Europaudvalget 2015-16
EUU Alm.del Bilag 851
Offentligt
1661107_0001.png
SEPTEMBER 2016
09
Journal
European Court of Auditors
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0002.png
Past editions of the Journal can be found on:
ECA’s website: http://eca.europa.eu/en/Pages/Journal.aspx
PRODUCTION
Rédacteur en chef / Editor in Chief : Rosmarie Carotti
Tél. / tel.: 00352 4398 - 45506 - e-mail : [email protected]
Mise en page, diffusion / Layout, distribution : Direction de la Présidence - Directorate of the Presidency
Photos : Reproduction interdite / Reproduction prohibited
© ECA
The contents of the interviews and the articles are the sole responsibility of the interviewees and
authors and do not necessarily reflect the opinion of the European Court of Auditors
Cover photos:
Rimantas Šadžius, new ECA Member
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0003.png
TABLE OF CONTENTS
1
02
02
There are lots of areas where the ECA could have its say
Interview with Rimantas Šadžius, new ECA Member
By Rosmarie Carotti
05
05
Special report no 19/2016: Implementing the EU budget through financial instruments –
lessons to be learnt from the 2007-2013 programme period
Questions to Iliana Ivanova, ECA Member
08
08
The ECA’s reformed Chambers and Committees
By James McQuade, private office of the President
10
ECA auditors visited the ITER project facilities in Saint Paul-lez-Durance (France)
By Alvaro Garrido-Lestache, principal auditor and head of task for the audit of
the EU research Joint Undertakings and Richard Hardy, principal manager in Chamber IV
10
17
Experiences and views on the discharge procedure
At the invitation of Alex Brenninkmeijer, ECA Member, three young practitioners from the
European Parliament, Council and Commission shared their experiences and views on the role of
discharge in the political decision-making process
By Rosmarie Carotti
17
20
20
Recent EU Case-law on State aid
The Legal Service invited all ECA staff to an information session given by Íde Ní Riagáin on the
case-law of the Court of Justice and the General Court from March 2016 to June 2016
By Rosmarie Carotti
22
22
FOCUS
- Engagement solennel des nouveaux Membres de la Cour, 6 juillet 2016
- Special reports No 13, 15, 17, 18, 19/2016
25
25
Performance auditing: Current methods and future prospects
By Luc T'Joen, senior administrator in Chamber II
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0004.png
There are lots of areas where the ECA could have
its say
Interview with Rimantas Šadžius, new ECA Member
By Rosmarie Carotti
2
interest with your present tasks? Did you have to
give up all your previous mandates upon joining
the ECA?
Rimantas Šadžius:
With the present tasks in the
ECA there is no conflict of interest whatsoever.
Of course, in the future, I will be very careful
and avoid any conflict of interest to the best of
my possibilities. The positions you referred to,
Governor of the European Stability Mechanism, the
European Investment Bank, the World Bank and
alternate Governor of the International Monetary
Fund, all these positions are ex officio. That means
that Ministers of Finance are appointed for these
positions. Boards of Governors have limited power;
the executive power belongs to other bodies.
For auditing, mostly the executive bodies are
responsible. Of course, when I will have to deal with
the Boards where I was Governor, I will carefully
weigh the scale to which I can or cannot be
responsible for a particular audit.
R. C.: In your hearing in the European
Parliament you said you were very proud that
during your term and under your leadership
Lithuania successfully joined the euro zone on
1 January 2015. What has changed for Lithuania
with the adoption of the euro?
Rimantas Šadžius:
Many things have changed.
In fact, the adoption of the euro meant a new
start for Lithuania. Now the country has to use this
means for improving the economic conditions and
fostering development.
First, the risk profile of the country changed. Before,
Lithuania had its own currency. It was pegged to
the euro since 2002 but still there was a risk of
devaluation. This was always included in investment
plans and when calculating the overall risk of the
country, for example when assessing its sovereign
debt. The sovereign debt of Lithuania became
significantly cheaper and its credit rating stepped
up immediately after the European Council adopted
the decision on the introduction of the euro in
2014.
Rimantas Šadžius, ECA Member
R. C. : Sir, you have formally been sworn in at the
European Court of Justice on 6 July. What did
that mean for you?
Rimantas Šadžius:
It was a very moving moment
and an important one in my life because it started
a new part of my career. From a politician for whom
it is necessary to plan and to act ex ante I became
an auditor representing an independent institution
which acts mainly ex post. It is quite difficult for a
person to change overnight but I had to do this. On
15
th
June I still was Minister of Finance in Lithuania
and on 16
th
June I was appointed ECA Member.
R.C.: What areas will you be responsible for?
Rimantas Šadžius:
I was assigned to Chamber IV
which acts in the audit domain of regulation of
markets and competitive economy. On my account
now are the financial and compliance audit of the
European agencies, the performance audit of the
Erasmus+ programme and the performance review
of Joint Undertakings in research and innovation.
R. C.: You held very important positions in many
international financial institutions. How can you
make sure that there is no potential conflict of
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0005.png
3
Second, there was the indirect effect of the
abolition of the exchange rates. These exchange
operations in the Lithuanian commercial banks
amounted to over two thirds of the exchange
operations overall. The euro opened up better
possibilities to access the European markets. The
Lithuanian economy is characterised by a very
large percentage of exports going to the EU, out of
which most goes to the Eurozone. To have a simple
contract with partners without any devaluation
clause makes things much simpler.
Third, bank transfers have become much simpler
since joining the Single European Area starting from
January 1
st
2016. Also financial security is important
and Lithuania is a member of the European Stability
Mechanism which is another safeguard.
Last but not least, one of the factors that
determined the high appreciation of the new
currency by the Lithuanian population was
geopolitical security. Having this strong currency in
place meant to be fully integrated in the Western
European economic world and in the Western
defence mechanism. Joining the Eurozone finalised
a very important process that began more than ten
years ago with Lithuania’s entrance into NATO and
the EU. The advantages of being member of NATO,
the EU, the Eurozone are absolutely evident for
everyone.
R. C.: “Investment rather than better spending”
was clearly voiced in the course of the
Lithuanian Presidency of the Council. As a new
ECA Member, do you now share the concerns
expressed by the ECA in its opinion on the EFSI?
Rimantas Šadžius:
Of course, I always will have
to share the ECA’s consolidated point of view. Let
me however be precise here. The ECA expressed
its opinion on the regulation of the EFSI. This
was a very important ex ante opinion during the
discussion of this legislation and also influenced its
implementation. Now our turn is to assess how it
works. I hope this will be one of the priorities in the
ECA’s 2017 activities although it might be too early
to express a judgement on the overall operation of
the EFSI.
R. C.: Will the ECA only be able to give an opinion
on the EFSI lending directly linked to the EU
budget?
Rimantas Šadžius:
No, on the operation overall.
The ECA will assess how the fund operates from
the performance point of view. It is wider than the
angle on budgetary money, which in this case is
used for supplying the guarantee. It is absolutely
impossible in such a complicated mechanism as the
EFSI to confine ourselves with counting the money
of the guarantee. Looking only at this money, it will
be very difficult to tell if it was used effectively not
knowing the context. The main aim of this money
is to generate flows of private resources for funding
riskier projects that should have European added
value. Here there are lots of areas where the ECA
could have its say, starting from efficiency of using
this money to dealing with the European added
value of the projects.
If we, as an institution, confine ourselves to financial
and compliance audit and only care about the
regularity of the expenses, it can happen that,
absolutely in accordance with the law provisions,
the money will be spent for nothing and we will
miss a larger picture
We should try to develop methods to assess the
European added value in euros. This could already
be a substantial and relevant result of the activities
of our important independent audit institution.
I see this as the best for the institution to move
forward. In our annual reports the performance
component has already been integrated for a
couple of years. Landscape reviews are another
very important attempt to assess European politics
horizontally, from an economic, financial and
compliance point of view.
R. C.: It took the ECA many years to strengthen
its performance audit role. How can the ECA’s
work become more relevant for the citizen?
Rimantas Šadžius:
It is less important for people
to discuss whether everything went precisely in
accordance with the law, that’s to say financial and
compliance audit. But performance evaluation can
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0006.png
There are lots of areas where the ECA could have its say
continued
4
be made interesting and important for citizens
given we guess rightly what the hottest issues on
the European table are and if we try to mobilise our
limited resources just in these directions.
R. C.: How important is the role of the European
Parliament and the other EU institutions in this?
Rimantas Šadžius:
It is very important to listen to
all stakeholders. I believe there is good cooperation
with the European Parliament. The Council can
make suggestions, too, although so far there is
not an extensive practice of that. Civil society
organisations are another source of ideas. This is a
hotspot where we should concentrate our forces.
Another element which is important for citizens is
a fast result. This for auditors is the most difficult
thing because audit is a very lengthy, careful and
time-consuming exercise. In the ECA, we could
try to think about fast products, fast assessments,
with opinions on legislation for example, where
we do have experience. One has however to
acknowledge that there already is a visible shift in
the ECA’s activities in this direction. There already
are so-called “quick reports”. I think we can improve
on that first experience and concentrate more on
recent and current problems. This could also make a
contribution to the reliability of the EU as a whole.
