is possible to offer tax allowances for
renovations that reduce the heating demands of buildings and private homes. It is recommended that
broad political agreement be forged in this area.
Such an initiative shall, however, be carried out consistent with a comprehensive evaluation of the
economic impact and not just a desire to move from fossil fuel at any price.
Electrical market (prices)
The Faroese electricity marked is vertically organized as the electricity company SEV is a de facto
monopoly owning almost 100% of the production, the transmission grid and all the distribution
system. The company’s activities are regulated in an electricity law administered by the Faroes energy
authorities. The electricity prizes are the same for the same user groups throughout the country. The
overall prize consists of an electricity prize and VAT.
The prizes are different for different user groups, and SEV is right now looking into differentiating the
prizes day and night to cope with the intermittent production and the unequal usage of electricity in
daytime and night-time. The differentiating will furthermore be an incitement for enhancing the
electrification of energy usage.
9
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0044.png
Energy storage - Pumped Hydro
Figure 4 Pumped Storage
Demonstration of a wind/water energy storage system
Earlier studies have shown that there is good potential for the construction and operation of pumped
storage power plants in the Faroe Islands. In 2013, the Nordic Council provided financial support for
a preliminary study for such a facility in Suðuroy. The report
2
examines the technical issues and focus
especially on the optimal size and related costs.
Based on the above-referenced report, a detailed analysis of the possibilities of constructing a pumped
storage power plant is recommended. It will be a major challenge to discover exactly how pumped
storage and wind power will work together and whether the pumps can quickly adjust to fluctuating
wind. The report shall also discuss whether an independent, stand-alone power plant or one linked
into the grid is the best option or whether it would be possible to use either. In addition, the report
shall explore which locations in the Faroes are most appropriate. It is recommended that a Pumped
Storage power plant be set up and evaluated in a special report.
2
Wind power based pumped storage. Nordic Energy Research 2013
10
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0045.png
Cable possibilities involving Faroe Islands
Figure 5. approximate length and depth of some possible cable routes involving Faroe Islands. (Google Maps)
Cable route
Approximate length (km)
Maximal depth (m)
Iceland - Faroes
450
500
Faroes - Shetland
350
1100
Faroes – Scotland
400
1100
Faroes – Norway
650
1500
Table 1
The picture and table above show approximate length and depth of some possible cable routes
involving Faroe Islands.
It is interesting to note that given the fact, that there are good reasons for having cables as short as
possible and as shallow as possible
3
, that it could make good sense to connect the whole area with
Faroe Islands and Shetland as interconnection nodes.
3
Worzyk T. Submarine Power Cables: Design, installation, repair, environmental aspects. Berlin: Springer-Verlag Berlin
Heidelberg; 2009
11
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0046.png
Connection point in the Faroes
Taking account of the size of converterstation at a connection point, it is likely that there will be only
one such connection point. This has to be choosen with regard to
-
the cable routes to and from the Faroes
-
connections points to the high voltage transmission network
-
connection points from power production units (windfarms etc)
-
access to other infrastructure (construction and service)
In order to choose the best cable route, there are also several considerations to take
-
fishing grounds
-
anchors
-
natural hazards landslides, earthquakes, ocean current
-
places where it is possible to protect the cable
From Iceland most likely the cable would be laid from Reyðarfjørður on the south/east coast.
In The Faroes the connection point most likely will be on one of the two main islands, Streymoy or
Eysturoy.
Cable sizes and cable prizes
The factors most influential on cable cost is of course length and size(transmission capacity) and also
the environmental factors, where depth to the seabed is most important (see also the main report)
A very approximate estimate of the cost of a 500 km, 100 MW connection between Iceland and the
Faroes was made in 2007
4
and updated in 2012 says a prize of 2,5 bio DKK (370 mio USD) included
cable cost, converterstations on both sides and laying the cable. An estimate of a 600 MW, 1070 km
cable between South-East Iceland and Peterhead in Scotland says 14 bio DKK (2,1 mio USD) also
included cable cost, converterstations on both sides and laying the cable.
5
4
“Indledende vurderinger af muligheden for at lægge elkabel fra Island til Færøerne”, Jarðfeingi 2007/2012
5
IceScot Submarine Power Cable from Iceland to Scotland. Reykjavik Iceland 25th of March 2011
Annad veldi ehf.Skuli Johannsson
12
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0047.png
Cable for supplement of Faroese electricity production or cable for import
or cable for both import and export
This is a crucial question regarding the economy of cable projects. For it is very clear, that it is the
amount of transmitted electrical energy that shall finance the project.
This can be seen in figure 2, where a summary of the calculations in (6) are presented.
The cost of energy from the cable goes down from roughly 1 DKK/kWh with a transmission of 350
GWh/year to 0,6 DKK/kWh with an increased transmission to 700 GWh/year.
Figure 6. Estimates of cost of production from subsea cable between Iceland and Faroe Islands
6
It is therefore important to have a good indication of the future development of the Faroese electrical
energy production and consumption. There has in 2015 been published an official report
7
on these
issues, as you can read some parts of in the upper part of this report.
6 “Indledende vurderinger af muligheden for at lægge elkabel fra Island til Færøerne”, Jarðfeingi 2007.
7ACTION PLAN. Report and Recommendations on the future electric energy system of the Faroe Islands.
Faroese Ministry of Trade and Industry January 2015
13
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0048.png
Figure 7. 2012 energy mix Faroe Islands.
Figure 8. Electrification scenarios
It is an important fact to notice, that over 90% of the primary energy comes from heavy fuel and
diesel (fig 7), and that in 2015 the electricity production will be around 310 GWh with approximately
40 % coming from heavy fuel. It is also important to notice the governmental energy policy
8
, which
aims at electrifying all the heating of buildings and all the transportation on land. Together with the
general increase in energy usage this will eventually lead to a rise in electric energy usage to about
1000 GWh/year. (see figur 8)
This is interesting in the cable context. First, because as can be seen in figure 9, there will be
produced a lot of energy – maybe from 300 to 400 GWh/year with heavy fuel, even if the share of
wind energy grows very much. This is mostly due to the fact, that in the summer months there is lack
of both wind and rain, and the need for “secure” electricity from heavy fuel is big
9
.
Figure 9 Scenarios of future powerproduction in the Faroe Islands
8
Comprehensive Plan for Electric Energy in the Faroe Islands.
Vinnumálaráðið / Ministry of Trade and Industry 2011
9
Etablering af nødvendig el-produktionskapacitet. Idéoplæg, Rev.6a, September 2013. Ingeniørfirmaet P.A. Pedersen
14
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0049.png
Secondly, it is interesting in a cable context to notice, that the future electricity production will be
very much from wind energy. This is because the Faroes are among the best wind sites in the world
(figure 10) and therefore existing wind turbines have a very high capacity factor (above 42%
producing more than 3,9 GWh/MW/year. SEV 2015)
Figure 10. Windregimes in Northwest Europe
10
As you can see from figure 9, with more wind turbines installed, there will be much more surplus
wind energy that cannot be used because of the stochastic nature of wind energy and the mismatch
between production and usage. The amount could be above 200 GWh/year and could be transmitted
through interconnectors to other markets.
Now the last interesting fact in the cable context is to mention the possibilities that have been
mentioned about making very big wind farms in the Faroes with the purpose to export renewable
energy through one or several interconnectors. Figure 11 shows a slide from a presentation by
Jarðfeingi, where a windfarm of 600 MW is placed in the area south of the capital Tórshavn. This
farm could produce over 2000 GWh/year. Compared with a similar project in Shetland (Viking
Windfarm
11
), the farm could generate an income of up to a billion DKK/year depending on energy
prizes.
10
11
http://www.vikingenergy.co.uk/the-project
15
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0050.png
Figur 6 Windregimes in Europe showing the supreme conditions of Faroe Islands and Shetland (6)
Economy issues. Installation, operation and maintenance, backup issues, economic gain
Synergy effects of cable networks
Potential:
Local interaction – transmission system, energy production, electrical market, prizes, economic
interests, secure power – backup issues, building new power plants
Power: > 600 MW
Energy production: > 2000 GWh/year
Figure 7. Onshore windpark with 600 MW capacity (jarðfeingi 2012)
Figure 11. Imaginary windfarm south of Tórshavn, for export of windenergy.
Conclusion
The above mentioned cable scenarios can sum up to:
A 100 MW IceFar cable is possible, but might be too small to be economically competitive.
A 600 MW IceScot cable is possible, but also with doubtful economy.
Faroe Islands and Shetland have “offshore wind conditions on land”.
Large windfarms in the Faeroes and Shetland need powerful interconnectors.
A cable from Iceland to Scotland could be laid via the Faroes and Shetland, and made even
bigger to be able to transmit both energy from Iceland and energy from the Faroes and
Shetland to Scotland and Europe. A probable synergy effect could be to transmit
hydropower from Iceland in summer and wind power from the Faroes and Shetland in
winter.
16
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0051.png
Appendix B
North Atlantic Energy Network
Greenland
Greenland Innovation Centre
Arne Villumsen
November 2015
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Table of content
Conclusion
Introduction
Infrastructure
Supply of water, heat, and electricity
Energy production and use
Energy prices
CO₂ Emission
Potentials: Hydropower
Potentials: Solar energy
Potentials: Wind energy
Greenland data cable connection
Future cable for transport of electricity
1. Connection to the West
Iqaluit/Nunavut
Cable connection to Labrador
2. Cable connection to the East
Connection to Iceland
3. Domestic cable connection in West Greenland
Benefits of a domestic cable
Legal aspects
Final remarks and conclusions
3
3
5
6
8
11
14
14
18
21
21
22
22
22
25
26
26
26
29
31
32
2
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Acknowledgements
References
33
33
Conclusion.
Greenland has a big hydropower and solar energy potential, which is not
known in detail. Further work is needed to map the potentials. It is
suggested that a domestic electricity grid is established starting on the
west coast with 3 cities (Nuuk, Maniitsoq, and Sisimiut). Hydropower
potential within this area is better known and should be used for this grid.
Industrial development including mining should benefit from the grid and
the hydropower. Future enlargement of the domestic grid to cover most
of the west coast of Greenland where the cities are can be foreseen. For
distant cities and settlements focus should be on local sustainable energy
sources and on reduced energy consumption f.ex.via improved insulation
of houses and the use of heat pumps. Due to lack of infrastructure and
experience a cable connection between Greenland and the neighbouring
countries is not realistic in the nearest future. The use of the energy
potential should be managed as flexible as possible – f.ex following the
Icelandic way some 50 years ago, where an industrial partner “exported”
energy via processing imported raw materials for metal production and
gave the economic base needed for grid development. Cooperation with
the North Atlantic Countries and with Nunavut and Labrador should
continue and be strengthened for exchange of experience and for an
optimal development and use of the enormous energy resources which
are available in Greenland.
Introduction.
Greenland – figure 1 - is the biggest island in the world. It is a part of the
North American Continent. Kap Morris Jesup, the most northerly situated
locality in Greenland is 740 km from the North Pole, and Kap Farvel, the
southern tip of Greenland is at the same latitude as Oslo. From north to
3
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0054.png
south the distance is 2670 km; from east to west on the widest place is
1050 km. (Statistisk Årbog 2015)
Figure 1.
Greenland. Red dots = cities or settlements. Most people live on
the west coast
The total area of Greenland is 2.166.086 km² of which 81 % is
permanently covered by the icecap. 19% - corresponding to 410.449 km²-
is ice free. ( Statistisk Årbog 2015)
4
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0055.png
Greenland belongs to the Arctic climate zone with an average
temperature in the warmest month below 10 C° Celcius. Ocean currents
around Greenland are responsible for lower temperatures on the east
coast ( high arctic climate ) and elevated temperatures on the west coast
where harbours as far north as Sisimiut are free from ice throughout the
year.
As a consequence of this most people are living on the west coast of
Greenland – in 16 cities and 60 settlements. January 2013 Greenland had
56.370 inhabitants in total.
Grønlandsk
Nanortalik
Qaqortoq
Narsaq
Paamiut
Nuuk
Maniitsoq
Sisimiut
Aasiaat
Qasigiannguit
Ilulissat
Qeqertarsuaq
Uummannaq
Upernavik
Qaanaaq
Tasiilaq (Ammassalik)
Illoqqortoormiut
Dansk
Nanortalik
Julianehåb
Narsaq
Frederikshåb
Godthåb
Sukkertoppen
Holsteinsborg
Egedesminde
Christianshåb
Jakobshavn
Godhavn
Uummannaq
Upernavik
Thule
Tasiilaq
Scoresbysund
Beliggenhed
Syd (vest)
Syd (vest)
Syd (vest)
Sydvest
Midt-syd(vest)
Midt-syd (vest)
Midt (vest)
Midt-nord (vest)
Midt-nord (vest)
Midt-nord (vest)
Midt-nord (vest)
Midt-nord (vest)
Nord (vest)
Nord (vest)
Syd (øst)
Midt (øst)
Indbyggertal
ca. 2.300
ca. 3.400
ca. 1.700
ca. 2.000
ca. 15.000
ca. 3.000
ca. 6.000
ca. 3.000
ca. 1.300
ca. 4.500
ca. 1.000
ca. 1.300
ca. 3.000
ca. 660
ca. 3.100
ca. 530
Figure 2: Greenlands towns. ( “indbyggertal “ = number of inhabitants)
Infrastructure
5
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
There are
no roads
between cities and settlements in Greenland except
for in South Greenland where there are some unpaved tracks/roads
between sheep farmers. About 380 km of roads in total are inside the
towns.(Statistisk Årbog 2015)
Transport of passengers and goods is by ship or airplane.
Supply of water, heat and electricity
For the Greenlandic society the company Nukissiorfiit ( Greenlands
Energy Supply- owned by the Government of Greenland) is responsible
for the public supply of water, heat and electricity in towns and
settlements. The first public electricity plant was for Nuuk (1949). The last
town to get a plant was Kangaatsiaq ( 1975). (Statistisk Årbog 2015)
There are no transmission grid connections between the towns.
Before the first hydropower plant was introduced (in 1993 for Nuuk) the
supply of electricity was based on a diesel fired plant and a supply grid for
each town. Many plants are small and emergency sources of power are
installed and ready for operation in every
town.
This will of course
increase the production costs of electricity.
Public heat supply was introduced in 1960 where Maniitsoq established a
combined power and heat supply plant. At present Nukissiorfiit runs
district heating in 12 towns.
To-day Greenland has 5 hydropower plants which supply 6 towns with
electricity (Nuuk, Sisimiut, Qaqortoq, Narssaq, Ilulissat, and Tasiilaq ). Part
of the produced electricity is used for electrical heating (in Nuuk, Sisimiut,
Qaqortoq, and Narssaq).
6
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0057.png
Figure 3. A settlement in Greenland.
In the
settlements
the power supply is less stable compared to the towns
because there are no emergency generators. Instead there are normally 3
diesel generators. In case of brake down of one, the two remaining shall
take over the supply. Outside the public areas supplied by Nukissiorfiit
there are private farmers and others who run their own generators. There
is no public heat supply in the settlements. The houses are heated by oil
burners or central heating systems based on oil. At some small localities
bottled gas or kerosene (petroleum) is used for heating.
The public water supply began in 1950 (in Narsaq). To-day Nukissiorfiit
supplies all the towns and 51 of the settlements with water. The drinking
water is normally taken from lakes. In 9 settlements reverse osmotic
plants are installed. In the settlements water is not normally installed in
the houses. Public drinking water tap facilities are instead available.
7
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0058.png
Energy production and use
In Greenland the main part of the public energy supply is delivered by
Nukissiorfiit as electricity and district heating. Up to 1993 oil was the only
fuel for the production of electricity and heat. Still oil is the dominating
fuel but its share is getting less from year to year. The public energy
supply is around 1/3 of the total inland energy consumption.
Since 1993 Greenland has been partly self - supplying with energy thanks
to hydropower plants and the use of heat from waste incineration.
Although there has been an increased self-production, Greenland is still
depending on imported oil, primarily
gas oil, kerosene and petrol.
Greenlands total inland energy comsumption was in 2013 8979 TJ(2500
GWh). Sustainable energy reached in 2013 the highest level ever - 15,5%
- of the total energy consumption. (Grønlands Statistik 2014)
Figure 4. Energy consumption in Greenland. Light blue curve : total
consumption.Dark blue graph: self- production. The right part of the
diagram shows the fuels applied.Green:sustainable energy; blue: gas-
and dieseloil;orange:kerosene;red : motor- and aviation petrol.
8
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0059.png
The fluctuations in the energy consumption – figure 4 - have different
explanations- one of these is the 20% increase in 2010 and 2011 due to
exploration drillings for oil and gas .
Figure 5. Energy consumption in different sectors. Energy- and water
supply uses 29%; agriculture, fishery, and hunting 21 %; households use
19% and transport,post,tele 15 %
9
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0060.png
Figure 6. Greenlands production of sustainable energy: hydropower (blue
color) and energy from incineration of waste ( green). Solar- and wind
energy is not included in the figure.
In 2013 the production of sustainable energy was
1395
TJ(388 GWh)
including loss in transmission system from hydropower plants. Heat from
waste incineration was
117
TJ(33 GWH) in 2013.
Hydropower production was in 2013
1278
TJ(355 GWh) ( incl loss in
transmission system) ( Buksefjord : 861 TJ; Tasiilaq , Qorlortorsuaq ,
Sisimiut , and Ilulissat :20 – 86 – 184 – and 128, respectively ( incl. loss in
transmission system
10
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0061.png
Energy prices
The electricity is sold to different prices depending on type of customers
and locality in the country.
An average price for all the electricity sold in Greenland (2013) is 2,44
DKK/kWh. (Grønlands Statistik 2014)
In 2013 a total of
1145
TJ(318 GWh) electricity was used. In this number
electricity for heating is a little above 300 TJ( 83 GWh).
The electricity was (2013) sold to different customers:
Normal consumers (households): 702 TJ(195 GWh)
Fishing industry (land based) : 119 TJ ( 33 GWh)
Electricity for heating (only Nuuk): 324 TJ(90 GWh)
Figure 7. Consumption of electricity for lighting and power (blue),
electrical heating (orange) and consumption of district heating ( green )
11
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0062.png
Until 2004 the prices were the same for electricity (like for heat and
water) all over the country – but since 2005 a gradually change towards
real cost prices has been in progress. In 2013 the highest price was 3,24
DKK pr kWh and the lowest 1,60 DKK- both prices for “normal
consumers”. For the fishing industry the highest and the lowest price was
3,24 and 0,66 DKK respectively. Electricity for heating is about 0,80 DKK.
Figure 8 . Consumer prices for different types of energy. Light green
graph: motor petrol DKK /L;orange: gas- and diesel oil DKK/L; dark green:
12
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0063.png
price for electricity for lightning and power DKK/ kWh; black: price for
district heating DKK/kWh.
Figure 9. Electricity sold for “normal consumers” (excl electrical
heating).First upper column gives the total amount (“samlet salg”)- the
two next columns is the amount sold in cities and settlements ,
respectively.
The figure illustrates where in Greenland the consumption is. The total
consumption in the settlements is less than 10% of the consumption in
the towns.
13
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0064.png
CO₂ Emission
Almost all CO₂ emission ( 94%) in Greenland comes from the energy
consumption. Waste incineration is considered CO₂ neutral in the
statistics in Greenland. For 2013 the emission was in total 555.000 ton
CO₂ equivalent . The variations with time can be seen in figure 10.
Figure 10. Total emission of green house gases from energy use. CO₂, CH₄
and N₂O are recalculated to CO₂ - equivalents.
Potentials : Hydropower
From roughly 1975 and onwards estimates on the hydropower potentials
have been made regularly (Thomsen 1996). In the beginning the purpose
14
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
was to produce estimates on the biggest potentials to find energy for
energy demanding industries such as mining, production of fertilizers
and aluminium . During the 1980´ ies the priorities were changed and
the hydropower studies were concentrated on “city- near potentials”and
minor basins which could replace or supplement the existing energy
production which was based on diesel for the Greenlandic cities.
The work was carried out by Greenland Technical Organisation (GTO),
which in 1989 was replaced by Nukissiorfiit (Greenlands Energy
Supply).Since then Nukissiorfiit has been responsible for the use of
hydropower in Greenland in a cooperation with Asiaq ( Greenland
Survey) and Greenland Geological Survey – now GEUS.
Most of the studies have only estimated the potentials in South Western
and Western Greenland (up to Uummannaq) and in a minor area in
Eastern Greenland where most towns and settlements are located -see
figure 11.
A total of 16 catchment areas with an annual potential of 13.000
GWh(46800 TJ) are shown in this figure. In the same area 15 minor
catchments are present and these are estimated to add 620
GWh/year(2200 GWh) to this value - given a total of a little less than
14.000 GWh /year (50000 TJ) in this part of Greenland. Although this
estimate is based on many years research work it must be stated that
especially the contribution of melt water from the ice cap is determined
with great uncertainty. It is recommended to update the estimated
potentials for hydropower since there has been major climatic changes
through the latest years.
Geological Survey of Greenland (now GEUS) estimated in 1994 a
theoretical maximum potential (“gross theoretical capability”) for
the ice cap
in Greenland. The estimate implies that all natural
15
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
water is taken from the locality where it is formed and via
turbines transported to sea level. A very theoretical value,of
course.
