Forsvarsudvalget 2015-16
FOU Alm.del Bilag 150
Offentligt
NOT FOR PUBLICATION UNTIL RELEASED BY
THE HOUSE ARMED SERVICES COMMITTEE
SUBCOMMITTEE ON TACTICAL AIR AND LAND FORCES
STATEMENT OF
THE HONORABLE SEAN J. STACKLEY
ASSISTANT SECRETARY OF THE NAVY
(RESEARCH, DEVELOPMENT AND ACQUISITION)
AND
LT GENERAL CHRISTOPHER C. BOGDAN
PROGRAM EXECUTIVE OFFICER, F-35
BEFORE THE
TACTICAL AIR AND LAND FORCES SUBCOMMITTEE
OF THE
HOUSE ARMED SERVICES COMMITTEE
ON
F-35 PROGRAM REVIEW
MARCH 23, 2016
NOT FOR PUBLICATION UNTIL RELEASED BY
THE HOUSE ARMED SERVICES COMMITTEE
SUBCOMMITTEE ON TACTICAL AIR AND LAND FORCES
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
I
Introduction
Chairman Turner, Ranking Member Sanchez and distinguished Members of the
Subcommittee, thank you for the opportunity to appear before you today to discuss the F-35
Lightning II.
The F-35 Lightning II is the Department of Defense`s largest acquisition program,
matched by its importance to our Nation’s security. The F-35 will form the backbone of United
States (U.S.) air combat superiority for decades to come, replacing or complementing the legacy
tactical fighter fleets of the Air Force, Navy, and Marine Corps with a dominant, multirole, fifth-
generation aircraft, capable of projecting U.S. power and deterring potential adversaries. For our
International Partners and Foreign Military Sales (FMS) customers, who are participating in the
program, the F-35 will become a linchpin for future coalition operations and will help to close a
crucial capability gap that will enhance the strength of our security alliances. Accordingly,
delivering this transformational capability to front-line forces as soon as possible remains a top
priority.
II Accomplishments
The F-35 program is executing well across the entire spectrum of acquisition, to include
development and design, flight test, production, fielding and base stand-up, sustainment of
fielded aircraft, and building a global sustainment enterprise. In February 2016, the F-35
reached 50,000 flight hours, including approximately 26,000 for the F-35A, 18,000 for the F-35B
and almost 6,000 hours for the F-35C. We are pleased to report many accomplishments by the
F-35 team during the past year, since we last addressed this committee. Of note, we have seen
declaration of Initial Operating Capability (IOC) for the F-35B by the U.S. Marine Corps
2
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
(USMC) last summer, providing our Combatant Commanders with a 5
th
generation strike fighter
capable of operations from expeditionary airstrips or sea-based carriers, the delivery of first
seven F-35A aircraft to Hill Air Force Base (AFB) in preparation for the U.S. Air Force’s
(USAF) declaration of IOC later this year, and delivery of Block 3F software to flight test in
support of Navy F-35C IOC in 2018. The F-35 team remains committed to sustaining and
expanding these fielded capabilities.
Accomplishments in flight testing in recent months include completion of F-35B Block
2B Operational Test aboard the USS WASP and successful completion of the second round of
sea trials with the F-35C aboard the USS DWIGHT D. EISENHOWER (CVN 69). We have
now completed a total of five sea trials with the F-35B and F-35C. The developmental test
program is progressing steadily with a focus on wrapping up testing of the Block 3i software this
spring. This last iteration of Block 3i software will give the F-35A the combat capability
required for USAF IOC. The team also completed F-35A high angle of attack and performance
testing and continued flight envelope expansion for all aircraft variants. High angle of attack
flight testing will complete this spring for F-35C and fall for F-35B. For the F-35A, we have
performed a series of successful AIM-9X air-to-air missile launches and airborne test firings of
its GAU-22 internally-mounted 25-millimeter cannon. Air-to-ground accuracy testing of the
GAU-22 is now underway and expected to complete in summer 2016. Additionally, we
successfully conducted the first operational fleet weapons drops for the USMC and USAF, and
completed all Block 3i weapons delivery accuracy events.