R. C.: Things will change in the EU after the Brexit
concerning the budget. Is the ECA concerned?
Rimantas Šadžius:
The ECA will be able to
participate indirectly, through the working groups
that are already in place and try to formulate rules
for results-based budget. In some particular areas
the ECA can also have its say but it should not be
mixed into this political process. Political process
of the Brexit negotiations and the assessment of
the effectiveness of European policies by the ECA
should be kept separate.
R. C.: In some EU countries there is now an
independent budget policy monitoring
authority (so-called Fiscal Council). Should there
be one at EU level, too?
Rimantas Šadžius:
The existence of these kinds
of institutions is legitimate and necessary and
obligatory according to the European legislation,
which was signed at least by all the Eurozone
Member States. Independent fiscal institutions
exist in all European countries that subscribed to
the Fiscal Compact. In Lithuania we did not create a
new institution but decided to assign the function
to the Supreme Audit Institution.
On the European level, according to the five
Presidents’ Report (Commission, European
Parliament, European Council, European Central
Bank and Eurogroup) there was a proposal to
establish an advisory European Fiscal Board that
could coordinate activities of the independent fiscal
Councils in the Eurozone countries and provide
with insights. Such a European Fiscal Board should
lead to better compliance with the common fiscal
rules, a more informed public debate, and stronger
coordination of national fiscal policies.
Up to now to my best knowledge the personal
composition of this Council has not been yet
determined and in fact this institution did not start
operating, but such kind of centralised supervision
certainly make sense. I think that the ECA should
come back to this issue, to the economic and
monetary governance of the Union, the European
Semester, the application of the Stability and
Growth Pact and further explore its remit in this
field.
R. C.: Is there something at personal level, you
would like to add?
Rimantas Šadžius:
Specificities of audit are a new
area of activity for me. From a personal point of
view, I want to efficiently start working. I am very
glad that as the latest appointed ECA Member I can
learn very much from my 27 colleagues.
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0007.png
Special report no 19/2016: Implementing the EU
budget through financial instruments – lessons
to be learnt from the 2007-2013 programme
period
Questions to Iliana Ivanova, ECA Member
5
From left to right:
Mihail Stefanov- attaché; Iliana Ivanova – ECA Member; Niels-Erik Brokopp –principal manager;
Rares Rusanescu – team leader; Tony Murphy – head of private office; Agathoclis Argyrou – auditor
Q.: What does “Implementing the EU budget
through financial instruments” mean? And is the
meaning of financial instruments the same in
banking and the EU?
A.:
Financial instruments are a different delivery tool
from grants and are used in different parts of the EU
budget such as cohesion policy and agriculture. The
support that they provide to beneficiaries takes the
form of loans, guarantees, equity and quasi-equity.
Here it is important to stress that financial
Instruments which are the subject of our report
should not be confused with derivatives, which are
an entirely different class of high-risk investments
used by some participants on the financial markets.
Q.: How much money has been invested
through financial instruments in the 2007-2013
programming period?
A.:
In the 2007-2013 programme period more
than one thousand instruments have been set up
using ERDF and ESF funding totalling € 16 billion.
In addition, the Commission centrally manages
twenty-one financial instruments for an amount of
€ 5.5 bn.
For information, there are also instruments set
up with EAFRD and EFF (EU fisheries fund) but
there was no requirement for formal reporting for
them in 2007-2013 programme period. They are
estimated to be around € 770 m including national
contributions.
Q.: Would the conclusion of your report be that
financial instruments as a funding mechanism
should be abandoned or significantly reduced?
Are grants and the public budgets the only
realistic alternatives?
A.:
Absolutely not. Our report is the result of an
in-depth analysis of the functioning of financial
instruments during the 2007-2013 programme
period, and highlights challenges related to their
implementation as well as advantages of using
them. As the decision for using grants and/or
financial instruments as a funding mechanism
should be based on an analysis of the specific needs,
the conclusion may be that financial instruments are
the preferred option to grants or vice-versa. What I
would say is that the fact that loans have to be paid
back, guarantees have to be released or in the case
of equity investments returned should in principle
have an impact on the behaviour of final recipients,
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0008.png
Special report no 19/2016: Implementing the EU budget through
financial instruments – lessons to be learnt from the 2007-2013
programme period
continued
6
leading to a better use of public funds and reducing
the likelihood that they become dependent on
public support.
Q.: In the SR you state that “improvements
were made in the legal framework for the 2014-
2020 programme period as regards financial
instruments”. What are these improvements?
A.:
Indeed, while we highlight several weaknesses
in our report we also acknowledge the efforts of
the Commission in several areas relating to the new
period.
For example, the provisions included in the legal
basis for 2014-2020 programme period will limit the
risk of setting-up instruments with excessive capital
endowments and as a consequence also help to
increase the likelihood of achieving a revolving
effect. This of course also requires that managing
authorities are more realistic about the share of
the ESIF funds that can be implemented through
financial instruments.
Q.: In the SR several observations relate to the
management costs and fees in the 2007-2013
programme period, and it seems that this is a
weak point for financial instruments. What has
been done already to address the issue in the
2014-2020 programme period?
A.:
Yes, we found that that a significant share of
initial endowments of shared management financial
instruments was spent on management costs and
fees. Moreover, their fee level was significantly
higher than for centrally managed instruments or
private sector investment funds when compared to
the financial support provided to beneficiaries.
The 2014-2020 legislation was significantly
improved in relation to management costs and
fees by providing ceilings on cumulative amounts
which are below those applicable for the 2007-2013
programme period, and by making performance-
related fees mandatory. However, the performance
based elements are not yet sufficiently strong and
we believe that the Commission must provide
additional clarification on how management
authorities should make use of these provisions
when negotiating the funding agreements.
funds allocated to these instruments exceeded
the needs. Does this mean that the excessive
funds were wasted? What were the problems
with market needs assessments? Why were they
missing or not trustworthy?
A.:
This observation of the report relates to
instruments that have been set up with the financial
support of the different operational programmes
(through ERDF, ESF). Our report concludes that in
nearly half of the cases surveyed, the initial market
needs have been overestimated which shows
that the underlying analysis was not sufficiently
robust during the 2007-2013 programming period.
This was also related to the fact that the 2007-
2013 framework did not require a mandatory
assessment of the market needs. This situation led
to instruments which were oversized and exceeding
the market needs.
I would like to clarify that while they could
potentially have been used for other purposes the
unused financial resources are not lost or wasted as
at the end of the eligibility period, the funds which
are not provided to final beneficiaries will be paid
back to the EU budget
In this respect, I would like to welcome the efforts
of the Commission for the 2014-2020 programming
period under which a detailed ex ante assessment
is mandatory for financial instruments under shared
management to establish evidence of market
failures (or suboptimal investment situations)
and to estimate the level and scope of public
investment needs. Moreover, the new financial
Regulation introduced a requirement for an ex ante
evaluation for all instruments directly managed by
the Commission.
Q.: Provisions in the legal base for the 2007-
2013 programme period created incentives for
Member States to use financial instruments to
circumvent the risk of de-commitment of EU
funds. Please explain.
A.:
The automatic decommitment rule also
known as “n+2” rule was introduced to help clear
outstanding commitments and requires automatic
decommitment of all funds not spent or covered
by a payment request by the end of the second
year following the year of allocation. However, the
legal basis for the previous programme period
allowed Member States to absorb EU funds from
Q.: One of the issues you mentioned was that the
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0009.png
7
the ERDF and ESF upfront through the use of
financial instruments. These payments made
from the operational programmes to the financial
instruments (funds) are considered absorbed and
therefore could be used as a mechanism to avoid
the risk of decommitment.
Q.: Did financial instruments succeed in
attracting private capital? And what was the
leverage effect of the private and public capital
for shared management instruments?
A.
: One of the key advantages of EU financial
instruments is the fact that additional funds may
be leveraged, or in other words that private and
public funds can contribute to the funds capital
endowment. A high leverage would mean that the
instrument is successful in attracting additional
funding.
During our audit we have found that the
Commission and Member States have faced serious
difficulties in attracting private sector investors
for both shared and centrally managed financial
instruments during the 2007-2013 programme
period.
Q.: Similar structures as the ones covered by
your report are currently used by the Juncker
plan (EFSI). Does the weaknesses identified in
your report relate to it as well?
A.:
Our audit report focuses on the 2007-2013
programme period and covers instruments
managed directly by the Commission and those
instruments set up at national level and supported
through the operational programmes. At the time
the audit has been carried out it was still too early
to audit the Juncker plan instruments, as it was in
the early stage of implementation.
However, I consider this report to be very relevant
in the context of the Juncker plan and I hope that
the EU Commission and all bodies involved in the
implementation of the EFSI will go thoroughly
through the report and take appropriate measures,
if necessary, based on the weaknesses and risks
identified in it.