The result was about 470 Terawatthours/year.(1692000 TJ)
This type of estimation gives results far from the real available
hydropower energy, which can be applied only when the water
comes into hydrological catchment areas where hydropower
plants in reality can be constructed.
At the same time Asiaq (Greenland Feasibility Study) estimated
350 Terawatthours/year (1260000 TJ) for the
ice free part
of
Greenland. (Thomsen 1996).
16
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0067.png
Figure 11 : Hydropower potentials in West Greenland ( Thomsen 1996)
Blue areas indicate hydropower basins, black squares possible locatilities
for hydropower plants and black circles are observation localities for
water flow estimates operated by GEUS. (Geological Survey)
17
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0068.png
Potentials: Solar energy
Solar energy delivered to an area with optimum tilting in
Greenland (Sisimiut) is roughly the same as in Denmark
(Copenhagen), namely about 1160 kWh/m²year(1.7 MJ) (Andersen
et al. 2007)- see figure 12.
Figure 12: Comparison of monthly solar radiation in Copenhagen (red) and
Sisimiut (green).
The global radiation potential is high in the Arctic as indicated in
figure 13. (Andersen et al. 2007)
18
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0069.png
Figure 13: Global radiation in the Arctic on a horizontal surface.
19
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0070.png
Case story for a grid connected PV system in Sisimiut,Western
Greenland:
.
Figure 14. The monthly production of electricity is high during spring and
summer. Total annual production is around 7500 kWh (2013 and 2014)
which is 1,05 kWp/Wp . In Denmark you can typically expect 0,85- 1,0
kWh/Wp. The house in Sisimiut has an optimal localization: roof tilted 45
degrees, facing to the south and close to the sea which gives a god
refleksion. (data for 2014 not fully illustrated) (Larsen 2015).
20
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Potentials: Wind energy
The wind energy potential has been studied to some extent in Greenland
(Andersen 2007). The potential is considered
in general
to be of minor
interest.
Only the southern part of Greenland lies in an area with constant wind
load. The potential is not well known, however.
Local wind conditions governs in the rest of the country. Wind velocity
change from periods without wind to very heavy storm periods. The
precise placement of a wind turbine must be based on local (expensive)
measurements and the cost for the erection of a turbine is high – due to
infrastructure.
Consequently at present wind energy is – except for Southern Greenland -
considered to be only of local interest.
Greenlands data cable connection
”Greenland Connect” is the name of a sea cable project which was
carried out 2007 / 2008. (http://www.tele.gl/da).Alcatel Submarine
Systems got the job to establish the data transmission cable ( price 734
MDKK). It has a length of 4780 kilometers and links Nuuk/ Qaqortoq to
New Foundland ( Milton) and Iceland ( Landeyarsandur) – see figure 15.
21
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0072.png
Figure 15: Data transmission cable ( black) connects Greenland to the
west and to the east.
Future cable for transport of electricity.
1. Connection to the West
Iqaluit/Nunavut:
Probably inspired by the above mentioned data transmission cable and
the technical development of the HVDC concept ideas have been
described in Greenland for export of electricity either to the neighbours
to the west or probably to Europe – of course via Iceland. Also earlier
connections between Greenland and the neighboring countries have
been suggested.
22
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Support was given ( some 10 years ago) from the Nordic Council of
Ministers to a Nordic Working Group for “Renewable Energy in Sparsely
Populated Areas”. The group mapped renewable energy potentials in the
West Nordic Countries and arranged a symposium entitled “ Energy from
the Edge” in 2007. The overall focus for the Nordic Countries was to
stimulate the energy cooperation with Shetland Islands and Canada (
Nunavut) – the neighbour to the West (Sørensen 2008).
In the NAEN pre- feasability study we have decided to follow up on this
topic:
Looking to the west- Nunavuts capital -Iqaluit - is 800 km from Nuuk.
The population in Nunavut is small ( about 23.000 people of which 5000
live in the capital - Iqaluit) - and there is a strong need for energy .
Further investigations and discussions with the authorities of Nunavut
are needed to describe the potential, the social acceptance , and
rentability of a connection between Greenland and Iqaluit.
23
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0074.png
Figure 16 . Relatively short distance to the neighbour to the west. The distance
between Nuuk and Iqaluit - capital in Nunavut- is about 800 km .
24
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0075.png
Cable connection to Labrador:
Another target for a cable connection to the west might be to the area
in Labrador/Newfoundland where a major hydropower plant is under
construction ( Muskrat Falls Project). If a connection from Greenland
could be established there would be a possible link to the North
American grid and of course a huge market for selling energy from
Greenland. However the distance from Greenland is long ( 1000 km +)
and the ocean water depth is 2- 4 km. Also here further considerations
and studies are needed to support a link between Greenland and
Labrador.
Figure 17. Muskrat Falls hydropower project. A possible connection from
Greenland to North America?
25
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
2. Cable connection to the East.
Connection to Iceland.
The NAEN project mainly aims at creating connections between countries
east of Greenland. The distance between East Greenland and Iceland (
from Tasiilaq to Isafjordur) is about 500 km and the water depth is
not critical for the cable (800 m max). However there is at present only a
small hydropower plant in operation for the supply of Tasiilaq – and
sparse knowledge on the energy potential in East Greenland. If energy
should be transported from Iceland to East Greenland there are only few
consumers in Eastern Greenland.
A continuation of a cable connection from Iceland via East Greenland to
West Greenland where there are more consumers is a possibility. In
western Greenland there is a known and high potential for hydropower-
see fig 11.There might be found hydropower potentials in East
Greenland too in the future - but there is more than 500 km between
Tasiilaq and the southern cities in Western Greenland . The investments
for a connection between East Greenland and South/West Greenland will
be huge. However it should not be let out of the visions for the future.
3. Domestic cable connection in West Greenland.
We should remember that the main reason for linking the North Atlantic
countries with a cable is not to sell electricity to each other but rather to
reach other markets with energy developed in each of the countries.
Another possibility is to attract energy demanding industries and raw
materials to North Atlantic areas with big energy potentials.
26
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
These are long term perspectives for Greenland, of course. The efforts to
attract Alcoa to place an alumina smelter in West Greenland is part of this
scenario.
On a closer horizon another possibility, namely a domestic connection
between cities on the west coast seem to be more realistic for Greenland.
As earlier mentioned mapping of the hydropower potential in Greenland
has focused on “city-near “ localities. The annual production from city
near catchment areas was estimated to 400 GWh/year(1440 TJ)
(Teknologirådet, 2002) which is of course low compared with the total
potential in West Greenland of 14000 GWh /year (50000 TJ) which was
mentioned earlier.
In the area between Nuuk and Sisimiut the potential has been further
investigated and more precisely described during the last ca 10 years
to evaluate if the potential would be sufficient for a major hydropower
plant for industrial purpose ( Alcoa alumina smelter).
Recently Alcoa has expressed a decreasing interest in applying the
hydropower potential for aluminium production- and other potential
users are now been looked for.
An estimate based on precipitation and ablation from the icecap for 3
major catchment areas says that the potential is in total ca 4500
GWh/year( 16200 TJ)for the area between Sisimiut and Nuuk. This
potential is included in the total potential of 14000 GWh/year shown in
figure 11 – but it represents a better and more precise estimate on
which the planning could based .The 3 areas could be developed one by
one with hydropower plants depending on the need of electricity.
The map figure 19 below shows the area.
27
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0078.png
28
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Figure 19. Possible first phase of a domestic cable connection in Western
Greenland connecting Nuuk, Maniitsoq, and Sisimiut.
The figure shows an area in western Greenland between Nuuk and
Sisimiut, where a detailed study of the hydropower potential has been
carried out. The purpose was to find sufficient energy potential for an
alumina smelter. Catchment areas are indicated by dotted lines. 5
possible localities for hydropower plants ( grey squares) are shown
together with transmission lines ( black/ green/red/blue).Localities for
the alumina smelter (9 in total) are shown with a dark “industry
signature”.
It seems natural to look for a domestic and stable use of this
potential via a common grid for the city inhabitants in a combination
with industrial use ( smelters to handle imported raw materials , mining
in the area, production of building materials etc).
A HVDC connection or another type of connection between the cities on
the west coast – starting with Sisimiut, Maniitsoq, Nuuk would have
many benefits. Settlements close to the siting of the cable should be
connected to it , thereby giving an improved energy supply situation.
Benefits of a domestic cable.
The following points can be considered beneficial for the consumers
linked to a domestic cable in Greenland:
A more stable grid i.e. improved “quality “ of the electricity for all
categories of consumers
An expected lower price for electricity – which will give better
possibilities for heating houses directly or by using heat pumps.
29
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Lower consumption of oil for electricity production and for district
heating.
Lower CO₂ emission
Industry development a.o. the fishing industry will be stimulated
due to easier access to electrical energy
Greenhouse production of food articles which are imported to-day
could be economic attractive by cheaper electricity.
Land transport could favour electricity as energy source for cars.
Without road connections between cities the distances for cars
etc to drive are small and hence the recharging will not impede
the daily use of electrical vehicles.
Sustainable and clean energy supply for future mining industry in
the area –e.g the Isua iron occurrence close to the icecap near
Nuuk, possible nickel mining near Maniitsoq ,and the anorthosite
mine already under upstart between Maniitsoq and Sisimiut.
The cost of the cable and the construction of the hydropower plants are
two very essential factors. An economic plan is outside the scope of this
report. Pay back time for an investment that will last 40 years or more
should delineate the length of the cable and thus which parts of
Greenland could be linked within the project.
A further enlargement of the cable connection with the cities from South
Greenland to the Disko Bay area will need at least 1000 km of cable .
Nuuk – Maniitsoq – Sisimiut should be the first cities to be connected. (40
% of the Greenlandic population lives here).
A combination of societal use and industrial use of the electricity would
be optimal. Iceland was in the same situation 30 years ago as Greenland
is to-day as for solving the investment issue. An agreement with a major
30
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
industy consortium was part of the solution in Iceland. It started in 1966
with a contract with Alusiuisse regarding building a smelter ÍSAL in
Straumsvík for about 33.000 tons/year of aluminium. This contract
enabled Landsvirkjun to build its first large hydro power plant
Búrfellsvirkjun as the bulk of the electricity was already sold to Alusiuisse.
The settlements in Greenland which are closest to the cable should of
course be connected to it. But there will still be remote areas (cities and
especially settlements) in Greenland outside the new grid. These areas
should have improved the energy supply based on local sustainable
energy sources. Long connection lines and few customers may give bad
economy in part of the grid – such as it was demonstrated by a
hydropower rentability study in the area between Aasiaat and
Qasigiannguit ( Disko Bay area) ( Sørensen 2015).
Legal aspects
Hydropower is regulated by a Greenlandic law ( from 2009) . The
Greenlandic Government has a monopoly on the investigation and use of
hydropower resources. This is valid for potentials higher than 1 MW. The
government can allow companies to carry out investigations of potentials.
Results including data shall be reported to the government when the
study ceases.
Asiaq (Greenland Feasibility Study) has as a primary goal the study of
non- living resources as for example the study of hydropower potentials.
Nukissiorfiit (national company responsible for energy and water supply).
Main goal is the energy and water supply to cities and settlements and
not for energy demanding industry outside existing cities and
settlements.
31
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Final remarks and conclusions.
Greenland has a very big energy potential related to hydropower and
solar energy. Wind potential is considered to be of only local interest. The
abundant sustainable energy resources in Greenland are at the moment
stranded due to the isolated location of the country. Norway and Iceland
both started their energy export of power through heavy industry.
Greenland could follow this way.
The energy potentials are not known in details for Greenland as a whole
and more studies are needed to support and justify future investments.
However the hydropower potential in South West Greenland can be
estimated to 50000 TJ ( 14000 GWh/year). Compared to the
total
energy
consumption in Greenland which is (2013) a little less than 9000 TJ ( 2500
GWh/year) it is an enormous potential.
For an area between Nuuk and Sisimiut the hydropower potential is
known in more detail compared to the rest of Greenland.
Solar energy potential is high and at the same level as in for example
Denmark (1160 kWh/year pr m²).
The present project has focused on the future sustainable energy use by
connecting the North Atlantic Countries by HVDC (high voltage direct
current) cables.
It is technically possible to link either to the West – to Nunavut or
Labrador with a possible further connection to North America or link to
the East via Iceland and thereby with a possibility to reach the European
market. Greenland is at present not able to use these options due to lack
of economy and energy infrastructure.
32
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
The above mentioned better known hydropower potential between Nuuk
and Sisimiut is recommended used for establishing a first phase of a
Greenlandic national electricity grid. The first cities and settlements to be
connected should be Nuuk, Maniitsoq, and Sisimiut and the settlements
in this area .Connected to this grid should be mining and fishing industry,
and other heavy energy demanding industries which f.ex. upgrade
imported or local raw materials. The grid shall - depending on the need
and economic capability- in a later phase be enlarged to cover the cities
and settlements in the west coast of Greenland. A national grid will have
a lot of benefits for the country – such as a more stable electricity supply,
less CO₂ emission, reduced oil consumption, lower price for electricity,
and improved possibilities for new energy demanding industries.
An electrical grid as described here is expensive to establish and it is not
realistic that it can- within a foreseeable future - be covering all of the
country. Therefore focus should be also put on the development of local
sustainable energy solutions to be used in remote cities and settlements.
Included in this work should be improved insulation of houses as an
example of reduced energy demand.
Acknowledgements.
Economical support to the project has been given by Nordic Council of
Ministers and by the Greenlandic “VEK – pulje” (Governments grant for
supporting development of sustainable energy).
REFERENCES
Andersen Elsa, Furbo Simon, Hansen Kurt S., Hansen Martin ,
Kjeldmann Peter ,Larsen Esben,Nielsen Morten Holtegård,Villumsen
33
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0084.png
Arne ( 2006):
Fyrtårnsbygd-083 Sarfannguaq – Forprojekt. Nukissiorfiit /
ARTEK Januar 2007.
Greenland Connect (2008) :
Tele Greenland – press release
Grønlands Statistik ( 2014/2015) og Statistisk Årbog (2015) :
http://www.stat.gl
Larsen Esben (2015) :
Case story for grid connected PV system. Personal
communication.
Naalakkersuisut (2010):
Redegørelse om Vandkraftundersøgelser.
Departement for Boliger ,Infrastruktur og Trafik.- Nuuk.
Teknologirådet (2002):
Grønland savner teknologi. - Fra Rådet til Tinget
.Nr 168, maj 2002
Thomsen Henrik Højmark (1996):
Is og energi. – Temanummer.- GEUS nr
5 December 1996.
Sørensen Margrethe (2008):
Sustainable Energy Supply in the West
nordic Region-Policies and Visions.- Proceedings from the international
conference on sustainable Energy Supply in the Arctic- Sisimiut 2008.-
ARTEK.
Sørensen Jacob
(2015): Personal communication.
34
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0085.png
Appendix C
North Atlantic Energy Network
Iceland
Orkustofnun (OS) - National Energy Authority of Iceland
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
2
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Table of Contents
Introduction............................................................................................................................................. 5
Conclusions.............................................................................................................................................. 5
Earlier investigations and ideas ............................................................................................................... 6
Transmission system in Iceland ............................................................................................................... 9
Transmission reinforcement and cost for a connection in the eastern part of Iceland...................... 9
Production scenario ...................................................................................................................... 10
The landfall of the HVDC link......................................................................................................... 10
Grid reinforcement ........................................................................................................................ 11
The Highland connection............................................................................................................... 11
Reinforcement of the current 132 kV circle .................................................................................. 12
Cost for the connection ................................................................................................................. 13
Pros and cons for the Icelandic transmission system ....................................................................... 13
Landsnets role regarding Interconnectors ........................................................................................ 13
Interconnector up to 1,000 MW ........................................................................................................... 13
Landfall and the effects on the grid’s development ......................................................................... 14
Landfall in the Eastfjords ............................................................................................................... 14
Landfall in the South...................................................................................................................... 16
Other landfalls ............................................................................................................................... 17
Things to be concidered .................................................................................................................... 17
Electricity production ............................................................................................................................ 18
Electricity market .................................................................................................................................. 22
Benefits.................................................................................................................................................. 22
Potential ................................................................................................................................................ 22
Timescale for each energy source ......................................................................................................... 23
Environmental issues concerning a submarine cable ........................................................................... 23
Borders .............................................................................................................................................. 24
Economic gain ....................................................................................................................................... 24
CO
2
emission.......................................................................................................................................... 25
Legal perspectives ................................................................................................................................. 26
Regulation of the operation of undersea cable .................................................................................... 27
Weather systems in the North Atlantic................................................................................................. 27
References ............................................................................................................................................. 27
3
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
4
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Introduction
This report is an appendix to the report North Atlantic Energy Network (NAEN), on various alternatives
for connecting the electrical systems of Greenland, Iceland, Faore Islands, Shetland and Norway via
subsea electric cables.
Iceland is an island in the middle of the North Atlantic Ocean, the settlement of which dates back to
around 870. Iceland has about 330,000 inhabitants and the majority, or over 200,000 people, are
located in the southwestern part. Iceland is 103,000 km
2
and it is both difficult and expensive to build
up infrastructure like roads and a transmission system that cover long distances.
Iceland’s electricity production is almost 100% from renewable sources and there are possibilities to
increase its installed capacity in hydro, geothermal and wind power. Iceland also has potential for tidal
power but this has not been explored on a commercial basis. This report gives an overview of the
production, transmission and prices of electricity in Iceland, and sheds light on what needs to be
investigated further if a cable connection to other parts of the world is to be realized.
Conclusions
It is technically possible to connect all of the neighbouring countries around Iceland with subsea cables.
Iceland now produces about 18 TWh of electricity per year and could have the potential to double
production from geothermal and hydropower alone. This could be constrained by economy and
environmental and socio economic aspects. The total capacity of power generation for wind has not
been explored and the same can be said about other renewables such as tidal and solar power.
Electricity from Iceland could significantly contribute to saving CO
2
emissions in other European
countries even if it will always be only a limited part of the European system.
There are many unclear aspects that need to be investigated further to draw a full picture of the pros
and cons of interconnectors from Iceland. The legal and regulatory framework must be in place before
a project of this kind can be realized. Even if we had social acceptance for increased electricity
generation, a long term investment such as this requires stable economical conditions secured by the
governments involved. The alternative is to move energy intensive processing industries to Iceland as
has been done successfully in the past.
The largest unknowns are energy politics and policies in Iceland and Europe. Social and environmental
issues also need to be looked into in more detail. Export of electricity from Iceland would implicate a
certain environmental cost. More data is needed to be able to verify if the environmental and social
cost is outweighted by financial gain and positive environmental impact in the receiving countries.
In the beginning of the project, the idea was to find out if a 100 to 200 MW cables were a feasible
choice for interconnectors. It turned out that (see main report) that because of the cost of laying the
cables and the losses it is not financially feasible for long stretches to lay cables with low capacity.
As the current installed capacity in Iceland is 2,500 MW, adding a cable of 1,000 MW is a large increase
in comparison to the existing electricity market in Iceland and the risk involved needs to be mitigated.
At least three different types of contracts are possible; a regulated cable, merchant cable and a cap
and floor model. The ownership and contract type can make a big difference in regards to what the
outcome will be.
Norway is a leader in long distance subsea interconnectors with the largest cable NorNed between
Norway and Netherlands. The power system in Norway is fourteen times larger than the system in
Iceland with installed power of 34 GW. The relative risk for the economy and system operation in
5
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Iceland by adding a cable of 1,000 MW is much larger than for Norway. However, an interconnector
could improve the energy security and efficiency of the electricity production in Iceland. Cable
connection from Iceland to other parts of the world gives rise to opportunities to utilize the renewable
energy potential of Iceland and can also enhance the energy sercurity. In an island system the installed
power needs to match peak demand which otherwise is unused throughout the year. This excess
capacity could be put to good use through a subsea cable.
Extensive grid reinforcements are needed to support export through a cable at a single connection
point in Iceland. Even if a converter station provided fast acting reactive power and thereby supported
the transmission system by regulating the voltage power factor, the main problem of the Icelandic
power system would not be cured. Transmission between areas within Iceland is limited to 100 MW in
the current system which thus can not support export through a 1,000 MW link, except for production
stationed close to the landfall.
Earlier investigations and ideas
For over half a century there have been discussions regarding a cable connection between Iceland and
UK. Iceland has potential for additional 35 TWh of renewable energy and UK is in search of renewable
resources. A 1,000 MW connection to UK is under discussion and a survey between Iceland and UK
was conducted last summer (2015) by a company called Atlantic Superconnection Corporation.
In June 2012 a counceling group was established by the Minister of Commerce and Industry, with the
role of investigating the socio-economic aspects of a subsea cable as well as technical, environmental
and legal aspects. The group delivered a report in 2013 (Iðnaðarráðuneytið, 2013) where, among other
things, it was established that an interconnector between Iceland and Europe could be profitable, but
the outcome had a very large, reflecting all of the still existing uncertainties for the prerequisites.
The parliament, Althingi, discussed the report and decided that the matter should be investigated
further. Consequently, the Ministry of Industries and Innovation defined eight different tasks which
are being looked into in more detail, an administrative committee was established for that purpose.
The eigth tasks are:
1. A thorough estimate of the influence of a subsea cable on commerce, industries and homes,
based on cost and benefit analysis.