Our overall assessment is that the program is making solid progress across the board and
shows improvement each day while continuing to manage emerging issues and mitigate
3
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
programmatic risks. We are confident the F-35 team can overcome these challenges and deliver
on our commitments. In this testimony, we present a detailed update on the progress that has
been made over the past year, providing a balanced assessment of the current status of the
program, highlighting both the accomplishments and the setbacks, as well as articulating where
we believe risks remain.
III Development
Steady progress continues toward completion of the F-35 System Development and
Demonstration (SDD) phase in fall of 2017. Last year, we testified before this subcommittee and
said the program was nearing completion of Block 2 software development and was closing in
on completing all flight testing necessary to field our initial warfighting capability, also known
as Block 2B. We are now in the same position for our next increment, Block 3i. We should
complete all 3i testing this spring and convert all the fielded aircraft with earlier versions of
Block 3i to the latest version starting this summer.
The final block of F-35 development program capability, known as Block 3F, provides a
fully capable F-35 aircraft and marks the end of the SDD program. Block 3F Mission Systems
software is currently undergoing Developmental Test (DT), and many of the deficiencies
discovered in Blocks 2B and 3i software will be corrected in Block 3F. However, since both 2B
and 3i testing took longer than originally planned, the program estimates there is a risk to
completing Block 3F on time – it is now projected to be about four months late and will be
delivered in late fall of 2017. This delay is an improvement over our projection from one year
ago, and it is not expected to impact U.S. Navy (USN) IOC for the F-35C in 2018 or the other
U.S. and coalition partner’s capabilities. There are still some stability issues with both the 3i and
4
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
3F software that we are currently working through.
Looking beyond the SDD program, the Follow-on Development or Modernization effort,
also known as Follow-on Modernization, will be the means to deliver improved capabilities to
the weapon system to ensure its relevance against advanced and emerging threats. The program
anticipates the Joint Requirements Oversight Council will approve the Follow-on Modernization
/ Block 4 Capabilities Development Document this summer. Work continues with the U.S.
services and International Partners to ensure the Modernization Program will be “right-sized” for
affordability and sustainability. In addition, the Department will ensure that separate cost,
schedule, performance and earned-value data will be available to provide detailed insight into
program execution. To this end, we awarded the initial Planning and Systems Engineering
contract in June 2015, and execution remains on track to conduct a comprehensive System
Requirements Review this fall. Two additional contract actions are planned. The first will allow
for the decomposition of system level requirements through a rigorous systems engineering
effort, and the second will continue that work through Preliminary Design Review planned in
spring 2018 and will support a Defense Acquisition Executive decision point to move forward
with the Block 4 development program in mid-2018.
F-35A Dual Capable Aircraft (DCA) continues to be aligned with and included in the
Block 4 Follow-on Modernization effort. This past summer a series of test flights were
conducted to assess the vibration, acoustic, and thermal environments of the F-35A weapons bay
with the B61-12 weapon. Nuclear Certification planning efforts have been initiated as part of the
Block 4 contracting activity in anticipation of beginning B61-12 integration on the F-35A in
2018.
5
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
Commensurately, we have begun to “right size” the Development Test fleet of aircraft in
preparation for Follow-on Modernization. As part of this process, the services and program
office are working together to determine the correct mix of capacity and capabilities to allow us
to operate a flight test fleet that is representative of the warfighter’s fleet. This will provide the
needed capability at a lower cost, allowing the services to put more resources toward capability
enhancements.
Although solid progress is being made -- we are now 80 percent complete with all of
SDD -- F-35 development is not without technical discoveries and deficiencies, which are
common for a system that is still in development.
On August 27, 2015, the U.S. Services and International Partners restricted F-35 pilots
weighing less than 136 pounds from operating the F-35 after safe escape tests indicated the
potential for increased risk of injury to this pilot population. Currently, no F-35 pilots are
impacted by this restriction. The restriction is focused on this population, as lighter pilots are
assessed to have lower neck strength and are therefore more prone to injury as a result of neck
loading observed during testing.