A high-level conference organised by Iliana Ivanova will take
place at the ECA on 15 November 2016 with the participation of
representatives of EU institutions, practitioners and other public
and private stakeholders
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0010.png
The ECA’s reformed Chambers and Committees
By James McQuade, private office of the President
8
In June 2016, the ECA reformed the Chambers and Committees it uses to prepare and take
ECA decisions on important audit and organisational matters. This reform was brought
into effect by revising key provisions of the ECA’s rules for implementing its Rules of
Procedure, which set out its governance arrangements. Three changes with respect to the
previous arrangements are particularly noteworthy.
James McQuade
First, the reform establishes
five equal chambers
of five Members, including the Dean
each Chamber elects to help coordinate its work. Previously, the ECA had four “vertical”
Chambers and a “horizontal” Chamber, the CEAD Chamber, which had three permanent
Members plus a representative from each of the other four Chambers.
The main function of the five Chambers will continue to be adopting ECA special reports
and opinions, preparing the chapters of the Annual Report, and overseeing the associated
audit tasks. However, instead of each Chamber being responsible for specific EU budget
areas or bodies, each Chamber now has an EU policy-based “theme” to guide its work.
Chamber I
Sustainable use of
natural resources
Chamber II
Investments for
cohesion, growth
and inclusion
Chamber III
External action,
security and justice
Chamber IV
Regulation of
markets and
competitive
economy
Chamber V
Financing and
administering the
Union
The Chambers’ themes effectively represent five policy perspectives (environmental, social, economic,
external affairs, and internal governance) that help the ECA to analyse EU activities and develop related
audit tasks. Under the new work-programming procedure, the ECA identifies audit tasks and allocates the
responsibility and resources for carrying them out to Chambers. Each Chamber is supported by an audit
directorate.
As regards the preparation of the Annual Report, the tasks and coordinating role of the CEAD chamber with
a new Member for the Annual Report taking over the role and responsibilities previously played by the ECA’s
DAS Member.
Second, the reform establishes a new Committee to oversee the ECA’s audit quality management framework.
The
Audit Quality Control Committee
is composed of the Member for Audit Quality Control and two
Members from Chambers, who are appointed by the ECA on a proposal of the President.
The Committee is already up and running. It has taken over responsibilities in the areas of promoting audit
quality and coordinating the ECA’s participation in international audit standard setting bodies that were
previously carried out by part of the CEAD Chamber. From now on, the AQCC will be the driving force behind
the ECA’s development as a professional audit institution. The AQCC is supported by a dedicated directorate
not responsible for carrying out audits, thus reinforcing the independence of the audit quality control
function within the ECA in line with best practice.
Third, the reform provides for new responsibilities and an additional Member for the ECA’s
Administrative
Committee
(AC). The AC maintains its current responsibilities for preparing ECA decisions on strategy, the
work programme and organisational matters and takes on additional decision-making responsibilities with
respect to certain staff matters. The new Member for Audit Quality Control joins the AC, which comprises the
President (the Committee Chair), the Deans of the Chambers and the Member for Institutional Relations with
the participation of the Secretary General. The work of AC continues to be supported by the Directorate of
the Presidency and the services of the Secretary General.
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0011.png
9
A major milestone towards implementing the 2013-2017 ECA Strategy
The reform of the ECA’s Chambers and Committees complements two other major reforms linked to
implementing the ECA Strategy 2013-2017; the introduction of task-based organisation at the start of 2016
and the ongoing initiative to establish an ECA-wide network to strengthen knowledge management.
Under the new task-based organisation, audit directorates are composed of a management team (a director
and principal managers) and a “pool” of staff (auditors and assistants). For each task, the Chamber responsible
assigns a reporting Member, a head of task (a senior auditor) and an audit team. In future, knowledge
management will be led by internal “policy experts” with responsibility for following specific subjects (the
“nodes” in the ECA-wide knowledge network), with the main subjects for creating, maintaining and sharing
knowledge decided by the ECA in the Work Programme.
All three reforms - the newly configured Chambers and Committees, the task-based organisation, and
the knowledge network - are provided for in the ECA’s newly revised rules for implementing its Rules of
Procedure. Together they aim to make the ECA more flexible in selecting tasks, assembling audit teams and
sharing knowledge. In this way, the ECA will be able to make better use of its knowledge, skills and experience
to carry out relevant, high-quality audits in a timely manner - a key goal of the ECA’s strategy for 2013-2017.
The ECA’s new organisation structure can be found at
http://www.eca.europa.eu/en/Pages/Structure.aspx.
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0012.png
ECA auditors visited the ITER project facilities
By Alvaro Garrido-Lestache, principal auditor and head of task for the audit of
the EU research Joint Undertakings and Richard Hardy, principal manager in
Chamber IV
1
1
10
.
On 20 and 21 June the ECA audit team in charge of the audit of the European Joint Undertaking for ITER and
the Development of Fusion Energy visited the ITER project facilities located in Saint Paul-lez-Durance (France)
together with the Joint Undertaking Audit Committee, representatives of the management of the Joint
Undertaking, representatives of the Directorate General of the European Commission responsible for the ITER
project (DG ENERGY), and representatives of the Internal Audit Service of the Commission (IAS).
From left to right: Richard Hardy, principal
manager in Chamber IV,
Alvaro Garrido-Lestache, principal auditor and
head of the Joint Undertakings audit task,
Marco Corradi and Santiago Fuentes, members
of the ECA audit team for the European Joint
Undertaking for ITER and the Development of
Fusion Energy.
Introduction
Following an invitation from the Chair of the Audit
Committee of the European Joint Undertaking for
ITER
2
and the Development of Fusion Energy, Brian
Gray, the ECA audit team participated in the 13th
meeting of the Joint Undertaking Audit Committee
and were given a tour of the ITER project facilities
under construction, enabling an appreciation of
the current status of the works, and the scale and
complexity of the project. The ECA auditors also met
the ITER Organization Director General, Dr Bernard
Bigot.
The ITER project “bringing the power of the sun to
earth”
(Sources: ITER Organization and Fusion for Energy Joint
Undertaking
3
)
The ITER project is an international experimental
facility, and is one of the most important and
ambitious projects in the field of energy today. It
is focused on the development of a secure and
sustainable source of energy based on nuclear fusion.
Since the idea for an international joint experiment
in fusion was first launched in 1985, thousands of
engineers and scientists have contributed to the
design and construction of the world’s first large-
scale experimental thermonuclear reactor.
ITER was launched at the Geneva Superpower
Summit in November 1985, when the idea of a
collaborative international project to develop fusion
energy for peaceful purposes was proposed by
General Secretary Gorbachev of the former Soviet
Union to US ex-President Reagan.
3
Sources: https://www.iter.org; http://fusionforenergy.europa.eu
1 This article is based on information available on the websites of
the ITER Organization and of the European Joint Undertaking
for ITER and the Development of Fusion Energy, and at other
European Union Institutions, including ECA publications.
2 ITER: International Thermonuclear Experimental Reactor.
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0013.png
11
The fusion energy process
Fusion is the process which powers the sun. Energy
is produced by the fusing together of atoms, such
as hydrogen, at the extremely high pressures and
temperatures which exist at the centre of the sun
(15 million ºC). At these high temperatures any
gas becomes plasma
5
. The fusion reaction that is
easiest to accomplish is the reaction between two
hydrogen isotopes: deuterium, extracted from
water and tritium, produced during the fusion
reaction through contact with lithium. When
deuterium and tritium nuclei fuse, they form a
helium nucleus, a neutron and a large amount of
energy.
US President Ronald Reagan and General Secretary Mihail
Gorbachev of the former Soviet Union at the Geneva
Superpower Summit (1985).
The building phase of the project started in 2007
after the signature of the ITER agreement
4
at the
Elysée Palace in Paris on 21 November 2006 by
Ministers from the seven ITER Members—
the
European Union, China, India, Japan, South
Korea, Russia and the United States.
Since then,
the ITER members have been engaged in a 35-
year collaboration to build and operate the ITER
experimental device, which aims to demonstrate
that fusion energy can be part of the solution to
achieve sustainable and secure sources of energy for
the future.
Two atoms, deuterium and tritium, fuse together,
forming a helium nucleus, a neutron and lots of
energy.
The core of the ITER project: the thermonuclear
fusion reactor “Tokamak”
The thermonuclear reactor “Tokamak” is an
experimental machine designed to harness the
energy of fusion. ITER will be the world's largest
thermonuclear fusion reactor, with a plasma radius
(R) of 6.2 m and a plasma volume of 840 m³.