2. Environmental assessment according to Act No. 105/2006 on Strategic Environmental
Assessments.
3. An estimate of the electricity needs of current companies, heavy industry and new
establishments in the coming years.
4. An estimate of how many power plants need to be built, if and how present power plants can
be better utilized with the existence of a subsea cable and what power plants would be needed
to sell electricity through a subsea cable.
5. A study of different scenarios regarding the development of the energy market in Europe.
6. A study of technical issues regarding laying a subsea cable and possible contribution by the
other party.
7. An investigation of Norway’s experience with subsea cables.
8. An estimate of the utilization of land and operation of small power plants.
On the 28
th
of October 2015 the Prime Ministers of Iceland and UK, Sigmundur Davíð Gunnlaugsson
and David Cameron, agreed to launch a working group to investigate the possibilities for an
interconnector between the countries. Consequently, the administrative committee for the eight tasks
6
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
described above was expanded by two members, one from the Ministry of Finance and one from the
Prime Minister’s Office and the reformed group will take on the role of this working group on behalf
of Iceland as the ninth task. The completion of all these tasks is estimated to be May 2016.
The Icelandic government is not the only one looking into the idea of a subsea electrical cable between
Iceland and UK. The British Icelandic Chamber of Commerce organized a public seminar in September
2015 called: Interconnecting interests aimed to examining the issues surrounding a potential
submarine cable that might supply the UK and Europe with Icelandic green energy. The speakers at the
meeting were Bjarni Benediktsson, Minister of Finance; Dr. Douglas Parr, Chief Scientist and Policy
Director at Greenpeace UK; Edward M. Stern, President and CEO of PowerBridge, LLC; Charlotte
Ramsay, Head of Commercial Regulation & New Business at National Grid, European Business
Development; and Hörður Arnarson CEO of Landsvirkjun.
The representatives from UK were all in favour of a cable connection between Iceland and UK,
including the representative of Greenpeace. Mr. Stern from USA stated that conditions for financing a
cable were favourable today, and he was positive that with the right expertise and partners it could be
financed in such a way that the project would prove to be profitable. Two additional public meetings
regarding interconnectors have been held in Reykjavík since this seminar and the interest regarding
the subject seems to be growing.
The idea of a cable network like the NAEN project is not new. The CEO of Orkustofnun at the time,
Jakob Björnsson (Björnsson, 1993), wrote an article titled North-Atlantic Power System (NAPS). The
article describes an interesting multi-terminal HVDC system, consisting mostly of submarine cables and
AC/DC converter stations connecting the DC system to the AC system of the countries involved. This is
a very ambitious idea which is best described with a picture from the article.
7
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0092.png
North-Atlantic Power System (NAPS): Orkustofnun (National Energy Authority). 1993. A
Concept of a North-Atlantic Power system (NAPS). (Björnsson, 1993).
8
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0093.png
Transmission system in Iceland
Landsnet owns and operates all major electricity transmission lines in Iceland. The bulk transmission
system (“the grid”) consists of power lines with voltages of 66 kV and higher, some 33 kV lines and all
major substations in the country.
The Icelandic transmission system in 2015.
The total length of the transmission lines in Landsnet’s system is about 3,200 km where two thirds
belong to the main system that connects production to usage. The transmission system is
characterized by a strong 220 kV network in the south-west part of the country, a weak 132 kV circle
with long transmission lines around the country and some local 66 kV networks. Also in the east, where
the chosen landfall for the NAEN project is, there is a strong 220 kV “island” with a 690 MW hydro
power plant and an aluminium smelter.
The installed power capacity of the power plants connected to the grid is 2,593 MW where 80% is
generated with hydro power and the rest is thermal power. Over 60% of the power production is in
the south-west part and over 30% in the north-east.
Transmission reinforcement and cost for a connection in the eastern part of Iceland
The chosen landfall in this analysis for the NAEN-Link is in the eastern part of Iceland. Due to the
location of the landfall with respect to the production scenario, some reinforcement of the
transmission system is required to be able to deliver up to 150 MW to the interconnection and fulfil
an N-1 level of security. The reason for this is that the transmission capacity between regions in the
present transmission system is insufficient due to low transmission capacity in transmission lines
between the north and south east parts of Iceland.
9
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0094.png
Production scenario
In order to estimate the production needed to supply the NAEN-Link, the link is treated as a 100-150
MW user. For this size of a user it is assumed that the power can be delivered from the grid. This
evaluation is based on the present Master Plan for Hydro and Geothermal Energy Resources in Iceland,
if 50% of the feasible energy resources according to the present Master Plan are realized. The 50% of
the feasible energy resources is one of the scenarios that Landsnet bases their grid reinforcement plans
on and is one of the scenarios that could provide the NAEN-Link with energy.
Estimated production increase in MW if 50% of feasible energy resources are realized.
The landfall of the HVDC link
In this study a landfall in the eastern part of Iceland has been chosen as it is the most natural position
of such a connection. However, in previous studies on an HVDC link to Iceland, three different landfalls
have been investigated. The two additional landfalls are located on the South-East Coast and on the
South Coast of Iceland.
10
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0095.png
Three possible landfalls.
The connection on the southern shore connectes to a stronger point in the Icelandic power system,
but a connection on the eastern shore makes the sea-cable shorter.
Grid reinforcement
Landsnet is already planning to reinforce the grid with a 220 kV connection between the north-east
area and the south-west area. There are two main options for this reinforcement with some variations:
A. The Highland connection where new transmission lines connect the southern, northern and
eastern part of the system crossing the highland.
B. Rebuild the circle around the country.
The options and variations are evaluated with regard to stability, flexibility, power delivery, short-
circuit power, security, proximity to power production and losses.
The Highland connection
The Highland connection is based on new transmission lines across the highland of Iceland as
illustrated in the following figure. The first variations (A.1) scores highest in the evaluation whereas
the other variations are less viable.
11
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0096.png
A.1
A.2
A.3
A.4
Variations of option A, the Highland connection.
Reinforcement of the current 132 kV circle
This option is based on reinforcment of the existing 132 kV circle around the country, the variations
include either new 220 kV or 132 kV transmission lines parallel to the existing ones, upgrade of the
existing lines to 220 kV or combination of both variations.
B.1
B.2
B.3
B.4
B.5
Variations of option B, Reinforcement of the current 132 kV circle.
Here the B.1 scores highest in the evaluation.
12
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Cost for the connection
A rough cost estimate for options A and B indicates that the total cost for option A is about 40-50 bn
ISK whereas option B costs around 60-70 bn ISK. The main reason for this cost difference is that the
transmission lines needed to reinforce the grid in option B are much longer than in option A. The
variation in the estimation is due to different technologies used, e.g. underground cables or overhead
lines.
Pros and cons for the Icelandic transmission system
The main advantage of the NAEN link for the Icelandic transmission system would probably be the
implementation of an HVDC converter station to the grid. The converter station would provide fast-
acting reactive power on the transmission system and thereby support it by regulating the voltage,
power factor and harmonics.
The main problem with the Icelandic transmission system is, as mentioned before, the limitation on
transferrable energy between areas. In order to maintain the reliability and stability of the system it is
necessary to strengthen the transmission capabilities of energy between areas, especially between
east and west. As the main system around the country consists of rather long and weak 132 kV
transmission lines, a single failure somewhere in the system can cause severe instability problems if
the transmission lines are heavily loaded.
The disadvantage of the link for the current transmission system would be during energy export with
the link. Any export through the link would increase the loading of the transmission system thus
increase the risk for any instability issues. This disadvantage will be reduced should any of the grid
reinforcement plans be realized in the near future.
Landsnets role regarding Interconnectors
Currently Landsnet has no role regarding interconnectors. According to the Icelandic Energy Law
65/2003 its role is to develop the transmission system in a cost effective manner, taking into account
the safety, efficiency, reliability of supply and quality of electricity.
Interconnector up to 1,000 MW
A 100-150 MW interconnector may not be feasible due to its relatively small size. Thus a 1,000 MW
interconnector has also been investigated. This is relatively small compared with the largest
connections, although it is a fairly large part of the installed capacity of power plants in the current
grid (which is around 2,500 MW). This alone makes it impossible to directly replicate methods used
elsewhere into the local environment.
Throughout the years, Landsnet has pointed out that the current electrical transmission system is at
its tolerance limit, and its renewal and reinforcement are necessary, whether a marine cable abroad is
constructed or not. Ideas for future development are, for the most part, variations of two basic paths;
on one hand the connection between North and South Iceland across the highlands, along with the
further development of the transmission system in the North and the North-East; and on the other
hand the development of a new circle transmission network around the island.
The premises for these two basic paths do not include a marine cable, with a transmission capability
of 1,000 MW, to be connected to the transmission grid. Landsnet has been working on system analyses
and research to map out the need for necessary reinforcements for connecting to a marine cable, apart
from the two possible paths included in the Grid Plan. The production premises for these analyses are
largely based on the utilization category of the Master Plan for nature conservation and energy.
13
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Landfall and the effects on the grid’s development
Several possible landfalls for a marine cable have been looked at, from the Eastfjords of Iceland and
along the southern coastline. A landfall in the Eastfjords would be economical in terms of the overall
length of the marine cable. However, a landfall there would demand great reinforcements for the
transmission system, as the majority of new power harnessing options, which the research is based
on, are located in the South-West and North, and current grid connections from there to the East are
weak. A landfall in the South, however, would mean a significantly longer marine cable route, but less
reinforcement of the grid as a landfall in the Eastfjords would entail, as the South is the strongest part
of the grid, and the area also contains the most power harnessing options. Other options fall in
between the two.
How to secure the necessary strengthening of the grid, in order to maintain full security of supply
through the marine cable, has been researched with these possible landfalls in mind. The focus has
been on the necessary development of the grid between the regions. Reinforcements that might be
necessary within each region have not been elaborated on, as a realistic estimate would require further
information on the power harnessing plants and the harnessing options that would be utilized. An
estimate regarding the arrangement of the connection between the landfalls and the grid has not been
made.
Landfall in the Eastfjords
Development options of the transmission grid, vis-a-vis a landfall of a marine cable in the Eastfjords,
have been investigated, both from the point of view of a highland route and an inter-regional circle
line on the other. These routes are based on the same premises as the future development of the grid.
The aim of the analysis was to evaluate if, and then how much, the grid would need reinforcement
above and beyond these basic grounds, so that it would be able to handle the transmission required
for the marine cable. Due to the demand for full security of supply to the marine cable, it is necessary
to maintain a double connection to the landfall, even though a 400 kV transmission system were to be
constructed. Transmission of up to 1,000 MW to the cable is so great that using a 220 kV system is not
realistic, if the landfall were to be in the Eastfjords. The reason is the amounts of voltage drop in the
system, as so much of the energy needs to be transmitted from the southern parts of the country.
Building two 220 kV lines that could carry a greater load is not a solution either, double 400 kV lines
must be constructed, instead of single 200 kV lines.
Next figures show how development options for marine cables comply with plans for the future
electrical grid.
14
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0099.png
The development of the grid, taking a marine cable into account and the future grid
(option A), Landfall in the eastfjords.
The development of the grid, taking a marine cable into account and the future grid
(option B). Landfall in the eastfjords.
In both cases, the grid must be significantly reinforced beyond what is included in the planned future
development. Given that the maximum power, 1,000 MW, and the demand for N-1 security of supply
to the line, the results of the analysis show that there would always be a need for double 400 kV lines,
15
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0100.png
instead of simple 220 kV lines, from the South and/or South-West to the landing area in the Eastfjords.
Power requirements call for the voltage level and the security of supply of a double line. By relaxing
the demand for N-1 security of supply, one could get by on a single line, but it would nonetheless have
to be 400 kV.
Landfall in the South
Delivery to a marine cable, which would be connected to the grid in the South (a non-specific location
in the Thjórsá-Tungnaá area), was analyzed, using the same premises as for a possible landfall in the
East. As mentioned earlier, connecting a marine cable into the grid in the South is well suited in terms
of available power harnessing options.
For the transmission of up to 1,000 MW, it would suffice to build 220 kV lines between the regions (the
North-East and the South). To maintain an N-1 security of supply through the cable, they would have
to be doubled, but their transmission capacity wouldn’t have to be more than is already planned in the
Grid Plan premises (i.e. given the production premises).
If a highland option were chosen, the 220 kV connection would have to be doubled between the power
harnessing areas in the North-East and the South with 400 kV lines instead of 220 kV, as shown in next
figure.
The development of the transmission grid, taking inot account a marine cable and
future grid (option A) Landfall in the south.
The Inter-Regional Transmission Network is, by its very nature, a double connection between the
power harnessing areas in North-East and South Iceland. Analyses have shown that there is no need
for further strengthening, above what is already planned for future development based on option B,
given that the Network is completed in full. The variations of option B that include a voltage level
upgrade of the current Network to some or full extent are ruled out.
16
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0101.png
The development of the grid, taking into account a marine cable and the future grid
(option B). Landfall in the south.
Necessary reinforcements of the 220 kV grid in the South and the South-West are not discussed here,
as this would depend on the exact location of the marine cable’s connection to the grid as well as the
location of new power harnessing options. One can assume that such reinforcements will be needed,
first and foremost to increase the transmission capacity. Neither has it been investigated how the
transmission from the landfall to the grid would be arranged.
Other landfalls
As mentioned earlier, one can assume that other landfalls, between the South and the Eastfjords,
would be a varying mixture of the two options. The landfall would always require a double connection,
both of which would have to be able to handle all of the transmission.
What is mentioned here above is vis-a-vis the export of electricity through a marine cable. All plans for
the operation of the marine cable assume that for the majority of its operational period, the electricity
will be exported. The domestic system, however, must be prepared for import. For the most part, the
same principles apply when energy is transported into the country. The majority of energy is used in
the Southwest corner of the country, and to transmit energy to that area from the landfall, one would
need the same kind of transmission system as for export.
Things to be concidered
The debate in society on whether or not to construct a marine cable to other countries has become
more prominent over the past few seasons. People have varying opinions on the construction of such
a cable, and therefore it is important that all decision be based on as trusty a ground as possible.
Landsnet’s research has been concentrated on analysing the big picture domestically, that is to say to
compare a few options based on the same premises, and taking into account the need for future
developments of the grid. These studies have not included possible changes in electricity use, beyond
what is set forth in the electricity forecast. The exact implementation of how the marine cable should
17
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
be connected to the grid has not been examined. Neither has there been an in-depth analysis of which
harnessing options need to be activated due to the project, nor their future connections to the grid.
A demand for higher security of supply to the cable, that is to say that the required energy is available
on a N-1 principle, means that the delivery point must have two connections, as discussed earlier.
A more in-depth analysis is needed as to how the Icelandic electricity system can react due to sudden
changes in the cable’s operations, for example how quickly the flow could be reversed (from export to
import) and also, if the cable were suddenly to become disabled during a time of great export. It is
important that domestic electricity users be not overly disturbed by such events. In reality, the marine
cable would be comparable to a power-intensive consumer, although it would be somewhat larger
than the biggest users within the current system.
According to the rough picture revealed here, the Icelandic grid must be reinforced if it is to be able to
handle transmission to the landfall of a marine cable, given the premises listed here. The grid
reinforcements needed, i.e. above the ones already suggested by Landsnet for the future development
of the grid, range from relatively minor to quite significant. However, it must be emphasised that there
are still many unclear variables regarding the project. Location, size, and the nature of new power
harnessing plants (i.e. wind, hydro, or geothermal), can significantly impact the need for
reinforcement. Also important are points of view regarding, on the one hand, a lesser reinforcement
to the grid and, on the other hand, a longer marine cable. Furthermore, factors such as the quality of
the landfall and environmental effects on both sea and land must be considered. The analysis that
Landsnet has concluded is only in terms of the necessary strengthening of the domestic grid.
It should not be forgotten that this strengthening of the grid would also be beneficial in addressing the
increased domestic load. Dependability and security of supply of the grid would significantly improve
in general, and it would become better equipped to receive electricity and deliver it to the end users.
Electricity production
The capacity of renewable electricity production in Iceland is a little less than 2,000 MW in Hydro
power, 665 MW in geothermal power and 3.2 MW in wind power. Diesel power accounts for about
0.01 to 0.02% of electricity production in Iceland and is mainly used for backup power. Hydro power
provides around 13 TWh, Geothermal about 5 TWh which gives about 18 TWh of electricity production.
Utilisation of wind power started in the year 2011 but research has shown that there is a great
potential for harvesting wind power on land. The majority of electricity production in Iceland is in the
hands of three companies, Landsvirkjun, ON and HS Orka. Landsvirkjun owns the majority of the hydro
power plants but the main source of energy for ON and HS Orka is geothermal. Capacity belonging to
RARIK is purely diesel generators for backup power.
18
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0103.png
MW
2500
Installed capacity in Iceland in year 2014
2000
1500
1000
500
0
HS Orka
2014
176
Landsvirkjun
1991
ON
435
Orkusalan
37
Orkubú
Vestfjarða
37
RARIK
41
Aðrir
40
Production company
Installed capacity in MW of each production company in Iceland in year 2014.
Production of each production company in 2014
GWh
Other producers 152 GWh; 1%
Orkusalan 277
GWh; 2%
HS Orka 1.337 GWh; 7%
ON 3.443 GWh; 19%
Landsvirkjun 12.810 GWh; 71%
HS Orka
Landsvirkjun
ON
Orkusalan
Aðrir framleiðendur
Production in GWh of each production company in Iceland in year 2014.
19
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0104.png
Landsvirkjun, the largest power company in Iceland, produces 71% of all the electricity used in Iceland
and the majority of that power is hydro power.
Electricity production in Iceland in 2014
Fuel 0,01%
Gethermal 28,91%
Hydro 71,03%
Wind energy
0,05%
Fuel
Geothermal
Wind
Hydro
Origin of the electricity production in Iceland in year 2014.
Electricity consumption in Iceland in year 2014
Distribution systems 715 GWh; 4%
Services 1129 GWh; 6%
Agryculture 229 GWh ; 1%
Ferro-alloy 970 GWh; 6%
Homes 842 GWh; 5%
Industry 709 GWh; 4%
Fishing industry 48 GWh; 0%
Aluminium production 12,440 GWh; 74%
Fishing industry
Ferro-alloy
Homes
Agriculture
Industry
Services
Aluminium plants
Distribution systems
Electricity consumption in Iceland in year 2014.
20
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0105.png
Aluminium production in Iceland accounts for 74% of all the electricity usage in the country and is a
way of exporting the natural resources without a subsea cable connection. This has many advantages
as the usage is very steady, based on long term contracts and the bulk load in the system is rather even
through days and seasons.
Energy load in the power system in Iceland in year 2013 (Orkustofnun, 2013).
The dark blue pattern in the figure, Energy load in the power system in Iceland in year 2013, shows the
priority load in the system and the light blue line shows the controllable load. As can be seen 200.000
kW out of max 500.000 kW load are steady throughout the whole year.
GWh
20.000
18.000
16.000
14.000
12.000
10.000
8.000
6.000
4.000
2.000
0
1970
1972
1974
1976
1978
1980
1982
1984
1986
1988
1990
1992
1994
1996
1998
2000
2002
2004
2006
2008
2010
2012
2014
Developement of electricity production in
Iceland since 1970
Year
Development of electricity production in Iceland since 1970.
21
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0106.png
The electiricity production in Iceland has been growing steadily since 1970 and in 2007 there is a jump
in the graph when the third aluminium plant in Iceland started ramp up to full product production in
2008.
Electricity market
Market prices are not publicly available in Iceland except for homes; the price pr. kWh for Icelandic
homes is about 5.3 ISK (0.27 DKK or 0.036 EUR). Most of the production capacity is tied up in long term
contracts so the market as a whole is not very active.
Benefits
The benefits of a North Atlantic Energy Network for Iceland may wary in light of how it will be built up
and how market conditions develop. Different parts of the network have different benefits for Iceland
and all the other countries involved in the NAEN project.
Iceland is an island and therefore the electrical system is also an island system. As the capacity of the
power plants in Iceland is over 2,500 MW a connection through the NAEN network is not seen as a
backup power unless the cable capacity is considerable. None the less if some catastrophic events
would happen in the geologically active mid-section of Iceland where the majority of power production
is today it might be very helpful to be able to have access to some power through a cable connection.
Electricity prices in Iceland are low compared to the rest of Europe and market conditions are those of
oligopoly. A real, well functioning market could emerge if an interconnector of a sufficient capacity
opened up business to other parts of Europe. The downside of an interconnector is mainly twofold;
very likely the prices of electricity would go up and the energy sold through a cable would not be used
to contribute to the labour market in Iceland.
The benefits for Iceland largely depend on how the profit and risks in a project like this are distributed.
Potential
Iceland has a potential for increased use of geothermal, hydro and wind power. As the wind intensity
is highest in the winter time in Iceland when water level in the reservoirs is going down, the
combination of wind and hydro can be profitable for the power system.
As windfarms may have different production capacity at a given time in Iceland, Shetland and Faroe
Islands, combining production of wind power from different locations with hydro power in Iceland,
Norway and possibly Greenland may give favourable results. The Met Office (Nawri et al., 2013) in
Iceland estimates that a preliminary study of existing data to show if and how average wind changes
between areas could be prepared in a couple of weeks.