There are three technical solutions that when in place will reduce the risk of neck injury
to all pilots and will eliminate the restriction to any pilot population. Two of the solutions
pertaining to the ejection seat, have been verified through testing, and will be ready to
incorporate into production aircraft and retrofit to delivered aircraft by the end of 2016. These
solutions are a head support panel between the parachute risers that prevents neck over-extension
and a pilot-selectable weight switch, which adds a very slight delay in the opening of the main
parachute, thus reducing opening shock loads. The third solution applies to the helmet and
6
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
involves reducing its weight. This lighter helmet is expected to field by the end of 2017, but the
program intends to accelerate this timeline.
Another deficiency the Program is solving involves the Ground Data Security Assembly
Receptacle (GDR), which is part of the Off-board Mission Planning system and is used to
encrypt and decrypt the mission and maintenance data carried on the Portable Memory Device to
and from the airplane by the pilot. In 2015, the program faced significant challenges with the
pilot debrief timeline, because the GDR required approximately 1.5 hours to download a 1.5
hour flight -- far too long. We have now developed an improved GDR that will decrease the
timeline to download mission data by a factor of 8, meaning a 1.5 hour flight will be downloaded
in about 15 minutes. The new program successfully completed a CDR for the redesign in
September 2015. Test units are now being built for qualification and integration testing. We
will deliver the new GDR in summer 2016 with the first ten units delivered to Hill AFB in Utah
in support of USAF IOC. Further GDR deliveries to back-fill other units will begin in fall 2016.
As previously reported, in September 2013, during F-35B full-scale durability testing, we
experienced a significant bulkhead crack at 9,056 equivalent flight hours (EFH). The root causes
have been established and redesign effort for the bulkheads is well underway. A laser shock
peening process is being developed to address specific locations requiring additional material
improvement to meet full life. The qualification of this process is progressing satisfactorily and
is expected to be available for both production and retrofit of fielded aircraft by the end of 2017.
The F-35B durability test restarted in February 2015 and progressed to 11,915 EFH by August
2015. At that time, cracking had developed at a previously identified short life location and
7
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
required repair. That repair work is nearing completion now. The F-35B durability test is
expected to complete its second life of durability testing during summer 2016.
In October 2015, the F-35C test article experienced cracking in the wing front spars at
13,731 EFH. The root cause has been established and redesign efforts for the spars has begun.
Standard redesign techniques, such as local material thickening and cold-working are expected to
be used to achieve full intended life. This finding does not affect the F-35A or B variant spars
because the F-35C spars are designed differently to account for the aircraft’s larger wings. In
addition, at 13,931 EFH additional cracking was found in the left side of a main fuselage
bulkhead. Once an investigation got underway, a similar, though smaller crack was also found
on the right side. This new cracking is under investigation and analysis in on-going. There is no
near-term airworthiness concern for fielded or test aircraft due to either case of cracking because
these aircraft can fly for approximately 10 years or more before these structural issues require a
fix. The F-35C is expected to complete its second life of durability testing in late 2016.
The F-35 Program Office is making progress in resolving two technical issues involving
the fuel system: fuel tank overpressure at elevated g-loading and fuel tank inerting for lightning
protection. The technical solution for the fuel overpressure has been designed, tested and is in
the process of being fielded. This will allow all F-35 variants to reach their full structural
capability. Additionally, the F-35 team recently qualified the improved fuel tank inerting
system, and the operational restriction to avoid lightning in-flight was lifted for the F-35A in late
2015. The fuel systems differences among the three aircraft variants require additional measures
to qualify the new inerting system for F-35B and F-35C. The F-35B requires the next software
release, which is expected this spring, and the F-35C will be corrected with a hardware change
8
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
beginning summer 2016. Implementation of both overpressure and lightning corrective actions
will provide full g-envelope and full lightning protection for all three variants prior to SDD
closure and is expected to meet all IOC requirements.