The amount of fusion energy a Tokamak is capable
of producing is a direct result of the number of
fusion reactions taking place in its core. Scientists
Ceremony hosted by French President Jacques Chirac and the
President of the European Commission José Manuel Durão
Barroso, on the occasion of the signature of the ITER Agreement
in Paris on 21 November 2006
4 Agreement on the Establishment of the ITER International
Fusion Energy Organization for the Joint Implementation of the
ITER Project of 16 December 2006. (OJ L358/62)
5 Plasma is the fourth state of matter (solid, liquid and gas being
the other three), and is described as an ‘electrically-charged gas’
in which the negatively charged electrons in atoms are completely
separated from the positively charged atomic nuclei (or ions).
Although plasma is rarely found on earth, it is estimated that
more than 99% of the universe exists as plasma (Source: Fusion
for Energy Joint Undertaking website )
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0014.png
ECA auditors visited the ITER project facilities
continued
12
state that the larger the vessel, the larger the
volume of the plasma, and therefore the greater the
potential for fusion energy. While previous Tokamak
experiments such as JET
6
succeeded in producing
significant amounts of fusion power for short
periods, none so far was capable of demonstrating
fusion on a scale needed to allow it to generate part
of its own fuel and produce power on a continuous
basis. The Tokamak ITER is designed to achieve this
objective, as a unique experimental tool, capable
of longer plasmas and better confinement. The
machine has been designed specifically to reach the
goals shown in the following table:
ITER's goals
7
The Tokamak thermonuclear reactor ITER
1) Produce 500 MW of fusion power
The world record for fusion power is held by the European tokamak JET. In 1997, JET produced 16 MW
of fusion power from a total input power of 24 MW (Q=0.67). ITER is designed to produce a ten-fold
return on energy (Q=10), or
500 MW
of fusion power from 50 MW of input power. ITER will not capture
the energy it produces as electricity, but—as the first of all fusion experiments in history to produce net
energy gain—it will prepare the way for the machine that can.
2) Demonstrate the integrated operation of technologies for a fusion power plant
ITER will bridge the gap between today's smaller-scale experimental fusion devices and the
demonstration fusion power plants of the future. Scientists will be able to study plasmas under
conditions similar to those expected in a future power plant and test technologies such as heating,
control, diagnostics, cryogenics and remote maintenance.
3) Achieve a deuterium-tritium plasma in which the reaction is sustained through internal heating
Fusion research today is at the threshold of exploring a "burning plasma"—one in which the heat from
the fusion reaction is confined within the plasma efficiently enough for the reaction to be sustained for a
long duration. Scientists are confident that the plasmas in ITER will not only produce much more fusion
energy, but will remain stable for longer periods of time.
4) Test tritium breeding
One of the missions for the later stages of ITER operation is to demonstrate the feasibility of producing
tritium within the vacuum vessel. The world supply of tritium (used with deuterium to fuel the
fusion reaction) is not sufficient to cover the needs of future power plants. ITER will provide a unique
opportunity to test mockup in-vessel tritium breeding blankets in a real fusion environment.
5) Demonstrate the safety characteristics of a fusion device
ITER achieved an important landmark in fusion history when, in 2012, the ITER International Organization
was licensed as a nuclear operator in France based on the rigorous and impartial examination of its safety
files. One of the primary goals of ITER operation is to demonstrate the control of the plasma and the
fusion reactions with negligible consequences for the environment.
6 Joint European Torus (JET), the world’s leading fusion device
located in the Culham Centre for Fusion Energy in Oxfordshire,
UK, is now under the umbrella of the EUROfusion consortium
agreement (formerly the European Fusion Development Agreement
(EFDA).
7 Source: https://www.iter.org; and http://fusionforenergy.europa.eu
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0015.png
13
Inside of the Tokamak ITER where fusion is to take place.
The ITER Organization
The ITER Organization is the international body
set up to run the ITER project. It is managed by
a Director General, under the supervision of
the ITER Council, the highest Governing Board
of the organization where its seven parties are
represented. The Chair of the ITER Council since 1
January 2016 is Professor Emeritus Won Namkung.
The Director General of the ITER organization
since 5 March 2015 is Dr. Bernard Bigot. The ITER
Organization is staffed by men and women from the
seven ITER Members. Approximately 7000 directly
employed staff and 500 external contractors work
for the ITER Project in its installations at the
CEA
8
Reseach Center of Cadarache, Saint Paul-
lez-Durance, France. The accounts of the ITER
Organization are audited by a Financial Audit Board
made up of independent representatives from
each ITER Member, and which provides an annual
audit report that is included in the Annual Financial
Report of the ITER Organization
9
.
The European Joint Undertaking for ITER and
the Development of Fusion Energy
The European Joint Undertaking for ITER and
the Development of Fusion Energy (F4E Joint
Undertaking) was set up by Council Decision
2007/198/Euratom of 27 March 2007 for a period
8
The French Alternative Energies and Atomic Energy
Commission (CEA).
9
https://www.iter.org/doc/www/content/com/Lists/list_items/
Attachments/625/2014_iter_financial_statements.pdf.
of 35 years. While the main fusion facilities of the
ITER project are in Cadarache, France, the European
Joint Undertaking is located in Barcelona. The main
task of the F4E Joint Undertaking is to provide the
EU contribution to the ITER Organization under the
ITER International Agreement. Other tasks of the
Joint Undertaking are to provide the contribution
of Euratom to ‘Broader Approach’ (complementary
joint fusion research) activities with Japan for the
rapid development of fusion energy; and to prepare
and coordinate a programme for the construction
of fusion reactors. The Chair of the Governing Board
of F4E Joint Undertaking since 2 December 2015
is Dr. Joaquín Sanchez. The Director General of the
Joint Undertaking since 1 January 2016 is Johannes
Schwemmer. As of 31 December 2015, the total
number of staff at the Joint Undertaking was 434, of
which 252 EU Officials and Temporary Agents, 167
Contract Agents, and 15 interim staff. The accounts
of the F4E Joint Undertaking are audited by the ECA,
which has produced a Specific Annual Report on the
accounts of the Joint Undertaking since the 2008
financial year.
The members’ contributions to the ITER project:
“in-kind contributions”
The seven parties of the ITER project have committed
themselves through the signature of the ITER
International Agreement to contribute to the project
mainly with “in-kind contributions”. Around 90% of
the ITER project is based on in-kind contributions.
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0016.png
ECA auditors visited the ITER project facilities
continued
14
To this end, the components that make up the ITER
facility have been divided into 85 procurement
“packages” distributed among the seven parties
to the ITER Agreement. To value the “in-kind
contributions” of each party to the project, the ITER
Organization has set up its own ITER Unit of Account
(IUA).
Europe, as the host party, and France, as the
host state, have special responsibilities for the
success of the project. Europe supports 46% of the
construction cost and 34% of the cost of operation,
deactivation and decommissioning of the facility, as
well as the preparation of the site.
The role of the ECA
The ECA is the external auditor of the F4E Joint
Undertaking but does not have any audit mandate
for the ITER Organization accounts, which are
audited by its Financial Audit Board.
The first work of the ECA in relation to the F4E Joint
Undertaking was the formulation of Opinion 4/2008
of 6 October 2008 on the Joint Undertaking’s
Financial Regulation. This Opinion contained 50
recommendations which were broadly accepted by
the F4E Joint Undertaking’s Governing Board and
introduced in its Financial Rules
10
. Of significant
value in order to strengthen the financial control
framework of the Joint Undertaking was the ECA
recommendation to allow for the same powers
for the Internal Audit Service of the Commission
(IAS) over F4E JU as it exercised in respect of other
EU bodies. That has proved to be a very important
instrument within the internal control framework
of the Joint Undertaking. Other important
recommendations were to further develop
the conditions under which exceptions to the
budgetary principles of the Framework Financial
Regulation could be applied and, in view of the size
of the budget and the complexity of the tasks to be
performed by the Joint Undertaking, to set up an
Audit Committee, which was created by Decision of
the Governing Board on 10 June 2010.
The ECA issued its first Specific Annual Report
on the accounts of the F4E Joint Undertaking in
relation to the 2008 financial year
11
. Since then,
and for seven consecutive financial exercises,
the ECA’s audit opinions on the reliability of the
accounts and the legality and regularity of the
transactions underlying the accounts of the Joint
Undertaking have been positive. Without calling
the audit opinions into question, as a result of its
audits, the ECA has raised numerous observations
and recommendations which have contributed
to reinforcing the internal control systems of the
F4E Joint Undertaking in different areas: ex ante
and ex post controls, the legal framework for the
operational tendering procedures launched for
the components to be provided in kind to the ITER
project, the Joint Undertaking’s industrial policy
10 www.eca.europa.eu/Lists/ECADocuments/.../OP08_04_
EN.PDF
11 Last one referred to the financial year 2014. The Specific Audit
Report on the 2015 Joint Undertaking Accounts will be made
available on 15 November 2016.
Sharing of the contributions to the construction cost of ITER by
each of the ITER Parties (Fusion for Energy 2015 Annual Activity
Report)
View of the construction of the ITER Tokamak in Cadarache-
March 2016
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0017.png
15
and rules for the protection and dissemination
of intellectual property rights, anti-fraud strategy
and rules on the management of the prevention
of conflicts of interest, as well as the control and
monitoring of the operational procurement
contracts and grants launched by the F4E Joint
Undertaking for the implementation of its activities.