Landsvirkjun has introduced plans for a 200 MW windfarm in the vincinity of Búrfell power plant at a
place called Hafið and a 100 MW windfarm in the vincinity of Blanda power plant. Iceland’s potential
for using wind power has been documented in a wind atlas provided by the Met Office
(http://vindatlas.vedur.is/). The report, Wind Energy Potential of Iceland (Nawri et al., 2013), also gives
a clear overview of the possibilities for wind power.
The two biggest wind turbines in Iceland that Landsvirkjun has set up at a location called Hafið have
been producing electricity since February 2013. Operations have been reported by Landsvirkjun to be
beyond expectations, with average capacity factor approximately 44% and operational availability
nearly 98%.
22
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Timescale for each energy source
The timescale for building geothermal and hydro power plants is a couple of years (three to four years)
following thorough research which again may take decades. The timescale for setting up a wind turbine
can be relatively short and basic research on wind energy potential is available for all of Iceland.
Lifetime for power plants of these different energy sources is 40 years for hydro, 25 to 30 years for
geothermal and 20 to 25 years for wind turbines.
Environmental issues concerning a submarine cable
A submarine cable can influence its environment in many ways (OSPAR, 2009). The influence differs
between different periods in the cable lifecycle. The impact is short term during laying, repair or
removal of a cable but long term during the operation of the cable.
Impacts during operation are mainly from electromagnetic fields and heat. The electromagnetic impact
diminishes rapidly with distance and the cable type and how it is laid can make a difference. The
electromagnetic impact can be minimized by using the correct type of cable with a bipole
configuration, by burying the cable and keeping a minimum distance between cables.
Increase in temperature very close to a cable can effect living organisms and it is necessary to take this
into consideration during the design of the cable.
Environmental impact is more complicated during laying, maintenance, repair and possible removal of
a cable. Possible environmental impacts include disturbance at the seabed, visible influences, noise,
exhaust, waste from ships and tools for laying the cable.
It is very difficult to prevent disturbance at the seabed during the laying of a cable. Therefore, it is
crucial to choose the route carefully and avoid areas where it takes living organisms a long time to
regrow. Areas that are crucial for reproduction of living organisms should also be avoided.
A cable route in areas of soft sediment will lead to artificial introduction of hard substrates. The
submarine cables themselves will also provide a solid substrate for variety of species.
Information regarding the ocean around Iceland is limited in regards to the seabed and living
organisms. Possible routes for cables in this area must be investigated thoroughly to try and avoid cold-
water coral habitats and other biologically important areas, as well as areas that are important to the
livelihood of fish stock like spawning grounds etc.
In the conclusions of the OSPAR report (2009), there are guidelines as to mitigation measures and
removal of cables when they are out of operation.
Regarding various topics that need to be looked into, it is unclear what data are available concerning
various issues. At best the data available are fragmentary. A committee regarding these issues is being
formed and these matters need to be clear at least for the routes under consideration for cables from
Iceland. As for this project, the first step to investigate who has relevant data is underway. Many
institutions have parts of the available information, such as the Marine Research Institute, the Icelandic
Coast Guard, the Environment Agency of Iceland, the Icelandic Road and Coastal Administration, the
Directorate of Fisheries and the Icelandic Institute of Natural History. A full overview of the available
data is not yet complete.
23
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0108.png
Borders
National and administrative borders are clear as Iceland is an island and has custody over the area
shown in the map below from the Icelandic Coast Guard.
Map of of the Icelandic Exclusive Economic Zone (Landhelgisgæslan, 2015).
Economic gain
Looking at the household prices in Europe in 2012 according to
http://www.iiea.com
and comparing
them to the prices in Iceland, reveals a huge price difference (IIEA, 2014). The weighted average price
for consumption band DD was 14,74 ISK in 2012, which, with an exchange rate of 160,7 ISK pr. EUR,
amounts to 0,092 €/kWh. The average price of the 27 EU countries was at that time 0,178 €/kWh, and
thus the electricity prices to households in Iceland were only half of the EU prices in 2012.
This price difference can amount to profit for energy sold through interconnectors from Iceland if the
connection cost itself is less than the price difference. This again may cause opposition from the
general public as one of the pluses of living in Iceland are low electricity prices.
24
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0109.png
Houshold electric prices in the EU.
CO
2
emission
CO
2
emission from electricity production in Iceland is not seen as a great problem as the majority of
electricity comes from hydro power and a large portion is geothermal power where sulphur is more of
a concern than CO
2
.
25
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0110.png
One of the largest power companies in Iceland, ON, runs a project called CarbFix, which has the primary
goal of imitating the natural storage processes of CO
2
already observed in basaltic rocks in Icelandic
geothermal fields. This project may help mitigating global warming as basaltic bedrocks with potential
for storing CO
2
are widely found on the planet.
CO
2
in kiloton emission in Iceland in the years 1990-2012
4000
3500
3000
2500
2000
1500
1000
500
0
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
Year
Total emmision resulting from human activity, without capture
Indutrial procedures
Waste
Geothermal power plants.
CO
2
emission in Iceland in the years 1990 – 2012.
The increase in CO
2
emission in the years 2006 through 2008 is mainly due to the ramp up of the third
Aluminium factory on the East Coast of Iceland.
Legal perspectives
In Iceland, there are no specific laws regarding high voltage electrical cables in the sea. Act No. 41 from
1979 regards the territorial waters, economic zone and continental shelf, and according to Paragraphs
9 and 10, research regarding these waters are required to be approved by the Icelandic government.
Act No. 65 from 2003 covers issues regarding production licenses, transmission, distribution and
business transaction in Iceland in regards to electricity. EU regulation regarding sale of electricity
between countries have partly been enforced through EEA agreement.
In 2013, specialists on behalf of the Ministry of Industry and Innovation regarding laying of a submarine
cable wrote a report (Iðnaðarráðuneytið, 2013) were it is stated that Icelandic law does not specifically
cover the laying of a cable between two countries.
26
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
In the report, the legal issues in Europe are discussed along with models for a cable connection to the
UK. Models mentioned are feed-in tariffs with contract for differences, bilateral long-term agreements,
as well as the NEMO system.
Regulation of the operation of undersea cable
There is no legislation in Icelandic regarding the operation of an undersea cable.
Weather systems in the North Atlantic
Interest in harvesting wind power in Iceland is increasing so wind may potentially become a greater
source of electric power in Iceland in the future. It would be interesting to investigate if there is an
additional benefit to interconnect Iceland, Faroese Islands and Shetland from the point of view that
weather conditions may be out-of-sync so that maximum production capacity by wind power may vary
between these locations.
References
Björnsson, Jakob (1993).
A Concept of a North-Atlantic Power system (NAPS).
Reykjavík:
Orkustofnun.
Iðnaðarráðuneytið. 2013.
Raforkustrengur til Evrópu, Niðurstöður og tillögur ráðgjafahóps
iðnaðar- og viðskiptaráðherra.
Reykjavík: Iðnaðarráðuneytið.
IIEA (2014). Household Electricity Prices in the EU. http://www.iiea.com (on the 28
th
of April 2014)
http://www.iiea.com/blogosphere/household-electricity-prices-in-the-
eu?gclid=CjwKEAjw3_ypBRCwoKqKw5P9wgsSJAAbi2K9lhqghkVxEQCqv-jMgsz-
IOwzeoUtT0E_qq6Tq4nVaRoCBoPw_wcB
Landhelgisgæslan (2015). http://www.lhg.is/starfsemi/sjomaelingasvid/sjokort/kortaskra/
Nawri, N., Petersen, G. N., Björnsson, H. & Jónasson, K. (2013).
The wind energy potential of
Iceland.
Reykjavík: Veðurstofa Íslands (Icelandic Meteorological Office).
Orkustofnun (2013).
Raforkuspá 2014-2050. Endurreikningur á spá frá 2010 út frá n�½jum gögnum
og breyttum forsendum.
Reykjavík: Orkustofnun.
OSPAR (2009).
Assessment of the environmental impacts of cables.
27
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
28
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0113.png
APPENDIX D
North Atlantic Energy Network
Norway
Yngve Birkelund,
UiT - The Arctic University of Norway
Cathrine Henaug, Rambøll, Tromsø
1
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Table of Contents
Summary ................................................................................................................................................. 4
1.
The North Atlantic Energy network............................................................................................. 5
International subsea HVDC cables projects.......................................................................................... 5
Likely connection point in Norway ....................................................................................................... 5
2.
Impacts ........................................................................................................................................ 6
References ............................................................................................................................................... 7
3.
Transmission system and Electrical energy production .............................................................. 7
Energy production ................................................................................................................................ 8
Total production of energy ................................................................................................................... 8
Total production of electrical energy ................................................................................................... 9
Installed capacity ................................................................................................................................ 10
The electrical energy mix.................................................................................................................... 10
Hydro used as energy storage ............................................................................................................ 12
Thermal power ................................................................................................................................... 12
Wind power ........................................................................................................................................ 13
Total consumption of energy ............................................................................................................. 14
The renewable share .......................................................................................................................... 14
Total consumption of electrical energy .............................................................................................. 15
Consumption of electricity by consumer groups ............................................................................... 16
Annual and daily variations in production and consumption ............................................................ 16
References .......................................................................................................................................... 17
4.
Electrical market (prices) ........................................................................................................... 17
Structure of the power market .......................................................................................................... 18
Price formation ................................................................................................................................... 19
Price differences between areas ........................................................................................................ 19
Price differences between years and seasons.................................................................................... 20
Price differences between consumer groups ..................................................................................... 21
Additional costs for end-users ............................................................................................................ 22
Grid rent for different consumer groups............................................................................................ 22
Contract types .................................................................................................................................... 23
Households ............................................................................................................................................ 23
References .......................................................................................................................................... 24
5.
Potentials................................................................................................................................... 24
Hydropower ........................................................................................................................................ 26
Onshore wind ..................................................................................................................................... 27
2
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Geothermal......................................................................................................................................... 29
Ground heat ....................................................................................................................................... 29
Deep Geothermal Energy ................................................................................................................... 29
Solar .................................................................................................................................................... 30
Solar thermal collectors...................................................................................................................... 31
Solar cells ............................................................................................................................................ 31
Offshore renewable energy................................................................................................................ 31
Wave ................................................................................................................................................... 32
Tidal .................................................................................................................................................... 32
Wind ................................................................................................................................................... 34
References .......................................................................................................................................... 34
6.
7.
Timescale and licensing process................................................................................................ 36
CO
2
emission.............................................................................................................................. 37
Emissions of other greenhouse gasses.................................................................................................. 38
8.
Legal perspectives ..................................................................................................................... 39
3
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Summary
Statnett is the system operator in the Norwegian energy system. It is stately owned, and responsible
for the main power grid system in Norway. Their national grid development plan lays the foundation
for achieving energy and climate policy objectives. International interconnectors have a high priority
in Statnett as they contribute to the domestic supply security as the difference between dry and wet
years becomes more challenging than before. The transition from fossil to renewable energy in
Northen Europe also introduce power production dependent of sun and wind condition, which
cannot be regulated upwords and downwords with the consumption, and the accees to the flexible
Norwegian hydropower therefore plays an important role in the development.
The current subsea HVDC interconnectors, including the new cables to UK and Germany that are in
the construction phase, have a yearly capacity of 45 TWh. The average yearly electricity production in
Norway is approximately 120 TWh, with hydropower as the main resource (in 2013, 96%), and
thermal gas power plants (2.5%) and wind power (1.4 %) as the remaining resources.
The renewable energy potential in Norway is large. Although most of the hydropower potential is
already utilized, the possible new potential is estimated to approximately 30 TWh. The wind power
potential, on the other hand, is very large, estimated to 250 TWh with a development cost between
0.03 and 0.044 EUR/kwh. Geothermal power (heat pumps for heating of building) and solar cells can
increase the yearly surplus of electrical energy with 37 TWh and 4 TWh, respectively.
The electricy prices in Norway are low compared to European prices, with average household price in
first quarter of 2015 close to 0,096 EUR/kWh. This difference has created a great market for
international interconnectors. The NorNed cable between Norway and Nederland had an income
during the first two months of €50M, exceding the expectation of a yearly income of €64M according
to the budget.
The expectation for the new interconnectors to Great Britain and Germany is 25-35 TWh in new
export from Norway/Nordic contries, development of new renewable energy power plants and
correspondingly less coal power in neighbor contries.
Althourgh the NAEN project have discovered nice potential for introduction of electricity from
renewable resources for both Shetland and oil platforms alond the cable rute, the economical
benefit seems reduced with respect to Norwegian interest. Especially with the new HVDC subsea
interconnector to Great Britain to be finished in 2021.
4
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0117.png
1. The North Atlantic Energy network
International subsea HVDC cables projects
Statnett are involved in several projects with international subsea HVDC cables, as shown in
Figure 1. The first cable between Norway and Denmark was established in 1976, and that
single cable connection has been increased to four HVDC cables between those contries with
Figure 1: Subsea HVDC cables between Norway and EU contries. Red lines show
connector under constructions.
at total capacity of 1700MW in 2014. The next connection was the NorNed cable between
Norway and Netherland opened in 2008, with a capacity of 700MW. Early in 2015, the
decision to build two additional interconnections was made: Nordlink cable to Germany, to
be finished in 2019 with 1400 MW capacity, and the NSN link to Great Britain, to be finished
in 2021 with 1400 MW capacity. The total yearly capacity for these cables is approximately
45 TWh.
Likely connection point in Norway
A possible connection point for the NAEN project HVDC subsea cable from Shetland (or
Faroe) Island is between Bergen and Florø at the west coast of Norway The length from
Shetland to Bergen is approximately 350 km. The new NSN link from Great Britain has a
connection point at Kvilldal Power Station; about 120 km southeast of Bergen, but the exact
location of a NAEN has to be investigated with respect to potential new renewable sources
and the national power grid capacity. Statnett have pointed out that the Bergen region is
vurnerable with respect to the current power supply security, and new renewable power
5
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
production and the NAEN interconnector may increase the need for large upgrades to main
grid inland and towards northen Norway.
2. Impacts
Baseline information for the influenced area on the Norwegian continental Shelf
Several environmental impact assessments (EIA) have been conducted for the North Sea.
This includes regional EIAs and local assessments and monitoring. Hence, natural resources
and environmental conditions in the North Sea are well documented and described.
However, naturally the information are more detailed in the areas were petroleum fields are
located, as these require different environmental studies throughout the different life
stages.
Reports such as the Management Plan (Integrated Management of the Marine Environment
of the North Sea and Skagerrak) and Regional Environmental Surveys can be used to retrieve
baseline information for the influenced area (with respect to the North Atlantic Energy
Network Project) on the Norwegian continental Self.
The North Sea is generally shallow, reaching the greatest depths (just above 100 m) in the
northerly parts of the basin. The Norwegian Trench separates Norwegian coastal waters
from the shallower parts of the North Sea further west and south. The coastal side of the
Norwegian Trench slopes steeply to the deepest water just off the Norwegian coast, while
the offshore side rises more gently to the North Sea Plateau west and south of the Trench
(ref: white paper).
The Norwegian Continental Shelf is divided into 11 regions with respect to monitoring of the
seabed. The Regional Environmental Survey for each region is performed every third year,
and alternates between the different regions. The extent of the surveys is related to the
offshore activity in the regions.
Particularly valuable and vulnerable areas are areas that on the basis of scientific
assessments have been identified as being of great importance for biodiversity and for
biological production in the North Sea-Skagerrak area.
The designation of areas as particularly valuable and vulnerable does not have any direct
effect in the form of restrictions on commercial activities. Nevertheless, it indicates that it is
important to show special caution in these areas. To protect particularly valuable species
and habitats, it is for example possible to use current legislation to make activities in such
areas subject to special requirements. Such requirements may apply to the whole of a
particularly valuable and vulnerable area or part of it, and any exploration must be
considered on a case-by-case basis.
6
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0119.png
References
Integrated Management of the Marine Environment of the North Sea and Skagerrak (Management
Plan), Meld. St. 37 (2012–2013) Report to the Storting (white paper)
2013,Raforkustrengur til Evrópu, Niðurstöður og tillögur ráðgjafahóps iðnaðar- og viðskiptaráðherra
2013. Experience in transporting energy through subsea power cables: The case of Iceland. Svandís
Hlín Karlsdóttir
2015 28. September . Ing.dk.
http://ing.dk/artikel/740-kilometer-elkabel-skal-sende-dansk-stroem-
til-england-179078?utm_source=nyhedsbrev&utm_medium=email&utm_campaign=daglig
3. Transmission system and Electrical energy production
Norwegian electricity production in 2013 was in total nearly 134 TWh and the consumption
was about 142 TWh (Ssb 2015, table 08307)
.
The production was distributed between
hydro-, thermal- and wind power. Hydropower was responsible for the most of the
production with 96.1 % (Ssb 2015, table 08307). Thermal power had the second biggest
share with 2.5 % and wind power produced the remaining part of 1.4 % (Ssb 2015, table
08307). The total installed capacity was 33.486 TW in 2013 (Ssb 2015, table 10431).
The most recent data retrieved of the distribution of electricity consumption by consumer
groups is from 2007 and does not show any changes in the distribution of any significance in
the prior years. “Manufacturing, mining and quarrying” had the biggest share of about 44 %
of the total consumption (Ssb 2015, table 05216). The second biggest portion belongs to
“Households” representing 32 % and the third is “Services and construction” with 22 % (Ssb
2015, table 05216). The remaining part of about 2 % is consumed by “Fishing and
agriculture” and “Transport” (Ssb 2015, table 05216).
Both the total production and the consumption of electrical energy is now nearly five times
as much as it was in 1960 and the overall trend is that it has been growing gradually by a
constant amount each year (Ssb 2015, table 09386). The peak of the year, both of the
production and the consumption, is in January, as more power to heating is needed during
this cold winter month (Ssb 2015, table 08583).
7
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0120.png
Energy production
Total production of energy
shows the
primary energy
production in Norway
in the period 2009 –
2014. It tells us that the
total production has
decreased about 9% in
just five years. The
decrease is caused by
the reduction in
production of energy in
the form of crude oil
while the other energy
sources have
maintained more
stable.
Figure 2
Primary Energy Production
10.000
9.000
8.000
7.000
9.048
8.721
8.328
8.587
8.150
8.242
PJ per year
6.000
5.000
4.000
3.000
2.000
1.000
0
2009
2010
2011
Natural gas/LNG
Hydro- and wind energy
Gasoline
Coal
2012
2013
2014
Crude oil
LPG /NGL
Biofuels and waste
All energy products
Figure 2:
(Ssb 2015, table 09380)
Primary Energy Production
Distribution 2014
Natural gas/LNG (3985 PJ) 48 %
Crude oil (3128 PJ) 38 %
Hydro- and wind energy (500 PJ = 139 TWh) 6 %
LPG /NGL (349 PJ) 4 %
Gasoline (177 PJ) 2 %
Biofuels and waste (55 PJ) 1 %
Coal (47 PJ) 1 %
Figure 3:
(Ssb 2015, table 09380)
The distribution of the primary energy
production as it was in 2014 is presented in
Figure 3
. The pie chart shows that the most of
the energy produced is natural gas/LNG and
crude oil. A big share of it is exported to
other countries. The third biggest energy
source is hydro- and wind energy. This
source is transformed to electrical energy
and delivered to the power grid and is the
reason why the energy is also given in TWh.
Almost all of the hydro- and wind energy
comes from hydro as this is a highly utilized
energy resource in Norway as it has been for
many years. A small fraction of the natural
gas/LNG is also used for production of
electric energy.
8
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0121.png
Total production of electrical energy
Figure 4
shows the total
production as well as the
import and export of
electric power. The total
production seems to
follow a linear path from
1960 to 1990, it is
growing steadily from
year to year with some
variations. From 1990 to
2014 the overall increase
has slowed down and the
variation from year to
year is much bigger.
Electricity Commodity Balance
160
140
120
TWh per year
100
80
60
40
20
0
1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010 2015
Total production
Imports
Exports
Figure 4:
Ssb 2015, table 09386 and 08307)
In the same time period bigger variations also appears in import and export. This
fluctuation has to do with the development of a bigger energy network where more and
more regions and countries are connected in a bigger energy market. This market
facilitates both imports and exports when necessary or profitable. E.g. is the annual
production peak registered in 2012 (partially due to much rain resulting in filled water
basins) responsible for the peak in export the same year and therefore also the low import
of electrical energy. When the production in Norway is bigger than the consumption the
price will decrease. To counteract this effect and to be as profitable as possible the energy
is exported to a marked that has higher prices at the moment. The net commodity (or
trade), imports minus exports, is shown in the figure below. Overall Norway exports more
electricity than what is imported and those years are represented in red in
Figure 5
.
20
Net Commodity
TWh per year
10
0
1960
-10
-20
Figure 5:
(Ssb 2015, table 09386 and 08307)
1965
1970
1975
1980
1985
1990
1995
2000
2005
2010
2015
9
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0122.png
Installed capacity
Number of power stations
1200
1000
800
40
35
30
25
Installed capasity
TW
600
400
200
0
1974
1977
1980
1983
1986
1989
1992
1995
1998
2001
2004
2007
2010
2013
20
15
10
5
0
1974
1977
1980
1983
1986
1989
1992
1995
1998
2001
2004
2007
2010
2013
Wind power
Thermal power
Hydro power
Wind power
Thermal power
Hydro power
Figure 6:
(Ssb 2015, table 10431)
Figure 7:
(Ssb 2015, table 10431)
As the figures above illustrates, the installed capacity has doubled in the last 40 years. In
2013 the total installed capacity was 33.486 TW (Ssb 2015, table 10431). The capacity has
grown gradually and the contribution from thermal power plants has increased profoundly
from 2006. The first operative wind power plant delivering electricity to the grid opened in
1993. Although the installed capacity has increased steadily for the past 40 years the number
of power stations have stayed stable until about 2006. From 2006 to 2013 the number of
hydro power plants increased by 46 %.