IV
Cost, Schedule, and Performance Metrics and Production Status:
Affordability remains a top priority. We continue to make it clear to the program
management team and the F-35 industrial base that the development phase must complete within
the time and funding allocated, continue to drive cost out of aircraft production, and reduce life-
cycle costs. To that end, the program has engaged in a multi-pronged approach to reduce costs
across production, operations, and support. The government/industry team is reducing aircraft
production costs through "blueprint for affordability" initiatives and reducing F135 engine costs
via ongoing engine "war on cost" strategies. These efforts include up-front contractor
investment on cost reduction initiatives, mutually agreed upon by the government and contractor
team. This arrangement motivates the contractors to accrue savings as quickly as possible in
order to recoup their investment, and it benefits the government by realizing cost savings at the
time of contract award. The goal is to reduce the flyaway cost of the USAF F-35A to between
$80 and $85 million dollars by 2019, which is anticipated to commensurately decrease the cost to
the Marine Corps F-35B and Navy F-35C variants. The program has also set a goal of
decreasing overall operating and support life-cycle cost by 30 percent.
The price of F-35s continues to decline steadily Lot after Lot. For example, the price
(including airframe, engine, and contractor fee) of a Low Rate Initial Production (LRIP) Lot 8
aircraft was approximately 3.6 percent less than an LRIP Lot 7 aircraft, and an LRIP Lot 7
aircraft was 4.2 percent lower than an LRIP Lot 6 aircraft. LRIP Lots 9 and 10 contract
9
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
negotiations are nearing completion, and LRIP 9 contract award is anticipated no later than May
of this year. LRIP 10 will award when the Secretary of the Air Force certifies that F-35As
delivered during FY18 will be full Block 3F capable.
The program met its 2015 production goal of delivering 45 aircraft and is on track to
meet the goal of delivering 53 aircraft in calendar year 2016, with 48 of those aircraft produced
in Fort Worth, Texas and another five produced in the Italian Final Assembly and Check Out
facility at Cameri, Italy. As of March, 2016, a total of 171 aircraft have been delivered to our
test, operational and training sites. The delivery schedule for aircraft also continues to improve.
LRIP Lot 6 aircraft averaged 68 manufacturing days behind contracted delivery dates, and LRIP
Lot 7 aircraft have improved to an average of 30 manufacturing days behind contract dates. We
expect that gap to continue to reduce as we approach the first LRIP Lot 8 deliveries in the
March-April 2016 timeframe. We continue to work with both Lockheed Martin and Pratt &
Whitney to prepare the program for the production ramp increase over the next few years.
The F-35 enterprise is exploring the possibility of entering into a Block Buy Contract
(BBC) for LRIP Lots 12-14 (FY18-20). A BBC would enable significant program cost
avoidance by allowing the contractors to utilize Economic Order Quantity purchases, increase
cost reduction initiatives enabling suppliers to maximize production economies of scale through
batch orders. To substantiate the potential savings of a BBC concept, the F-35 Program Office
contracted with RAND Project Air Force (a Federally Funded Research and Development
Center) to provide an independent assessment, which is expected in March 2016. Due to budget
timing and uncertainty, the Department of Defense intends to begin the Block Buy in Lot 13
rather than Lot 12. However, we are considering an option to allow the F-35 Partners and FMS
10
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
customers to begin a BBC in Lot 12, followed by U.S. participation in LRIP Lots 13 and 14.
This option will still result in significant cost savings.
Overall, we believe the risk of entering into a BBC in LRIP Lot 12 (FY18) to the F-35
International Partners and FMS customers is low. By the time it is necessary to commit to a
Block Buy many aspects of the program will be stable including completion of durability testing
for all three variants, near completion of all hardware qualification, completion of the majority of
3F software and weapons delivery testing, and stable production processes and ramp.
Earlier this year, the program reached agreement with Pratt & Whitney on the next two
lots of F135 propulsion systems. The F-35A/F-35C propulsion system reduced 3.4 percent from
the previously negotiated LRIP Lot 8 price to the negotiated LRIP Lot 10 price. The F-35B
propulsion system (including lift systems) reduced 6.4 percent from the previously negotiated
LRIP Lot 8 price to the LRIP Lot 10 price. For calendar year 2015, all F135 production
deliveries met contract requirements. However, recurring manufacturing quality issues have
created issues with delivered engines. Recent quality escapes on turbine blades and electronic
control systems resulted in maintenance activity to remove suspect hardware from the
operational fleet prior to delivery, but Pratt & Whitney still met their timeline for the Lockheed
production line. Pratt & Whitney has taken action to improve quality surveillance within their
manufacturing processes and is executing a rigorous quality program with their supplier.