In performing the task, the ECA auditors have
maintained very close and productive cooperation
with the management and staff of the Joint
Undertaking, the IAS, the Internal Audit Capability
of the Joint Undertaking, the private audit firms
performing the audit of the reliability of the
financial statements of the F4E Joint Undertaking
since the 2014 financial year, and other auditing and
consulting firms which have carried out evaluations
of the performance of the Joint Undertaking over
the years
12
.
A major concern for the European Union: “The
cost of the EU contribution to the ITER project”
One of the main concerns of the EU budgetary
authority has been the cost of the EU contribution
to the ITER project. The EU is the main contributor
to the construction phase of ITER. In view of its
complexity, the progress of ITER has been the
subject of numerous debates in the Budgetary
Control Committee of the European Parliament,
which takes a particular interest in the development
of the project.
Article 4 (3) of the Council Decision setting up
the European Joint Undertaking for ITER and the
Development of Fusion Energy
13
refers to
€9 653 million in 2008 values as the indicative
total resources deemed necessary for the Joint
Undertaking to carry out its tasks under the
timeframe of 35 years for which it was set up.
Already in July 2010, the Council agreed a revised
budget estimate for the EU contribution to the first
phase of the project, “the construction phase”,
initially targeted to be finalised in 2020, from the
initial estimate of €2.7 billion euro to €6.6 billion
(2008 value)
14
. This figure, which doubled the
initial budgeted costs for this phase of the project,
did not include €663 million proposed by the
European Commission in 2010 to cover potential
contingencies
15
.
ECA has been reporting since 2010 that the
complexity of ITER activities implies that the
amount of the F4E Joint Undertaking’s contribution
to the construction phase of the project is exposed
to significant risks of increase, mainly as a result of
changes in the scope of the project deliverables
and delays in the schedule. At the time of the
publication of the last Specific Annual Report, on
the 2014 accounts of the F4E Joint Undertaking, the
Joint Undertaking was working together with the
ITER Organization on a revised estimate for the cost
of the EU contribution to the construction phase
of the ITER project. These two issues concerning
the cost and schedule of the project have been
the subject of an emphasis of matter in the ECA
audit reports on the accounts of the F4E Joint
Undertaking since 2013
16
.
Current status of the ITER project: the road to
“First Plasma”
As a result of a two-year exercise carried out by
the ITER Organization and its seven members to
establish a new baseline schedule, the ITER Council
endorsed in its meeting of 15-16 June 2016
17
, an
updated Integrated Schedule for the ITER Project,
which identifies the date of achievement of “First
Plasma” as December 2025. The updated integrated
schedule proposed by ITER is the following:
12 See for example “`Potential for Reorganization within the ITER
project' of 2013, carried out by Ernst & Young upon request of the
European Parliament,
13 Council Decision 2007/198/Euratom of 27 March 2007
establishing the European Joint Undertaking for ITER and the
Development of Fusion Energy and conferring advantages upon
it (OJ L 90, 30.3.2007, p. 58), amended by Council Decision 2013/
791/Euratom of 13 December 2013 (OJ L 349, 21.12.2013, p. 100)
and Council Decision (Euratom) 2015/224 of 10 February 2015
(OJ L 37, 13.2.2015, p. 8).
14 Council conclusions on ITER status of 7 July 2010 (Ref.
11902/10).
15 Communication from the Commission to the European
Parliament and the Council of 4 May 2010 on ITER status and
possible way forward (COM(2010) 226 final).
16 See Specific Annual Reports on the annual accounts of the F4E
Joint Undertaking for 2013 and 2014 at
www.eca.europa.eu.
EU
Oficial Journal at http://eur-lex.europa.eu/legal-content/EN/TXT/
HTML/?uri=OJ:C:2015:422:FULL&from=EN
17 https://www.iter.org/org/team/odg/comm/pressreleases
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0018.png
16
ITER Timeline to achieve first plasma
18
2005 Decision to site the project in France
2007
Formal creation of the ITER Organization
2007-2009
Land clearing and levelling
2010-2014
Ground support structure and seismic
foundations or the Tokamak
2012
Nuclear licensing milestone: ITER becomes a
Basic Nuclear Installation under French law
2014-2021*
Construction of the Tokamak Building
(access for assembly activities in 2019)
2010-2021*
Construction of the ITER plant and
auxiliary buildings for First Plasma
2008-2021*
Manufacturing of principal First
Plasma components
2015-2021*
Largest components are transported
along the ITER Itinerary
2018-2025*
Assembly phase I
2024-2025*
Integrated commissioning phase
(commissioning by system starts several years
earlier)
Dec 2025* First Plasma
According to the ITER Council conclusions of 15-16
June 2016, the updated schedule is challenging
but technically achievable, and will have now to be
duly validated with a thorough and comprehensive
review by the independent ITER Council Review
Group
19
.
Further information on the ITER project, the
European Joint Undertaking for ITER and the
development of Fusion Energy and the reports by
the ECA can be found at:
www.iter.org/
http://fusionforenergy.europa.eu/
http://www.eca.europa.eu
ITER work site-April 2016
18 Source: ITER Organization https://www.iter.org/proj/
inafewlines
19 The ITER Council Review Group provides external validation of
ITER Project progress.
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0019.png
Experiences and views on the discharge
procedure
By Rosmarie Carotti
At the invitation of Alex Brenninkmeijer, ECA Member, three young practitioners from the
European Parliament, Council and Commission shared their experiences and views on the role
of discharge in the political decision-making process
11 July 2016
17
From left to right:
Di Hai, ECA auditor structural policies; Kristina Maksinen, ECA auditor external actions; Dessislava
Velinova, member of Commissioner Kristalina Georgieva’s private office; Martina Dlabajová, Member of
the European Parliament and rapporteur for the 2014 discharge procedure; Sabine Klok, chairperson of
the Council’s budget committee; Alex Brenninkmeijer, ECA Member; Danièle Lamarque, ECA Member;
Katja Mattfolk, head of private office of Bettina Jakobsen, ECA Member
The panel:
Martina Dlabajová, Member of the European Parliament and rapporteur for the 2014 discharge procedure
Sabine Klok, chairperson of the Council’s budget committee
Dessislava Velinova, member of Commissioner Kristalina Georgieva’s private office
Danièle Lamarque, ECA Member
Katja Mattfolk, head of private office of Bettina Jakobsen, ECA Member
Kristina Maksinen, ECA auditor external actions
Di Hai, ECA auditor structural policies
The basic idea behind this seminar organised and
moderated by Alex Brennikmeijer was to create
a dialogue between young practitioners from
the EP, Council, Commission and ECA and to give
perspectives on what could be important for the
future of the ECA.
Giving a positive message to citizens
Martina Dlabajová, Vice-Chair of the Committee
of Budgetary Control (CONT) of the European
Parliament talked about the 2014 discharge to the
Commission. As rapporteur, she had submitted a
report on the Commission’s budget implementation
to her colleagues in the EP and negotiated the
discharge text with the other political groups.
[Her
main concern is to give citizens a positive
message on how the budget is used. Not every error
leads to misspending and EU budget allocations
have to present added value on concrete projects.
Shifting to more performance makes citizens better
understand the added value of EU funding. There
is the need however for balance between formal
matters and performance results and the need to
consider the economic reality and the economic
policy environment. Continuity is needed to
facilitate the contact between the CONT and the
Member States.
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0020.png
Experiences and views on the discharge procedure
continued
18
Balancing costs and benefits in EU financial
management
Sabine Klok, chair of the Council’s Budget
Committee during the 2014 discharge negotiations,
recalled the Council’s regret of the estimated
level of error for payments as a whole of 4.4%
and expressed a wish for more openness of what
is happening in the Member States. 80% of the
EU funds are under shared management. She
underlined the need to strike a balance between
risk of error and cost of control. Prevention is better
than cure, but she also called upon the Commission
to continue with the implementation of all available
corrective measures.
Concerning the ECA’s annual report, she stressed
the importance of ensuring continuity and
comparability between years and policy areas and
she expressed the wish for more performance
information.
The priorities of the European Commission were
presented by Dessislava Velinova, member of the
Cabinet of Vice-President Georgieva. She also
identified as the main challenge to achieve an
appropriate balance between performance and
compliance. She explained the Commission’s
initiative of a budget focused on results and,
concerning the reporting on the EU budget,
presented the novel annual Management and
Performance Report.
For her performance is a process in which it is
important to maintain realistic expectations,
identify best practices, address root causes of error
and simplify where possible.
Katja Mattfolk, head of private office in the ECA,
recalled that in the 2004 ECA annual report there
was no error rate and very little mention of Member
States. The special reports presented during the
year were just summarized at the end of each
chapter. In the last ECA 2014 report, there is a
multitude of assessments: global, risks, error rates,
performance, cases sent to OLAF. However there are
still opportunities to develop further, for example to
integrate performance to a greater extent. Another
point of discussion is how big a percentage of the
error rate could have been avoided if the Member
States had used all the information available.