The electrical energy mix
General
Figure 8 demonstrates how important hydro has
been for the production of electrical energy in
Norway since hydro power plants really started
to pop up after WWII. At the time about 61 % of
the available hydro energy is being harnessed.
Much of the remaining non-utilized-energy is
located in protected areas and cannot be
harnessed. The efficiency of the hydro power
plants are already high, often about 95%.
Together these two factors make the expected
production from hydro to flatten out. It will still
increase for some years as a few more hydro
power plants are under construction. Also it
would vary from year to year as the participation
changes.
Production of Electrical
Energy Distribution
160
140
120
100
TWh
80
60
40
20
0
1950
1962
1966
1970
1974
1978
1982
1986
1990
1994
1998
2002
2006
2010
Wind power production
Thermal power production
Hydro power production
Figure 8:
(Ssb 2015, table 08307)
10
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0123.png
Electricity Production Distribution
2013
(total prod. 133975 GWh)
Hydropower
production 96.1 %
However there is a way to utilize the
hydro power plants even more. The
way to do so is to take advantage of
basins and dams by using them as big
batteries by storing energy from other
sources there. The principle is called
pumped storage and more about it in
section ref.
To keep the production of electric
energy increasing it is necessary to
keep developing more power plants
that utilizes other sources of energy,
preferably renewables. Figure 9 shows
that this is happening, but it is still at a
very moderate level compared to
hydro. The share “Thermal power
production” mostly comes from gas
Thermal power
production 2.5 %
Wind power
production 1.4 %
Figure 9:
(Ssb 2015, table 08307)
turbines using natural gas/LNG.
Hydropower
Norway’s electricity production is highly dependent of hydropower as previously mentioned.
Figure 1.8 shows that in 2013 hydropower was responsible for 96.1% of the total production
of electricity. The installed capacity was 31033 MW which constitutes for 92.7 % of the total
capacity (Ssb 2015, table 10431). This big share makes the supply system vulnerable to
longer periods without a sufficient water inflow.
The precipitation and the useful inflow varies quite much throughout the different seasons
and also the regions. It also varies from year to year and in the past 23 years it has varied by
about 60 TWh (Norwegian Ministry of Petroleum and Energy 2014, p.24-25). Even though it
can be a lot of precipitation in the winter months the inflow to the hydro power plants are
low due to the downfall usually comes as snow and does not melt until the spring. In the
spring the inflow is therefore at its highest and declines towards the end of the summer.
Usually the inflow increases again in the autumn.
Compared to other renewables hydropower is very flexible. When consumption is low much
of the potential energy of the water can be stored in reservoirs while generating enough
electricity for the consumers. Those reservoirs are established in lakes and artificial basins. In
Norway the consumption of electricity is higher in the winter due to more energy used for
heating. In those months the generation of energy can be adjusted to the increased demand
by letting more of the stored water go through the generators.
11
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0124.png
Hydro used as energy storage
The high level of flexibility hydropower has can be utilized by using the excess energy
produced by other energy sources to pump up water to reservoirs with a greater head. The
energy is stored as potential energy and can be transformed to electrical energy when the
demand is higher. This technique is called pumped storage and already existing reservoirs
and hydro power plant can be used.
Building pumped storage enables other less flexible renewable energy sources to be a bigger
part of the market. E.g. solar power does not yet deliver any power to the grid in Norway,
but is expected to arise in the future. Solar cells (PV) will produce most electricity when the
demand in the region is at its lowest, in the summer. If the production of electricity is higher
than the demand, this excess energy can simply be stored using pumped storage without
much loss of energy to friction. The reservoirs are usually at their lowest during the summer
allowing much energy produced from other sources to be stored there without risking full
reservoirs.
Norway is ideal for pumped storage as it has allot of elevations and the installed capacity of
hydro is already high. New reservoirs and generators can be made, but by using more of the
capacity of the existing reservoirs and hydro power plants will enable a lot of energy to be
stored. In 2013 the capacity of hydro power plants was 31.033 GW (Ssb 2015, table 10431)
and the produced energy was 133 975 GWh (Ssb 2015, table 08307). On average throughout
the year 49.25 % of the total capacity was being used. The calculation is presented below.
=
133 975
ℎ/
31.033
∙ (24 ∙ 365.25)ℎ/
∙ 100 % ≈ 49.25 %
Thermal power
Thermal power in Norway comes mainly from power plants using natural gas. Norway pump
up and export allot of oil and gas and most of the thermal power plants are associated with
refineries onshore. When producing electricity from gas quite much CO
2
is emitted and the
power plants have faced opposition from environmentalists. The government has planned to
install carbon dioxide capture and storage facilities on one of the power plants.
In 2013 thermal power was responsible for 2.5 % of the total production of electricity in
Norway (Ssb 2015, table 08307). The share increased severe in 2007 (see figure 1.7) when
the number of thermal power plants almost tripled from the year before (Ssb 2015, table
10431). The same year the installed capacity was 1635 MW accounting for 4.88 % of the
total capacity in Norway (Ssb 2015, table 10431).
Gas-fired power plants are highly flexible and is primary used when the demand is bigger
than the supply from other types of power plants. As a backup Norway has two gas-fired
power plants only to be used in special situations and require permits from the Norwegian
authorities. Together they have a total capacity of 300 MW. (Norwegian Ministry of
Petroleum and Energy 2014, p.24).
12
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0125.png
Wind power
Norway generally has good wind resources. A lot of it has to do with the long coastline to the
Norwegian Sea. In the coast the average annual wind speed 50 meters above ground is
usually between 7 to 9 m/s (Norwegian Ministry of Petroleum and Energy 2014, p.28). An
average annual wind speed of more than 6.5 m/s (Norwegian Ministry of Petroleum and
Energy 2014, p.28) is considered to be sufficient for establishing wind farms. The good
conditions both onshore and offshore leads to a big potential for wind power in Norway.
However, the great potential remains almost unutilized as the start-up cost are still high,
especially offshore. Wind power plants have not yet been commercially profitable in Norway
and are heavily dependent on public funding (Norwegian Ministry of Petroleum and Energy
2014, p.28).
In 2013 wind power was responsible for 1.4% of the total production of electricity in Norway
(Ssb 2015, table 08307). The share is not big, but as the installed capacity increases rapidly,
so does the production of electricity from wind farms. Figure 10 shows how the capacity of
the installed wind power plants has developed since the first power plant was operative in
1993. In 2013 the installed capacity was 818 MW accounting for 2.44 % of the total capacity
in Norway (Ssb 2015, table 10431).
Installed Wind Power Capasity
900
800
700
600
512
348
265 284
97 97
3
3
3
4
4
5
14
13 13
152
425
395 423
500
400
300
200
100
0
705
818
In opposition to hydro is wind power very inflexible. The power plants produce electricity
when the wind speed at hub height is from a gentle breeze (3-4 m/s) and up to storm (25
m/s) (Norwegian Ministry of Petroleum and Energy 2014, p.27). In the operative region of
wind speed the output varies tremendously as the power of the wind increases by the cubed
of the wind speed. The kinetic energy that passes the rotor blades at 25 m/s any given
moment is almost 600 times more than at the lowest operating speed 3-4 m/s.
MW
Figure 10:
Norwegian Water Resources and Energy Directorate (NVE). 2015. “Vindkraft - Produksjon i 2014.” Accessed
28. of July 2015. http://publikasjoner.nve.no/rapport/2015/rapport2015_18.pdf
13
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0126.png
Total consumption of
energy
Figure 11 shows the
energy consumption in
Norway in the period
2009 – 2014. It tells us
that the total
consumption and also
the distribution of the
different energy
sources have
maintained relatively
stable over the five
year period.
In 2014 the total
consumption was 759.5
PJ and is only 9.21 % of
the total energy
produced the same
year.
Energy Consumption
900
800
700
600
749
808
780
789
785
760
PJ
500
400
300
200
100
0
2009
2010
2011
Petroleum coke
Coke
Other gases
Natural gas/LNG
Kerosene
Biofuels and waste
Electricity
2012
2013
Heavy fuel oil
LPG /NGL
District heating
Coal
Gasoline
Middle distillates
All energy products
2014
Figure 11:
(Ssb 2015, table 09380)
The distribution of the energy consumption as it was in 2014 is presented in the figure
below. The pie chart shows that half of the energy consumption is electricity. One quarter is
middle distillates which is a generic term for oil refinery products in the middle distillation
range.
T
he renewable share
Figure 12 shows the overall renewable energy share in Norway from 2004 to 2013.
Consumption in all sectors are included e.g. industry, transport and households. The share
seems to be quite stable and the trend is a slightly increasing renewable share over the
period. The share of electricity gross consumption from renewables is very high. In some
years it is even more than 100 % which can be explained by a high export of electricity that
year. The share of renewable energy sources in heating and cooling is much lower and has a
big potential of improving.
14
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0127.png
120%
100%
80%
60%
40%
20%
Consumption - The overall renewable energy share in Norway
Share of electricity from renewable
sources in gross electr. consum.
Overall renewable share
Share of renewable energy sources in
heating and cooling
2006
2008
2010
2012
0%
2004
Figure 12:
(Ssb 2015, table 10842)
Total consumption of electrical energy
Figure 13 shows both the
Electricity Consumption vs. Production
total consumption and the
160
total production of electric
140
power. The two graphs are
following each other pretty
120
well. The reason for this
100
coherence is simply that
80
the production is being
60
adjusted to the demand.
40
Generally the consumption
20
is a little less than the
0
production and the excess
1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010
power is exported. The
Total production
Gross consumption
total consumption is more
stable and does not
Figure 13:
(Ssb 2015, table 09386)
fluctuate as much as the
production.
TWh per year
2015
15
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0128.png
Consumption of electricity by consumer groups
Distribution of Electricity Consumption
by Consumer Groups 2007
Manufacturing, mining and
quarrying 44 %
Household 32 %
Services and construction 22 %
Fishing and agriculture 2 %
Transport 1 %
Figure 14:
(Ssb 2015, table 05216)
Figure 14 shows the distribution
of electricity consumption by
consumer groups. The time
series goes back to 1990 and
does not show any changes in
the distribution of any
significance. The increase of
popularity of electric and hybrid
cars and busses in the more
recent years makes it
reasonable to believe that the
share consumed by transport
has increased by some extent.
Annual and daily variations in production and consumption
Monthly production and consumption of electricity
18
16
14
12
10
8
6
4
2
0
Total production
Figure 15:
(ssb 2015, table 05224)
Gross consumption
Figure 15 shows that both the production and the consumption of electricity is highest in
the winter months peaking in January. Some of the annual variation is caused by that the
cold winter months require more power to heating. In the summer not much power is used
on cooling. Also parts of the industry is either shut down or the capacity is reduced in the
summer due to vacation. The relation between domestic production and consumption is
strong. When consumption is high the production is adjusted so the need for importing
electric power is minimalized. This domestic dependency could be reduced if a bigger
market for electricity is established.
Twh
16
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0129.png
Figure 16 shows the daily variations in two random days in 2015. Usually the consumption
peaks around 4 pm as many people are cooking dinner.
20
15
January the 1st 2015
20
15
June the 1st 2015
MWh
MWh
10
5
0
12:00 AM 4:00 AM 8:00 AM 12:00 PM 4:00 PM 8:00 PM 12:00 AM
10
5
0
12:00 AM4:00 AM 8:00 AM 12:00 PM 4:00 PM 8:00 PM 12:00 AM
Figure 16:
Statsnett 2015
References
Norwegian Ministry of Petroleum and Energy. 2014.
"Facts 2015 – Energy and Water
Resources in Norway."
Accessed June, 2015.
https://www.regjeringen.no/contentassets/fd89d9e2c39a4ac2b9c9a95bf156089a/facts_201
5_energy_and_water_web.pdf
Ssb (Statistics Norway). 2015. “Statistics Norway.” Accessed June and July 2015.
http://www.ssb.no/en/
Statnett. 2015. “Drift og marked.” Last modified 17. of July 2015.
http://www.statnett.no/Drift-og-marked/Nedlastingssenter/Last-ned-grunndata/
Norwegian Water Resources and Energy Directorate (NVE). 2015. “Vindkraft - Produksjon i
2014.” Accessed 28. of July 2015.
http://publikasjoner.nve.no/rapport/2015/rapport2015_18.pdf
4. Electrical
market
(prices)
The electrical power marked can be divided into two layers of markets, the wholesale
market and the end-user market. The price of the electric power naturally changes with the
overall demand and supply, but is also dependent on the consumer group and the type of
contract. The price of electricity has varied a lot in Norway, especially in the past ten years,
and it is difficult to see a general trend.
In the first quarter of 2015 the electricity price excl. taxes on the wholesale market was 24.1
øre/kWh (Ssb, table 09363). This is the same as 0.201 DKK/kWh, 3.99 ISK/kWh and 0.0270
EUR/kWh by the exchange rate of July 23, 2015.
17
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0130.png
In general the price on the end-user market is higher than on the wholesale marked. Since
2012 the price difference for the different consumer groups in the end-user marked has
been relatively small. However, the average grid rent is still very dependent on the
consumer group and therefore so is the total price for power.
End-users do not just pay for electricity by itself to receive the power. In addition several
other components of the service is charged such as a grid tariff, electricity tax, value added
tax and a couple of fees. For household the electricity price only makes up about one-third
of the total power bill for households. In the first quarter of 2015 the total price for
electricity in households in Norway was 86.4 øre/kWh (Ssb, table 09387). This is the same as
0.720 DKK/kWh, 14.3 ISK/kWh and 0.0958 EUR/kWh by the exchange rate of July 23, 2015.
Structure of the power market
The electrical power marked can be divided into two layers of markets. The top layer
consists of a wholesale market where large bulks of power are bought and sold. The traders
are power producers and suppliers. Also large-scale consumers attend. The market in the
layer below the wholesale market is called the end-user market. Here the energy supplier
resells energy to households, industry and medium sized consumers, such as chain stores
and hotels. The price of the electric power naturally changes with the overall demand and
supply, but is also dependent on the consumer group and the type of contract. Large-scale
companies that buys large bulks of power over a longer period usually pay less than the
average household consumer per kWh. (Norwegian Ministry of Petroleum and Energy, p. 52)
Figure 17 provides the general overview of how the power marked Norway is a part of
operates. NASDAQ WMX Group is an American corporation that owns and operates many of
the stock markets in West-Europe. NORDPOOL Spot operates the largest market of
electricity in Europe. Among other countries it operates in all the Nordic countries except
(for) Iceland. Statnett is a Norwegian state owned company responsible for the power grid in
Norway.
Figure 17:
Organization of the electrisity trading market
18
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
As figure 27 illustrates, there are three submarkets in the physical power market. Here
traders can bid and the prices within that submarket are determined. The three submarkets
are:
-
-
-
Elspot – “day-ahead market”
Elbas – “continuous intraday market”
Balancing market – “regulating power market”
(Norwegian Ministry of Petroleum and Energy, p. 54)
Price formation
The most decisive factor when it comes to how the prices are formed in Norway is the
overall generation and consumption in the Nordic counties. Also the developments in
markets outside the Nordic region can influence the price.
The foundation for production of electricity in Norway is hydro which is very dependent on
the very unpredictable and highly fluctuating precipitation levels and the inflow to the
reservoirs. The big dependency on hydro is deceive for the fluctuations in the power price.
When the reservoirs of the hydro power plants are full, the price usually declines. Almost
empty or empty reservoirs will result in high prices for electric power. Cold periods in the
winter leads to a higher consumption of energy and the prices usually goes up.
Consumption and therefore also the power prices are also dependent on the European
economy. (Norwegian Ministry of Petroleum and Energy, p. 55)
Price differences between areas
Some places there are insufficient grid capacity and big bulks of power cannot be
imported/exported. These bottlenecks in the grid make it necessary to divide the bidding
area into smaller regions on each side of the bottleneck. Currently Norway is divided into
five bidding areas (Norwegian Ministry of Petroleum and Energy, p. 55). The power situation
differs between the bidding areas and cause variations in power price from region to region.
Area prices are higher in areas with a shortage of power compared to the areas with a
surplus. The difference in the power price provides a foundation when deciding where it
would be most profitable to build power plants or power demanding industry. (Norwegian
Ministry of Petroleum and Energy, p. 55)
19
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0132.png
Electricity Prices on the Wholesale Market excl. taxes
60
50
Øre/kWh
40
30
20
10
0
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
WHOLESALES OF ELECTRICITY
Poly. (WHOLESALES OF ELECTRICITY)
Figure 18:
(Ssb, table 04725 and 09363)
Price differences between years and seasons
The electricity prices are different depending on the type of contract. On the wholesale
market there are many different types of contracts and the figure above shows the average
price. The electricity prices on the end-user market can differ quite much to the prices on
the wholesale market. However, Figure 18 can illustrate the overall development in the
electricity prices.
Annual
Figure 18 shows that the electricity price on the wholesale market has varied quite much in
the past 17 years. The quarterly lowest registered price in the period is 8.4 øre/kWh
measures in the summertime both in 1998 and in 2000. The highest price occurred winter
2010 with 49.3 øre/kWh, almost six times the price as in 1998 and 2000. In the first quarter
of 2015 the electricity price excl. taxes on the wholesale market was 24.1 øre/kWh. This is
the same as 0.201 DKK/kWh, 3.99 ISK/kWh and 0.0270 EUR/kWh by the exchange rate of
July 23, 2015.
The red-dotted line is the best quadratic fit. The polynomial says something about the
development in the period, but it cannot really say much of how the development is going to
be in the future.
Seasonal
The demand of electric power is higher during the cold winter months compared to the rest
of the year in Norway. So is also the production. Therefore the higher consumption of
electricity in the winter does not necessarily lead to higher prices. The relation may change
from year to year depending on many factors e.g. the degree of filling in the hydro
reservoirs. Figure 18 shows that in the periods 1998 – 2004 and 2007 – 2015 the prices has
been highest in the winter months and usually the annual peak is in the first quarter of the
year. The period 2004 – 2007 does not show the same clear trend and the variation appears
more random. In that period the quarterly highest price occurred in the summer either in
the second or the third quarter of the year.
20
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0133.png
Price differences between consumer groups
Electricity Prices by Consumer Groups
50
45
40
35
30
25
20
15
10
5
0
1998
2000
2002
2004
2006
2008
2010
2012
2014
Øre/kWh
HOUSEHOLDS
SERVICES
MANUFAC. EXCL. ENERGY-INTENSIVE MANUFAC. AND PULP AND PAPER INDUSTRY
ENERGY-INTENSIVE MANUFACTURING AND PULP AND PAPER INDUSTRY
WHOLESALES OF ELECTRICITY
Figure 19:
(Ssb, table 08925, 08926, 09365 and 09366)
The electricity prices are different depending on the consumer group. Figure 19 shows the
average price excl. taxes on the end-user marked for different consumer groups and also the
average price on the wholesale marked is added as a reference. In general the price on the
end-user market is higher than on the wholesale marked. The power price for “Energy-
intensive manufacturing and pulp and paper industry” (EIMPPI) is in most of the period even
lower than the wholesale price. Also it does not seem to be affected so much to the overall
fluctuations in the price. Some of the reason for the stable and low price for EIMPPI is that
some of the companies are flexible regarding when to use the power and is consuming less
when the overall demand in the market is high.
In the period the price “households” has been paying has maintained the highest. In 2003 it
was almost four times as much as the average price for EIMPPI. “Services” usually has had
the second highest price followed by “Manufacturing excl. EIMPPI”. Since 2012 the price
difference for the different consumer groups in the end-user marked has been relatively
small compared to the rest of the period displayed in Figure 19.
21
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0134.png
Additional costs for end-users
End-users are the traders who purchase power for their own consumption. In Norway they
are free to choose their own power supplier and the type of contract. Large-scale
consumers, e.g. large industrial companies, might buy their power in bulks directly on the
wholesale market while smaller consumers purchase power from a power supplier.
End-users do not just pay for electricity by itself to receive the power. In addition several
other components of the service is charged. The total electricity bill for end-user consists of:
Power price - the raw material of electricity
Grid tariff - connection to and use of the power grid
Electricity tax
Other charges
o
Value added tax (VAT)
o
Fee for the Energy Fund (Enova)
o
Fee for electricity certificates
(Norwegian Ministry of Petroleum and Energy, p. 56)
Grid rent for different consumer groups
Figure 19 shows that since 2012 the price
difference for electricity for the different
consumer groups in the end-user marked
has been relatively small. In 2014 the
price difference from the consumer
group with the highest average price
compared to the one with the lowest
average price for electricity was only 3
øre/kWh.
Even though the electricity price may not
be very different for the different
consumer groups the total bill can. Figure
20 shows that the average grid rent is
very dependent on the consumer group.
In 2014 the grid rent for “Private
household and agriculture” was over 12
times the price applied for “Power
intensive manufacturing”.