Additionally, the program office manufacturing quality experts have engaged both Lockheed and
Pratt & Whitney to ensure quality improvement processes are in place to meet production ramp
requirements. We are also continuing to conduct stringent Production Readiness Reviews with
hundreds of suppliers to ensure the production ramp will be achievable and smooth.
11
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
V
Sustainment
As of the beginning of March 2016, there are 151 operational (fleet and operational test)
and 20 DT F-35s in the inventory operating at eight sites. Together, the entire fleet has logged
more than 50,000 flight hours since our first flight in 2006. F-35A deliveries to Eglin AFB in
Florida are complete, and the program continues deliveries to Luke AFB, which is the main
training base for the USAF and Partners, including Australia’s and Norway’s first two F-35As.
During 2015, the program began delivering F-35As to Hill AFB in support of the USAF’s first
operational F-35 wing. The program has also started F-35B pilot training at Marine Corps Air
Station Beaufort in South Carolina. In the next four years, we will add another seventeen
operating bases to the F-35 enterprise across all three regions: North America, the Pacific and
Europe.
As additional aircraft come off the production line, the program is working to ensure sites
across the globe are ready to accept the F-35. Since January 2015, the program has sent out
fifty-one site activation teams supporting detailed planning at twenty-five different locations
around the globe. These sites include stand up of F-35 capability for six of the Partner Nations,
all three of the foreign military sales customers, as well as additional sites for USAF, USMC and
USN. Planning commenced in 2015 for base standups in Norway, the Netherlands, Turkey,
United Kingdom, Israel, Japan and Korea. The site activation highlight for 2015 was the
successful preparation and arrival of the F-35 at Hill AFB, forming the foundation for a projected
2016 USAF IOC.
Aircraft availability rates continue to be a focus area for the program and various
program initiatives are now showing a positive trend in this area. A disciplined Reliability &
12
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
Maintainability program, improved maintenance procedures and manuals, continued
improvement in Autonomic Logistics Information System (ALIS), better forecasting of spares
requirements, improved repair turn around times from supplier, and incorporation of aircraft
design improvements have resulted in excellent gains in mission capability rates and aircraft
availability rates. Today, across the fleet, we are seeing 55 to 60 percent availability rates with
units performing at 63 percent mission capability.
Last year the program provided information regarding its efforts toward the establishment
of the Global Sustainment posture across Europe, Asia-Pacific, and North America. In 2015, the
program made progress in standing up regional Maintenance, Repair, Overhaul, and Upgrade
(MRO&U) capabilities for airframes and engines in the European and Pacific regions. These
initial MRO&U capabilities will support overseas F-35 airframe and engine heavy-level
maintenance for all customers, including the U.S. Services, and will continue to provide the best-
value to the enterprise. Italy will provide initial airframe MRO&U capability in the European
region in 2018. Turkey will provide engine heavy maintenance in the European region in 2018
with The Netherlands and Norway providing additional capability a few years later. F-35
airframe MRO&U capability in the Pacific region will be provided first by Australia in 2018 and
then by and Japan. Australia will also be providing initial engine heavy maintenance, followed
by Japan about five years later.
In 2015 the program also kicked-off initial planning efforts for expansion of component
repair into the European and Pacific regions. Efforts began to identify ‘best value’ repair sources
in each region for approximately 18 key depot-level repairable items. International Partners and
their respective industries will be requested to propose component groupings which leverage
13
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
their strongest industrial competencies to deliver optimum repair capability at best cost to the
global sustainment solution.
The program will continue this process in 2016 and 2017 with the Department of Defense
assigning to our Partners and FMS customers repair capabilities such as wheels and brakes,
electrical and hydraulic systems, maintenance of support equipment, and warehousing for the
global supply chain. These same capabilities either currently exist or are being developed at the
U.S. Services’ CONUS depots in accordance with current U.S. law.
VI Risk & Challenges
Although improving, the Program is not without risks and challenges. Currently, our
most significant technical concern is the development and integration of mission systems
software.