What is the cost of reducing this error rate? It comes
at a significant cost. Administrative costs are also
increasing. Everybody is also keen on promoting
simplification but it has to be balanced towards
the issue of performance. Sometimes simplification
and performance are contradictory. There are many
ways of increasing the information value of the
annual report and thus providing more added value
to administering EU funds in the Member States.
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0021.png
19
Reflecting performance in the ECA's annual
report
Kristina Maksinen, ECA auditor, talked about
performance and the ECA special reports. The ECA
has to provide a balanced view of what the EU
achieves and be strategic about how its work is
used by others. Special reports complement the
annual report which focuses on figures, percentages
and error rates. Looking at the latest ECA report of
2014, although it addresses explicitly the special
reports, it only provides a limited overview on them
and shows the need to strengthen the link between
performance audit and the annual report.
Di Hai, ECA auditor, also felt that not much of her
work was reflected in the annual report during
the discharge procedure. Much of the attention
of the annual report and the discharge procedure
goes to defining the financial activities of the
EU, whereby the error rates expresses a political
attitude. In between the lines of the annual report
and the discussion during the discharge there is a
huge gap for questions like how the EU is actually
doing. Performance audit can be used as a tool to
provoke that question even if at the end of the day
performance audit should be focusing on analysing
projects resolved. But to analyse projects you need
clearly defined objectives and for that a strong
political and policy framework.
Even if performance may aim at a public outreach,
the ultimate platform for discussion in the European
context is Parliament. It is therefore important
to strengthen or re-strengthen the institutional
focus within the ECA’s performance audit reports.
The key thought guiding this debate should be
the supranational character of the EU institution,
additionality and EU added value. Even though this
concept has well established legal ground, it is not
always very clear what this concept means.
Developing the way the ECA works
Danièle Lamarque, ECA Member, stressed that
there still are gaps and expectations in terms of
responsibility and transparency. To whom is the
EU accountable? The citizens should be better
informed about what happens with the use of the
EU funds. Who is in charge of the improvement
of the use of the EU funds in the Commission but
also in the Member States? There still is a lack of
cooperation with the Member States.
In order to become more efficient the ECA has
made improvements in the use of its resources and
changes in its methodology allowing it to rely more
on the work done by others. On the question of
balance, the ECA is committed to show not only the
error rates but also how practices can be improved,
and to report best practices.
The discharge can be an occasion to improve clarity
and better understanding of what the added value
of the EU is. A challenge for the coming years in
terms of responsibility will be the cooperation
with the Member States whereby the EU may be
accountable for 80% shared management.
The general discussion brought interesting ideas on
risks and costs. To manage means to take risks. And
reducing risks cause costs of control. We should not
neglect the opportunity cost for the performance
of projects when better projects are ignored due to
burdensome rules.
Corruption is a risk for the whole system. Could the
ECA use a new approach and make better use of
performance audit answering the question if the EU
expenditure is well protected against corruption?
It was also said that prevention of corruption is
important and that special reports might contribute
to that effect.
The discussion further centred on the cooperation
between the EU institutions and the national
authorities. Could the profile of the Budget ECOFIN
Council meeting be raised in a way that there would
be a separate meeting with the deputy ministers
before the general ECOFIN ministers meeting?
The EU budget is implemented under shared
management (i.e. both Member States and
Commission are responsible). Next to shared
management there is shared finance. The ECA
only reports on the part that is financed by the EU
and leaves out what is financed by the Member
States. Would the interest of national parliaments
in the EU discharge procedure be raised if the ECA
included in its reports the shared financing and did
mention who the primary responsibility belongs
to? Ultimately each euro comes from the same
taxpayers.
To conclude, it is up to all politicians in the Member
States to change their rhetoric and for the EU to
come up with realistic stories. To use the words of
Alex Brenninkmeijer, “auditing is listening” and this
audit process should be part of the learning process
and continuity. It also is important that the message
of the ECA to the outside world is a balanced one,
not only a negative one.
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0022.png
Recent EU Case-law on State aid
By Rosmarie Carotti
20
The Legal Service invited all ECA staff to an information session given by
Íde
Ní Riagáin on
the case-law of the Court of Justice and the General Court from March 2016 to June 2016
Íde
Ní Riagáin, Lawyer
conferred on the Frucona Košice, the Commission
had to carry out a” global assessment” (since
Case 124/10 P EDF v Commission), taking into
account all relevant evidence in the case enabling
it to determine whether Frucona Košice would
manifestly not have obtained comparable facilities
from a private creditor. The judgment considers
whether the Tax Office would have been better
off accepting the conditions proposed under the
arrangement or whether it would have been more
advantageous to initiate bankruptcy proceedings or
to make some other arrangements..
Case T-471/15
Germany v Commission
(10 May 2016)
received a lot of attention in the media, particularly
in Germany. The German law on renewable energy,
in its 2012 version, established a scheme to support
undertakings producing energy from renewable
energy sources. The Commission considered that
the feed-in tariffs and market premiums, which
guarantee producers of EEG electricity a higher
price for the electricity they produce than the
market price, constituted State aid which was
however compatible with the internal market.
It also considered that the reduction of the EEG
surcharge for certain energy-intensive users also
constituted State aid, the compatibility of which
would be recognised only if it fell into certain
categories. .
Germany argued that the surcharge was not such
an economic advantage and that the mechanism
set up by the German environmental law was such
that it was not a case of State resources. The General
Court distinguished it from the Case Preussen
Elektra where the CJEU had found that there was
no transfer of State resources and accordingly no
State aid, because Germany merely had imposed an
obligation on electricity distributors to buy green
electricity without establishing a mechanism that
would allow to exercise control over the resources
that flowed between users, distributors and
producers of electricity.
Even though under the mechanism at issue
Germany did not have actual access to the
resources generated by the EEG surcharge, it
influenced the use of the resources in that it was
able to decide in advance, through the adoption of
There are four cumulative conditions for State aid:
aid granted through State resources, conferring
a selective advantage on undertakings, having
an impact on trade between Member States and
distortion of competition (article 107(1) TFEU).
In May 2016, the Commission finally adopted a
Notice on the Notion of State aid
which seeks to
provide guidance on all aspects of the definition of
State aid, by systematically summarising the case
law of the EU courts and the Commission's decision-
making practice.
The first Case T-103/14
Frucona Košice v Commission
– the Frucona II Case (16 March 2016) discussed
deals with the notion of advantage, one of the
criteria which must be fulfilled in order that a
measure be considered State aid. Advantage is an
economic benefit which an undertaking would not
have obtained under normal market conditions. Tax
exemptions tax arrangements and infrastructure
provisions may also be considered an advantage.
Frucona Košice was a Slovak company which
produced spirits and benefited from several
deferrals of payment of tax debts. The Commission
felt that this agreement by the fiscal authorities was
State aid as it would not have been given under
normal market conditions.
The case is interesting because it concerns the
application of the private creditor test. In order
to assess whether an advantage was actually
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0023.png
Recent EU Case-law on State aid
continued
21
the EEG 2012, which objectives were to be followed
and how those resources were to be used.
There has since been a revision of the German
energy law on this in 2014 and another revision will
take place in 2017.
Three cases (Cases T-50/06 RENV II (IRL), T-56/06
RENV II (FRA) and T-60/06 RENV II (ITA) (22 April
2016) involved tax exemptions for producers of
alumina in three countries.
A Council decision granted tax exemption on the
mineral oil they needed for the production of
alumina. The Commission later held that those
measures constituted unlawful State aid. The
General Court held that the Commission had the
power to examine the Council’s authorisation
since State aid is an objective concept. When the
Commission assesses a measure, it must examine its
effects.
The General Court also found that the companies at
issue had an advantage vis-à-vis other companies
and that despite the unreasonably long delays
for the Commission to take a decision, the latter
had not infringed on the principle of protection
of legitimate expectations. It followed that the
Commission was entitled to order recovery.
The final case Case C–
270/15 P Belgium v
Commission
(30 June 2016) had to do with
selectivity. Belgium’s, partial or full, financing of
the compulsory BSE (transmissible
spongiform
encephalopathies (TSE) in bovine animals)
screenings
was considered by the Commission and the General
Court to be State aid.
Belgium challenged both decisions on the basis
that one of the four criteria for State aid, namely
the selective nature of the measure, was not
fulfilled because it was a general scheme and the
measure did not confer a selective advantage on
undertakings.
There are very interesting elements to this
judgement. Article 107(1) TFEU does not distinguish
between State interventions by reference to their
causes or aims but defines them in relation to their
effects and distortion of competition within the
Member State.
The situation of the operators in the bovine sector
was compared to that of all undertakings which
are like them subject to inspections which they
are required to perform. The Advocate General
had previously concluded in his opinion: “The fact
remains that the financing of BSE screening tests
through State resources constituted a selective
advantage that was not available for other sectors”.