Grid rent, weighted average
35
30
25
Øre/kWh
20
15
10
5
0
2008
2009
2010
2011
2012
2013
ALL CONSUMER GROUPS
POWER INTENSIVE MANUFACTURING
MINING AND EXTRACTION
MINING, EXTRACTION AND MANUFACTURING EXCLUDING
POWER INTENSIVE MANUFACTURING
MANUFACTURING EXCLUDING POWER INTENSIVE
MANUFACTURING
VARIOUS SUPPLY AND REMIDIATION ACTIVITIES
TRANSPORTATION AND STORAGE
Figure 20:
(Ssb, table 08358)
22
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0135.png
Contract types
There are different benefits with
the different types of contracts
regarding the risk and reliability.
The most profitable and suitable
type of contract will differ from
companies and is depending on e.g.
how flexible the company is with
the consumption and also the size
of the bill. However, as Figure 21
shows, contracts tied to a spot
price was by far the most popular
in the first quarter of 2015. About
30 % of households had variable
price contracts.
Figure 21:
(Ssb, table 09364)
Households
Figure 22 reveals that the
electricity price only makes up
about one-third of the total bill
for households. In the first
quarter of 2015 the total price
for electricity in households in
Norway was 86.4 øre/kWh. This
is the same as 0.720 DKK/kWh,
14.3 ISK/kWh and 0.0958
EUR/kWh by the exchange rate
of July 23, 2015.
Contracts tied to spot price are
the most commonly used for
households in Norway. In those
types of contacts the grid rent,
VAT and the tax on consumption
of electricity will maintain the
same per kWh, but the price for
the electricity itself will vary with
the spot price.
Electricity Prices, grid rent and taxes
for Households, 1st quarter 2015
Total price: 86.4 øre/kWh
26.3
øre/kWh
30%
28.8 øre/kWh
33 %
31.3 øre/kWh
36%
Grid rent
Electricity
VAT and tax on consumption of electricity
Figure 22:
(Ssb, table 09387)
23
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0136.png
References
Norwegian Ministry of Petroleum and Energy. 2014.
"Facts 2015 – Energy and Water
Resources in Norway."
Accessed June, 2015.
https://www.regjeringen.no/contentassets/fd89d9e2c39a4ac2b9c9a95bf156089a/facts_201
5_energy_and_water_web.pdf
Norway, Energy Policies, Laws and regulations handbook. Volume 1- Strategic information
and basic laws.
Ssb (Statistics Norway). 2015. “Drift og marked.” http://www.ssb.no/en/
Statnett. 2015. “Drift og marked.” Last modified July 17.
http://www.statnett.no/Drift-og-marked/Nedlastingssenter/Last-ned-grunndata/
5. Potentials
The hydropower potential is estimated to be 213 TWh annually. 61 % of it is already
developed, 24 % is protected leaving a potential increase of about 15 % (30.7 TWh).
(Norwegian Ministry of Petroleum and Energy 2014, p.27)
Norway generally has good wind resources. In 2014 the produced electricity from onshore
wind power plants was 2.2 TWh and is responsible for 1.5 % of the total production of
electricity in Norway (NVE 2015 (source 3), p.4).
In a research published in 2009 by NVE the total domestic exploitable wind potential was
first presented. Most of the potential lies in the northernmost counties and is very
dependent of what mean wind speed it is decided to be sufficient profitable. If all the
locations with an average wind speed 8 m/s or more are utilized the annual potential is 419
TWh. Setting the requirement down to 7 m/s or more increases the potential to 1243 TWh
and dropping it further to 6 m/s gives the potential of 1847 TWh. (NVE 2009 (source 2), p.17)
NVE did a similar research in 2005 and found that the wind power potential which can be
developed at a cost varying between 27-40 øre/kWh was found to be 250 TWh. This is the
same as 0.223-0.330 DKK/kWh, 4.42-6.55 ISK/kWh and 0.0299-0.0442 EUR/kWh by the
exchange rate of July 29, 2015. (NVE 200 (source 1), p.5)
Currently geothermal energy is only being used for heating/cooling purposes in Norway and
according to the different sources used in this report large scale production of electricity is
not to be expected in the near future. NGE estimates the technical potential for energy
savings by using geothermal energy and heat pumps to be about 37 TWh annually
(Fornybar.no 2015).
Even though the potential of solar power in Norway is quite much less than in countries lying
closer to the equator the annual radiation is still about 1700 times the annual consumption
24
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
(NVE 2015 (source 5)). The practical potential of solar cells is estimated to be 4.4 TWh per
year by the year 2020 (KanEnergi and SINTEF 2011, p. 65). In this estimate big solar power
plants that deliver power to the grid are not included as they are not expected to be able to
compete in the Norwegian energy marked by 2020. If the development continues the power
from solar cells will sometime in the future be competing with power from other sources,
and the potential will (then) be very much higher, almost unlimited. (KanEnergi and SINTEF
2011, p. 51, 65 and 66).
The ocean is an enormous source of energy. Norway has a long coast line and big properties
in the sea making the potential of renewable energy from the sea gigantic. The potential of
wave power is estimated to be 600 TWh annually and about 12 – 30 TWh is considered to be
possible and realistic to develop (SWECO Grøner, ECON, and Kjeller Vindteknikk 2007). The
potential of tidal power is estimated to be about 1.2 TWh with a maximum power output of
337 MW. (SWECO Grøner, ECON, and Kjeller Vindteknikk 2007, p. 11).The offshore wind
potential in Norway is huge. It is estimated to about 14,000 TWh(SWECO Grøner, ECON, and
Kjeller Vindteknikk 2007, p.20). How much electricity it is possible to produce of it is
essentially not limited by the available energy, but by the power market and other practical
relations.
25
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0138.png
Hydropower
Overviev of hydropower potential as of 01.01.2014
Hydropower is already a well-utilized
source of energy in Norway and is
responsible for most of the electricity
production in the country. The
hydropower potential is the total energy
in the Norwegian river system that is
technically and economically feasible to
generate electricity. In the start of 2014
the total hydropower potential was
estimated to be 213 TWh per year. The
distribution of how the potential is
exploited is shown in Figure 23. The
yellow share on the pie chart is the mean
annual developed production capacity
and is about 61 % of the total potential.
The red share present the share of the
potential that cannot be utilized. This
energy cannot be utilized because it is
either located in protected river systems
or in areas where license applications
have been rejected.
Developed (131.4 TWh/year, 61 %)
Small power plants (13.1 TWh/year, 6 %)
New power production exceeding 10 MW, incl.
upgrades/expansions (4.8 TWh/year, 2 %)
Licence applied for/application notified (7.7 TWh/year, 4 %)
The blue and the green shades represent
the total potential for growth in the
Development permit granted (3.6 TWh/year, 2 %)
production capacity. Together they add
Under devlopment (1.5 TWh/year, 1 %)
up to 30.7 TWh/year which corresponds
to 14.4 % of the total potential. Power
Protected/rejected (50.9 TWh/year, 24 %)
plants with a total potential of 7.7
TWh/year was in the start of 2014
Figure 23:
(Norwegian Ministry of Petroleum and Energy
waiting to be approved. 3.6 TWh/year
2014, p.27)
was already approved and 1.5 TWh/year
was under development. 13.1 TWh/year
lies in smaller rivers where small power plants are needed to harness the energy Upgrades
and expansions on already existing and operating hydropower plants have a potential of 4.8
TWh/year.
26
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0139.png
Onshore wind
Norway generally has good wind
resources, as shown in Figure 24. Most of
the resources are in the sea, but there is
still a lot of wind to harness onshore by
the long coastline to the Norwegian Sea,
especially in the northernmost part of the
country. Start-up costs for onshore wind
parks are still high, but not as high as
offshore parks as they e.g. are less
accessible to the power grid. In 2014 the
total installed capacity of all the onshore
wind power plants was 856 MW (NVE
2015 (source 3), p.4). The same year they
produced 2.2 TWh and is responsible for
1.5 % of the total production of electricity
in Norway (NVE 2015 (source 3), p.4). In
the coast the average annual wind speed
50 meters above ground is usually
between 7 to 9 m/s (Norwegian Ministry
of Petroleum and Energy 2014, p.28). An
average annual wind speed of more than
6.5 m/s (Norwegian Ministry of
Petroleum and Energy 2014, p.28) is
considered to be sufficient for
establishing wind farms.
Annual mean wind in 80m [m/s]
Figure 24:
(NVE 2009 (source 2), p.1)
The potential of onshore wind in Norway can be calculated in many ways depending on what
areas to include considering constraints like settlements, environment, average wind speed
and price range. NVE is the Norwegian Water Resources and Energy Directorate, a
government agency that does a lot of research related to the energy situation in Norway
including making an inventory of the onshore wind potential.
27
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0140.png
In a research published in 2009 by
NVE the total domestic exploitable
wind potential was first presented.
In this study it is not made any
assessment of how much of these
resources that actually can be
developed in practice. The numbers
are presented Table 1 and are
based on an assumption of a
development density of 8 MW/km
2
.
Most of the potential lies in the
northernmost counties listed in the
bottom of the table. In order to
build big/many wind power plants
here the capacity of the grid in the
area needs to be improved.
As the table shows the potential is
very dependent on what exploitable
region of the annual mean wind, U,
is being developed and utilized.
County
Østfold
Akershus
Oslo
Hedmark
Oppland
Buskerud
Vestfold
Telemark
Aust-Agder
Vest-Agder
Rogaland
Hordaland
Sogn og Fjordane
Møre og Romsdal
Sør-Trøndelag
Nord-Trøndelag
U > 6 m/s
[TWh]
0.4
0.2
0
72.9
101
49.1
0.1
32.9
9.8
32.6
55.1
81.3
120
86.9
97.8
116
U > 7 m/s
[TWh]
0
0
0
41.3
55.2
35.4
<0.1
23.9
6.8
29.4
46.8
50.3
84.0
57.4
74.1
82.7
U > 8 m/s
[TWh]
0
0
0
10.8
19.1
13.3
0
9.2
1.6
11.1
23.7
10.4
41.2
17.5
27.7
28.3
Nordland
289
197
66.6
NVE did a similar research in 2005.
In that research the simulation
Troms
202
109
18.4
capacity was not as big as the one a
Finnmark
500
349
120
few years later published in 2009
1847
1243
419
The whole country
and only 12.5 % of the total
domestic area was included. The
Table 1:
NVE 2009 (source 2), p.17)
included areas were coastal areas
and other areas with favorable weather conditions. Unlike the research in 2009 this study
considered the formal development restrictions and the economic criteria and gave a more
practical potential. The wind power potential which can be developed at a cost varying
between 27-40 øre/kWh was found to be 250 TWh. This is the same as 0.223-0.330
DKK/kWh, 4.42-6.55 ISK/kWh and 0.0299-0.0442 EUR/kWh by the exchange rate of July 29,
2015.
The practical potential found in 2005 would probably be more like the numbers from the
study published in 2009 if more areas had been included. Regardless, the study shows that
the wind power potential in Norway that is achievable within reasonable production costs, is
at least hundred times the 2.2 TWh that was being utilized in 2014.
28
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0141.png
Geothermal
Geothermal energy is thermal energy generated and stored in the Earth. Geothermal energy
can be divided into “deep geothermal energy” and “ground heat” separated by different
depth and existing techniques for exploitation. Currently geothermal energy is only being
used for heating/cooling purposes in Norway and according to the different sources used in
this report large scale production of electricity is not to be expected in the near future.
“Norwegian Geological Survey” (NGE) is a government agency responsible for mapping and
research of the geology in Norway. NGE estimates the technical potential for energy savings
by using geothermal energy and heat pumps to be about 37 TWh annually (Fornybar.no
2015).
Ground heat
By using ground-sourced heat pumps, heat energy from low-temperature areas in the
bedrock and groundwater can be exploited. Usually wells are drilled down to about 100 to
180 meters where the temperature is stable throughout the year and can be used for
heating purposes (NVE 2015 (source 4)). Ground-sourced heat pumps are the only utilization
of geothermal energy as of 2011(Fornybar.no 2015).
In theory can ground heat be used to cover all of Norway’s need for heating and cooling
buildings directly. In practice is the potential restricted by high start-up costs. If the cost
limit is set to 70 øre/kWh (equivalent the price of electric heating) the potential is 45 TWh
(Fornybar.no 2015). 70 øre/kWh is the same as 0.580 DKK/kWh, 11.42 ISK/kWh and 0.0777
EUR/kWh by the exchange rate of July 30, 2015. Today it is approximately 26 000 heating
systems in Norway that combined produce 3.5
TWh for heating/cooling purposes and not to
produce electricity (NVE 2015 (source 4)).
Deep Geothermal Energy
Deep geothermal energy lies deeper than the heat
harnessed by ground- sourced heat pumps and
require different and more expensive techniques
to be utilized. In Norway it is necessary to drill
relatively deep to reach a desirable temperature.
The drilling costs increases rapidly as the wells go
deeper. To achieve a temperature of more than
100 °C it is in Norway needed to drill down to
about 4,500 to 6,000 meters (Norconsult AS 2012).
According to Norconsult AS, deep geothermal
energy can in the future cover up to 40% of the
heating market in Norway, but in the near future,
the potential is very limited to the costs.
Figure 25:
Map of depth to find 100°C temperatures
29
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0142.png
Solar
Solar is by many predicted to be the energy source of tomorrow. Even though the potential
in Norway is quite much less than in countries lying closer to the equator the annual
radiation is still about 1700 times the annual consumption (NVE 2015 (source 5)). Solar
radiation can directly be utilized by either solar thermal collectors, mainly used for heating,
and solar cells for production of electricity.
Due to the location far north the solar radiation varies
greatly with the seasons in Norway. At the same
time it can be very different from the south to
the north. Figure 27 on the right shows the
daily mean radiation on a horizontal surface
in January and in July. The annual radiation
on a horizontal surface variesfrom about
700 kWh/m
2
in the north to about
1100 kWh/m
2
in the south (KanEnergi
and SINTEF 2011, p. 44). By tilting
solar collectors and photovoltaic
modules to thebest gradient
depending onthe latitude the
radiation will be somewhat
stronger.
Figure 27:
(KanEnergi and SINTEF 2011, p. 44)
Figure 26 displays simulation of how much the radiation is changing throughout a year based
on climate data. Five places that can be considered as weather representatives for each
region was picked: Oslo (southeast), Kristiansand (south), Bergen (west), Trondheim (middle)
and Tromsø (north). (Multiconsult 2013 p. 7).
Climate data used in simulations
Radiation, horizontal surface [kWh/m
2
]
6
5
4
3
2
1
0
1
2
Jan.
Feb.
Marh April May
June
July
Aug.
Sep.
Oct.
Nov.
Dec.
Figure 26:
(Multiconsult 2013, p. 8)
30
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Solar thermal collectors
Solar thermal collectors collects heat by absorbing the sunlight. This heat can later be
converted to electrical energy by heating a fluid to drive a turbine. Using solar energy
directly to heating in Norway is considered not to be desirable as the radiation is very small
when the demand for heating is high during the winter (KanEnergi and SINTEF 2011, p. 44).
A typical solar collecting system for heating homes is estimated to produce/store heat to a
price of about 70 – 120 øre/kWh
(thermal)
(KanEnergi and SINTEF 2011, p. 65). This is the same
as 0.583 – 1.000 DKK/kWh, 11.49 – 19.69 ISK/kWh and 0.0781 – 0.1339 EUR/kWh by the
exchange rate of July 30, 2015.
The practical potential of solar thermal collectors for heating homes and other buildings by
2020 is estimated to be 1.6 TWh
(thermal)
per year(KanEnergi and SINTEF 2011, p. 65). The
potential is reached if solar collectors are installed on all the new and renovated buildings by
2020. An estimate of what is actually realistic to expect is a production between 53 and 66
GWh
(thermal)
per year by 2020(KanEnergi and SINTEF 2011, p. 65).
Solar cells
Solar cells, or photovoltaic cells (PV), converts the radiation energy in the sun lights directly
into electricity by the photovoltaic effect. The potential of producing electricity from solar
cells is very high, even in Norway, but high costs stands in the way of the development. The
most resent overview of the installed capacity found is from 2011. The overview estimates
the installed capacity of solar cells in Norway to be about 8MW, which of only 7 % was
connected to the power grid (KanEnergi and SINTEF 2011, p. 51).
The practical potential of solar cells is estimated to be 4.4 TWh per year by the year 2020
(KanEnergi and SINTEF 2011, p. 65). The potential is reached if solar cells are installed on
roofs and facades on all the new and renovated buildings by 2020. In this estimate big solar
power plants that deliver power to the grid are not included as they are not expected to be
able to compete in the Norwegian energy marked by 2020. In the past decade the costs of
solar cells have decreased tremendously while the efficiency is constantly being improved. If
the development continues the power from solar cells will sometime in the future be
competing with power from other sources, even in Norway, and the potential will be very
much higher, almost unlimited. (KanEnergi and SINTEF 2011, p. 51, 65 and 66).
Offshore renewable energy
The ocean is an enormous source of energy that is powered by the sun, geothermal sources,
the earth's rotation and gravitation. Hydrothermal processes drive the energy transport in
the ocean and the Norwegian Sea and the North Sea annually gets a lot of energy from the
coast outside North America in the form of hot water that is transported by the Gulf Stream.
Norway has a long coast line and big properties in these two seas as well as Skagerrak and
the potential of renewable energy is gigantic. Regarding offshore renewable energy is this
report focusing on wave, tidal and wind, but it could also be conceivable to produce
electricity from the salinity gradient.
31
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0144.png
Wave
In a study ordered by Enova SF, a Norwegian government enterprise responsible for
environmental friendly production of electricity, published in from 2007, the potential of
wave power in Norway was estimated to be 600 TWh annually (SWECO Grøner, ECON, and
Kjeller Vindteknikk 2007). About 12 – 30 TWh was considered to be possible and realistic to
develop. (SWECO Grøner, ECON, and Kjeller Vindteknikk 2007)
The waves are generated by the wind,
which is powered by the pressure
gradients in the air. The energy transfer
occurs in the top layer of the sea and to
utilize it devises that transfers the
mechanical energy into electricity need
to be installed here. Near the coast can
refraction and reflection phenomena
cause the energy to focus in certain
geographic areas. These areas make
suitable locations for power plants. The
power in the waves changes a lot
throughout the year. Even in the best
areas the potential power in the
summer is less than 15 KW/m, in the
same areas it increases up to 125
kWh/m in the winter (SWECO Grøner,
ECON, and Kjeller Vindteknikk 2007, p.
Figure 28:
(SWECO Grøner, ECON, and Kjeller Vindteknikk 2007, p. 8)
9). Figure 28 shows the annual mean
wave power density per meter along the coast.
However, the development of wave power plants is in conflict with other preexisting
industries in the region like the fish industry and the oil industry. Another challenge that
faces wave power is whether it will be profitable in the near future. Many different solutions
has been designed and developed, but they are yet to be commercialized enough to get the
prices down.
Tidal
Table 2 shows is the potential of tidal power estimated to be about 1.2 TWh annually in
Norway with a maximum power output of 337 MW. The table only includes fjords, straits
and other suitable locations north of Bodø, a city in the middle of Norway. There are fewer
fjords and strait from Bodø and southwards to Trøndelag and the ones in the region are
orientated in a way that the tides do not give rise to strong currents. Further south the tidal
variations decreases and no locations are considered to be suitable for generating electricity.
The tidal variations in the different parts of Norway are illustrated in Figure 29. LAT stands
for "Lowest astronomical tide" and correspondingly HAT means "Highest astonomical tide"
32
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0145.png
Only locations with water flow of 3 knots (about
1.5 m/s) or more are included as this is considered
to be the minimum velocity needed to be
profitable as the energy increases with the
velocity cubed. The numbers in the table are
based on the assumption that about half of the
cross section of the flow can be utilized by
different technologies giving a total efficiency of
about 40 %. Some of the locations included in the
potential cannot fully be utilized for different
reasons. One reason is that some of the locations
are currently partly protected. Another reason is
that big power plants would interfere with the
shipping industry in some locations. Because of
these reasons is the practical potential of tidal
power in Norway somewhat less than 1.2 TWh
annually. (SWECO Grøner, ECON, and Kjeller
Vindteknikk 2007, p. 10 and p. 11)
Fjord/strait/location
Saltstraumen
Sundtstraumen
Tysfjorden
Moskenstraumen
Nappstraumen
Gimsøystraumen
Moholmen
Raftsundet
Strauman/Øksfjorden
Risøysundet/-renna
Ballstadstraumen
Sandtorgstraumen
Ramsundet
Rystraumen|
Kvalsundet i Troms
Skagerøysundet
Kågsundet
Utenfor Sørøya
Kvalsundet i Finnmark
Straumsfjorden
Vargesundet/Straumen
Måsøysundet
Magerøysundet
Utenfor Nordkinnhalvøya
Total Norway
Power
[MW]
9
1
0
216
5
4
1
2
0
4
1
2
2
10
5
4
6
4
14
3
21
9
10
3
337
Energy
[GWh]
30
30
0
758
18
15
5
6
0
15
3
5
8
36
17
14
22
14
48
12
72
32
34
9
1178
Table 2:
SWECO Grøner, ECON, and Kjeller
Vindteknikk 2007, p. 11)
Figure 29:
(SWECO Grøner, ECON, and Kjeller Vindteknikk 2007, p. 10)
33
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0146.png
Wind
The offshore wind potential in Norway is
huge.