The aircraft has approximately eight million lines of code, with another 16 million lines
of code on the off-board systems. This is an order of magnitude greater than any other aircraft in
the world and represents a complex, sometimes tricky, and often frustrating element in the
program. Several years ago the program instilled discipline in the way software is developed,
lab tested, flight tested, measured and controlled by the program office. This has produced much
better and more predictable results over the past two years. However, both the fielded Block 3i
software and the 3F software in flight test are not as stable as they need to be to support our
warfighters. We are experiencing instability in the sensors -- particularly the radar – leading it to
shut off and “reboot” in flight. Currently, this problem occurs about once every four hours of
flying, and we expect to improve this to once every eight to ten hours of flying. We believe we
have identified the root cause of these stability problems to be the timing of software messages
14
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
from the sensors to the main F-35 fusion computer, and we have tested solutions in the lab
environment. We will be flight testing these fixes in the March-April timeframe. If the fixes are
successful, we will add them to a new version of 3i software and field that in time for USAF
IOC. We will also incorporate the fixes in the 3F software we are developing and flight testing.
To ensure we completely understand these issues the program office has launched an in-depth
look at this issue in the form of a software stability “Red Team.” This team, made up of a group
of experts from the Navy and Air Force, will conduct its study beginning in March and report
back to the Program Office.
The final software version, Block 3F, has the most software risk facing the program for a
number of reasons. First, 3F testing started later than planned because we had to spend more
time fixing Block 2B and 3i software. Second, 3F has the same stability issues as Block 3i as
described above. Third, the Block 3F software must take information from other sources, such
as other non-F-35 aircraft, satellites, and ground stations and fuse this information with F-35
information, giving the pilot a complete and accurate picture of the battlespace. Additionally,
the remaining flight loads, buffet, and weapons delivery accuracy flight testing needs to be
accomplished.
We estimate there is about four months of risk to this schedule, placing full 3F
capability to the warfighters in the late fall of 2017.
The next version of ALIS, version 2.0.2, which includes new capabilities to support
USAF IOC, also has some schedule risk. This version of ALIS combines the management of
F135 engine maintenance within ALIS and tracks all the life-limited parts on each and every
F-35 aircraft. The development of these capabilities is proving to be difficult because they
15
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
require integration with Lockheed Martin’s and Pratt & Whitney’s Enterprise Resource Planning
systems, or the “back end” of ALIS.
We are also working closely with the Joint Operational Test Team to finalize its F-35
FY16 Cyber Test Plan. This testing is scheduled to begin in April 2016 and will perform end-to-
end Vulnerability and Adversarial Testing on ALIS and the F-35 Air Vehicle. Hundreds of
penetration and cyber security test have already been accomplished on the system, enabling us to
connect the F-35 systems to the DoD Global Information Grid (DoD and Services networks).
We have also instituted an ALIS initiative aimed at fixing prior deficiencies and rapidly
fielding them to the warfighter. As we continue to develop new capabilities, the Program has set
up a parallel effort -- known as “Service Packs” -- to fix many of the deficiencies the maintainers
in the field have brought to our attention. These deficiencies usually result in workarounds and
add workload to our maintainers’ already busy jobs. Service Packs are developed, tested and
fielded on a much quicker timeline than our larger increments of ALIS. We fielded the first
Service Pack in January, and feedback from the field has been encouraging. We will continue to
rapidly field Service Packs to improve the usability of ALIS for our maintainers, the next of
which will be fielded this spring.
One final comment concerning risks and issues on the program deals with the recent
report issued by the Director of Operational Test and Evaluation (DOT&E). This report is
factually accurate and was written entirely based on information that came from the F-35
Program Office – there is no information in the report that was not already known by the
Program Office, the U.S. Services, and our Partners. While not highlighted by the DOT&E
report, for each issue cited the F-35 Program has a dedicated effort underway to resolve or
16
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
otherwise mitigate the issue. We are prepared to provide further details on any of these issues
and our actions to address them.
VII
Delivering Combat Capability
Following the declaration of IOC in June of 2015, the USMC has continued to train and
exercise its combat capable F-35B aircraft. At the beginning of December 2015, Marine Fighter
Attack Squadron 121 deployed eight F-35Bs to Twentynine Palms in California for Exercise
Steel Knight. The team executed 32 sorties in support of the combined arms live-fire exercise,
taking an important step toward integrating the F-35B into the Marine Corps Ground Combat
Element and demonstrating their capability to execute close air support and strike missions from
an austere operating site.