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0024.png
E
FOCUS
A
Focus
22
Engagement solennel des nouveaux Membres de la Cour
6 juillet 2016
Les cinq nouveaux Membres de la Cour, Messieurs Janusz Wojciechowski, Samo Jereb, Jan Gregor, Mihails Kozlovs
et Rimantas Šadžius s’engagent solennellement devant la Cour de justice, conformément aux dispositions du
traité.
Cette cérémonie souligne une fois de plus l’importance que revêtent l’indépendance et l’intégrité de chaque
Membre pour la réputation de la Cour en tant qu’institution d’audit externe des finances de l’Union ayant pour
mission d’améliorer la gestion financière, renforcer l’obligation de rendre compte et la transparence, et protéger
les intérêts financiers des citoyens.
Monsieur Vítor Manuel da Silva Caldeira assiste à la cérémonie d’engagement solennel comme Président de la
Cour des comptes européenne pour la dernière fois avant de prendre les fonctions de Président de la Cour des
comptes du Portugal à partir du 1
er
octobre 2016.
Janusz Wojciechowski
Samo Jereb
Jan Gregor
Mihails Kozlovs
Rimantas Šadžius
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0025.png
E
FOCUS
A
Focus
EU assistance for strengthening the public administration
in Moldova
23
Special report
N° 13/2016
Moldova receives the highest amount of EU aid per inhabitant of all of the EU’s
eastern neighbours. We assessed whether EU aid had contributed effectively to
improving the country’s public administration.
We concluded that budget support had had a limited effect. The Commission
could have responded more quickly when risks materialised, and programmes
were not sufficiently aligned to Moldovan strategies. The Commission did not
make full use of its ability to set conditions for disbursement, and additional
incentive-based funds were not fully justified.
The projects we assessed were relevant, and had delivered the expected
outputs. However, they were not always well coordinated with budget support
programmes, and results were not always sustainable.
This report was published on1 September 2016 and is available on our website
www.eca.europa.eu.
Special Report
N°15 /2016
Did the Commission effectively manage the Humanitarian
aid provided to populations affected by conflicts in the
African Great Lakes Region?
The auditors conclude that humanitarian aid to the populations affected by
conflicts in the African Great Lakes area was generally managed effectively by
the Commission.
The funding was allocated to well-established main priorities, but there was
insufficient clarity at a later stage when further specifying priorities and
selecting projects. It was not possible to determine whether the most suitable
projects had been selected.
Overall, the Commission’s monitoring was appropriate, although it could have
made better use of the information it obtained. Finally, taking into account
the particular challenges faced in the region, most of the projects examined
delivered satisfactory results.
This report was published on 4 July 2016 and is available on our website
www.eca.europa.eu.
Special Report
N°17/2016
The EU institutions can do more to facilitate access to their
public procurement
EU institutions procurement rules are broadly in line with the general EU
legislation on public procurement which requires putting procurement
contracts out to tender on the broadest possible basis to maximise competition.
The management and control arrangements of the EU institutions are robust
and in general mitigate the risk of errors. We found however that EU institutions
can do more to facilitate access of economic operators (especially of small and
medium-sized enterprises) for example by simplifying the rules to the fullest
possible extent and by removing unnecessary hurdles which make life difficult
for potential tenderers who want to identify procurement opportunities offered
by the EU institutions.
This report was published on 13 July 2016 and is available on our website
www.eca.europa.eu.
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0026.png
E
FOCUS
A
Focus
24
Special Report
N°18 /2016
The EU system for the certification of sustainable biofuels
The Member States must ensure that the share of energy from renewable
sources in transport in 2020 will be at least 10 % of the final energy
consumption in this sector. They can count towards this target biofuels
certified as sustainable by voluntary schemes recognised by the Commission.
We conclude that, because of weaknesses in the Commission’s recognition
procedure and in the subsequent supervision of voluntary schemes, the EU
certification system for the sustainability of biofuels is not fully reliable.
As regards the achievement of the 10 % transport target, we found that the
statistics might be overestimated, because Member States could report as
sustainable biofuel whose sustainability was not verified.
This report was published on 21 July 2016 and is available on our website
www.eca.europa.eu.
Special report
N° 19/2016
Implementing the EU budget through financial instruments –
lessons to be learnt from the 2007-2013 programme period
Financial instruments are increasingly used to provide financial support from
the EU budget through loans, guarantees and equity investments. During the
2007-2013 programming period, some €21.5 billion from the EU budget were
allocated to financial instruments. We found that while they may have distinct
advantages compared to other forms of EU funding such as grants, their
implementation faces significant challenges which could limit their efficiency.
This report was published on 7 July 2016 and is available on our website
www.eca.europa.eu.
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0027.png
Performance auditing: Current methods and
future prospects
By Luc T'Joen, senior administrator in Chamber II
25
Luc T'Joen
The ECA has launched the
EKA (Enabling Knowledge for Audit) initiative
with the aim of promoting a corporate culture of knowledge-sharing and
collective learning. An important part of this initiative in the praparation of
Subject Briefs in which staff members set out and share their professional
knowledge on specific subjects.
This Subject Brief contains a number of personal suggestions for further
developing performance audit knowledge. Audit is a knowledge-based
activity.
Introduction
This brief highlights the importance of using
performance auditing in addition to other forms
of auditing to further improve the quality of
EU spending. Increased performance auditing
knowledge, new ways of sharing the knowledge
and better use of performance audit results are
key to better spending, and to convincing policy-
makers and the general public of the possibilities
offered by performance auditing.
Performance auditing
Currently, most of the Commission's attention
regarding policy and audit matters is directed
towards the legality and regularity of EU
expenditure. Policy incentives for rewarding
performance in cohesion policy are limited (a 6 %
performance reserve has existed since the 2007-
2013 programme period) but in practice these
reserves are hardly used.
In the context of an increased public expectation
to prove that every euro of the EU budget spent is
used to deliver tangible results, there is growing
consensus on the relevance of using performance
audit methods. This was acknowledged by the new
Juncker Commission, which explicitly recognised
that there is a need for a budget aimed at results,
rather than rules: “A
road to nowhere, built according
to the rules, is still a road to nowhere”
and “the
budget
for us is therefore not an accounting tool, but a means
to achieve our political goals”
1
.
The Commission considers that the progressive
development of a performance culture will take
several years to come to full effect, and there is a
1
Speech by Commission President Juncker at the Conference
“EU budget focused on results” – Brussels, 2015.
“limited development of mechanisms to reward
performance and penalise non-effective use of the
funds.”
2
Some progress has been noted over time in the
form of recent small steps towards assessing
results, or at least paving the way to obtaining
better results. While these changes were not always
directly connected to previous ECA performance
audits, the Commission has used some of the
ECA's performance audit outcomes as a basis
for proposing policy directed towards greater
performance orientation. For example:
-
The ECA's Special Report on seaports
3
provided
support for the Council and Parliament to
adopt legislation for the 2014-2020 period
which included “ex-ante conditionality”,
meaning that future EU-funding for transport
infrastructure, amongst other investment
areas, must be framed within a long-term
strategic plan which must be submitted to, and
assessed by, the European Commission before
any EU funding can be provided from the
2014-2020 framework period;
The same report was one reason why 11,3
billion euro in EU funding for transport
investment, originally allocated to the
Member States and regions to be spent
under the “shared management” umbrella,
were transferred to the Commission for direct
centralised management by the Commission
via its Innovation and Networks Executive
Agency (INEA) through the Connecting Europe
Facility (CEF) instrument;
-
2
Commission reply to paragraph 10.1 of the ECA “Annual Report
concerning the financial year 2012”.
3
See Special report No 4/2012: “Using Structural and Cohesion
Funds to co finance transport infrastructures in seaports - an
effective investment?”
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0028.png
Performance auditing: Current methods and future prospects
continued
26
-
Procedures for assessing the
underperformance of Cohesion Fund projects
in the programming period 2000-2006 were
adopted to assist Commission desk officers
in the closure process. These set out a
consultation procedure for possible financial
corrections;
A new Cost-Benefit Analysis (CBA) guide has
been published, building upon the experience
gained over time;
The “JASPERS” instrument will provide technical
assistance at EU-level for major projects and
Cohesion fund projects.
target audit topics, scope and population,
as recommended by the Court in 2012.
Commission audit teams do not work on
performance and continue to give priority to
lowering the historical error rate.
-
INEA project officers and Managing Authority
officials have not been trained in performance
measurement and still sign off invoices as soon
as a construction has been completed, even
if the output would not be in use. In addition,
the legal annexes to the grant agreements
have not been amended. As a result, empty
port quays, airports which are too large and
unused or underused, roads which are empty
for most of the day and so on, would therefore
still get the EU funding agreed upon at the
start of the project.