Table 3
shows that the total estimated
potential is about 14,000 TWh. The potential
is calculated using the efficiency of already
existing windmills and measurements and
simulations of the weather throughout the
year. How much electricity it is possible to
produce of it is essentially not limited by the
available energy, but by the power market
and other practical relations. Those
limitations are e.g whether the seafloor
makes an acceptable foundation, distance to
the power grid and conflict of interest with
other industry. (SWECO Grøner, ECON, and
Kjeller Vindteknikk 2007, p. 14 -20)
Area
Water depth
Energy
[TWh]
6.8
334
2320
2660
100
51
3740
3890
0 – 30 m
South of Lat. 61ºN
30 – 60 m
60 – 300 m
Total
0 – 30 m
30 – 60 m
Lat. 61ºN to Lat. 67.5ºN
60 – 300 m
Total
0 – 30 m
17.6
Table 3:
(SWECO Grøner, ECON, and Kjeller Vindteknikk
2007,
Lat.
North of
p. 20)
67.5ºN
30 – 60 m
486
60 – 300 m
6910
Most of the available energy is far away
Total
7420
from the coast and the power grid, but the
0 – 30 m
125
potential energy closer than 20 km to the
Sum
30 – 60 m
871
shore is still a lot, about 200 TWh annually
60 – 300 m
12970
(SWECO Grøner, ECON, and Kjeller
Vindteknikk 2007, p. 20). Windmills that are
Total
13970
fixed to the seabed can be installed on
locations where the sea is less than 60 meters deep. On locations where the sea is from 60
to 300 meters deep floating structures have to be used. Most of the available energy is
found in these areas, but the technology to utilize it on a large-scale is not quite ready yet.
Locations where the sea is deeper than 300 meters are considered to be unlikely to utilize as
the price for anchoring the turbines are too high. (SWECO Grøner, ECON, and Kjeller
Vindteknikk 2007, p. 16)
References
Fornybar.no. 2015.
“Geotermisk energi.”
Accessed July 30, 2015.
http://www.fornybar.no/nye-
teknologier/geotermisk -energi
KanEnergi, and SINTEF. 2011.
"Mulighetsstudie solenergi i Norge.”
Accessed July 31, 2015.
http://www2.enova.no/publikasjonsoversikt/publicationdetails.aspx?publicationID=637
Multiconsult. 2013.
“Kostnadsstudie, Solkraft i Norge 2013.”
Accessed July 31, 2015.
http://www2.enova.no/publikasjonsoversikt/publicationdetails.aspx?publicationID=654
Norconsult AS. 2012.
"Studie dypgeotermisk energi.”
Accessed July 30, 2015.
http://www2.enova.no/minas27/publicationdetails.aspx?publicationID=608
Norwegian Ministry of Petroleum and Energy. 2014.
"Facts 2015 – Energy and Water
34
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Resources in Norway."
Accessed June, 2015.
https://www.regjeringen.no/contentassets/fd89d9e2c39a4ac2b9c9a95bf156089a/facts_201
5_energy_and_water_web.pdf
Norwegian Water Resources and Energy Directorate (NVE source 1). 2005.
“Vindkraftpotensialet for Norge.”
Accessed July 28, 2015.
http://www.nve.no/Global/Publikasjoner/Publikasjoner%202005/Rapport%202005/Rapp%2
017-2005.pdf
Norwegian Water Resources and Energy Directorate (NVE source 2). 2009.
“Vindkart for
Norge.”
Accessed July 28, 2015.
http://www.nve.no/Global/Publikasjoner/Publikasjoner%202009/Oppdragsrapport%20A%2
02009/oppdragsrapportA9-09.pdf?epslanguage=no
Norwegian Water Resources and Energy Directorate (NVE source 3). 2015. “Vindkraft
-
Produksjon i 2014.”
Accessed July 28, 2015.
http://publikasjoner.nve.no/rapport/2015/rapport2015_18.pdf
Norwegian Water Resources and Energy Directorate (NVE source 4). 2015.
“Geotermisk.”
Accessed July 30, 2015.
http://www.nve.no/no/Energi1/Fornybar-energi/Geotermisk/
Norwegian Water Resources and Energy Directorate (NVE source 5). 2015.
“Solenergi.”
Accessed July 30, 2015.
http://www.nve.no/no/Energi1/Fornybar-energi/Solenergi/
Ssb (Statistics Norway). 2015.
“Statistics Norway.”
Accessed June and July, 2015.
http://www.ssb.no/en/
Statnett. 2015.
“Drift og marked.”
Accessed July 17, 2015. http://www.statnett.no/Drift-og-
marked/Nedlastingssenter/Last-ned-grunndata/
SWECO Grøner, ECON, and Kjeller Vindteknikk. 2007.
“Potensialstudie på havenergi.”
Accessed August 4, 2015.
http://www2.enova.no/publikasjonsoversikt/publicationdetails.aspx?publicationID=266
35
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0148.png
6. Timescale and licensing process
The licensing process in Norway is thorough and detailed. The process involves
governmental bodies, stakeholders and public interests. In each step of the process public
consultation is a major part. Decisions on licenses for new major power lines longer than 20
Kilometers carrying a voltage of 300 kV or more are now made by the King in Council. The
NVE is still responsible for normal licensing procedures, but not for making a decision on
whether to grant a license. Instead, they consider applications in a normal way, but will not
make decisions as the authority of first instance. Instead, the NVE submits its
recommendation to the Ministry. The Ministry holds a public consultation on the
recommendation for consultation, and prepares the matter for the King in Council, who
makes a decision on licensing. Such decisions cannot be appealed.
Figure 30 show the authority process for licensing
Several factors have impact on the time spent on license processing, for example the conflict
level and complexity of each project. Energy projects are most likely to affect commerce and
industry, local communities, the environment and other user interests. The licensing
authority is responsible for ensuring that a project has been thoroughly assessed and
described before a decision is made, and must during the application procedure consider the
need for additional studies of various topics and supplementary statements on issues raised
during the process. For new interconnectors it is crucial that the projects are socioeconomic
profitable and contributes to safety and stability.
36
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0149.png
7. CO
2
emission
The Norwegian parliament on 25th of March 2015 approved a plan that will see the country
take on a target to reduce carbon emissions at least 40% below 1990 levels, pending a
bilateral agreement with the EU, and implement a national climate law.
The decision means Norway will go through with its plan to pledge a minimum cut of 40%
from 1990 levels in its
INDC,
which will be submitted to the UN before the end of the month,
but make the target dependent on reaching a deal with the EU next year on bilateral
cooperation. “Within the emissions trading sectors Norway will contribute to achieving a 43
percent cut in emissions compared to 2005 within the EU Emissions Trading System,” the bill
said.
The country’s power and heavy industrial sectors are already linked to the
EU ETS,
but
Norway’s bilateral negotiation also foresees Norway linking regulation under remaining non-
ETS sectors such as transport, agriculture and buildings. “The target will likely be to cut
emissions in the sectors outside the EU ETS with 40 percent by 2030 compared to the 2005
level,” said Stig Schjolset, an Oslo-based analyst with Thomson Reuters Point Carbon.
“Norway will buy a substantial, but not yet defined, amount of
CERs
to comply with the 2020
target under the Kyoto Protocol, while it will have access to flexible mechanisms at EU level
to ensure compliance with the 2030 target,” he said.
Figure 31 shows the annual
carbon dioxide emission to air
in Norway by source. From
1990 to 2014 it increased by
over 25% and has maintained
quite stable since 2009. The
share of the emission from oil
and gas extraction has
increased the most in the
period. Also the emission
associated from the energy
supply has amplified since
2008. In 2014 the total
emission from all the sources
was over 44 megatons carbon
dioxide.
CO
2
-Emission to Air by Source
50
45
40
35
30
25
20
15
10
5
0
1990199219941996199820002002200420062008201020122014
Other
Agriculture
Aviation, navigation, fishing, motor equip. etc.
Road traffic
Heating in other industries and households
Energy supply
Manufacturing industries and mining
Mt CO
2
Figure 31:
(Ssb 2015, table 08940)
37
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0150.png
Emissions of other greenhouse gasses
Other greenhouse gases (GHG) are also emitted
throughout the year. The different gasses have very
different characteristics and CO
2
is therefore used as a
reference gas. The amount of any GHG is converted to
the mass of CO
2
that would cause the same level of
radiative forcing.
Figure 32 shows that carbon dioxide was responsible
for most (82 %) of the radiative forcing from any GHG
in Norway 2014. In CO
2
-equivalent the total emission
added up to 55.8 Mt CO
2
and methane was the
second biggest contributor accountable for about
10%. The total emission has not changed much the
past decades, but the distribution has. HFK has
increased from no registered, or negligible, emissions
in 1990 and was in 2014 responsible for 2 % of the
radiative forcing. On the other hand have PFK and
SF6 emissions decreased significantly in the period.
GHG Emissions to Air in
CO
2
-Equivalents,
Distribution 2014
Total 2014: 55.8 Mt CO
2
Carbon dioxide (CO2), 82 %
Methane (CH4), 10 %
Nitrous oxide (N2O), 5 %
Hydrofluorocarbons (HFK), 2 %
Perfluorocarbons (PFK), < 1 %
Figure 32:
(Ssb 2015, table 08940)
GHG Emissions to Air by
industry in CO
2
-Equivalents,
Distribution 2014
The Pie chart in Figure 33 shows the
distribution of GHG emissions to air by
industry.
Sources:
https://www.ssb.no/en/klimagassn
Sources:
https://www.ssb.no/en/klimagassnrefere
Figure 33:
(Ssb 2015, table 09288)
38
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0151.png
8. Legal perspectives
The Storting (Norwegian parliament) determines the political framework for energy and
water resources management in Norway. The Government has the executive authority, and
exercises this through various ministries. Figure 44 show the state organization for energy
activities. Various Ministries are involved with the Ministry of Petroleum and Energy with the
Ministry of Petroleum and Energy has the overall responsibility for managing the energy and
water resources in Norway. The Ministry’s job is to ensure that this management is carried
out according to the guidelines provided by the Storting and the Government. The Ministry’s
Energy and Water Resources Department has ownership responsibility for the state-owned
enterprises Enova SF and Statnett SF. Interconnectors to countries outside of the Nordic
region require a license for facilitation of power exchange - a so-called foreign trade license.
The Norwegian Ministry of Petroleum and Energy processes the application.
Figure 34 shows Norway state organization of energy and water resources activities
Norwegian Water Resources and Energy Directorate The NVE, which reports to the Ministry
of Petroleum and Energy, is responsible for managing domestic energy resources, and is also
the national regulatory authority for the electricity sector. The NVE is also responsible for
managing Norway’s water resources and for central government functions as regards flood
and avalanche/landslide risk reduction. The NVE is involved in research and development
and international development cooperation, and is the national hydrology expert body.
Enova is a state-owned enterprise that manages the assets in the Energy Fund. Enova’s
objective is to promote a shift to more environmentally friendly consumption and
production, as well as development of energy and climate technology.
39
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Statnett is the state-owned enterprise responsible for building and operating the central
grid. The enterprise is the transmission system operator (TSO) for the central grid and owns
more than 90 per cent of it. Statnett is responsible for both short- and long-term system
coordination, responsibility for ensuring the instantaneous power balance, and facilitating
satisfactory quality of supply throughout the country.
One of the objectives of Norway’s legislation is to ensure that these different interests are
heard and considered, and that the various measures are subject to government control and
conditions that safeguard these interests. The legislation is also intended to ensure effective
management of our resources. Security of energy supply and a well-functioning power
market are key considerations here.
Comprehensive legislation applies to the energy sector and to water resource management.
The most important legislation governing these areas is:
Water Resources Act,
the Watercourse Regulation Act,
the Industrial Licensing Act,
the Electricity Certificate Act,
the Offshore Energy Act and the Energy Act,
There are also a number of other statutes that are significant for energy and water
resources. With the exception of the natural gas legislation, these statutes are administrated
by authorities other than the Ministry of Petroleum and Energy and the NVE.
• Planning and Building Act (Ministry of Local Government and Modernization)
• Nature Diversity Act (Ministry of Climate and Environment)
• Expropriation Act (Ministry of Justice and Public Security)
• Competition Act (Ministry of Government Administration,
Reform and Church Affairs)
• Natural Gas Act (Ministry of Petroleum and Energy)
• Consumer Purchases Act (Ministry of Justice and Public
Security)
• Pollution Control Act (Ministry of Climate and Environment)
• Neighboring Properties Act (Ministry of Justice and Public
Security)
• Cultural Heritage Act (Ministry of Climate and Environment)
• Outdoor Recreation Act (Ministry of Climate and Environment)
• Reindeer Husbandry Act (Ministry of Agriculture and Food)
• Public Administration Act (Ministry of Justice and Public
Security)
Energy policy is an important area for the EU, and a number of directives and regulations in
this field have been incorporated into Norwegian regulations and legislations.
40
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0153.png
Shetland Islands Council
Appendix E
North Atlantic Energy Network
Shetland
1
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Table of Contents
Shetland .................................................................................................................................................. 1
Introduction........................................................................................................................................2
Conclusions.........................................................................................................................................4
Transmission system ........................................................................................................................... 5
Electrical energy production ............................................................................................................... 5
Shetland’s Energy Mix 2015 ............................................................................................................ 5
Overview of Electricity Generation in Shetland .............................................................................. 5
Generation Capacity....................................................................................................................... 6
Heating ........................................................................................................................................... 9
A New Energy Solution for Shetland ............................................................................................. 10
Sub-Sea Interconnector ............................................................................................................... 11
Renewable Energy Developments on Shetland ............................................................................ 12
Viking Energy................................................................................................................................. 12
Wave and Tidal Energy.................................................................................................................. 14
Electrical market (prices) .................................................................................................................. 15
Benefits (interests) ............................................................................................................................ 16
Interconnectors from Iceland, Faroe and Norway........................................................................ 16
Potentials .......................................................................................................................................... 17
Timescale for each energy sources ................................................................................................... 17
Additional cost .................................................................................................................................. 17
CO
2
emissions.................................................................................................................................... 17
References ........................................................................................................................................ 18
2
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Introduction
The Shetland Islands are located at the latitude 60 degrees north and longitude 1 degree west; the
same latitude as Bergen, Oslo and the Southern tip of Greenland. The capital, Lerwick is about 360
km west of Bergen and 365 km SE of Torshavn. The North of Scotland, Duncansby Head, is about
200km from Lerwick and the main shipping port of Aberdeen, 340km.
Shetland is an Archipelago of 100 islands, 15 of which are inhabited. The islands, including Fair Isle,
stretch north to south about 160 km and have an area of 1,468 square kilometres, with a long
indented coastline of 2,702km.
The waters of the Atlantic and North Sea surrounding Shetland are warmed by the North Atlantic
Drift, an extension of the Gulf Stream. The islands have a maritime climate, with a max average daily
mean of 14.4 degrees Centigrade in August and an average minimum of 1.1 degrees Centigrade in
February. It doesn’t get particularly cold in Shetland during the winter but the islands are in line for
many of the fierce Atlantic storms and weather systems that track through. The sea around
Shetland is rich in nutrients, the phytoplankton and zooplankton provide the bases of a food chain
that support commercial fish stocks and over 1 million breeding pairs of seabirds, as well as a large
variety of marine mammals.
Shetland’s commercial fishery has been the mainstay of the Shetland economy for several centuries.
The modern fishery is a highly mechanised and energy intensive industry. Fish catching and
processing of pelagic and whitefish; along with aquaculture, salmon farming and mussel farming
contribute over £300 million to the Island’s economy.
For the last 40 years Shetland has proven to be a strategic location, in the heart of the UK oil and gas
industry with its close proximity to the North Sea and West of Shetland Oil and Gas fields. The
Sullom Voe Oil Terminal and the soon to be commissioned Total Gas plant are important
infrastructure in the UK sector, handling oil and gas production. The Ninian & Brent pipelines land at
the Sullom Voe Terminal with an oil pipeline from the West of Shetland Clare field and Lagan
Toremore gas pipeline, as well as the Magnus EOR pipeline.
Oil and gas contributes approximately £70m to the local economy through local businesses and
services supporting the sector on Shetland. The operation of the terminal and also the transport of
personnel to offshore installations are significant sources of employment in Shetland. Sullom Voe
Terminal, since production started in 1978, has seen circa 8 billion barrels flow through it and has
been a major contributor to the UK exchequer.
Agriculture and tourism, although smaller industry sectors are important contributors to the
Shetland economy, particularly in rural areas; Shetland also has a vibrant creative industries sector
including knitwear and music that bring World-wide recognition to the islands. Being an island
group remote from the Scottish Mainland, there is a large public service sector to meet the needs of
the community. Shetland has a low unemployment rate of about 1%.
3
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0156.png
Shetland – Economic Output Value 2011 = £1.091 billion
Industry Sector
Fisheries & Aquaculture
Oil Terminal
Oil Supply Services
Marine Engineering
Tourism
Agriculture
Textiles
Construction
Other Manufacturing
Ports & Harbours
Retail & Distribution
Public Services
Other Services
£ millions
310
46
25
11
17
18
4
89
11
23
68
205
120
Harnessing the potential of Shetland’s abundant renewable energy resource will reduce Shetland’s
reliance on imported fossil fuels, reduce carbon emissions and has the potential to establish a new
industry sector. The Burradale wind farm has pioneered commercial renewable energy on Shetland
and proven the exceptional wind regime; two Vestas V52 and three V47 wind turbines have
produced electricity consistently at over a 50% capacity factor each year since their blades started
turning in 2001.
Conclusions
The submission of Scottish Hydro Electric Transmission’s (SHE-T) needs case for developing a 600
MW transmission cable between Shetland and the UK national grid, is expected to be submitted to
the UK electricity regulator Ofgem in 2016. The innovative, 284 km, single circuit, HVDC sub-sea
cable, would allow for the Viking Energy island onshore wind farm on Shetland to be constructed
and generate ca. 400MW of electricity. The interconnector project has been driven by the wind
farm development and will only be built if Viking Energy Partnership secures a contract to supply its
low carbon electricity to the UK electricity market; under the Contract For Difference (CFD) bidding
process now expected in late 2016.
The Shetland to UK interconnector project has been in process for over a decade and is the main
focus for harnessing Shetland’s exceptional wind resource. The North Atlantic Energy Network has
highlighted the potential for Iceland and Faroe to export renewable energy to electricity markets in
the UK, Norway and connect to the wider European grid. Cable routes from Iceland to the UK are
currently being investigated and Faroe also has an interest in securing a supply of renewable energy
from Iceland.
Shetland could become a strategic location for grid connection with the commissioning of a HVDC
connection to the UK National Grid. Any cable from Iceland would most likely require additional
capacity but an interconnector between Faroe and Shetland could provide electricity supply to Faroe
and an export route for Faroese renewable generation into the UK; utilising head room in the
4
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Shetland to UK cable. The renewable energy developer Element Power is working on a proposal for
an interconnector between Shetland and Norway. The ‘Maali’ interconnector project is at an early
investigative stage but is included in the EU Ten Year Network Development Plan 2016. A
transmission link between Shetland and Norway would make Shetland a more attractive landfall for
an Icelandic or Faroese cable that would in turn strengthen the case for the ‘Maali’ link.
A scenario with additional interconnectors provides a more secure transmission network, improving
the security of supply to Shetland consumers. The ‘Maali’ link from Shetland to Norway would allow
the flow of electricity to Norway north from the UK grid and East from Shetland; an alternative to
electricity always having to flow south into the UK grid and reducing the occurrence of bottle necks
in the transmission network, that require wind generation in the north of Scotland to be constrained
off the grid. A renewable energy mix of hydro, geothermal and wind; from Iceland, Faroe and
Norway, could provide a very good balance to UK renewable generation. With a diverse energy mix
and wide geographical spread of wind resource, the energy of weather systems can be harnessed as
they travel across the regions. This can provide a much more consistent supply of renewable energy
to the UK and reduce the requirement for back up generation from fossil fuels.
The North Atlantic Energy Network has explored the potential of connecting up some of the best
renewable energy sources in the Arctic, Nordic and northern European regions to the large energy
markets of the UK and European continent. The project has allowed informative exchange of
knowledge between the participating regions and organisations. Shetland’s immediate focus is on a
new energy solution for the islands; the Shetland to UK interconnector and Shetland generation
projects but realises the potential and scale of developments within the NAEN regions could include
Shetland in a wider transmission network. Shetland values the continued co-operation with NAEN
project partners and wishes to be kept informed of future developments.
Transmission system and production
Electrical energy production
Shetland’s Energy Mix 2015
Shetland’s electricity is supplied predominantly from fossil fuels in the form of fuel oil generation,
gas fired generation, with a contribution from windpower and micro renewables.
Shetland has a population of 23,240. Around half of the islands population live within 10 miles of
Lerwick and the main power station. As there is no mains gas supply a large number of consumers
rely on electricity for heating, hot water and cooking. The average household electricity
consumption in Shetland is 10,348 kWh pa, twice the Scottish average.