The USAF also showed their increasing capabilities with the F-35A, executing a
deployment of six Operational Test aircraft from the 31
st
Test and Evaluation Squadron at
Edwards AFB, California to Mountain Home AFB, Idaho. The squadron executed 54 sorties
over twelve days of flying as part of a joint training exercise with U.S. Navy Seals, F-15Es,
A-10s, and Apache and Blackhawk helicopters, delivering 10 GBU-31 and 20 GBU-12 precision
guided inert munitions. This is the first time the F-35A has deployed to and operated from a
base with no organic F-35 support or presence.
The F-35 Lightning II Joint Program Office’s top priority is now meeting USAF IOC at
Hill AFB, Utah with Block 3i capabilities between August and December 2016. Hill's active-
duty 388th Fighter Wing and Reserve 419th Fighter Wing will be the first USAF combat-coded
units to fly and maintain the Lightning II. In support of meeting the USAF’s IOC date, Hill AFB
17
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
has already received its initial F-35As and is now training with them, including the first weapons
employment from an operational F-35A.
The USN has set August 2018 as its IOC objective date with the F-35C. In support of
meeting the USN IOC, sea trials will continue this year and culminate in the third and final DT
period afloat. This test is expected to last approximately 21 days and will test and certify the
remaining embarked launch and recovery environmental envelopes, including those with various
ordnance and fuel load combinations expected in fleet use. The test will also complete all initial
shipboard flight deck and hangar deck supportability procedures and processes, paving the way
Operational Test and Fleet use.
VIII
International Partner and FMS Participants
International participation on the program with eight Partners and three FMS customers
remains solid. The program has now delivered the first Royal Norwegian Air Force F-35 to
Luke AFB expanding the International Partner pilot training currently ongoing there. The first
Italian Air Force F-35A was also delivered from the production facility in Cameri, Italy, and then
subsequently completed the first F-35 trans-Atlantic flight in February, landing at Naval Air
Station, Patuxent River in Maryland. After completion of some program testing, this aircraft will
also join the pilot training effort at Luke AFB. F-35A has also conducted aerial refueling flight
testing with a Royal Australian Air Force KC-30A tanker and completed aerial refueling flight
testing and certification with an Italian Air Force KC-767 tanker.
In 2015, as part of initial site planning, we commenced standup of maintenance
capabilities in Norway, Netherlands, Turkey, United Kingdom, Israel, Japan and Korea. Also,
the Japanese Final Assembly and Check Out assembly facility is now complete with both
18
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
Electronic Mate Assembly Stations tools installed and accepted. Construction and installation
activities remain on schedule, and the major components are now being shipped. The first
Japanese F-35A is scheduled to rollout of the facility in November 2016.
We anticipate that Denmark will make its final decision on its fighter replacement late
spring 2016. Additionally, although Canada has indicated that it will conduct a new fighter
replacement competition, it still remains a full partner in the F-35 program. We continue to
provide the Canadian government with the most up-to-date and accurate information to aid them
in their future selection process.
IX Conclusion
In summary, the F-35 program is making solid progress across all areas including
development, flight test, production, maintenance, and stand-up of the global sustainment
enterprise. As with any big and complex program, new discoveries, challenges and obstacles
will occur. The F-35 is still in development, and it is the time when technical challenges are
expected. However, we believe the combined government / industry team has the ability to
resolve current issues and future discoveries. The team’s commitment to overcoming these
challenges is unwavering and we will maximize the F-35’s full capability for the Warfighter.
We will continue executing with integrity, discipline, transparency and accountability,
holding ourselves accountable for the outcomes on this program. The team recognizes the
responsibility the program has been given to provide the pillar of the U.S. and allied fighter
capability with the F-35 for generations to come, and that your sons and daughters, grandsons
and granddaughters may someday take this aircraft into harm’s way to defend our freedom and
way of life. It is a responsibility we take very seriously.
19
FOU, Alm.del - 2015-16 - Bilag 150: Kampflyforligsnotater, fra forsvarsministeren
Thank you again for this opportunity to discuss the F-35 program. We look forward to
answering any questions you have.
20