-
-
However, although these are steps in the right
direction, they are only small steps since there is, as
yet, no clear focus on sound financial management
in the ERDF and CF policy or its practical
implementation:
-
Indicators (common indicators and
programme-specific indicators) will be set
for each priority in the 2014-2020 cohesion
policy framework to assess progress towards
achieving objectives. However, this will not
solve future ineffective spending practices,
as the information available at project level
will not feed in to the higher level strategic
framework information (the indicators do not
match).
In other words, whilst it is true that bad
performers will not get money out of the
reserve, bad performance will still be rewarded
with the full amount of EU money, as the
rules only provide for outputs to be assessed.
If these outputs have been built, the money
will be paid, and there is no penalty, other
than... not getting a bonus. This means that
EU project management is vulnerable to flaws,
and the Commission’s responsibility for sound
management is still at high risk for the years to
come.
-
So far, the Commission’s auditors have not
carried out any of the performance checks
on projects using risk-based sampling to
There are several ways to significantly improve
the future value of money implemented in the EU
budget. For example:
-
Increased use of repayable instruments
(e.g. loans and guarantees), with fewer
unconditional grants, which are often
perceived by the beneficiaries as ‘free
money’. For the 2014-2020 period the
Commission is already exploring this
option by increasing the share of the EU
budget spent through repayable forms of
financial support, implemented through
financial instruments which are managed
by the European Investment Bank (EIB), the
European Investment Fund (EIF) or financial
intermediaries in Member States.
The spread of performance audit methods
and their use for financial decisions should be
pursued. Internal control bodies (such as the
audit authorities checking cohesion policy
expenditure) and programme managers in
Member States or the Commission should
become more performance-oriented in their
work. To do so, they could apply the methods
used by the ECA and other supreme audit
institutions. Not all Member States need help,
-
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0029.png
27
but training in our methodology could, and
should, be provided upon request;
-
Financial and compliance audits at Member
State level could also collect more performance
information from the management systems
and projects and could include a focus on
assessing the impact of irregularities on
performance rather than just reporting on
irregularities, which often have little to do
with whether the intended results have been
achieved or not.
While performance audits are generally carried
out ex-post (“after
the harm has been done”),
audit bodies could get involved earlier in the
EU funding process. They could examine,
for example, whether there is a robust
performance measurement process in place
before projects selected for EU funding are
implemented, i.e. whether SMART
4
objectives
and RACER
5
indicators have been set. They
could also check to what extent the cost-
effectiveness concept has been systematically
applied when selecting the projects
6
.
Considering that 80 % of the EU budget flows
through shared management, in which the
Member States have direct responsibility
for a number of key activities (e.g. needs
assessment, project selection, management,
reporting), the ECA could get more involved
with Member State authorities by presenting
more performance audit reports before
national parliaments
7
, more regularly.
-
As suggested by the European Parliament
8
,
the ECA could also seek closer cooperation
with national Supreme Audit Institutions to
cross-fertilize knowledge, harmonize audit
approaches, and carry out the following:
o
“coordinated”
audits,
where the activities
of various audit teams are coordinated.
There are recent examples of some of
these audits in Chamber II (e.g. JASPERS
performance audit being coordinated
between ECA, the Polish SAI, the Croatian
SAI and ...), and
o
“joint”
performance audits.
In this
case, ECA auditors would take part in
Member State performance audits of
nationally-funded projects (e.g. an audit
of national roads with methodologies
discussed and agreed upfront), and
Member State auditors would take part in
ECA performance audits of similar EU co-
funded projects. This would increase the
horizons of the work of ECA auditors, since
EU-funded projects are usually only a very
small part of the overall picture in a given
field and give them a better overall view
of the things we report upon. This would
also give national auditors an increased
understanding of how the ECA applies
its methods in practice, and enable both
parties to collect important information
on the quality and management of EU co-
funded projects compared with nationally-
funded projects (are the EU-funded
projects better, or worse, and why?)
Conclusions
The EU budget remains a mystery to many
Europeans
9
: while 80 % of the EU budget is
managed at Member State level, only 34 % of
Europeans have heard about EU co-financed
projects to improve the area in which they live
10
.
The Commission has recognised politically that
more needs to be done to move from being a
8
European Parliament, “Report on the future role of the Court
of Auditors” (2014) paragraph 17-19 and 31.
9
G. Cipriani, “The EU budget: responsibility without
accountability?” (2010, p. 66) – CEPS.
10
European Commission, “Spotlight on European public opinion
in 2013” – Eurobarometer (2013:31).
-
-
4
SMART = Specific, Measurable, Achievable, Realistic, Time-
based.
5
RACER = Relevant, Acceptable, Credible, Easy, Robust.
6
L. Pirelli, “The added value of the European Court of Auditors’
performance audits”, ECA Journal N°11/2015, page 21.
7
Some ECA performance audit reports have already been
presented in national parliaments in the past. For example:
(i) Mr Brenninkmeijer (NL ECA Member) sent 16 performance
audit reports to the Dutch Parliament in 2014-2015.
This lead to several presentations, 23 parliamentary questions to
the Dutch Ministers and 6 motions to the Dutch
Government related to ECA performance audit reports;
(ii) Mr Herics (AT ECA Member) presented the ECA’s performance
audit work to the Austrian Parliament’s
Rechnungshofausschuss on several occasions, usually combined
with discussions on the annual report. For example, on
6.11.2014, 3.12.2014, 24.6.2015 and 14.4.2016.
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0030.png
Performance auditing: Current methods and future prospects
continued
28
spending body to being an effective spending
body. Political will has been demonstrated at the
highest level by the recent Juncker Commission,
and EU cohesion policy has been adapted for the
2014-2020 period to reflect the search for results,
but work on this is by no means complete yet. As
long as EU budget disbursements remain largely
disconnected from results, particularly in relation to
CEF, ERDF and CF payments, and no active efforts
are made to pursue and implement real incentives
for effective spending (or sanctions based on
negative performance audit outcomes, such as
empty and unused infrastructures), clearly positive
results will remain just a “noble aim” of the EU
budget.
By increasing the visibility of its performance audit
reports in Member States and by demonstrating the
usefulness of performance audit methods to assess
the relevance of EU spending, by working together
and, more generally, by spreading a performance
culture, the ECA may significantly help to bridge the
gap between the EU's citizens and its institutions
and restore the citizens’ trust in the EU.
Whatever the future priorities for it, performance
auditing will be a key contributor to ensuring better
quality and more efficient spending of EU funds.
There is still room to enhance the role of
performance audit and share knowledge about it, in
which the ECA can play a pioneering role.
Or, as the great Mahatma Ghandi once said:
“Be the change that you wish to see in the world”
Although the Commission monitors the
implementation of its policies and provides
evaluations on the performance and impact of
these policies, the ECA - in its role of external
auditor - is in a prominent position to provide
EU policymakers and citizens with independent
opinions on results achieved. This has been
acknowledged by the European Parliament when
it asked the ECA to “devote more resources to the
examination of whether economy, effectiveness
and efficiency have been achieved in the use of
public funds entrusted to the Commission”
11
.
Performance audit can help a lot to restore
confidence in what the EU is trying to do. For
instance, in 2003 the European Parliament noted
that “the focus actually given to the legality and
regularity of the spending does not help to inform
the legislator and the public as to whether the
money has been spent effectively”
12
.
At this point in time, and based on the follow-up
of earlier recommendations in the transport field,
the most promising prospect for performance audit
seems to be its development as a widespread tool
to be used not only for ex-post examination of EU
spending by (too few) ECA performance auditors,
but also to improve future funding allocation and
project selection and move towards a performance-
based reward system.
11European
Commission, “Spotlight on European public opinion
in 2013” – Eurobarometer (2013:31).
12
European Parliament, 2003 discharge: section III of the
general budget, par. 32(d).
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0031.png
© European Union, 2016
Reproduction is authorised provided the source is acknowledged/Reproduction autorisée
à condition de mentionner la source
EUU, Alm.del - 2015-16 - Bilag 851: Rapport fra Den Europæiske Revisionsret september 2016
1661107_0032.png
ISSN 1831-449X
Main Contents
02
05
08
10
17
25
INTERVIEW WITH RIMANTAS ŠAD�½IUS, NEW ECA MEMBER
SPECIAL REPORT NO 19/2016: IMPLEMENTING THE EU BUDGET THROUGH FINANCIAL INSTRUMENTS
THE ECA’S REFORMED CHAMBERS AND COMMITTEES
ECA AUDITORS VISITED THE ITER PROJECT FACILITIES IN SAINT PAUL-LEZ-DURANCE (FRANCE)
EXPERIENCES AND VIEWS ON THE DISCHARGE PROCEDURE
PERFORMANCE AUDITING: CURRENT METHODS AND FUTURE PROSPECTS
For more information
European Court of Auditors
12, rue Alcide De Gasperi
1615 Luxembourg
LUXEMBOURG
[email protected]
eca.europa.eu
@EUAuditorsECA
EUAuditorsECA
QJ-AD-16-008-2A-N