Overview of Electricity Generation in Shetland
Units of electricity generated in 2013 were 214,185,500 kW hrs
Maximum Demand in 2014 of 45.5MW
Minimum Demand in 2014 of 11MW
The electricity network has 1,650km of overhead lines and underground cables operating at
33kilovolts and below. There are 13 subsea cables joining up smaller islands.
5
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0158.png
Lerwick Power Station and a map of the Shetland distribution grid.
Generation Capacity
Lerwick Power Station (67MW)
– Medium and Heavy Fuel Oil meeting around 52% of Shetland
demand over the course of a year. All but one of the engines in the plant is over 25 years and half
the plant has now been in service for over 35 years. This plant is planned for replacement as it can
no longer meet permitted EU emissions levels.
Sullom Voe Terminal Power Station (15MW)
The Sullom Voe station is a 100MW gas fired power station which was developed in the 1970s solely
to meet the oil terminal’s full electricity demand. 15MW of this is put into the Shetland grid. The
contract with Sullom Voe Power Station is up for renewal; there is no guarantee that the plant will
continue to supply power to the Shetland grid.
The map above shows the proximity of Shetland to the North Sea oil and gas fields and the
developments west of Shetland. The supply of offshore facilities with electricity from onshore
generation has been under investigation in the Norwegian oil and gas sector. With a robust grid
infrastructure in the North Atlantic, there may be scope to investigate the electrification of oil and
gas installations in the UK sector from shetland or passing subsea infrastructure.
6
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0159.png
Burradale Windfarm
Burradale windfarm
Burradale Wind Farm (3.68MW) was commissioned in the year 2000 and consists of five Vestas wind
turbines. The windfarm has an average load factor of 52% since it began production. A 900kW and
a 3MW Enercon wind turbine have recently connected to the grid close to Lerwick; bringing the total
installed wind capacity, along with micro renewables up to approximately 8.9 MW
This bar chart compares the capacity factor of the Burradale wind farm and the average capacity
factor for UK wind farms. It can be clearly seen how much more wind energy there is in Shetland.
7
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0160.png
The electricity production from wind turbines located in Shetland is significantly higher than the UK
average capacity factor. This map shows annual mean wind speed for the UK, Shetland stands out
in red. Many of the hills having an average wind speed above 10m/s.
8
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0161.png
Heating
Above: The incinerator plant in Lerwick that generates the majority of heat to its 400 customers on
the Lerwick district heating scheme.
The district heating scheme in Lerwick has a capacity of around 10 MW of heat. The heat source is
from incineration of municipal waste and some oil and biomass. Biomass is also used in some rural
villages to heat larger public buildings. Biomas accounts for around 1.5 MW of heat capacity. This
biomass capacity is expected to increase over the next few years as a number of large buildings such
as leisure centres with swimming pools are replacing oil fired boilers with biomass. The biomass is
from a mix of waste wood, imported pellets and also timber that is shipped in, dried and chipped.
Many households use oil fired boilers and some solid fuel, coal and peat for heating.
There is potential to use windpower in combination with a large thermal store to reduce the
requirement to meet peak demands at the Lerwick district heating scheme with the use of oil
boilers. Shetland Heat Energy and Power, operators of the district heating scheme are also
investigating the potential of a seawater heat pump as another heat source.
Northern Isles New Energy Solutions (NINES)
This project was developed by Scottish Hydro Electric Power Distribution to look at reducing
maximum demand in Shetland; increasing renewable generation output; reducing the reliance of
fossil fuels and reducing the size and cost of a replacement energy solution for Shetland.
The system uses active network management servers to control storage via a 1MW battery; and via
domestic demand side management for 234 homes connected via the NINES trial and linked to
renewables generation output.
9
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0162.png
A New Energy Solution for Shetland
Various consultations on a new energy solution for Shetland have been undertaken over the last few
years. As far back as 1997 replacement options for the Lerwick Power Station were being discussed;
that included as an option, a sub-sea interconnector to the UK Mainland and the National Grid. The
decisions are still to be made in regard to the replacement for the Lerwick Power Station, with some
generating plant over 35 years old. The Lerwick power station is also in breach of permitted EU
emissions levels under the combustable plant directive and is another reason that a new plant is
required. The cost of the Electricity supply to Shetland customers is subsidised across the
consumers of the North East of Scotland to around the sum of circa £30 million per annum and a
new energy solution should look at how this figure can be reduced. When this is taken into account
over the cost of an interconnector it has a net present value figure of around £250 million.
The proposed replacement power station was to be generating by 2017 and a plan was presented
that incorporated the NINES project and a new modular 90MW dual fuel power station. This
proposal was rejected by the UK electricity regulator Ofgem and they wanted Scottish and Southern
Energy Power Distribution to carry out a competitive process to seek solutions from the market to
ensure the most cost effective and efficient solution could be found. The outcome of this bidding
process is expected to be completed by the end of 2015, with an outcome to be announced in
March/ April 2016. We are aware of one potential bidder to a future energy solution for Shetland
that would incorporate a sub-sea interconnector to the Scottish Mainland in their plan (This is
seperate from the proposed interconnector for the Viking Energy windfarm project) . The details of
this will only be clear after the tendering process. The cable option would allow more renewable
energy production to contribute to the energy mix on Shetland. A new energy solution for Shetland
is estimated to be in place no sooner than 2019 or 2020.
Scottish and Southern Energy diagram showing and overview of the NINES system.
10
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0163.png
Sub-Sea Interconnector
To add to this scenario of a new energy solution for Shetland, SHE-T (Scottish Hydro Electric
Transmission) has been developing the needs case for a 600 MW cable between Shetland and the
UK. This process has been driven by the Viking Energy windfarm development which has planning
permission consented for 103 turbines on the Shetland Mainland. SHE-T have developed and
tendered an innovative, single circuit, 284 km sub-sea cable as the most cost-effective solution. It
would connect Shetland to the National Grid and be able to import power to supply Shetland
electricity customers as well as export wind power. A backup arrangement would have to be in
place in case of a cable break. SHE-T‘s needs case for the connection will be considered by the UK
electricity regulator Ofgem before it can proceed.
The subsea interconnector would make landfall in Weisdale Voe in Shetland, close to the proposed
Viking Energy wind farm site and Sinclair’s Bay on the north coast of the Scottish Mainland. The DC
convertor station will be located in the Kergord Valley in Shetland. Once it makes landfall on
Scotland it will join into a proposed hub for connecting renewable energy from the Northern Isles
and Caithness before heading down the Caithness to Moray 1200MW capacity subsea cable to the
Buchan coast and onwards. Caithness to Moray has been approved by Ofgem and is now under
construction (estimated completion, late 2018)
Proposed route of interconnector from Shetland to Scottish Mainland.
The interconnector and onshore hub at Sinclair‘s Bay would allow the UK to access a major source of
efficient zero carbon energy. It would also reduce the subsidy that is required to keep consumers
11
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
electricity costs in Shetland on a level with consumers in the North of Scotland. The Viking Energy
project would be the largest UK community-owned windfarm, with 45% of the project owned by
Shetland Charitable Trust.
Renewable Energy Developments on Shetland
There are a number of renewable energy developments being worked on in Shetland. At an
advanced stage, there is about 10 MW of generation looking to connect to Shetland’s existing
distribution grid as part of the NINES project. Most of these projects will have a non-firm connection
agreement so they can be turned off the grid at periods of low demand. Some of these projects are
looking at the use of heat, thermal stores and other solutions to make use of the power rather than
having to turn off generation and losing all the energy, these alternative uses of the power are at a
fairly early stage of development. There is also a proposed 500kW tidal turbine array planned for
Bluemull Sound, the project has a grid connection under NINES. This tidal turbine technology has
been developed by Scottish Company, Nova Innovation Ltd. They have had a 30kW, grid connected
device deployed in Bluemull Sound, Shetland and conducted sea trials on its performance. Nova
Innovation are currently deploying the first 100kW, second generation turbine, that will be used in
the 500 kW array.
Large scale renewable energy projects will all require an interconnector to the UK National Grid or
connect to a location that can take the power.
Viking Energy
Viking Energy has planning consent for up to 457 MW of wind generation and a contracted grid
export capacity of 412 MW. The proposed interconnector is for a 600 MW single circuit HVDC link.
Based on wind power in Shetland of up to 600 MW, around 2.3 TW hrs would be delivered down the
cable. The cable is a separate contracted process with the transmission owner SHE-T currently
designing a connection for 600 MW. A date for landfall is 2020 and connection for 2021. The needs
case for the connection that looks at the technical and economic case has to be approved by Ofgem,
this is a two stage process. The submission of the initial needs case is expected to be made in 2016;
if approved, the interconnector project would move into Ofgem‘s assessment stage; this sets a
budget with an agreed spend and return by SHETL on the project, with a decision expected in early
2017. The Viking Energy Windfarm would pay an annual use of system charge for transmission over
the interconnector. It is planned for Viking to bid into the Contract for Difference(CFD) process; if
successful they will secure a contract to sell power into the UK energy market. The CFD contract
requires Viking Energy to meet a commitment to have the windfarm operational in line with that of
the connection dates of the cable. Viking Energy expect to enter the bidding process in late 2016
with wind generation from islands competing with offshore wind for CFDs. The Viking project would
aim to be at financial close in early 2017 based on current CFD contract timescales. Work is now
underway with the procurement process, including early discussions with turbine manufactures and
civil engineering contractors.
12
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0165.png
Photomontage of what the Viking windfarm would look like in Da Lang Kames, Shetland.
Proposed layout of the Viking Energy windfarm.
The development of renewable energy in Shetland aims to diversify the Shetland economy and
generate income to the community. The Viking energy project estimates an annual income to the
Shetland economy of £37 million per annum. The wind farm will produce enough electricity to
supply around 4% of Scotland‘s electricity demand.
The Viking project is ca 400 MW which means there would be spare capacity or ‘headroom‘ on the
interconnector for other generation. There are 2 further wind energy projects planned on Shetland
that are looking to secure space on the interconnector cable. None of these projects have formally
signed up for capacity on the cable as yet but are scoping for planning and have done some public
consultation as well as environmental studies. The project owned by Peel Wind Farms (Yell) Ltd is a
70MW project in South East Yell. Peel Wind is running a second round of consultation with the local
13
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0166.png
community, having revised their site layout based on local feedback on their initial plan. The other
project is a consortium of 18 Shetland businesses with a project called ‘Energy Isles’ looking at 150-
200MW of wind power in North Yell. Both projects would require to connect to the HVDC convertor
station in Kergord. This connection would involve a short subsea crossing from Yell to the Shetland
Mainland and some overland cabling.
Beyond these projects there is significant additional interest but it is difficult to come up with a
figure of how much more onshore wind is likely to be granted permission, given potential planning
and environmental constraints.
Wave and Tidal Energy
Winter Storm, Stenness, north west Shetland.
At the current rate of advancement in generation technology and the construction of necessary grid
infrastructure; the development of the wave and tidal industry in Scotland is thought to be at least
10-15 years away from seeing large scale commercial projects.
Maps showing Shetland‘s tidal and wave resources.
In Shetland, initial approaches have been made by wave and tidal developers to look at smaller
semi-commercial/ demonstration projects. This has been limited by constraints on the Shetland
grid. Resource assessment mapping and modelling has been undertaken for wave and tides around
Shetland and this data incorporated into the Shetland Marine Spatial Plan. Also initial planning
14
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0167.png
guidance has been issued on Marine Renewables. With so much of Shetland’s economy relying on
the use of the waters around Shetland for fishing and aquaculture, as well as other marine traffic, it
was felt important to look at potential marine renewable energy developments in context with other
marine uses and location of facilities around Shetland. This approach is aimed at saving developers
time in searching out suitable sites for developing their projects as well as providing all relevant
contacts to be able to consult with other marine users.
Nova Innovation‘s 30kW tidal stream turbine deployed in 2014 and the base of the first 100kW
machine now being deployed in September 2015.
Another marine energy concept has been investigated by the private sector, is a bridge between the
islands of Unst and Yell which could allow for the development of some tidal stream generation.
This project could be in the region of 40MW. For this project to go ahead it would most likely
depend on a level of generation capacity in Yell and Unst large enough to justify the cost of
connection back to the Shetland Mainland and Interconnector convertor station.
There is a huge potential for marine renewables in Shetland waters but at the moment the
technology is not there for large scale commercial developments and they will require access to the
grid. Shetland Companies already benefitting from the sector are Delta Marine Ltd who are involved
in servicing the offshore wind sector and specialise in wave and tidal installations. They have
worked in many countries and have also gained considerable experience in Orkney at the European
Marine Energy Centre where a number of wave and tidal devices have been deployed and
undergone trials. In the photo above, Delta Marine can be seen with one of their multipurpose work
vessels working with the Nova Innovation tidal device. Shetland Composites is another Shetland
business that has gained work from the wave and tidal sector, recently they have made blades for
tidal prototypes, the Nova Innovation devices being deployed and components for wave and tidal
test tank facilities. Shetland Composites also refurbished the blades of the Vestas wind turbines at
Burradale Windfarm. After 10 years of production the blades were in need of an overhaul, retipping
and resurfacing was carried out locally and paint systems applied. The refurbishment shows that
these skills are already available in Shetland.
Electrical market (prices)
In the case of the Viking Energy project it is bidding into the UK market under a CFD contract in
competition with offshore wind generation. When it comes to the trading of electricity between
different markets such as Iceland and Faroe, into the UK they would have to agree a mechanism to
allow the export of power into the UK market. This is an area that would require further
examination as to how any renewable projects build their business case.
15
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Benefits (interests)
Interconnectors from Iceland, Faroe and Norway
In terms of Shetland interconnectors, the focus has been on the 600MW interconnector to the UK
National Grid. The interconnector is scaled to match what the level of generation that is likely to be
developed on Shetland with a high level of certainty and not leave a ‘stranded‘ asset.
A cable from Faroe, Iceland or Norway would strengthen the security of supply to Shetland
customers compared with the single circuit planned to the UK National Grid, reducing the use of
fossil fuel back up. It would allow for the use of a clean cost effective hydro and geothermal sources
of renewable generation as opposed to the fuel oil to back up locally generated windpower in the
event of down time on the connection to the National Grid. It would also provide security of
connection for the renewable wind generated electricity being exported from Shetland.
Another possibility is that a connection to any source of hydro generation, geothermal or additional
wind, from a location experiencing different weather patterns, could ensure that the UK to Shetland
interconnector is fully utilised and would further improve the economics of the connection to the UK
National Grid. At times of high wind production on Shetland or other connected areas it can be used
to save on hydro resource. The project being investigated by Element Power called Maali is
proposing an interconnector between Shetland and Norway. The landfall in Norway being
somewhere north of Bergen. The Maali project is based on the 600 MW link going ahead between
Shetland and Scotland. The aim is to provide a more robust grid network between countries and
allow windpower in Scotland to be exported at times it is constrained off the UK grid; possibly
conserving Norwegian hydro power. At times of low wind energy, the cable would enable the
import of hydro electricity from Norway. The Maali project is part of the EU Ten Year Network
Development Plan 2016.
The scale of the export planned from Iceland in the longer term to the UK may be far beyond what
can be used on Shetland and the proposed interconnector network of 600MW. However the initial
600MW proposed cable may be large enough to take some of the readily available hydro and
geothermal power that does not require further planning and development in Iceland. A route from
Iceland through Faroe and connecting to the UK National Grid in Shetland would provide to some
extent the same benefits in Faroe as previously described for Shetland. The planned interconnector
from Shetland to the UK will certainly reduce the amount of subsidy required to keep electricity bills
in Shetland at a comparable level to consumers on the Scottish Mainland. The additional link to
Faroe and Iceland would increase the security of supply on Shetland and export links.
It is also possible that demand for a second circuit could be triggered between Shetland and the UK
National Grid if additional generation were to connect from Iceland, Faroe and Norway. If marine
renewables were to be developed around Shetland on any significant scale in the future it is likely to
require a second circuit. Links to other generation sources such as Hydro, Geothermal and
additional wind from Faroe, Iceland or Norway could help build a case for a second Shetland to UK
circuit and a marine renewables sector.
There would be significant economic benefits for Shetland in the development of a wind, wave and
tidal sector with a local supply chain of businesses and port facilities servicing the industry. Any
interconnector project would bring with it significant capital works and this will be of benefit to the
Shetland economy.
16
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
Potentials
In terms of renewable energy development the interconnector planned between Shetland and the
UK National Grid is rated at 600 MW and there is consented ca. 400MW of onshore wind power to
be connected. With other renewable energy projects in the early stages of planning it is expected
that there is capacity in the cable to meet these onshore wind and tidal projects. In a timescale we
are looking at 5 – 15 years from now. As marine renewable technology becomes commercial there
is great potential for wave power development in Shetland waters with a world class resource. From
discussions with wave developers that were investigating the potential for development in Shetland
waters, for the next 5 years to 10 years they were looking at small arrays of devices up to 10 MW. In
order to take advantage of the best wave climate and move the generating devices further offshore,
they envisioned that a wave farm of several hundred MW would be required to justify the cabling
and infrastructure costs. Another potential source of generation would be offshore wind, this also
depends on the technology. Floating offshore wind turbines look like they may be suited to the
deeper waters around Shetland. A floating wind turbine project is planned for the north east of
Scotland, part of Statoil’s Hywind project. This will see five of the 6MW floating turbines operating
in more than 100m of water about 12 miles off of Peterhead. The marine sector is probably at least
15 years away from large scale commercial projects, these projects will probably be looking for
additional interconnector infrastructure.
Timescale for each energy sources
Large Scale onshore wind - 6 to 15 years
Small scale wave and tidal - 6 to 15 years
Large scale wave, tidal and offshore wind - 15 to 20 years
Additional cost
Reinforcement of transmission system – Interconnector from Shetland to UK
National Grid is estimated at ca £700m
Building new power plants – Viking Energy wind farm capital cost is estimated ca
£700m; additional 200MW of wind/ renewable generation ca £350m
Backup issues – Cost of a new power station or standby generation plant/ additional supply via grid
connection would cost ca £100 - £200m
CO
2
emissions
The Shetland Energy Source Analysis conducted by the PURE Energy Centre in 2008 showed that
energy use had increased from 1990 to 2008 by 58%; corresponding with an increase of CO2
emissions of 57%. It estimated an increase from 1,000 to 1,550 GWh of energy use; in CO2 terms
that is 323,000 tonnes up to 507,000 tonnes of CO2. These levels are high per capita due to the
relatively energy intensive industry on the island and the small population.
The study noted CO2 levels had shown a decrease in vehicle transport. Despite a 42% increase in
vehicles the level of CO2 had decreased with more efficient vehicles and more diesel cars with
improved fuel economy.
Reductions in CO2 emissions could be made through increasing renewable on the electrical network
with the use of intelligent load management. Improved energy efficiency would reduce heating and
electrical demand, save consumers money on their bills and reduce the use of fuel oil. The use of a
clean energy tariff to encourage energy use when renewable energy was available could also be
17
GRU, Alm.del - 2015-16 - Bilag 32: Pressemeddelelse: Præsentation af rapporten om North Atlantic Energy Network (NAEN)
1593352_0170.png
effective in reducing the burning of fuel oil. The use of renewable heat would also contribute to
carbon savings and reducing the reliance on fuel oil.
A 600MW interconnector would transmit 2,365,200MWh of wind generated electricity per annum.
Based on the UK’s Department of Energy and Climate Change carbon saving factor for wind power
0.43kg/ MW hr, this would save an estimated 1,017,036 tonnes of carbon per year.
References
Shetland in Statistics 2014
– Published by Economic Development Unit – Shetland Islands Council
Viking Energy Wind Farm, Socio Economic Impact Statement - Avayl Engineering Consultancy and A
B Associates Ltd
Shetland Marine Spatial Plan – Shetland Islands Council
http://www.shetland.gov.uk/planning/documents/SIMSP_2015.pdf
Shetland Islands Wave and Tidal Resource – Natural Power
http://www.shetland.gov.uk/planning/documents/805_NPC_SIC_R_004-LowRes.pdf
Regional Locational Guidance for Wave and Tidal Energy Developments Around Shetland
http://www.nafc.uhi.ac.uk/research/msp/rlg/RLG_SMSP_2013_May.pdf
Scottish and Southern Energy Power Distribution – A New Energy Solution for Shetland October
Consultation Documents,
https://www.ssepd.co.uk/ShetlandEnergy/Documents/
Entsoe (European Network of Transmission System Operators for Electricity) - EU Ten Year Network
Development Plan
https://www.entsoe.eu/major-projects/ten-year-network-development-
plan/Pages/index.html
Pure Energy Centre, C2CI Shetland Energy Source Analysis -
http://pureenergycentre.com/download/
Scottish Government – Energy Use in the Home, Measuring and Analysing Domestic Energy use and
Energy Efficiency in Scotland.
http://www.gov.scot/Resource/0039/00398667.pdf
SSE NINES -
http://www.ninessmartgrid.co.uk
Shetland Heat Energy and Power -
http://www.sheap-ltd.co.uk/
Shetland Aerogenerators -
http://www.burradale.co.uk/
Viking Energy Limited -
http://www.vikingenergy.co.uk/
Peel Energy – Beaw Field Windfarm
http://www.beawfieldwindfarm.co.uk/
Element Power, Maali Project -
http://www.elpower.com/portfolio/maali
Delta Marine -
http://www.delta-marine.co.uk/
Nova Innovation -
http://novainnovation.co.uk/
18